ML17053C875

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-410/81-10 on 810901-03.No Noncompliance Noted.Major Areas Inspected:Unresolved Items,Facility Status & Familiarization Tour for Incoming Resident Inspector
ML17053C875
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 09/23/1981
From: Feil R, Kister H, Schulz R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17053C874 List:
References
50-410-81-10, NUDOCS 8110090248
Download: ML17053C875 (14)


See also: IR 05000410/1981010

Text

U. S.

NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION I

Report

No.

50-410/81-08

Docket No.

50-410

License

No.

CPPR-112

Priori ty

Category

Licensee:

Nia ara

Mohawk Power Cor oration

300 Erie Boulevard West

S racuse

New York

13202

Facility Name:

Nine Mile Point

Unit 2

Inspection At:

Scriba

New York

NRC Personnel:

Inspection

Conducted:

Se tember

1-3

1981

R. A. Feil, Reactor

Inspector

.

D.

Sc Olz,

Re Ltor Inspector

date

date

Approved by:

H.

B.

Ki

er, Chief, Reactor Project

Section

1C, Division of Resident

and

Project Inspection

date

Fg~

dat

Ins ection

Summar

Ins ection

on

Se tember

1-3

1981

Re ort No. 50-410/81-10

b

d i

of unresolved

items, facility status

and familiarization tour for incoming resident

inspector.

The inspection

consi sted of 46 inspector-hours

onsite

and

7 inspector

hours in-office by two regional

based

inspectors.

Results:

No items of noncompliance

were identified.

Region I Form

12

(Rev. April 1977)

8ii0090248 8i0924

<

'I

R AOaCK OSOOOeiO,

P~DR

'

1

DETAILS

Persons

Contacted

Nia ara

Mohawk Power Cor oration

NMPC

E

  • J
  • G. J.
  • P.

E.

"R. A.

'R.

L.

Czuba,

QA Engineer

Dillon, QA Engineer (Site

Lead)

Doyle,

QA Technician

Francisco,

Nuclear Licensing Engineer

Norman,

QA Supervisor

Patch,

QA Technician

Stone

and Webster

En ineerin

Cor oration

SWEC

  • S.

W.

  • C. E.

"B. L.

  • M. R.
  • H. J.

"L. E.

Crowe, Assistant Superintendent,

FQC

Hilton, Superintendent

of Construction

Holsinger,

QA Engineer

Oleson, Assistant Superintendent

of Engineering

Pierre,

Chief Office Engineering

Shea,

Superintendent

of Engineering

"Denotes

those present at exit meeting.

The inspectors

conferred with other licensee

and contractor

personnel

during the course of the inspection.

Licensee Action on Previous

Ins ection Findin

s

(Closed)

Unresolved

Item (79-07-04) Dikkers Relief Valve radiographs

below code density.

The licensee

and the

NSSS

have completed the review

and disposition of the radiographs

of the twenty seven

Di kkers Safety

.

Relief Valves for Nine Mile Point Unit 2.

The results of this review and

radiographic

examination of 1787 radiographic films revealed that

717

radiographs

exhibited localized areas of questionable

density.

The

ASTM

E142-72,

Section

7, states

in part,

"One penetration

shall represent

and

area within which radiographic densities

do not vary more than -15 or +

30 percent".

The film density through the penetration

and base material

area of interest

exceeded

-15 or 30 percent for the

717 radiographs.

The

NSSS contracted

to review all of the radiographs

supplied

by Dikker's.

The conclusion of the contractor

was

( 1) The quality of the material

satisfactory

and (2) none of the density variation problems

was severe

enough to inhibit the ability of the film interpreter to evaluate

the

Dikkers radiographs.

An engineering

evaluation

was

made

and the results

are

as follows:

1.

The stress

report of the Dikkers Safety/Relief valves were re-reviewed.

There

was

no indication of any region with excessive

stress

or

inadequate

thickness.

In general,

the stresses

are well below the

prescribed

code limits.

The calculated

body wall thickness is

E

y

~

0.63"; whereas

the actual

minimum wall thickness is 1.1".

The

primary stress

at the crotch between inlet and outlet is 3,493 psi,

compared to the code allowable of 18,900 psi.

The primary stress

at

the crotch between

bonnet

and outlet is 4,524 psi

compared to

a code

allowable of 18,900 psi.

2.

The Dikker's radiographic

examination

was sufficient to provide

volumetric analysis of all component part castings.

3.

Where the radiographs

displayed density variations

beyond specification

limits, the location

on the casting is that of either substantial

extra thickness

or of rapidly changing cross section.

4.

The inlet side

and outlet side of the

Dikker's Safety/Relief valves

were tested

to 1.5 times the design

pressure

during the hydrostatic

test.

The valve operability and pressure

containment tightness

were

verified after the hydrostatic test.

5.

Each complete valve was subjected

to a series of full flow, full

pressure

steam lifting tests.

The licensee

has concluded that the results of the program review of the

radiographic film, when evaluated with other available records,

such

as

satisfactory hydrostatic tests

and performance verification tests

under

full steam pressure

and flow conditions,

confirms that the valve material

is sound; that the valves will operate

safely and reliably and that the

records

are sufficient and adequate

to determine that the equipment

meets

the code.

The inspectors

observed

work activities in progress,

completed

work and

plant status

in several

areas of the plant during general

inspection of

the plant.

The inspectors

examined work for any obvious defects or

noncompliance with regulatory requirements

or license conditions.

Particular note was taken of presence

of quality control inspectors

and

quality control evidence

such

as inspection

records,

material identification,

nonconforming material identification, housekeeping

and equipment preserva-

tion, and quality inspection

personnel

as

such personnel

were available

in the work areas.

No items of noncompliance

were observed.

~

r

.

~

Faci1 it

Status

The licensee

informed the inspectors that the facility is

31% complete.

Manpower has

increased

to 2149 manual

and 594 nonmanual.

Construction

activity continues

on cable tray installation, lighting and communication

activities,

primary containment wall rebar installation,

secondary

contain-

ment exterior wall construction,

control building wall, electrical

tunnel

walls and roof, areas of the turbine building, pipe erection for RHR

service water,

HPCS

& component cooling,

and piping in the turbine building,

suppression

pool leak chase,

NDE and repairs to bottom liner and sparger

ring, repair of biological shield wall, lake tunnel excavation,

structural

steel

erection,

HVAC installation, cooling tower construction

and assembly

of the fuel pool liner.

Inleaka

e of Groundwater into

ECCS

Pum

Pits

On August 26,

1981

the licensee

reported

a

10 CFR 50.55e

item regarding

water leakage

into the

sump pits of 'the

ECCS

pumps.

The licensee

stated

that ground water was leaking through concrete

construction

points into

the pits of the suction barrels of 5

ECCS

pumps (3

RHR pumps,

1

HPCS

pump

and

1

LPCS pump).

The possibility existed during subsequent

operation

that

a

common

mode failure of the

ECCS

pumps could occur by flooding of

the

pump compartments.

The licensee

and

SWEC stated that at elevation

163'

10" approximately

8"-9" of porous concrete

has

been

poured

on top of bedrock.

Then .a minimum

1/4" seal

grout is placed over the porous concrete

to keep water out.

Then the mat is poured

on top of the seal grout.

The problem appears

that the 1/4" seal

grout layer extends all the way to the pipe form for

the pit.

The water is seeping

up through the porous concrete

and around

the water stop.

The water is then following the line between

the seal

grout layer

and the mat bottom over to the pipe form.

Once at the pipe

form, it can

go around or vertically up and

down and leak into the pit

through joints.

The proposed corrective action

was to (1) chip out the pipe form where

leakage

occurred

and grout in a water stop or (2) to line the pits with a

metal barrel.

SWEC i ssued

a Nonconformance

and Disposition Report

No.

1911

(N&D) on

October

14,

1980 stating the details of the water leaking into the pit of

the

RHR pump.

The proposed fix was to apply an epoxy adhesive

into

cracks

and other voids in the concrete

structure for bonding or grouting.

The report stated

in Block 23 that

no related activities were affected

(N/A).

- ~

~

A

1

L

Paragraph

3.3.1 of Engineering

Assurance

Procedure

(EAP) 15.2 states:

"3.3.1

The responsible

engineer providing the disposition shall:

Comply with the requirements

established

in the Instructions

for initiating, dispositioning,

and approving

N&D's included

as

Attachment 5.2.

Review the reported

nonconformance

to determine if an evaluation

of a potentially significant deficiency (10 CFR 50.55e) is

required.

Process

potentially significant deficiencies

according

to

EAP 16.2.

Draft a "Report of a Problem" according to

EAP 16.1, if a

reported

nonconformance

is considered

to be

a significant

engineering,

design,

construction,

or guality Assurance

problem,

and if other

S&W Projects

could benefit.

Consult with the requirements

Lead Engineer to determine

if the

N&D conforms to applicable licensing

documents

(see

paragraph 3.5.2)."

On the report is

a block for Related Activities Code.

As identified

in

SWEC Engineering

Procedure,

EAP 15.2 this block,

numbered

23 is

used to:

"Enter appropriate

related activites code.

Enter N/A if no

code applies."

B Affects Licensing Documents

(see

paragraph

3.3.1)

N "Report of a Problem" is Required

(see

paragraph

3.3.1)

0 -

Evaluation of potentially significant deficiency (10 CFR 50.55e) is required

(See

Paragraph

3.3.1)

The following N&D's,

same subject

were issued.

N&D No.

and Date

1911 - 10/14/81

2004

1/29/81

2040

2/27/81

2214

6/18/81

2311

8/3/81

e

~

Each

new

N&D superseded

the previous

N&D because

of an Engineering

request for revised disposition details.

Each

N&D stated

in Block 23,

Related Activities Code:

NA.

A meeting

was held

on July 24,

1981

between

SWEC and

NMPC personnel.

Agreement

was reached that

a metal liner would be placed in the pit and

a

schedule for the fix was prepared.

On August 18,

1981,

NMPC requested

SWEC to evaluate

N&D Nos.

1911

and

2004 for reportability under

10 CFR 50.55(e)

SWEC responded

on August 21,

1981 that

a determination

was

made that the item was potentially reportable.

On that date the

5 day review requirement

imposed

by

NMPC procedures

commenced.

The

NRC was notified on August 26,

1981.

A review of this reportable deficiency revealed that

SWEC failed to

adequately

review N&Ds for reportability and to take prompt action to

report the item to

NMPC as

a potential reportable

item when the deficiency

was originally discovered.

The problem

had been identified by

SWEC

10

months prior to

a request

by

NMPC to

SWEC to review the

N&Ds for potential

reportability.

The lack of timely reviews by

NMPC and the failure to

adequately

review and report potential deficiencies

in a timely manner

by

SWEC represents

a weakness

in the management

control in this area

and

reduces

the effectiveness

of control by

NMPC over their contractor s.

Pending resolution of this program weakness

for prompt,

adequate

and

timely reviews of N&Ds by

SWEC and

NMPC for potential

reportabi lity in

accordance

with 10 CFR 50.55(e)

and

NRC guidance,

this item is unresolved.

(50-410/81-10-01)

Un uglified A

re ate Pit

The inspector

was informed that aggregate

had

been

used since

May 1979

from a source

which had not been tested

and approved

in accordance

with

SWEC Specification

S 203H.

A Noncompliance

and Disposition Report dated

8/21/81

has

been

submitted

by

SWEC for disposition of the nonconforming

aggregate.

The disposition of the problem was to accept

"as is" since

-the aggregate

used in concrete at

NMP 2 was qualified by in-process

testing in accordance

with Specification

S 203H for concrete

and there

were

no adverse effects

from the

use of aggregate

from the unqualified

pit.

In addition,

SWEC conducted

a geological evaluation of the area

in

which the unqualified pit is located.

This evaluation

concluded that the

aggregate

from the unqualified pit is similar in nature

and origin to

aggregate

currently approved for use

from 3 qualified pits presently in

use since the aggregate

is derived from the

same glacial drift deposits

and with no significant differences

in the constituents

of the petralogic

make-up.

The licensee

requested

SWEC to qualify the aggregate

in accordance

with the specification

and to provide substantiation

and document action

on past

and present

uses

and source of aggregates.

The aggregate

supplier

had provided

a letter stating that

no material

from the unqualified pit

will be used in any production pending test results.

~~

~

The inspector

expressed

the following concerns:

1)

The adequacy of pit and site storage verification of aggregate

supplies

by Niagara

Mohawk Power

Company surveillance

personnel;

2)

this length of time to identify the problem

(May 1979

July 1981)

and;

3)

resolution of issues

raised

by the licensee with reference

to the

investigation of the aggregate

problem.

This item is unresolved.

On September ll, 1981 the licensee

telephoned

the inspector to report

this problem as potential deficiency in accordance

with 10 CFR 50.55(e).

A Stop Work order for Category

1 concrete

work has

been

issued

pending

resolution of the problem and qualification of the pit.

(CDR 81-00-05).

7.

Unresolved

Items

Unresolved

items are matter s about which more information is required in

order to ascertain

whether they are acceptable

items or items of noncompli-

ance.

Unresolved

items discussed

during the inspection

are detailed in

Paragraphs

5,

and 6.

Exit Interview

The inspectors

met with the licensee's

representatives

(denoted

in Paragraph

1) at the conclusion of the inspection

on September

3,

1981.

The inspectors

summarized

the purpose

and

scope of the inspection

and the findings.

The

licensee

acknowledged

the inspector's

findings.

4L'

~

4 ~+

~

0