On November 21, 2016, as a result of investigating an increased level rise in the Waste Hold-Up. Tank (WHUT), Operators identified a corresponding rise in containment sump level. A containment entry was made to investigate the source of the sump level rise and determined the source was a through wall leak in a Service Water ( SW) supply pipe elbow to the 24 Fan Cooler Unit (FCU). The leak constituted a breach of a closed system within containment. Technical Specification (TS) 3.6.1 (Containment) was entered and containment declared inoperable. TS 3.6.6 ( Containment Spray and Fan Cooler System) was entered when the 24 FCU was secured and SW to the 24 FCU was isolated. Inspections identified a through wall leak on .a SW supply pipe elbow to one of the 24 FCU water boxes.
The leak is on a 3 inch carbon steel epoxy-lined elbow.
The pipe fitting is in an ASME ISI Code Class 3, nuclear safety related piping system.
The direct cause was failure of the interior coating allowing brackish river water to corrode the carbon steel fitting. The root cause was the maintenance coating procedure requirements for post-coating inspections were inadequate. Key corrective actions included removal of the defective elbow and weld repair, recoating and re-installation.
Maintenance procedure 0-SYS-409-GEN will be revised to mandate detailed inspections and/or testing of surface preparation and applied coatings to ensure proper coverage and adhesion. The event had no effect on public health and safety.
NO:
Indian Point 2 05000-247 |
|
---|
Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000003/20240022024-08-0606 August 2024 NRC Inspection Report 05000003/2024002, 05000247/2024002, 05000286/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24171A0122024-06-18018 June 2024 Reply to a Notice of Violation EA-24-037 ML24156A1162024-06-0404 June 2024 Correction - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000003/20240052024-05-21021 May 2024 and 3 - NRC Inspection Report Nos. 05000003/2024005, 05000247/2024005, 05000286/2024005, 07200051/2024001, and Notice of Violation ML24128A0632024-05-0707 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24116A2412024-04-25025 April 2024 Annual Environmental Protection Plan Report ML24114A2282024-04-23023 April 2024 Annual Radioactive Effluent Release Report L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000003/20240012024-03-20020 March 2024 NRC Inspection Report Nos. 05000003/2024001, 05000247/2024001, and 05000286/2024001 (Cover Letter Only) ML24080A1722024-03-20020 March 2024 Reply to a Notice of Violation EA-2024-010 IR 05000003/20230042024-02-22022 February 2024 NRC Inspection Report Nos. 05000003/2023004, 05000247/2023004, 05000286/2023004, and 07200051/2023004 and Notice of Violation ML24045A0882024-02-22022 February 2024 Correction to the Technical Specifications to Reflect Appropriate Pages Removed and Retained by Previous License Amendments ML24053A0642024-02-22022 February 2024 2023 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report ML24011A1982024-01-12012 January 2024 ISFSI, Notice of Organization Change for Site Vice President ML23342A1082024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23353A1742023-12-19019 December 2023 ISFSI, Emergency Plan, Revision 23-04 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23338A2262023-12-0404 December 2023 Signed Amendment No. 27 to Indemnity Agreement No. B-19 ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23242A2772023-11-30030 November 2023 NRC Letter Issuance - IP LAR for Units 2 and 3 Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23338A0482023-11-30030 November 2023 ISFSI, Report of Changes to Physical Security, Training and Qualification, Safeguards Contingency Plan, and ISFSI Security Program, Revision 28 ML22339A1572023-11-27027 November 2023 Letter - Indian Point - Ea/Fonsi Request for Exemptions from Certain Emergency Planning Requirements for 10 CFR 50.47 and 10 CFR Part 50, Appendix E IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23100A1252023-11-17017 November 2023 Letter and Enclosure 1 - Issuance Indian Point Energy Center Units 1, 2, and 3 Exemption for Offsite Primary and Secondary Liability Insurance Indemnity Agreement ML23100A1432023-11-16016 November 2023 Letter - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Exemption Concerning Onsite Property Damage Insurance (Docket Nos. 50-003, 50-247, 50-286) ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23063A1432023-11-0101 November 2023 Letter - Issuance Holtec Request for Indian Point Energy Center Generating Units 1, 2, and 3 Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23292A0262023-10-19019 October 2023 LTR-23-0211-RI Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report-RI ML23289A1582023-10-16016 October 2023 Decommissioning International - Registration of Spent Fuel Casks and Notification of Permanent Removal of All Indian Point Unit 3 Spent Fuel Assemblies from the Spent Fuel Pit ML23270A0082023-09-27027 September 2023 Registration of Spent Fuel Casks ML23237A5712023-09-22022 September 2023 09-22-2023 Letter to Dwaine Perry, Chief, Ramapo Munsee Nation, from Chair Hanson, Responds to Letter Regarding Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23242A2182023-09-12012 September 2023 IPEC NRC Response to the Town of New Windsor, Ny Board Certified Motion Letter Regarding Treated Water Release from IP Site (Dockets 50-003, 50-247, 50-286) ML23250A0812023-09-0707 September 2023 Registration of Spent Fuel Casks ML23255A0142023-08-31031 August 2023 LTR-23-0211 Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 ML23227A1852023-08-15015 August 2023 Request for a Revised Approval Date Regarding the Indian Point Energy Center Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML23222A1442023-08-10010 August 2023 Registration of Spent Fuel Casks ML23208A1642023-07-26026 July 2023 Village of Croton-on-Hudson New York Letter Dated 7-26-23 Re Holtec Wastewater ML23200A0422023-07-19019 July 2023 Registration of Spent Fuel Casks ML23235A0602023-07-17017 July 2023 LTR-23-0194 Dwaine Perry, Chief, Ramapo Munsee Nation, Ltr Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River 2024-09-18 Some use of "" in your query was not closed by a matching "".
[Table view]Some use of "" in your query was not closed by a matching "". Category:Licensee Event Report (LER)
MONTHYEARNL-18-039, LER 2018-001-00 for Indian Point, Unit 2 Re Penetration Indications Discovered During Reactor Pressure Vessel Head Inspection2018-05-21021 May 2018 LER 2018-001-00 for Indian Point, Unit 2 Re Penetration Indications Discovered During Reactor Pressure Vessel Head Inspection 05000286/LER-2017-0042017-12-20020 December 2017 Reactor Trip Due to Main Generator Loss of Field, LER 17-004-00 for Indian Point Unit 3, Regarding Reactor Trip Due to Main Generator Loss of Field 05000458/LER-2017-0092017-11-13013 November 2017 Potential Loss of Safety Function of Secondary Containment due to Unsecured Personnel Door, LER 17-009-00 for River Bend, Unit 1 Regarding Potential Loss of Safety Function of Secondary Containment due to Unsecured Personnel Door ML17252A8662017-09-0909 September 2017 Letter Regarding a 04/26/1977 Occurrence Concerning Failure of Number 22 Main Steam Line Isolation Valve to Close to a Manual Signal Initiated by the Control Room Operator - Indian Point Unit No. 2 05000247/LER-2015-0012017-08-29029 August 2017 Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size that Results in Exceeding the Allowed Leakage Rate for Containment, LER 15-001-02 for Indian Point, Unit 2, Regarding Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size that Results in Exceeding the Allowed Leakage Rate for Containment NL-17-107, LER 15-001-02 for Indian Point, Unit 2, Regarding Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size That Results in Exceeding the Allowed Leakage Rate fo2017-08-29029 August 2017 LER 15-001-02 for Indian Point, Unit 2, Regarding Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size That Results in Exceeding the Allowed Leakage Rate for 05000286/LER-2017-0032017-08-29029 August 2017 Condensate Storage Tank Declared Inoperable Per Technical Specification, LER 17-003-00 for Indian Point, Unit 3, Regarding Condensate Storage Tank Declared Inoperable Per Technical Specification 05000247/LER-2017-0032017-08-23023 August 2017 Technical Specification Violation of Section 3.3.1 RPS Instrumentation, LER 17-003-00 for Indian Point Unit 2, Regarding Technical Specification Violation of Section 3.3.1 RPS Instrumentation 05000247/LER-2017-0012017-08-22022 August 2017 Manual Reactor Trip Due to Decreasing Steam Generator Levels Caused By Main Boiler Feedwater Pump Turbine Low Pressure Governor Valves Failed Closed, LER 17-001-00 for Indian Point, Unit 2 Regarding Manual Reactor Trip Due to Decreasing Steam Generator Levels Caused By Main Boiler Feedwater Pump Turbine Low Pressure Governor Valves Failed Closed 05000247/LER-2017-0022017-08-22022 August 2017 Auxiliary Feedwater Flow Indication Inoperable for Longer Than the Allowed Technical Specification Completion Time Due to Failure of Complete Restoration Following Calibration, LER 17-002-00 for Indian Point, Unit 2 Regarding Auxiliary Feedwater Flow Indication Inoperable for Longer Than the Allowed Technical Specification Completion Time Due to Failure of Complete Restoration Following Calibration 05000483/LER-2017-0012017-08-15015 August 2017 Violation of Technical Specification 3.7.9 Due to Ultimate Heat Sink (UHS) Cooling Tower Train Inoperability, LER 17-001-00 for Callaway, Unit 1, Regarding Violation of Technical Specification 3.7.9 Due to Ultimate Heat Sink (UHS) Cooling Tower Train Inoperability 05000286/LER-2017-0022017-08-0909 August 2017 Manual Isolation of Chemical and Volume Control System Normal Letdown to Stop a Valve Leak Resulted in an Exceedance of Technical Specification 3.4.9 Condition A Limit for Pressurizer Level, LER 17-002-00 for Indian Point, Unit 3 re Manual Isolation of Chemical and Volume Control System Normal letdown to Stop a Valve Leak Resulted in an Exceedance of Technical Specification 3.4.9 Condition A Limit for Pressurizer Level 05000286/LER-2017-0012017-07-13013 July 2017 Single Flow Barrier Access Point Found Unbolted, LER 17-001-00 for Indian Point, Unit 3 Regarding Single Flow Barrier Access Point Found Unbolted 05000247/LER-2016-0102017-02-28028 February 2017 Safety System Functional Failure Due to an Inoperable Containment Caused by a Through Wall Defect in a Service Water Supply Pipe Elbow to the 24, Fan Cooler Unit, LER 16-010-01 for Indian Point 2 Regarding Safety System Functional Failure Due to an Inoperable Containment Caused by a Through Wall Defect in a Service Water Supply Pipe Elbow to the 24 Fan Cooler Unit 05000247/LER-2016-0022017-02-28028 February 2017 Automatic Actuation of Emergency Diesel Generators (EDGs) Due to 480 VAC Bus Undervoltage Condition and Loss of Residual Heat Removal (RHR) While in Cold Shutdown, LER 16-002-01 for Indian Point, Unit 2 Regarding Automatic Actuation of Emergency Diesel Generators (EDGs) Due to 480 VAC Bus Undervoltage Condition and Loss of Residual Heat Removal (RHR) While in Cold Shutdown NL-16-108, LER 15-001-01 for Indian Point 2 Regarding Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size That Results in Exceeding the Allowed Leakage Rate for Conta2016-09-29029 September 2016 LER 15-001-01 for Indian Point 2 Regarding Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size That Results in Exceeding the Allowed Leakage Rate for Contai 05000286/LER-2015-0042016-09-14014 September 2016 Automatic Reactor Trip Due to a Turbine-Generator Trip Caused by a Failure of the 31 Main Transformer, LER 15-004-01 for Indian Point Unit No. 3 Regarding Automatic Reactor Trip Due to a Turbine-Generator Trip Caused by a Failure of the 31 Main Transformer 05000286/LER-2015-0052016-09-14014 September 2016 Automatic Reactor Trip Due to a Turbine-Generator Trip Caused by the Trip of 345kV Main Generator Output Breaker 3 due to a Failure of South Ring Bus 345kV Breaker 5, LER 15-005-01 for Indian Point 3 RE: Automatic Reactor Trip Due to a Turbine-Generator Trip Caused by the Trip of 345kV Main Generator output Breaker 3 due to a Failure of South Ring Bus 345kV Breaker 5 05000286/LER-2015-0072016-09-0606 September 2016 Manual Reactor Trip Due to Decreasing Steam Generator Water Levels Caused by a Miss- Wired Circuit Board in the Main Feedwater Pump Speed Control System, LER 2015-007-01 for Indian Point, Unit 3 Regarding Manual Reactor Trip Due to Decreasing Steam Generator Water Level Caused by a Miss-Wired Circuit Board in the Main Feedwater Pump Speed Control System 05000286/LER-2015-0062016-08-0808 August 2016 Technical SpecificatiOn Prohibited Condition Due to Two Pressurizer Code Safety Valves Discovered Outside their As-Found Lift Setpoint Test Acceptance Criteria, LER 15-006-01 for Indian Point Unit No. 3 Regarding Technical Specification Prohibited Condition Due to Two Pressurizer Code Safety Valves Discovered Outside Their As-Found Lift Setpoint Test Acceptance Criteria 05000286/LER-2014-0042016-08-0101 August 2016 Automatic Reactor Trip as a Result of Meeting the Trip Logic for Over Temperature Delta Temperature during Reactor Protection System Pressurizer Pressure Calibration, LER 14-004-01 for Indian Point Unit 3, Regarding Automatic Reactor Trip as a Result of Meeting the Trip Logic for Over Temperature Delta Temperature During Reactor Protection System Pressurizer Pressure Calibration 05000336/LER-2016-0012016-06-27027 June 2016 Turbine Driven Auxiliary Feedwater Putnp Room HELB Door Left Open, LER 16-001-00 for Millstone Power Station Unit 2 RE: Turbine Driven Auxiliary Feedwater Pump Room HELB Door Left Open 05000423/LER-2016-0032016-06-0808 June 2016 Loss of Safety Function- Supplementary Leak Collection and Release System, LER 16-003-00 for Millstone Power Station, Unit 3, Regarding Loss of Safety Function-Supplementary Leak Collection and Release System 05000247/LER-2016-0042016-05-31031 May 2016 Unanalyzed Condition due to Degraded Reactor Baffle-Former Bolts, LER 16-004-00 for Indian Point 2 re Unanalyzed Condition Due to Degraded Reactor Baffle-Former Bolts 05000247/LER-2016-0052016-05-25025 May 2016 Technical Specification (TS) Prohibited Condition Due to a Surveillance Requirement Never Performed for Testing the Trip of the Main Boiler Feedwater Pumps, LER 16-005-00 for Indian Point, Unit 2, Regarding Technical Specification (TS) Prohibited Condition Due to a Surveillance Requirement Never Performed for Testing the Trip of the Main Boiler Feedwater Pumps 05000247/LER-2016-0012016-05-0202 May 2016 Technical Specification Prohibited Condition Caused by One Main Steam Safety Valve Outside Its As-Found Lift Set Point Test Acceptance Criteria, LER 16-001-00 for Indian Point 2 RE: Technical Specification Prohibited Condition Caused by One Main Steam Safety Valve Outside Its As-Found Lift Set Point Test Acceptance Criteria 05000247/LER-2015-0042016-02-18018 February 2016 Safety System Functional Failure Due to an Inoperable Containment Caused by a Flawed Elbow on the 21 Fan Cooler Unit Service Water Motor Cooling Return Pipe, LER 15-004-00 for Indian Point 2 Regarding Safety System Functional Failure Due to an Inoperable Containment Caused by a Flawed Elbow on the 21 Fan Cooler Unit Service Water Motor Cooling Return Pipe 05000286/LER-2015-0082016-02-11011 February 2016 Automatic Reactor Trip Due to a Turbine-Generator Trip as a Result of a Fault on 345 kV Feeder W96 Tower Lines Caused by Pre-Existing Degraded Insulator, LER 15-008-00 for Indian Point, Unit 3, Regarding Automatic Reactor Trip Due to a Turbine-Generator Trip as a Result of a Fault on 345 kV Feeder W96 Tower Lines Caused by Bird Streaming 05000247/LER-2015-0032016-02-0303 February 2016 Manual Reactor Trip Due to Indications of Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to a Power Supply Failure, LER 15-003-00 for Indian Point, Unit 2, Regarding Manual Reactor Trip Due to Indications of Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to a Power Supply Failure NL-15-124, LER 15-001-00 for Indian Point 2, Regarding Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size That Results in Exceeding the Allowed Leakage Rate for Cont2015-10-0909 October 2015 LER 15-001-00 for Indian Point 2, Regarding Technical Specification (TS) Prohibited Condition Due to an Inoperable Containment Caused by a Service Water Pipe Leak with a Flaw Size That Results in Exceeding the Allowed Leakage Rate for Conta NL-13-166, Report on Inoperable Gross Failed Fuel Detector2013-12-20020 December 2013 Report on Inoperable Gross Failed Fuel Detector NL-13-038, Event Report for Discovery of a Condition That Prevented Immediate Protective Actions to Avoid Exposures to Radiation from Byproduct Material2013-02-19019 February 2013 Event Report for Discovery of a Condition That Prevented Immediate Protective Actions to Avoid Exposures to Radiation from Byproduct Material NL-12-060, Submittal of Report on Inoperable Gross Failed Fuel Detector2012-04-26026 April 2012 Submittal of Report on Inoperable Gross Failed Fuel Detector ML1101906402010-11-0909 November 2010 Event Notification Report; Subject: Power Reactor Indian Point Unit 2 NL-09-108, Submittal of Report on Inoperable Core Exit Thermocouples2009-08-10010 August 2009 Submittal of Report on Inoperable Core Exit Thermocouples ML0509600412004-12-17017 December 2004 Final Precursor Analysis - IP-2 Grid Loop ML0509600512004-12-17017 December 2004 Final Precursor Analysis - IP-3 Grid Loop NL-03-136, LER 03-03-00 for Indian Point Unit 3 Regarding Automatic Turbine Trip/Reactor Trip Due to Fault in 345kV Generator Output Breaker 32003-08-21021 August 2003 LER 03-03-00 for Indian Point Unit 3 Regarding Automatic Turbine Trip/Reactor Trip Due to Fault in 345kV Generator Output Breaker 3 ML0209104352002-03-19019 March 2002 LER 98-001-01 for Indian Point Unit 3 Re Potential Failure or Inadvertent Operation of Fire Protection Systems, Caused by Personnel Error in Design ML17252A8951979-05-25025 May 1979 Letter Reporting a 05/18/1973 Occurrence of a Pressure Transient within the Reactor Coolant System Due to the Closure of Certain Air Operated Valves in the Reactor Coolant Letdown System - Indian Point Unit 2 ML17252A8481974-02-19019 February 1974 Letter Regarding a February 1, 1974 Occurrence Where Both Door of the 80 Foot Elevation Personnel Air Lock to the Containment Building Were Inadvertently Open at the Same Time for a Period of About Thirty Seconds - Indian Point Unit. 2 ML17252A8461974-02-19019 February 1974 Letter Regarding Performance of a Surveillance Test PT-M2 Reactor Coolant Temperature Analog Channel Functional Test - Delta T Overtemperature and T Overpower - Indian Point Unit No. 2 ML17252A8471974-02-0808 February 1974 Letter Regarding an Occurrence on 1/25/1974 at the Indian Point Unit No. 2 Reactor Was Brought Critical in Preparation for Placing the Plant Back in Service Following Completion of Repairs Associated with No. 22 Steam Generator Feedwater Li ML17252A8491974-02-0606 February 1974 Letter Regarding an Occurrence Where Both Doors of the 80 Foot Elevation Personnel Air Lock to the Containment Building Were Inadvertently Opened at the Same Time for About Thirty Seconds - Indian Point Unit 2 ML17252A8501974-02-0505 February 1974 Letter Regarding an Occurrence Where a Slight Reactor Coolant System Pressure Transient Was Experienced in the Course of Placing a Reactor Coolant Pump in Service - Indian Point Unit No. 2 ML17252A8511974-02-0101 February 1974 Letter Regarding an Inspection of All Bergen-Paterson Hydraulic Shock and Sway Arrestors (Snubbers) Located in the Vapor Containment Was Performed and Two Did Not Meet the Established Criterion for Operability - Indian Point Unit No. 2 ML17252A8521974-01-31031 January 1974 Letter Regarding an Occurrence Where the Reactor Was Brought Critical Preparatory to Placing the Plant Back in Service Following Completion of Repairs Associated with the 11/13/1973 Feedwater Line Break Incident - Indian Point Unit No. 2 ML17252A8591974-01-28028 January 1974 Letter Regarding an Occurrence 01/23/1974 Where a Slight Reactor Coolant System Pressure Transient Above the Technical Specifications Limit Was Experienced in the Course of Placing a Reactor Coolant Pump in Service - Indian Point Unit No. 2 ML17252A8721974-01-18018 January 1974 Letter Regarding Analysis of Results of Monthly Periodic Surveillance Test PT-M11 (Steam Line Pressure Analog Channel Function Test) Indicated That One of the Low Steam Line Pressure Bistables Associated with High Steam - Indian Point Unit ML17252A8761973-12-28028 December 1973 Letter Regarding 12/17/1973 Analysis of the Results of Periodic Tests and Calibration Checks Relating to Pressurizer Level Indicated a Setpoint Drift - Indian Point Unit 2 2018-05-21 Some use of "" in your query was not closed by a matching "".
[Table view]Some use of "" in your query was not closed by a matching "". |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to Note: The Energy' Industry Identification System Codes are identified within the brackets {}.
DESCRIPTION OF EVENT
On November 21, 2016, while at 100 percent reactor power, Operations investigated an increase in level rise in the Waste Holdup Tank (WHUT) {WD} and identified a corresponding rise in Containment {NH} sump level. At 16:50 hours, Entered Technical Requirements Manual (TRM) 3.4.D (Containment Free Volume Leakage) Condition A (Total leakage into the containment free volume greater than 10 gpm). At 16:55 hours, entered procedure 2-A0P-Flood-1 (Flooding) due to calculated leakage into containment of approximately 15 gpm. At 17:30 hours, a Containment
- entry was made to investigate the source of the sump level rise. The Control Room was notified at 17:38 hourS, the investigation by Operations identified the source of the leak was a through wall defect in a Service Water {BI} supply pipe elbow {PSF} to the 24 Fan Cooler Unit {FCU}. Entered Technical Specification (TS) 3.6.1 (Containment)., Condition A (Containment Inoperable) due to the possibility of a loss of containment {NH} integrity. The 24 FCU was isolated and removed from service at approximately 17:38 hours. Entered TS 3.6.6 (Containment. Spray System and Containment Fan Cooler System), Condition C (One Containment FCU Train Inoperable). After completing isolation of the 24 FCU SW, TS 3.6.1 was exited. As SW is credited as a containment boundary the defect in the SW pipe was determined to be a loss of safety function requiring an 8-hour non-emergency notification to the NRC. A non-emergency notification was made to the NRC for a safety system functional failure under 10CFR50.72(b)(3)(v) by Event Notification number 52388 at 21:22 hours. The leak was recorded in Indian Point Energy Center (IPEC) corrective action program (CAP) as CR- IP2-2016-06934 and CR-1P2-2016-07271.
The SW System (SWS) {BI} is designed to supply cooling water from the Hudson River to various heat loads in both the primary and secondary portions of the plant. The ,design ensures a continuous flow of cooling water to those systems and components necessary for plant safety during normal operation and under abnormal or accident conditions. The SWS consists of two separate, 100% capacity, safety related cooling water headers. Each header is supplied by 3 pumps to include pump strainers, with SWS heat loads designated as either essential or non-essential.
The essential SWS heat loads are those which must be supplied with cooling water immediately in the event of a Loss of Cooling Accident (LOCA) and/or Loss of Offsite Power (LOOP). The essential SWS heat loads can be cooled by any two of the three SW pumps on the essential header. Either of .the. two SWS headers can be aligned to supply the essential heat loads or the non-essential SWS heat loads:
The leak was a defect in a pipe fitting that is within the ASME Section XI Code ISI Class 3 boundary. The pipe fitting leak is in a moderate energy ASME ISI Code Class 3, nuclear safety related piping system. Because the defect in the elbow was through wall and was located within the ASME Section XI boundary, it exceeded the flaw allowable limits provided per IWD-3000. Since the through wall defect was located in a welded fitting (elbow), the ASME Code Case N-513-3 could not be applied because it excludes socket welds and pipe fittings.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory .Commission, Washington, DC 20555-0001, or by intemet e-mail to U.S. NUCLEAR REGULATORY COMMISSION
CONTINUATION SHEET
The pipe elbow for the SW supply to the 24 FCU is epoxy on approximately the 76 foot elevation in containment.
next to weld of the elbow to SW supply pipe.
coated carbon steel located The through wall flaw was The Containment Fan Cooler system consists of five 20 percent capacity FCUs located inside containment. These FCUs are used for both normal and post-accident cooling of the containment atmosphere. Each FCU consists of a motor,fan, cooling coils, dampers, duct distribution system and instrumentation and controls. SW is supplied to the cooling coils of each FCU to perform the heat removal function. During normal operation, SW is supplied to all five FCUs and one or more FCUs may be operated for containment cooling. It is necessary to limit the ambient containment air temperature during normal operation to less than the limit specified in TS 3.6.5 (Containment Air Temperature).
An extent of condition review included a best effort visual inspection of all FCUs.
There,was no evidence of 'additional leakage at any other place in the 24 FCU supply or return line or at any other location in the other four FCU lines 3 inch SW supply or return lines. The potential exists for a similar condition of lining degradation on
- the remaining' spool pieces in the 24 FCU that were previously Enecon repaired..
Unit 3 is not applicable to this condition as the piping material is not similar.
Unit 3 utilizes 3 inch Schedule 40, 904L alloy stainless steel piping and does not have interior epoxy lining..
CAUSE OF EVENT
The direct cause was failure of the interior Enecon (epoxy) coating allowing brackish river water to corrode the carbon steel pipe fitting. The pipe elbow with the flaw resulted in containment out leakage in excess of 10CFR50, Appendix J limits. The root cause was maintenance coating'procedure (0-SYS-409-GEN) requirements for post-coating inspections were inadequate. A defect or holiday in the applied coating remained undetected which eventually resulted in a coating functional failure. The coating failure in turn allowed corrosion to initiate and propagate through-wall by allowing brackish river water to contact the interior of the carbon steel pipe fitting (elbow).
CORRECTIVE ACTIONS
The following corrective actions have been or will be performed under the Corrective Action Program (CAP) to address the causes of this event:
- The defective elbow was removed, code'weld repaired, recoated on the interior and reinstalled.
- Maintenance procedure 0-SYS-409-GEN will be revised to include a mandate for detailed inspections and/or testing of the surface preparation and applied coatings to ensure proper coverage and adhesion. Requirements will be added to document the specific components coated and extent of the coatings applied to each component. A requirement will be included that any changes in the scope of the components coated are to be documented and concurred with by engineering.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to to impose an information collection does not display ¤tly valid OMB control number, the NRC may Indian Point 2 05000-247
- The IPEC Site Specific Curricula for GL 89-13 Program Inspections (Qualification Card) will be updated to include specific requirements for coating and lining inspections for FCU piping.
- A detailed visual inspection will'be performed of all 3 inch FCU SW piping elbow coatings during the FCUs scheduled Preventive Maintenance.
- Procedure SEP-SW-IPC-001 will be revised to include a requirement in the GL 89-13 Program to conduct and document a 100 percent internal lining visual inspection of all 3 inch FCU piping spool pieces, when removed during future FCU cooling coil PMs.
EVENT ANALYSIS
The event, is reportable under 10 CFR 50.73(a)(2)(v)(C). The licensee shall report any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to (C) Control the release of radioactive material. This condition meets the reporting criteria because TS 3.6.1 Containment Operability was not meta The pipe flaw leakage was determined to be greater than the 10 CFR 50, Appendix J allowable leak rate. TS 3.6.1 (Containment) requires the containment to be operable in Modes 1-4. - TS Surveillance Requirement (SR) 3.6.1.1 requires visual examinations and leakage rate testing in accordance with the containment Leakage Rate Testing Program specified in TS 5.5.15. SR 3.6.1.1 leakage rate requirements comply with 10 CFR 50, Appendix J, Option B. As SW is required in an accident, the SW to the FCU would not be isolated in DBA and the piping credited as a closed system inside containment for containment integrity.
ConsequentlY, defects discovered within the FCU SW piping may adversely affect containment integrity and the ability to control releases of radioactive materkal.
The condition also meets the reporting criteria of 10 CFR 50.73(a)(2)(i)(B). The licensee shall report any operation or condition which was prohibited by the plant's TS. Dufing the previous period of operation for an unknown period of time the SW pipe contained a through wall leak that did not meet code requirements. This previously unrecognized condition required entry into TS 3.7.8 and corrective actions implemented to return.the pipe to operable. Failure to comply with the TS LCO and perform required actions is a TS prohibited condition.
PAST SIMILAR EVENTS
A review of the past three years of Licensee Event Reports (LERs) for, events that involved containment integrity due to flawed piping credited as a closed system inside containment identified two LERs. LER-2015-001-01 reported a Technical Specification prohibited condition and a Safety System Functional Failure (SSFF) due to a through wall leak on the 24 FCU motor cooler SW return line that results in exceeding the allowable leakage rate for containment. This LER is similar as the SW pipe defect was in piping credited as a closed system for containment integrity.
However, the pipe material (copper-nickel) and function (motor cooler return) are different. The direct cause was similar (pitting corrosion) but the apparent cause was different (length of time to replace the copper-nickel piping) as this LER concerns epoxy coated carbon steel. LER-2015-004 reported a SSFF due to an inoperable containment caused by a flaw on an elbow on the 24 FCU SW motor cooler return line.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to NRCFORM366A (11.2015) a '144/Wer U.S. NUCLEAR REGULATORY COMMISSION
CONTINUATION SHEET
SAFETY SIGNIFICANCE
This condition had no effect on the health and safety of the public.
There were no actual safety consequences for the event because there were no accidents or events during the degraded condition..
There were no significant potential safety consequences of this event. The leakage from the affected SW pipe was within the capability of the SW system to provide adequate SW flow to SW lOads. Current analysis for SW pipe failures are postulated to be limited to small through-wall leakage flaws as SW is defined as a moderate energy fluid system. The SW leak would eventually drain to the containment sump.
The containment sumps have pumps with sufficient capacity to remove excessive leakage and instrumentation to alert operators to a degraded condition.
The containment consists of the concrete reactor building, its steel liner, and the penetrations through the structure. The containment building is designed to contain radioactive material that might be released, from the reactor following a design basis accident (DBA). The containment building steel liner and its penetrations establish the leakage limiting boundary of the containment.
Maintaining the containment operable limits the leakage of fission product radioactivity from the containment to the environment. The DBA analysis assumes that the containment is operable such that., for the DBAs involving release of fission product radioactivity, release to the environment is controlled by the rate of containment leakage.
The containment was designed with an allowable leakage rate of 0.1 percent of containment air weight per day. Containment isolation valves form a part of the containment pressure boundary. -Two barriers in series are provided for each penetration so that no single credible failure or malfunction of an active component can result in a loss of isolation or leakage that exceeds limits assumed in the safety analysis. One of these barriers may be a closed system such as the SW piping for the FCUs. The only time containment integrity can be affected is post accident when the FCUs safety function is being performed and SW pressure for the FCU cooling piping and coils may fall below peak accident pressure. 'Mitigation of radiation release by the degraded SW pipe pathway can be by use of radiation monitors R-46 and R-53 which monitor containment fan cooling water for radiation indicative of a leak from the containment atmosphere into the cooling water. If radiation is detected, each FCU heat exchanger can be individually sampled to determine the leaking unit.
The SW for the 24 FCU can be isolated to prevent radioactive effluent releases.
During the time the FCU SW piping was degraded there was no leakage out of containment.