NRR E-mail Capture - Watts Bar Nuclear Plant Units 1 and 2 - Acceptance for Review - Request to Adopt TSTF-547, Revision 1, Clarification of Rod Position Requirements
ML17030A005
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 01/27/2017
From: Robert Schaaf
Plant Licensing Branch II
To: Gordon A, Wells R
Tennessee Valley Authority
References
CNL-16-148, MF8912, MF8913, ML16335A179, WBN-TS-16-025
Download: ML17030A005 (3)


Text

NRR-PMDAPEm Resource From: Schaaf, Robert Sent: Friday, January 27, 2017 4:21 PM To: Gordon Arent; Wells, Russell Douglas Cc: Saba, Farideh; Nadel, Jared; Edmondson, Carla; Beasley, Benjamin

Subject:

Watts Bar Nuclear Plant Units 1 and 2 - Acceptance for Review - Request to Adopt TSTF-547, Revision 1, Clarification of Rod Position Requirements (CAC Nos. MF8912 and MF8913)

Gentlemen, By letter dated November 23, 2016 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML16335A179), the Tennessee Valley Authority submitted an amendment request for Watts Bar Nuclear Plant (WBN), Units 1 and 2. The proposed amendment would revise the Technical Specifications by adoption of the changes contained in Technical Specification Task Force (TSTF) Traveler TSTF-547, Revision 1, Clarification of Rod Position Requirements, with minor variations. The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 160 hours6.667 days <br />0.952 weeks <br />0.219 months <br /> to complete. The NRC staff expects to complete this review in approximately 10 months, which is November 2017. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

If you have any questions, please contact me at 301-415-6020.

Regards, 1

Robert G. Schaaf Robert G. Schaaf Senior Project Manager, Watts Bar/Bellefonte Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8G9A Washington, DC 20555 301-415-6020 (o)

Robert.Schaaf@nrc.gov 2

Hearing Identifier: NRR_PMDA Email Number: 3299 Mail Envelope Properties (Robert.Schaaf@nrc.gov20170127162000)

Subject:

Watts Bar Nuclear Plant Units 1 and 2 - Acceptance for Review - Request to Adopt TSTF-547, Revision 1, Clarification of Rod Position Requirements (CAC Nos. MF8912 and MF8913)

Sent Date: 1/27/2017 4:20:37 PM Received Date: 1/27/2017 4:20:00 PM From: Schaaf, Robert Created By: Robert.Schaaf@nrc.gov Recipients:

"Saba, Farideh" <Farideh.Saba@nrc.gov>

Tracking Status: None "Nadel, Jared" <Jared.Nadel@nrc.gov>

Tracking Status: None "Edmondson, Carla" <cedmondson@tva.gov>

Tracking Status: None "Beasley, Benjamin" <Benjamin.Beasley@nrc.gov>

Tracking Status: None "Gordon Arent" <garent@tva.gov>

Tracking Status: None "Wells, Russell Douglas" <rdwells0@tva.gov>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 3239 1/27/2017 4:20:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: