Requests Review of Documentation Submitted in Instrumentation & Control Area & Confirmation That Documentation Reflects Actual Plant Design.Changes Should Be Submitted as Amends to FSAR in Timely Manner
ML17054A490
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 02/29/1984
From: Schwencer A
Office of Nuclear Reactor Regulation
To: Rhode G
NIAGARA MOHAWK POWER CORP.
Shared Package
ML17054A491 List:
References
NUDOCS 8403050370
Download: ML17054A490 (4)


Text

February 29, 1984 Docket No.:

5D-410,"

Mr. Geral d K. Rhode Senior Vice President Niagara Mohawk Power Corporation 300 Erie Boulevard West

Syracuse, New York 13202

Dear Mr. Rhode:

Subject:

Instrumentation and Controls D., IBUTION:

t Document Control ilRC PDR L

PDR iVSIC PRC LB¹2 File MFHaughey EHylton Bordenick, OELD Region I

Jordan, IE

.Grace IE, for Nine Mile Point unit z ACRS (16)

During the process of the review of documentation submitted in the instrumentation and controls area for Nine Mile Point Unit 2 (NMP-2) a number of discrepancies and items that need clarification to determine if they are discrepancies have been noted.

These concerns were identified to your staff by telephone calls in November 1983 and during meetings on January 18,

1984, and February 7 and 8, 1984.

A copy of the summary from those meetings is enclosed.

The concerns and some of the actions to be taken by NMPC are identified in the summary.

As noted, it was requested during the January 18, 1984, meeting that NMPC perform a review of the documentation submitted in the instrumentation and

, control area and confirm by letter that the documentation submitted reflects the actual plant design.

If, in fact, changes needed in the documentation are required in order for the documentation to reflect the design, marked-up or revised copies of the documentation should be included with the letter and a

confirmation that the documentation submitted previously as supplemented by the documents included by the letter, reflects the actual plant design.

Documentation provided by the letter should be submitted shortly afterwards as an amendment to the FSAR.

Major changes expected in the future should be identified in the letter.

Any changes, major or minor, should be submitted as amendments to the FSAR in a timely manner.

In order to facilitate the review of the instrumentation and controls area for NMP-2 and to meet our licensing schedule, the letter discussed above should be submitted no later than 60 days following the receipt of this letter.

If you have any questions concerning the above, please contact the licensing project manager, Mary Haughey, at (301) 492-7897.

&~pkeaX Iiga94 bp I

Enclosure:

As stated cc w/ enclosure:

Se next page DL:LB¹2/PM DL:L ¹ /BC MFHaughey:pt ASchvgncer AMI84 7-/+1184 SiOSOSO370 84aii9-PDR ADOCK 050004i0 A

PDR A. Schwencer, Chief Licensing Branch No.

2 Division of Licensing

ll

Nine Mile Point 2

Mr. Gerald K. Rhode Senior Vice President Niagara'Mohawk Power Corporation 300 Erie Boulevard West

Syracuse, Hew York 13202 CC:

Mr. Troy B. Conner, Jr.,

Esq.

Conner 8 Wetterhahn Suite 1050 1747 Pennsylvania

Avenue, H.W.

Washington, D.

C.

20006 Mr. Richard Goldsmith Syracuse Uni versi ty Col 1 e ge of Law E. I. White Hall Campus

Syracuse, New York 13210 Mr. Jay Dunkleberger, Director Technological Development Programs New York State Energy Office Agency Building 2 Empire State Plaza
Albany, New York 12223 Ezra I. Bialik Assistant Attorney General Environmental Protection Bureau New York State Department of Law 2 World Trade Center New York, New York 10047 Resident Inspector Nine Mile Point Nuclear Power Station P. 0. Box 99
Lycoming, New York 13093 Mr. John W. Keib, Esq.

Niagara Mohawk Power Corporation 300 Erie Boulevard West

Syracuse, New York 13202 Jay M. Gutierrez, Esq.

U. S. Nuclear Regulatory Comnission Region I 631 Park Avenue King of Prussia, Pennsylvania 19406

(

~

P