ML17054B536

From kanterella
Jump to navigation Jump to search
Insp Rept 50-220/85-01 on 850121-25.Deviation Noted:Diesel Fire Pump Not Separated from Electric Fire Pump
ML17054B536
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 03/04/1985
From: Anderson C, Krasopoulos A, Pullani S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17054B534 List:
References
50-220-85-01, 50-220-85-1, NUDOCS 8504080500
Download: ML17054B536 (36)


See also: IR 05000220/1985001

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

50-220/85-01

Docket No.

50-220

License

No.

DPR-63

Priority

Category

C

Licensee:

Nia ara

Mohawk Power

Cor oration

300 Erie Boulevard West

S racuse,

New York

13202

Facility Name:

Nine Mile Point

1

Inspection At:

Scriba

New York

Inspection

Conducted:

Januar

21-25

1985

Inspectors:

MA.alai

S.

ulla i, Fi"

rotection Engineer

A. Krasopoulos,

eactor

Engineer

date

9-

4-85'ate

Also participating

and contributing to the report were:

A. Coppola,

Mechanical

Systems Specialist,

BNL

A. Singh, Auxiliary System Branch,

NRR

H. Thomas, Electrical

Systems Specialist,

BNL

J.

Stang,

Chemical

Engineering

Branch,

NRR

Approved by: C..

nderson,

Chief, Plant Systems

Section,

DRS

date /r-

Ins ection

Summar

Ins ection

on Januar

21-25

1985

Re ort No. 50-220/85-01

Areas Ins ected:

Special,

announced

team inspection of the licensee's

efforts

to comply with the requirements

of 10 CFR 50, Appendix R, Sections III.G, J,

and 0, concerning fire protection features to ensure

the ability to achieve

and maintain safe

shutdown in the event of a fire.

The inspection

involved

166 inspector

hours onsite

and

53 inspector

hours in-office by the team

consisting of 6 inspectors.

(

85040805

pg000220

850402

PDR

WD<<~

pDR

8

I

t

0

i

Results:

No violation was identified.

One deviation

was identified for

failure to comply with an

FSAR commitment to design

and install all fire

protection

components

in accordance

with NFPA standards.

This deviation is

discussed

in Section 7.4.a.

In addition, three

items remain unresolved at the

end of inspection.

(See Section

11.0 for paragraph

numbers).

l

0

DETAILS

Persons

Contacted

Nia ara

Mohawk Cor oration

NMPC

J.

AJ

  • T

AD

4'p

AD

  • G

AD

AD

  • M.

AT

  • R.

"R.

AJ

  • T

AR

K.

  • C
  • G

"K.

Aldrich, Operations

Supervisor

Barrett, Assistant Supervisor - Technical

Support

Boyle, Nuclear

Compliance

and Verification

Corcoran,

Supervisor

Fire Protection

Chwalek,

Emergency Coordinator

Cifonelli, Licensing Engineer

Christiansen,

Junior Electrical

Engineer

Goodney, Electrical Engineer (Inspection Coordinator)

Gresok,

Manager

Nuclear Design

Jakubowski, Assistant Electrical Engineer

Kehoe,

Fire Training Specialist

Kamer, Fire Protection

Engineer

Lempges,

Vice President

Nuclear Generation

Mangan,

Vice President

Nuclear Engineering

8 Licensing

Main, Training Specialist

Pasternak,

Senior Nuclear Engineer

Pavel, Assistant Superintendent

Training

Perkins,

General

Superintendent

- Nuclear

Raymond,

Supervisor

Fire Protection

Roman, Station Superintendent

Sweet, Electrical Maintenance

Superintendent

Terry, Manager

Nuclear Engineering

Wilson, Systems

Engineer

Zollitsch, Training Superintendent

Nuclear

NMPC Contractors

  • J
  • E

Densford, Staff Engineer,

Gasser

Associates

Gasser,

Staff Specialist,

Gasser Associates

York, Engineer,

Compis

Nuclear

Re ulator

Commi ssion

NRC

  • R.

A.

  • J

Herman,

Senior Project Manager,

NRR

Hudson,

Senior Resident

Inspector

Luptak, Reactor

Engineer - Region I

Wechselberger,

Resident

Inspector

Oyster Creek

"Denotes

those present at the exit interview.

2.0

~Pun

oae

This inspection

was to ascertain

that the licensee

is in conformance with

10 CFR 50, Appendix R, Sections III.G, J,

and 0, including exemptions

approved

by the Office of Nuclear Reactor

Regulation

(NRR).

3.0

~Back round

10 CFR 50.48

and

10 CFR 50 Appendix

R became effective

on February

17,

1981.

Section III.G of Appendix

R requires that fire protection

be

provided to ensure that

one train of equipment

necessary

to achieve

and

maintain safe

shutdown

remains available in the event of a fire at any

location within a licensed operating facility.

For hot shutdown condi-

tions,

one train of the systems

necessary

must be free of fire damage

(III.G.l.a).

For cold shutdown conditions, repair is allowed using in

place procedures

and materials available onsite with the provision that

cold shutdown

be achievable within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of the initiating event

(III.G.l.b).

Section III.G.2 lists specific options

as follows to provide

adequate

protection for redundant trains of equipment

located outside of

the primary containment:

~

Separation

by a fire barrier having

a three

hour rating

(III'.2.a).

~

Separation

by a horizontal distance of at least

20 feet with no

intervening combustibles

and with fire detection

and automatic fire

suppression

installed in the fire area (III.G.2.b).

~

Enclosure of one train in a fire barrier having

a one hour rating in

addition to having fire detection

and automatic

suppression

installed

in the fire area (III.G.2.c).

If the protection required

by Section III.G.2 is not provided or the

systems of concern

are subject to damage

from fire suppression

activities,Section III.G.3 of the rule requires that

an alternate

or

dedicated

shutdown capability

be provided which is independent

of the

area of concern.

Any alternate

or dedicated

system requires

NRC review

and approval prior to implementation.

For situations

in which fire protection

does

not meet the requirements

of

Section III.G, however,

such protection is deemed to be adequate

by the

licensee for the specific situation,

the rule allows the licensee

to

request

an exemption

on

a case-by-case

basis.

Such exemption requests

are submitted to the

NRC for review and approval

and must be justified by

the licensee

on

a technical

basis.

4.0

Corres

ondence

All correspondence

between the'licensee

and the

NRC concerning

compliance

with Sections III.G, J and 0 was reviewed

by the inspection

team in

preparation for the site visit.

Attachment

1 to this report is

a listing

of the correspondence

reviewed.

5.0

Post-Fire

Safe

Shutdown

Ca abilit

5.1

S stems

Re uired for Safe

Shutdown

Shutdown of the reactor

and reactivity control is provided by the control

rods.

Primary coolant inventory makeup is not required

immediately after

scram but is subsequently

provided by the diesel driven fire pump and

control rod drive pump.

Reactor coolant pressure

control is maintained

by the primary relief valves.

Decay heat

removal is provided by the

emergency

condensers

in the hot shutdown

phase

and the

shutdown cooling

system,

reactor building closed

loop cooling water system,

and emergency

service water

system in cold shutdown

phase.

The diesel

generators

are

cooled

by the diesel

generator

cooling water system.

5.2

Areas

Where Alternate Safe

Shutdown is Provided

0

5.3

The licensee

has provided

an alternate

safe

shutdown capability in the

event of a fire within the control

complex (main control

room, auxiliary

control (relay)

room and cable

spreading

room) as redundant

safe

shutdown

equipment

and cabling cannot meet the requirements

of Appendix

R Section

III.G.2.

Remainin

Plant Areas

All other areas

of the plant not provided with an alternate

safe

shutdown

system

are required to be in compliance with Section III.G.2 of Appendix

R, unless

an exemption

request

has

been

approved

by the Commission.

The

licensee

requested

five exemptions

to certain provisions of Appendix

R

which were evaluated

and granted

by the Commission

by letter dated

March

21,

1983.

The exemptions

were for lack of 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> rated fire area

boundaries

and/or automatic

suppression

in the following five areas:

the

Battery Board Rooms, Battery

Rooms,

Reactor Building (upper level),

Turbine Building (upper level),

and the Control

Room.

Alternate

Safe

Shutdown

S stem

The alternate

safe

shutdown

system required for the control

complex

utilizes existing plant systems

and equipment

as identified in Section

5. 1 and two existing electrically independent

and isolated

remote

shutdown panels.

The panels

are located in separate

areas

of the plant.

The alternate

shutdown

system's

design objective is to enable

the

achievement

of the performance

goals outlined in Section III.Lof

Appendix

R as follows:

Reactivit

Control

Safe

shutdown of the reactor is performed

by manual scram of the

control rods from the control

room.

The control rods also provide

subsequent

reactivity control during cooldown.

Reactor Coolant Inventor

The licensee

has performed

an analysis to confirm that reactor

coolant

makeup is not immediately required

upon initiation of the

alternate

shutdown

system.

The analysis

shows that the core remains

covered for at least

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

assuming

maximum allowable technical

specification

leakage

(25 gpm)

and automatic initiation of the

emergency

condensers

with corresponding

reactor

vessel

isolation

(main

steam isolation valve closure)

when

Low-Low water level is

reached, in the reactor vessel.

In order to assure

the validity of

the latter assumption,

the control

room evacuation

procedures

require

both

a manual scram

and manual

reactor vessel

isolation

be performed

prior to leaving the control

room.

The main steam isolation valves

can also

be closed

by deenergizing

power at the breakers

outside the

control complex.

makeup to the reactor vessel

is available after

approximately

one hour of emergency

condenser

operation

by utilizing

the direct diesel driven fire pumps

and the existing interconnection

to the feedwater

system.

No credit is taken for the

use of diesel

generator for the reactor level makeup.

However,

once the diesel

generator

is repaired,

the makeup

can also

be provided by a control

rod drive pump.

Reactor Coolant Pressure

Control

Reactor coolant pressure

control is provided by the relief valves

and emergency

condenser

operation, with backup pressure

control

and

overpressure

protection provided by the safety/relief valves.

Reactor

Deca

Heat

Removal

Decay heat

removal in the hot shutdown

phase is accomplished

through

the

use of the emergency

condensers.

Nakeup to the secondary

side of

the emergency

condenser

s is supplied automatically

by gravity flow

from the makeup water storage

tanks.

The licensee

stated that sufficient water is available in the makeup

tanks for eight hours of emergency

condenser

operation.

Backup

makeup for long term operation of the emergency

condensers

is

provided by the condensate

surge

and storage

tanks via the condensate

transfer

pumps.

Nakeup is also available to the makeup tanks from

the direct diesel driven fire pump.

The emergency

condenser

operation is controlled from the remote

shutdown

panels

where valve

control switches

are located.

0

Decay heat

removal

in the cold shutdown

phase is provided by the

shutdown cooling system,

reactor building closed

loop cooling water

system,

and emergency

service water system.

Utilization of shutdown

cooling requires certain repairs,

manual

valve operation,

and

remote/local

pump control.

The repairs

are required to provide local

manual control of a diesel

generator,

control rod drive pump,

shut-

down cooling system pump/reactor building closed

loop cooling system

pump,

and emergency

service water

system

pump for achieving cold

shutdown.

Process

Monitorin

Direct indications of process

variables

including reactor vessel

level, reactor pressure,

reactor"temperature,

drywell temperature

and pressure,

torus temperature,

and

one train of emergency

condenser

level are provided at each

remote

shutdown panel.

Makeup

tank level indication is available at

a local indicator.

Diagnostic

monitoring ( local indication) available

includes

emergency

service

water system pressure,

reactor

building closed

loop cooling water

system temperature

and flow and

shutdown cooling system pressure.

Su

ort Functions

Other than the station batteries,

no other support functions are

immediately necessary

for achieving hot shutdown.

The diesel

generators,

diesel

generator cooling water system,

reactor building

closed

loop cooling water system,

shutdown cooling system,

and

emergency

service water system will be available to provide

necessary

support functions for the alternate

shutdown

system

following repair.

6.0

Ins ection Methodolo

The inspection

team examined

the licensee's

capabilities for separating

and protecting equipment,

cabling

and associated

circuits necessary

to

achieve

and maintain hot and cold shutdown conditions.

This inspection

sampled

selected fire areas

which the licensee

had identified as being in

compliance with Section III.G.

The following functional requirements

were reviewed for achieving

and

maintaining hot and cold shutdown:

Reactivity control

Pressure

control

Reactor coolant

makeup

Decay heat

removal

I

1

!

pl

~

Support

systems

~

Process

monitoring

The inspection

team examined

the licensee's

capability to achieve

and

maintain hot shutdown

and the capability to bring the plant to cold

shutdown conditions in the event of a fire in various areas

of the plant.

The examination

included

a review of several

drawings,

safe

shutdown

procedures

and other documents.

Drawings were reviewed to verify elec-

.

trical independence

from the fire areas

of concern.

Procedures.

were

reviewed for general

content

and feasibility.

Also inspected

were fire detection

and suppression

systems

and the degree

of physical

separation

between

redundant trains of Safe

Shutdown

Systems

(SSSs).

The team review included

an evaluation of the susceptibility of

the

SSSs to damage

from fire suppression

activities or from the rupture

or inadvertent operation of fire suppression

systems.

The inspection

team examined the licensee's fire protection features

provided to maintain

one train of equipment

needed for safe

shutdown free

of fire damage.

Included in the scope of this effort were fire area

boundaries,

including walls, floors and ceilings,

and fire protection of

openings such

as fire door s, fire dampers,

and penetration

seals.

The inspection

team also

examined the licensee's

compliance with Section

III.J, Emergency Lighting, and Section III.O, Oil Collection System for

Reactor Coolant

Pump.

7.

Ins ection of Protection

Provided to Safe

Shutdown

S stems

7. 1

Protection

in Various Fire Areas

The team reviewed the protection provided to SSSs

in selected fire areas

for compliance with Appendix

R, Sections III.G.1, 2,

and 3.

The following fire areas

were inspected:

~

Diesel Generator

Room

102

~

Diesel Generator

Room '103

~

Power Board

Room

102

~

Power Board

Room 103

~

Screen

House

The team did not identify any unacceptable

conditions.

7.2

Safe

Shutdown

Procedures

7.2. 1

Procedure

Review

The team reviewed the following safe

shutdown procedures:

~

Special

Operating

Procedure

Nl-SOP-ll, Control

Room Evacuation

(Fire), Revision

8

~

Selected

portions of Damage

Repair Procedures

N1-DRP-1 through 8,

All Revision 0.

The scope of this review was to ascertain

that the

shutdown could be

attained in a safe

and orderly manner,

to determine

the level of

difficulty involved in operating

equipment,

and to verify that there

was

no dependence

on repairs for achieving hot shutdown.

For purpose of the

review,

a repair would include installing electrical or pneumatic

jumpers, wires or fuses to perform an action required for hot shutdown.

For cold shutdown, repair is allowed using in place procedures

and

materials available onsite with the provision that cold shutdown

be

achievable within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

The team did not identify any unacceptable

conditions.

t

7.2.2

Procedure

Walk-Throu

h

The team walked through selected

portions of the procedures

to determine

that shutdown could be attained

in an orderly and timely fashion.

The team did not identify any unacceptable

conditions.

7.3

Protection for Associated Circuits

Appendix R,Section III.G, requires that protection

be provided for

associated

circuits that could prevent operation or cause

maloperation of

redundant trains of systems

necessary

for safe

shutdown.

The circuits of

concern

are generally associated

with safe

shutdown circuits in one of

three ways:

~

Common

bus concern

~

Spurious signals

concern

~

Common enclosure

concern

The associated

circuits 'were evaluated

by the team for common bus,

spurious signal,

and

common enclosure

concerns.

Power, control,

and

instrumentation circuits were examined

on

a sampling basis for potential

problems.

7.3.1

Common

Bus Concern

The

common

bus concern

may be found in circuits, either safety related or

non-safety related,

where there is a

common

power source with shutdown

equipment

and the power source is not electrically protected

from the

circuit of concern.

The team examined,

on

a sampling basis,

4160V,

480V and

125V

DC bus

protective relay coordination.

The team also examined,

on

a sampling

basis,

the protection for specific instrumentation,

controls,

and power

circuits, including the coordination of fuses

and circuit breakers.

The

licensee

plans to perform relay setting at approximately

24-month

intervals.

No unacceptable

conditions were identified.

However,

an item related to

lack of breaker

coordination identified by the licensee

was discussed

and

found acceptable

as described

below.

Breaker Coordination

The licensee

has identified two cases

where

a lack of circuit breaker

coordination exists.

By letter to NRR, dated

February

1,

1983, the

licensee

had indicated that

a possible

loss of coordination could exist

between

125

UDC feeder breakers

and the supply breakers

associated

with

Battery Boards ll and

12.

This could result in the loss of the battery

boards.

The licensee

also indicated that

no additional modifications were

required

and only certain administrative

procedures

were necessary

to lock

out certain alternate

feeder breakers

to prevent loss of the battery

boards.

The licensee

stated

and the team verified that the hot shutdown

capability is not affected

and the cold shutdown capability can

be

achieved

by using repairs which is permissible

under Appendix

R.

During the inspection,

the licensee

indicated that

a lack of coordination

had

been recently identified between

the diesel

generator

breaker

R1032

trip setting

and the

600V bus breaker

R1031.

The lack of coordination

could result in shutdown of diesel

generator

103.

However,

redundant

emergency

condenser

s are available for hot shutdown

and diesel

generator

103 which is needed

only for cold shutdown

can

be made available after

repairs permitted under the rule.

A-damage repair procedure

Nl-DRP-5

presently exists for this purpose.

Based

on the above,

the team did not identify any unacceptable

conditions.

However, the licensee

plans to review the coordination

schemes

further for

possible

improvements.

7.3.2

S urious Si nals

Concern

The spurious

signal

concern is made

up of 2 items:

False motor, control,

and instrument indications

can occur

such

as

those

encountered

during

1975 Browns Ferry fire.

These

could be

caused

by fire initiated grounds,

short or open circuits.

0

10

~

Spurious operation of safety related or non-safety related

components

can occur that would adversely affect shutdown capability (e.g.,

RHR/RCS isolation valves).

The team examined,

on

a sampling basis,

the following areas

to ascertain

that

no spurious

signal

concern exists:

~

Current transformer

secondaries

~

High/low pressure

interface

~

General fire instigated

spurious

signals

No unacceptable

conditions were identified.

7.3.3

Common Enclosure

Concern

The

common enclosure

concern

may be found when redundant circuits are

routed together

in a raceway

or enclosure

and they are not electrically

protected

or when fire can destroy both circuits due to inadequate fire

barrier penetrations.

A number of circuits, selected

on

a sampling basis,

were examined for

this concern.

No unacceptable

conditions were identified.

7.4

General

Fire Protection

Features

The team examined the general fire protection features

in the plant

provided to maintain

one train of safe

shutdown

equipment free of fire

damage.

Included in the

scope of this effort were fire area boundaries,

including walls, floors and ceilings,

and fire protection of openings

such as'ire

doors, fire dampers,

penetration

seals, fire protection

systems,

and other fire protection features.

No unacceptable

conditions were identified except

as follows:

a

~

Lack of Se aration

between

Diesel

Fire

Pum

and Electric

Fire

Pum

Control Cables

The Final Safety Analysis Report

(FSAR), Section

X.K, Paragraph

4.0,

states

that all fire protection

components

are designed

and

installed in accordance

with the applicable

standards

of the

National Fire Protection Association

(NFPA).

NFPA standards

20 and

803 require that the diesel fire pump be separated

from the electric

fire pump by a

3 Pour fire barrier.

Contrary to the above,

the diesel fire pump is not separated

from

the electric fire pump in that their control cables

are installed in

a

common tray located at elevation

261 feet of the Screen

and

Pump

House without any fire barrier separation

in between.

A single fire

>Ij I

1

I

11

event could therefore result in loss of both

pumps simultaneously.

The lack of separation

between

the control cables is

a deviation of

the

FSAR commitment (50-220/85-01-01).

Ade uac

of Fire Protection for Redundant

Safe

Shutdown Trains

in Reactor

Bui ldin

The licensee

established

several fire break zones

(FBZs) in the

Reactor Building to provide

20 feet of separation

between

the redun-

dant trains of safe

shutdown

systems

in accordance

with Appendix

R,

Section III.G.2.b.

The

FBZs are provided with automatic

suppression

and detection.

The

FBZs are generally but not completely free of

intervening combustible

in that they contained

some limited amount of

combustibles

such

as flamastic coated cables.

Smoke detection is provided throughout the Reactor Building.

However,

automatic

suppression

has not been provided through the Reactor

Build-

ing,

as clarified by Generic Letter 83-33.

By letter dated

December

22,

1983, the licensee

requested

an exemption for the lack of area

wide automatic

suppression.

Subsequently,

in an Appendix

R Lessons

Learned

Regional

Workshop held

on April 18,

1984,

NRC provided addi-

tional clarification that less

than full area wide suppression

and

detection

may also

be acceptable

provided that the licensee

performs

an evaluation to justify its adequacy

and retains

the evaluation for

subsequent

NRC audits.

Accordingly, the licensee

made the required

evaluation

and by letter dated

May ll, 1984, withdrew the above

exemp-

tions request.

The licensee's

evaluation

included technical justification for not

providing area

wide automatic

suppression

throughout the Reactor

Building and for the presence

of intervening combustibles

in the

FBZs.

The team reviewed the evaluation

and found additional

information would be required to resolve this item.

The licensee

verbally committed to provide the additional

information to

NRR.

This item remains

unresolved

pending receipt

and review of the

information and resolution of the issue

by

NRR (50-220/85-01-02).

Securit

Modifications to Fire Doors

The licensee

has provided

3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> fire rated barriers to separate

redundant

safe

shutdown trains in accordance

with Appendix

R,

Section III.G.2.a.

However, certain

3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> fire rated doors

(23

doors with Serial

Numbers:

D18,

150,

227,

116,

165, 9, 24, 52-2, 86,

105,

106,

109,

110-1,

110,

111-4,

117,

74,

112,

113,

114,

115,

52,

and 56) installed in the barriers

have

been modified by the

installation of security hardware.

These modifications

may have

degraded

the fire rating of the doors.

The licensee

could not

provide the

team with an evaluation of their fire rating.

However,

the licensee

committed to have Underwriters Laboratories

(UL)

5

12

inspect the doors

and

make

an evaluation

and to upgrade

the ratings

if and where necessary.

This is an unresolved

item pending

comple-

tion of the above licensee

action

and its review by

NRC

(50-220/85"01-03).

d.

Use of Diesel Fire

Pum

as

a Redundant

Safe

Shutdown

E ui ment

The diesel fire pump is used in many fire scenarios

as redundant

safe

shutdown

equipment

and provides

several

safe

shutdown functions.

The functions are backup

source of water for:

emergency

condenser

makeup,

reactor level

makeup,

diesel

generator cooling,

and for

emergency

service water system.

In addition, it also provides its

normal function as

a backup

source of fire protection water from the

electric fire pump.

Because

these

important functions could be lost

if the diesel fire pump is not available,

the team determined

and the

licensee

agreed that

an alternative

source of water should

be

made

available within an acceptable

time limit.

The licensee

committed to make

such

an alternative

source available

from the city water main within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

Because

redundant

means of

achieving

and maintaining the plant safe

shutdown exist using

emergency

condensers

without the diesel fire pump for at least

8

hours,

the team found this acceptable.

The licensee

accordingly

revised the procedure for a control

room evacuation fire (N1-SOP-ll)

and the operating

procedure for fire protection

system

(OP-21) to

reflect the above

commitment.

The team reviewed the revised

procedures

and found them acceptable.

This item is resolved

and

closed.

8.0

Emer enc

Li htin

10 CFR 50, Appendix R, Section III.J, requires that emergency lighting

units with at least

an 8-hour battery

power supply shall

be provided in

all areas

needed for operation of safe

shutdown

equipment

and in access

and egress

routes thereto.

The team examined the plant emergency lighting system to ascertain

the

licensee's

compliance with the above requirement.

The team did not identify any unacceptable

conditions except

as follows:

Enhancement

of Illumination Level Provided

b

Emer enc

Li htin

The licensee

has provided the required

emergency lighting in all areas

inspected

by the team

among those

areas

needed for operation of the safe

shutdown

equipment

and in access

and egress

routes thereto.

However, the

team felt that the illumination level provided by the installed

emergency

lighting may be marginal

in

some of these

areas

and additional

emergency

lighting may be desirable for safe

shutdown of the plant in the event of a

fire.

The licensee

agreed

to study the

need for additional lighting by

III

13

using operators

to walk down the safe

shutdown

procedures

and committed

to provide additional lighting wherever necessary.

This is an unr'esolved

item pending'ompletion

of the above licensee

action

and its review by

NRC (50-220/85-01-04).

9.0

Oil Collection

S stem for Reactor Coolant

Pum

s

10 CFR 50, Appendix

R,Section III.O, requires that the reactor coolant

pumps shall

be equipped with an oil collection

system if the containment

is not inerted during normal operation.

As the containment in this plant

is inerted during normal operation,

the above requirement

does not apply

to this plant.

Therefore,

no inspection

was performed in this area.

I

. ~iA

During the course of the inspection,

the team reviewed several

drawings,

fire hazard analysis, fire protection modification packages,

procedures,

and other fire protection

documents.

The scope of this review included

verification of their technical

adequacy,

appropriate

reviews,

design

and

procurement controls,

and other guality Assurance

requirements for the

licensee's fire protection

program.

Except

as noted in the previous

sections of this report,

the team did not identify any other unacceptable

conditions.

11.0 Unresolved

Items

Unresolved

items are matters for which more information is required in

order to ascertain

whether they are acceptable,

violations, or

deviations.

Unresolved

items are discussed

in Sections

7.4 and 8.0.

12.0 Conclusions

The significant findings of this inspection

are

summarized

as follows:

~

One deviation

from an

FSAR commitment to design

and install all fire

protection

components

in accordance

with NFPA Standards.

~

Three items remained

unresolved at the

end of the inspection

as

mentioned in Section

11.0 above.

Except

as above,

no other unacceptable

conditions

were identified.

13.0 Exit Interview

The inspection

team met with the licensee

representatives,

denoted in

Section 1.0, at the conclusion of the inspection

on January

25,

1985.

the team leader

summarized

the

scope

and findings of the inspection at

that time.

e

The team leader also confirmed with the licensee that the documents

reviewed

by the team did not contain

any proprietary information.

The

licensee

agreed that the inspection report

may be placed in the Public

Document

Room without prior licensee

review for proprietary information

(10 CFR 2.790).

At no time during this inspection

was written material

provided to the

licensee

by the team.

15

ATTACHMENT 1

LIST OF CORRESPONDENCE

Date

1.

08/07/80

Corres

ondents

Di se

Ippolito

NMPC

NRC

~Sub 'ect

Letter:

Fire Protection

Modification Schedule

2.

12/31/80

3.

02/13/81

4.

03/19/81

5.

05/19/81

Di se

Ippolito

NRC Staff

Di se

Di se

Ippolito

Disc

Ippolito

NMPC

NRC

NMPC

NMPC

NRC

NMPC

NRC

Letter:

Letter:

Letter:

Letter:

Fire Protection

Modification Schedule

Fire Protection

Schedular Relief

Fire Protection/

Appendix

R

Delays in Design

Information

6.

06/02/81

7.

06/09/81

8.

07/09/81

. 9.

09/30/81

Disc

Ippolito

Disc

Ippolito

Di se

Ippolito

Di se

Ippolito

NMPC

NRC

NMPC

NRC

NMPC

NRC

NMPC,

NRC

Letter

Letter:

Appendix

R

Submittal

Delay

Appendix

R III.G.3

Modifications

Letter:

Fire Brigade Training

Letter:

Remote

Shutdown

Panels

10.

09/30/81

11.

10/15/81

Denton

Disc

Eisenhut

Rhode

NRC

NMPC

NRC

NMPC

Letter:

Letter:

Fire Protection

Schedular Relief

Request for Comparison

of Current Fire

Protection

Program to

Appendix

R

12.

04/26/82

13.

06/30/82

14.

07/22/82

Vassallo

Di se

Lempges

Vassallo

Lempges

Vassallo

NRC

NMPC

NMPC

NRC

NMPC

NRC

Letter:

Fire Protection

Rule

Letter:

Informati on on III ~ G. 3

Letter:

Appendix

R III.G.3

Submittal

16

Date

15.

09/02/82

16.

09/30/82

17.

10/01/82

18.

11/03/82

19.

11/16/82

Corres

ondents

Mangan

Vassallo

Mangan

Vassallo

Mangan

Vassallo

Vassallo

Disc

Blasiak

Jirousek

Pasternak

Barrett

Randall

Wermiel

Fioravante

Polk

Eberly

Gasser

NMPC

NRC

NMPC

NRC

NMPC

NRC

NRC

NMPC

NMPC

NMPC

NMPC

NMPC

NMPC

NMPC

NMPC

NMPC

NMPC

Gasser

Subject

Letter:

Interim Response

to

Appendix

R III.G.3

Letter:

Transmittal of Alternate

Safe

Shutdown

Systems

Letter:

Transmittal

of

Appendix

R Review Safe

Shutdown Analysis

Letter:

Applicability of

Appendix

R III.G.3 and

III.Lto Nine Mile

Point Unit 1

NRC Meeting: Discussion of

Appendix

R Submittal

of October

1,

1982

York

Gasser

Casey

CYGNA

Bonner

CYGNA

20.

12/03/82

21.

12/03/82

22.

03/03/83

23.

03/21/83

24.

05/26/83

Mangan

Eisenhut

Mangan

Vassallo

Vassallo

Rhode

Vassallo

Rhode

Mangan

Vassallo

NMPC

NRC

NMPC

NRC

NRC

NMPC

NRC

NMPC

NMPC

NRC

Letter:

Letter:

Letter:

Letter:

Letter:

Automatic Depressuri-

zation

System Appendix

R

Modifications

Additional Information

on Appendix

R III.G.3

and III.L

Modification and

Alternate Safe

Shutdown

Capability to Comply

with Appendix

R

Appendix

R Exemption

Requests

Resolution to Three

Spurious

Valves

17

Date

25.

05/27/83

26.

12/22/83

Corres

ondents

Lempges

Vassallo

Mangan

Vassallo

NMPC

NRC

NMPC

NRC

Letter:

Appendix

R Exemption

Requests

Subject

Letter:

Remote

Shutdown

Panels

27.

12/22/83

28.

03/13/84

29.

05/01/84

30.

05/11/84

Mangan

Vassallo

Murley

Rhode

Mangan

Vassallo

Mangan

Vassallo

NMPC

NRC

NRC

NMPC

NMPC

NRC

NMPC

NRC

Letter:

Letter:

Letter:

Letter:

Reactor Building Fire

Break Zones

Appendix

R Lessons

Learned

Workshop

Tech Spec

Change for

Remote

Shutdown

Panels

Withdrawal of Fire Break

Zones

Exemption Request

0

31.

06/05/84

Mangan

Vassallo

NMPC

NRC

Letter:

Remote

Shutdown

Panels

Ig

E

E

sVpe.

, Q

li