ML16342C277
| ML16342C277 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 07/18/1991 |
| From: | Huey F NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML16342C278 | List: |
| References | |
| 50-275-91-07, 50-275-91-7, 50-323-91-07, 50-323-91-7, NUDOCS 9108050055 | |
| Download: ML16342C277 (86) | |
See also: IR 05000275/1991007
Text
U.S.
NUCLEAR REGULATORY COMMISSION
REGION
V
Report Nos.
50-275/91-07
and 50-323/91-07
License
Nos.
DPR-80 and
Licensee:
Pacific
Gas
and Electric Company
77 Beale Str eet
San Francisco,
94106
Facility Name: Diablo Canyon Nuclear
Power Plant.
Inspection at: Diablo Canyon Nuclear Power Plant
Inspection conducted:
April 22 - June
10;
1991
Inspectors:
W. Ang, Team Leader
N. Miller, Assistant
Team Leader
J. Jacobson,
Reactor Inspector,
A. Hon, Resident
Inspector
J.
Bess,
Reactor Inspector,
RGN IV
H. Leung, Atomic En rgy of Canada,
Ltd.
(AECL)
E. Choy,
AECL
J. Hailer,
AECL
Approved:
orrest
R.
uey, Chief
Engineering Section
Inspection
Summa'
Inspection
on April 22 through June
10,
1991 (Report Nos. 50-275/91-07
and 50-323/91-07).
Areas Inspected:
An announced
special
team inspection of the Electrical
Distribution system
was performed.
Temporary Instruction 2515/107
was
used
for guidance.
Results
o~fins ection
and General
Conclusions:
The Diablo Canyon Electrical Distribution System
ap'peared
to be acceptable.
The licensee's
Engineering organizations,
and the technical
performance of
those organizations,
in general,
appeared
to be good.
The physical condition
of the plant appeared
to be good.
Weaknesses
observed
included the
violations
and unresolved
items discussed
below.
In addition, weaknesses
were
related
to poor or incomplete work and to lack of identification and timely
resolution of deficiencies.
The weaknesses
identified by the
team are
summarized
in Attachment
2 of this inspection report.
9108050055
9i500700275
pDR
ADOC)( 05 0pDR
G
Significant Safety Matters:
None
Summary of Violations and Deviations:
One violation was identified in the area of incomplete acceptance
criteria for
two Emergency
Diesel
Generator
(EDG) surveillance
procedures.
One violation
was identified in the area of EDG test failure validity determination.
The following additional
items were identified:
UNRESOLVED ITEM 91-07-01 - 2.2.2 - A documented
technical
basis for the
increased
short circuit interrupting current rating for the 4160
V ac breakers
needed
to be obtained
by the licensee
from the vendor'.
UNRESOLVED ITEM 91-07-02 - 2.2.5 - An analysis
to determine
the effects of
degrade'd
grid voltage
on the operability of MOVs and
120
V ac contactors
needed
to be completed
and any necessary
setpoint
changes
determined
by the
analysis
needed
to be implemented.
UNRESOLVED ITEM 91-07-03 - 2.3. 1 - An
FSAR change
needed
to be submitted to
NRR,
and reviewed
and approved
b'y NRR, to reflect differences
between
loads listed in the
FSAR and
EDG loads established
in licensee calculations.
UNRESOLVED ITEM 91-07-04 - 2.6.3 - The methodology
and inconsistencies
contained
in calculations
126-DC, 7/25/83,
and
1956-DC, 5/17/91, for MOVs
require further-review during future
MOV inspections.
UNRESOLVED ITEM 91-07-05 - 3. 1.3 - The licensee
needed
to perform or obtain
calculations
to establish
maximum
EDG jacket water and lube oi 1 temperatures
under
maximum design
ambient temperatures
to ensure that vendor established
limits would be met.
In addition,
an evaluation of adequacy of the high
jacket water
and lube oil temperature
response
procedures
was
needed.
Further inspection
was also required,
to determine
the adequacy
of licensee
nonconforming condition identification, evaluation
and
performance of any analysis,
and performance of any resultant corrective
action, for high EDG,jacket water
and lube oil temperature
alarms that were
experienced
during
EDG 1-1
STPM-96 surveillance testing performed in
November,
1989.
NON-CITED VIOLATION 91-07-06 - 4.1 -
EDG 1-3 radiator
door was required to be
shut
and locked but was found open.
The licensee
took prompt corrective
action
and the safety significance
appeared
to be minimal.
VIOLATION 91-07-07 - 4. 1 - Acceptance criteria contained
in one
surveillance test procedure
did not fully implement Technical
Specifications
surveillance
test reouirements.
Two other surveillance
procedures
contained
poorly written data
sheets
with unclear acceptance
criteria and were
considered
by the
team
as
a
WEAKNESS.
-3-
VIOLATION 91-07-'07 - 4.1;1 - Additional example - Procedure
STP-V302,
Revision 1, allowed
EDG air start system
check valves to leak 30 psig
in'0
seconds.
No documented
technical
basis existed for the acceptance
criteria.
The licensee
needed
to establish
an appropriate
leak rate
and
a documented
technical
basis for the leak rate.
NON-CITED VIOLATION 91-07-08 - 4.6 - Battery Charger
11 had
slightly above
the acceptance
criteria during performance of preventative
maintenance
on April 18,
1991
and
was not identified in an appropriate
non-conforming condition report.
However, the acceptance
criteria was
conservative,
the item had minimal safety significance,
the licensee
took
prompt corrective action,
and it appeared
to be
an isolated case.
VIOLATION 91-07-9 - 5.2 -
EDG l-l did not start,
get to rated
speed
and
voltage
and load within the
10 second
Technical Specification
time limit
during the March 7,
1991 Unit
1 loss of offsite power event.
The failure was
considered
an invalid failure, although the cause
had not been definitely
determined,
contrary to Technical Specification 4.8. 1. 1.1.2.a
and Regulatory
Guide 1.108.
EXECUTIVE SUMMARY
DETAILS
TABLE OF
CONTENTS
PAGE
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
BACKGROUND, OBJECTIVES
AND METHODOLOGY
ELECTRICAL SYSTEMS
2. 1
Offsite Grid and
12
kVac Systems
2.2
4160
V ac Class
lE System
2.3
Emergency
Diesel
Generators
2.4
480
V ac Class
1E System
2.5
120 V=ac Class
1E System
2.6
125
V dc Class
1E System
2.7
Protection
and Coordination
2.8
Containment Penetrations
2.9
AFW Electrical
Syste~
MECHANICAL SYSTEMS
3.1
Diesel
Generators
and Auxiliary Systems
3.2
Heating, Ventilation and Air Conditioning System
3.3
Power
Demand for Major Loads
3.4
System
EQUIPMENT TESTING,
SURVEILLANCE AND MAINTENANCE
4.1
Diesel
Generator Testing
4.2
Relay Calibration Program
4.3
Setpoint Control
Program
4.4- Circuit Breaker Testing
4.5
Fuse Control
4.6
Charger
and Inverter Testing
4.7
Battery Testing
4.8
Equipment
Walkdown Inspection
4.9
Equipment Modification Review
ENGINEERING AND TECHNICAL SUPPORT
5.1
Identification of Nonconforming Conditions
5.2
Review of NCRs and Root Cause Analysis
5.3
~ Control of Vendor and Industry Information
GENERAL CONCLUSIONS
UNRESOLVED ITEMS
EXIT MEETING
4
~
7
11
14
16
17
19
19
20
20
21
24
25
25
25
25
29
29
29
30
30
31
31
33
33
33
34
35
35
36
36
Attachment
1, Persons
Contacted
Attachment 2, Inspection
Findings
37
38
0
EXECUTIVE SUMMARY
A, Nuclear Regulatory
Commission
(NRC) team conducted
an electrical
distribution system functional inspection
(EDSFI) at the Diablo Canyon Nuclear
Plant.
The inspection
was conducted
by personnel
from Region
V, Region IV,
the Office of Nuclear. Reactor Regulation
(NRR), and contractor
persohnel
from,
Atomic'Energy of Canada,
Ltd (AECL) from April 22 through June
10,
1991.
The
NRC team evaluated
adequacy of the design
and implementation of the
electrical distribution system
(EDS),
and the adequacy of associated
engineering
and technical
support.
The specific methodology is discussed
in
the next section of this report.
STRENGTHS:
There were
a number of strengths
noted
by the
team during the inspection.
For
example:
Engineering organizations
had reviewed findings of EDSFI inspections
at
other plants,
and
had aggressively
evaluated
the applicability of these
issues,
and initiated .corrective actions,
where necessary.
In general,
Engineering
appeared
to be technically competent
as
demonstrated
by the many calculations
generated
in'esponse
to team
questions.
An aggressive
vendor interface
program
had
been
implemented
to maintain
up-to-date
information on equipment installed in the plant.
E~n ineering Meaknesses
The following items were
some of the weaknesses
identified by the
team that
were considered
to demonstrate
poor or incomplete. technical
work and also
indicated
a weak
sense
of ownership of problems.
The 4160
V ac second
level undervoltage
setpoint
was set
such that 480
V ac
motor operated
valves
(MOV) and
120
V ac contactors
could not be
shown
to be operable at voltages just above the undervoltage trip setpoint.
The l.icensee's
engineering
organization
had not provided technical
direction or issued instructions
to the operations
organization
to ensure
continued operability during degraded
grid conditions.
In response
to
the
teams
concern
regarding
the continued operability of the
MOVs and
motors,
procedural
requirements,
to manually transfer to the
EDGs when the
trip setpoint
was approached,
were issued
by the licensee
during the
inspection.
Engineering
review, in response
to an
NCR, did not result in a
documented
technical
basis for the increased
4
KV IE breakers
short
circuit current ratings.
This occurred despite
the problem being caused
by
a previously supplied incorrect increased
rating for the
same breakers.
weakness
in the licensee's
calculation performance,
review and approval
process
was noted.
Many inaccuracies
in the load flow, voltage drop,
short circuit, etc., calculations
were noted that required reanalysis.
Similarly, non-conservative
assumptions
were noted in the
EDG fuel oil
consumption analysis.
The
EDG system design
basis
review was completed without identifying the
lack of a technical
basis for, nor confirmation of the adequacy of, the
air start
system
leakage criteria.
Three
EDG surveillance
procedures
contained
acceptance
criteria which
only partially implemented
the Technical Specification requirements.
Review of data did not identify EDG performance
outside of these
Technical Specification requirements.
Therefore,
EDG operability was not
considered
a concern.
The licensee
is implementing
changes
to the
procedures.
PROBLEM IDENTIFICATION AND TIMELY RESOLUTION
The following are
some of the weaknesses
identified by the
team in the
licensee's
problem identification and resolution
process
and implementation.
Evaluation of the validity of two fai lures of the emergency
diesel
generator
(EDG) were not performed appropriately,
contributed to by
the misquoting of Regulatory
Guide 1. 108.
During surveillance tests
on November
16,
1989, high temoerature
alarms
were received for jacket water temperature
and lube oil temperature.
However, the problem conditions
were not formally documented
and evaluated
by Engineering,
A fai lure of the inverter ripple voltage to meet acceptance
criteria was
not formally documented.
A failure to follow the procedure
to lock the
EDG radiator door was not
'formally documented within a week of the identification of the problem.
Since
an
NRC team inspection in 1988,
the minimum required
amount of EDG
fuel oil stored
on site
has not been
documented
in Technical
Specifications,
but in
a Justification for Continued Operation
(JCO)
supported
by calculations.
Although the licensee
agreed
in 1988 that
the appropriate
fuel oil volume required for operability should
be
included in Technical Specifications,
the issue
has
not been resolved in
a timely manner.
The licensee
stated
that the issue
would receive
increased
management
attention
as
a result of the concerns
identified in
this inspection.
CONCLUSIONS
In general,
the design of the
EDS and associated
systems
at Diablo Canyon
appeared
acceptable.
The team did not find any immediate safety/operability
concerns.
The team did not find any broad
scope
programmatic
breakdowns.
1.0
Background,
Objectives,
and Methodolo
Previous
NRC inspections
at other utilities have observed that the functionality
of safety-related
systems
were compromised
as
a result of design deficiencies
introduced during initial design
and subsequent
design modifications of the
electrical distribution system
(EDS).
Consequently,
the
NRC initiated
EDS
functional inspections
to assess
the, capability of the
EDS to perform their
intended functions during all plant operating
and accident conditions.
The two main objectives of the Diablo Canyon
EDS team inspection
were (1) to
assess
the capability of the
EDS to perform its intended functions during all
plant operating
and accident conditions,
and (2), to assess
the capability
and
performance of the licensee's
engineerina
and technical
support organizations
in providing engineering
and technical
support.
In preparation for the inspection,
the team reviewed Diablo Canyon
FSAR and
Technical Specification requirements
and available probabilistic risk
assessment
information.
The team also reviewed both plant specific
and
industry historical information such
as
NRC Information Notices 91-06
(EDG
Lock-out), 91-29
(EDS Deficiencies),
NRC inspection reports,
Licensee
Event
Reports,
and
so forth.
The team selected
Bus
"G" as the inspection
sample
load path.
However,
because
of the
EDS system interaction
and the generic
nature of design,
installation, modification, testing,
and.other
processes,
the team also
inspected
many activities associated
with the other
two safety related
buses.
The team reviewed calc'ulations
and associated
documents
to ensure that
electrical
power of acceptable
voltage, current,
and frequency would be
available to safety-related
equipment
powered
from the station
EDS.
The
review included portions of the onsite
and offsite
EDS including the station
startup
and auxiliary transformers,
the
12
kV system,
the 4160
V ac Class
1E
system,
the emergency
diesel
generators
(EDG), the 480
V ac Class
lE system,
the
120
Y ac Class
1E system,
the station batteries,
and the
125
V dc Class
1E
systems.
The team also reviewed
the mechanical
systems
which interface with
the
EDS.
The
team conducted
walkdowns,
and inspected
maintenance,
calibration,
and surveillance
activities
and records for the above mentioned
systems.
In addition,
the
team reviewed selected
modifications,
nonconformance
reports,
and
LERs to assess
the capability and performance of
the licensee's
engineering
and technical
support organizations.
The
team verified conformance with General
Design Criteria
(GDC)
17 and 18,
specifically,
and
10 CFR Part 50 Appendices
"A" and "B", as appropriate.
The
team reviewed plant Technical Specifications,
the Final Safety Analysis Report,
and appropriate
Safety Evaluation Reports
to verify that technical
requirements
and licensee
commitments
were being met.
2.0
El ectrica~lS
stem
2.1
Offsite Powe~rSn
lg
Two separate
and independent offsite transmission
systems
(500
kV and
230 kV) provide power to the Diablo Canyon Nuclear
Power Plant
(DCPP).
The
main generator
output, operating at 25
kV during normal operations,
provides
power to the 500
kV switchyard via
a generator
disconnect
switch and main-
generator
transformer.
The normal operating
power for both the safety
and
. the non-safety unit auxiliaries
is provided by the main generator.
The 230
kV system provides
power =to the unit auxiliaries during unit startup
and unit
shutdown
modes.
On
a- loss of the
230
kV system,
coincident with a
LOCA, offsite power could
also
be provided
by the
500
kV power supply.
A review of the system design
indicated that restoration of the
500
kV connection for back feeding to the
safety .related unit auxiliary loads
could take
30 minutes or longer due to
the time required for generator
voltage decay during coastdown
and the time
required for the switching process.
However, licensee
procedures,
training
and past operational
experience
indicated that the
500
kV power supply could
be. restored
in approximately
30 minutes.
2.1.1
Brid Stabil i~tand History
The licensee's
Power Control Department
operated
the transmission
system with
an on-line, real time, energy
management
system
(EMS).
Power load flow
analysis
was performed.
Daily operations
were maintained within stability
limits.
The licensee's
Transmission
Planning
Department
performed
power
system transient stability analyses
for existing and'uture
configurations of
the system.,
A summary of the 1'icensee's
system stability studies
and several
sample
cases
presented
by the licensee
were reviewed
by the
team.
The stability studies
demonstrated
that tripping of both
DCPP uni ts did not appear
to significantly
affect grid stability nor degrade
the availability of the
230
kV power supply-
to the station.
System frequency
was normally maintained well above
58 Hz.
System voltage
was maintained
between
520
kV and
546
kV at the
500
kV system.
The 230
kV system voltage
was maintained
between
227.5
kV and
232 kV.
The
DCPP offsite power supplies. appeared
to be reliable
and stable.
2.1.2
Sur~e Protection
The 500
kV and
230
kV systems
were designed with provisions for lightning
impulse voltage
and switching surge protection.
The transmission
lines were
protected
from direct lightning strikes using overhead
ground wires.
Lightning arrestors
were installed
near
each
high 'voltage bushing
on the'500
kV - 25
and
on the
230
kV -
12
kV standby startup
transformers.
,Lightning rods were installed
on the turbine, auxiliary and
fuel handling buildings,
as well
as
on containment structures.
Motors on the
12
kV system
were designed
with
a surge protector
on each
phase.
The
25
kV - 4
kV and the
12
kV - 4kV transformers
had totally 'enclosed
terminals.
Connections
were
made with. non-segregated
phase
bus duct.
The
transformer terminals
and connections
were not exposed
to direct lightning
strikes.
Any voltage
surges
on the
500
kV and
230
kV systems
would be
absorbed
by the lightning arrestors.
Any remaining propagating
voltage surge
wo'uld'e dampened
by two intervening transformers.
The design
and implementation of the offsite power supply voltage protection
schemes
and the overcurrent
schemes
appeared
to be acceptable.
2.!.3
M
g
A lii yT
f
2. 1.3. 1
Transformer Capacity
had two unit auxiliary and two standby star t-up transformers
per reactor
unit.
The maximum ratings of the unit auxiliary transformers
were
56
NVA and
40 NVA, respectively;
the maximum ratings of the standby start-up transformers
were
75
NVA and
40 MVA, respectively.
The team reviewed the loading
on each of
the transformers
with respect
to various reactor operating conditions,
including normal start-up,
shutdown, full load operation,
and
LOCA conditions.
The maximum transformer
loads
appeared
to be within the nameplate
rating of-
the transformers.
The licensee's
load flow and voltage drop calculation
96-DC, Revision 2, dated
4/29/91, including Volume 3, Revision 1, dated 8/25/89,
was reviewed
by the
team to evaluate
transformer. and,bus
loadings.
The calculation
used
a Sargent
II Lundy (SILL) Engineers
computer
based
program, Electrical
Load Monitoring
System - AC (ELMS-AC).
The
ELMS-AC program
was verified and validated
(V&V)
by
SILL and the
VSV documented
in
a letter from SILL to the licensee
dated
7/14/86.
A number of discrepancies
in the loading
used
by the licensee for
various safety
and non-safety
buses
were noted during the team's
review of the
calculation.
For example,
the loadings for the
same
bus
on different pages of
the report were different.
Loading
on one safety load train included
some of
the loads
from another safety load train.
The total loading
on
a bus did not
equal
the
sum .of all the feeder
loads
on the
same
bus.
The discrepancies
appeared
to have
been
caused
by the modeling of the station
EDS that was
used
as input to the
ELMS-AC computer
program.
The noted discrepancies
had the
potential for affecting the results of the shor t circuit calculations
(calculations
96A-DC and 968-DC),
and the voltage drop and load flow
calculations
(calculation
96-DC volumes
1 and 2).
As
a result of the discrepancies
identified by the team,
the licensee
reviewed
the input model of the
EDS connections
used in the
ELMS-AC load flow and
voltage drop program
and re-performed
th'e calculations.
Revision
3 of the
subject calculation
was provided to the
team at the
end of the inspection
period.
The
team did not have sufficient time to review the results
in
detail.
The licensee
stated
that the re-analysis
did not significantly change
the results.
A brief review of the results
by the teaoi appeared 'to confirm
the licensee's
conclusion.
Although the licensee
concluded that the modeling discrepancies
for the load
flow and voltage drop analysis
did not significantly change
the results,
this
could not be confirmed without the licensee
performing the re-analysis,.
This
was considered
to be
an example of poor design
performance
and review, in
,that the analysis
should not have
been
performed with the modeling
inaccuracies
and could not have
been readily reviewed with the modeling
~ inaccuracies
identified by the team.
2. 1.3.2
Transformer Protection
The unit auxiliary
and standby startup transformers
were protected
by
instantaneous
and time overcurrent relays,
sudden
pressure
relays,
and
differential current relays.
The team selectively reviewed the overcurrent
protection curves of the transformers
(incoming and load center feeders),
4160
Y large motor protection curves,
and the overcurrent protection curves of
the emergency
diesel generator.'he
protection
appeared
to have
been properly
selected.
Protection
and coordination of the offsite power supply incoming breakers,
the
unit auxi 1.iary and standby start-up transformers,
and the 4160
Y buses
appeared
to have
been acceptably
designed
and implemented.
2. 1.4
Transfer of the Loads
From the Unit Auxil~iar
2. 1'.4. 1
12
kV Automatic Transfer
The Diablo Canyon
EDS design
included
a provision for automatic transfer of
each
12
kV non-safety
bus
(D or E) from the unit auxiliary transformer
supply
to the standby start-up transformer
supply upon
a unit trip, auxiliary
transformer protective relaying trip, or 500 kV-generator breaker trip.
A
fast
bus transfer would occur first, if both normal
and alternate
supplies
were in synchronism.
Otherwise,
a slow bus transfer would occur.
2.1.4.2
4160
V Automatic Transfer
On
a unit trip or
a 4160
V bus undervoltage condition, without a
LOCA, any
4160
V bus fed from the auxiliary transformer
would be automatically slow
transferred
to the standby start-up transformer,
provided the start-.up
source
was energized.
The 4160
V loads
remained
connected
and would not trip.
On
a
4160
V bus undervoltage condition,
a slow bus transfer would occur when the
bus
voltage dropped
to
25% of rated voltage or 4 seconds
following a transfer
.
initiation signal, whichever
came first.
The team's
review of DCPP's transfer
schemes
generated
questions
that
necessitated
licensee
performance of further analysis.
In response
to team
questions,
the licensee
performed
an analysis
to verify that the load center
transformer feeder
breaker would not trip on transformer magnetizing current
inrush following transfer.
The licensee
also performed
an analysis
to verify
that the start-up transformer
incoming feeder breaker to the 4160
V safety
buses
would not trip on slow transfer.
Based
on the team's
review and licensee
analysis
and response
to the team's
questions,
the design of the slow transfer
scheme of the 4160
Y safety
buses
appeared
to be acceptable.
Class
IE 4160
V AC System
2.2
The 4160
V Class
1E system of each of the two units included three separate
and
independent
buses.
Each-bus
consisted
of an assembly of 250
MVA class
metal-clad switchgear.
The s'stem
served various safety-related
motors larger
than
350
HP and 480
V load center
transformers.
Safety'related
loads
were
assigned
to the buses
such that
a minimum. of two buses
could provide
power to
the minimum required safety related
loads in order to mitigate the
consequences
of a design
basis
accident.
s
The 4160
V system
was high resistance
grounded at the neutral
connections 'of
the unit auxiliary and startup transformers.
Ground fault detection
was
provided
on every feeder.
However,
the
EDGs were ungrounded
and thus the
4160
V safety system would be ungrounded
when powered solely by the
EOGs.
The
licensee's
ground detection
system
and the effects
on the ungrounded
EDG's are
further discussed
in Section 2.3.2.of this report.
2.2.1
4160
V SEstem
Short Circuit Level
The previously identified
ELMS-AC computer
program
was also
used in the
OCPP
short circuit calculation,
96A-DC, Revision 0, dated 4/19/91,, and voltage drop
calculation,
968-DC, Revision 0, dated 4/19/91.
The team reviewed the
calculations
and
had the following observations:
(a)
When all the station auxiliaries are
powered
by either the unit auxiliary
transformer or by the start-up
standby transformer,
and with the system
pre-fault voltage at the high range
(1.054
pu or 4385 V), the system three
phase
short circuit fault current at the 4160
Y safety
buses
would be
higher than the
250
MYA circuit breaker interrupting rating of 32.9
kA at
4385
Y.
(b)
During routine
EDG testing, while running in parallel with the unit
auxiliary transformer supply,
and with the generator
output pre-fault
voltage at its maximum voltage of 1.05 pu, the system short circuit fault
current could
be
as high as
37 kA.
However, Surveillance Test Procedure
(STP) N-9A, Revision 20, dated 4/10/91,
"Diesel
Engine Generator
Routine
Surveillance Test," limited the generator
output voltage to 1.0
pu during
the
EOG testing to avoid excessive
short circuit fault current
on the
4160
V buses
and to maintain minimum allowable operating voltage
on the
4160
V and 480
V bqses.
(c)
Calculation
96A-DC analyzed
system fault current duties
and voltage
conditions.
The
1990 system short circuit fault levels of both offsite
power supplies
were
used in the calculation.
The calculation did not
provide any allowance for future system expansion.
In addition,
the
calculation
used cable resistance
at 90 C.
While the latter provided
conservative
results
in the voltage drop calc'ulation,
non-conservative
results
were obtained
in the short circuit calculation.
To obtain
conservative
results for both calculations,
the short circuit fault
current calculation
and voltage drop calculations
should
have
been
performed separately
with their corresponding
conservative
input data.
The licensee
acknowledged
the team's
concerns
regarding
the calculations
but, pointed out that the calculations
showed that sufficient margin was
available to compensate
for the effects of the inaccuracies
that may be
4
caused. by the relatively non-conservative
input.
The team agreed with
the licensee's
evaluation
but noted that the margin could be affected
by
the licensee's ability to upgrade
the rating for the 4 kV breakers
(see
discussion
regarding
4
kV rating upgrade
in the next section of'this
report).
(d)
The
ELMS program did not evaluate
the 4160
V and 480
bus
voltages
and motor terminal voltage during motor star ting.
The licensee
informed the
team that the transient voltage profile analysis
would be
included in calculation
96C-DC, which would be completed
by the
end of
this year.
The team
saw
no immediate safety concerns
in this regar d and
considered
the licensee's
schedule for the mentioned analysis
to be
reasonable.
- .I.I
I 44~i
During the first week of this
team inspection,
the licensee
was in the process
of resolving
a nonconforming condition identified by
NCR DCO-90-EN-032
regarding
the
4
kV breakers.
The
NCR stated,
"During the procurement of
replacement
4
kV circuit breakers,
General Electric discovered
that
a previous
rating for short circuit (provided by General Electric)
may have
been
incorrect.
The actual
worse case fault current
may be closer to the equipment
rating then previously analyzed."
The licensee's
evaluations
and corrective
'ction for the
NCR were reviewed.
The licensee's
evaluation of the
indicated that during the Independent
Design Verification Program for DCPP,
.
verification of the adequacy of the
4
kV switchgear identified an interrupting.
requirement of 42,600
amperes for buses
F,
G, and
H, which was significantly
higher than the published interrupting rating of 33,100
amperes.
GE was
contacted
by the licensee
at that time and
GE provided
a letter, dated
February 25,
1983, to the licensee
to certify the breakers
to
a higher rating
of 45 kA.
In 1990,
the licensee
attempted
to procure similar replacement
circuit breakers
from GE.
GE subsequently
notified the licensee
that the
1983
"letter was
based
upon the interpretation of test results
on the originally
supplied breakers,
and'hat this interpretation
may represent
best
case
scenario
and
may not be representative
of all cases."
The breakers
were then
rerated
to an interrupting rating of 35
kA by GE.
Neither
GE letter included
test results,
nor did they include
a report- on the results of testing
sufficient to demonstrate
the acceptability of the reratings.
The licensee,
at that time, met with the vendor
and visited its facilities, and accepted
the
rerating to 35 kA.
The
team questioned
the acceptance
of the rerating
due to the lack of
documentation
of the technical
basis for the rerating.
Both the vendor
and
the licensee
attempted
to provide the
team with reports to show the basis for
the rerating.
Neither report provided adequate
technical
basis for the
rerating.
The team concluded
that the licensee
needed
to obtain
a documented
technical
basis for the increased
4
kY circuit breaker interrupting current
rating for the following reasons:
a)
The system short circuit fault level at the 4160
V safety
buses
was
higher than the
ANSI C37.06 interrupting rating for the
250
NVA breaker,
and under certain operating conditions,
the fault level
was also higher
than the
35
kA increased
rating.
b)
The manufacturer
had previously, in 1983, certified the
same breaker for
45
kA interrupting rating,
and subsequently
in 1990 admitted that -it was
an error and reduced
the interrupting rating to 35 kA.
Both
certifications were:provided in letters that contained
no technical
basis
for the upgrade rating.
The licensee
agreed, to further attempt to obtain the technical
basis for the
increased
4160
V safety
bus circuit breaker rating and provide'he technical
basis
to the
NRC for further review.
Pending licensee
action
and
NRC review
of that action,
the issue was'*identified as Unresolved
Item 50-275/91-07-01.
2.2.3
Protective
Re~la in
The
team reviewed
a sample of 4
kV motor overcurrent relay settings,
and the
protection coordination of the safety buses.
The settings
were based
on
normal running, short time overload,
and motor acceleration.
Motor
overcurrent relays
were coordinated with the upstream protective devices
and
the thermal
damage characteristic
of the motor.
The team also reviewed the
incoming feeder overcurrent protection trip setpoints
to verify that the
incoming feeder breaker
would not trip during slow transfer.
The protection
and coordination of the 4160
V motor fe'eders
and the- incoming
supply feeders
appeared
to be acceptable.
2'.4
Cable Sizina
All the safety related
4160
V loads
were located outside containment.
Standard
5
kV class,
133% insulation level cables,
per
ICEA S-68-516 or ICEA S-66-524,
were used.
The licensee
stated that the cables
were sized in accordance
with
ICEA P46-426/IEEE
S-135 standard
and the thermal electrical
design
standards
of PGIEE.
However,
no specific design
procedure
or calculations
to ensure that
the cables
had
been properly selected for their design functions were used.
Utilization of ICEA and the
PGImE standards
for cable sizing appeared
to be
acceptable if properly performed.
The licensee
agreed to perform an analysis
on selected
samples
to verify that the cables
had
been properly selected
and
sized with respect
to thei r voltage drop, short circui t current temperature
rise,
induced voltage along the cable shield,
and
so forth.
2.2.5
Degraded
Voltage
and Loss of Voltage
R~ela
s
The team reviewed settings
and the basis for settings
associated
with first
level undervol tage
pr otection relays,
second
level undervol tage protection
relays, startup
bus permissive relays,
and associated
timers.
First level
protection consisted
of two relays,
one
an instantaneous
relay,
and
one
an inverse
time relay.
The inverse
time relay provided
a delay of
approximately
25 seconds
at 2583 volts and
4 seconds
at 0 volts.
Both relays
were required to be activated
to avoid spurious actuation.
No adverse
findings were identified by the
team in relation to first level relays.
The startup
bus permissive relay was
used to detect
the availability of
voltage
on the startup
bus, during
a slow bus transfer of vital loads
from the
station auxiliary bus,
which was the
normal
supply for the Class
1E loads.
10
This relay was set
between
3342
and
3412 volts and
had
no associated
technical
specification.
The team noted that the startup permissive relays
were set
approximately
300 volts lower than the second'evel
protection.
With such
an arrangement;
loads could
be successfully
transferred
from .the
unit auxiliary bus to the startup
bus
and then disconnected
by actuation of
the second
level undervoltage.
The licensee
explained that this condition was
not credible
due to the fact that the degraded
grid condition would have 'to
occur within the
20 second
period after the transfer occurred,
and before the
actuation of the second
level undervoltage protection.
If the degraded
grid
condition was preexisting,
the second level undervoltage
would have already
actuated
and transferred
the vital loads to the, diesel
generators.
The
licensee
assessment
appeared
to be adequate.
At DCPP,
degraded
grid protection
was provided
by the second
level
relays,
which have
a minimum technical specification setpoint of
3600 volts.
Associated with these relays
were two timers;
a
10 second timer
for starting the diesel,
and
a
20 second
timer for. load shed.
The
10 second
diesel start timer allows for short v'oltage transients
and is in effect
for both
LOCA and
non-LOCA situations.
The adequacy of the second
level
(degraded grid) relay technical
specifications
and calibration setpoints
was reviewed to ensure that adequate
voltage would be available to all Class
1E loads at
a bus voltage just above
the point of relay actuation.
The second
level undervoltage
relays
were set
to activate
between
3682
and
3710
V ac.
The licensee
stated that the
adequacy
of this setpoint
was
under
review and
had
been
documented
in guality
Problem Report
dg0008201
dated January
22,
1991.
This document stated that,
if 4160
Y ac
bus voltage degraded just above
the relay setpoints,
480
V ac
motors required for accident mitigation could trip on thermal
overloads.
The
licensee
analysis
also stated that the degraded
grid condition would have to
be sustained for over 30 minutes before the motor tripping could occur.
Consequently,
the licensee
had re-sized
the thermal
overloads
to prevent
tripping on thermal overload.
However,
the licensee
had not performed
a
formal calculation to verify the operability of the
120 volt control circuits,
nor for evaluating
the effects of a postulated
degraded
voltage
on 480 volt
motor operated
valves.
Although the licensee
was planning to ra'ise
the
setpoints
to
a level that would ensure
operation of all Class
1E equipment,
no
interim actions
had
been
taken to ensure
equipment=operability.
As
a result
of this concern,
the licensee
issued
a change to Emergency
Procedure
EP-E-O,
to manually start the diesel
generators
and separate
from the grid should the
voltage fall below
a newly determined
minimum value.
Pending further licensee
evaluation
and performance of any necessary
setpoint
changes,
this was
identified as Unresolved
Item 50-275/91-07-02.
The
team also reviewed the calibration procedure
and calibration data for the
second
level undervoltage
relays.
Acceptance criteria for these
relays
were
contained
in Table
1 of MP E-50.33.
The table contained
a minimum acceptable
dropout,
a desired
drop out range,
and
a maximum acceptable
pickup.
The
actual calibration data
reviewed for these
relays
showed minimal .drift, and
documented
the accuracy of the test equipment
used to calibrate
these relays.
2.3
Emer enc
Diesel
Generators
EDG)
~EM
L
di
2.3.1
(a)
the total load
on bus
F was
2780
kW, which was higher than
the 2000 ho~rs rating of 2750
kW for the
EDG; and
(b)
the total load on bus
H was
2689
kW, which was higher
than the continuous rating of 2600
kW for the
EDG.
DCPP.
was licensed with two
EDGs per'nit with a swing
EDG shared
between
the
units.
Each of the three
EDGs operating per units
was designed
to provide
emergency
power to each of the vital 4160
Vac class
1E buses of each unit.
DCPP, at the time of the inspection,
was initiating a design
change to add
a
sixth
EDG.
The design criteria, operation,
and
bus loading for the
EDGs were
described
in
FSAR, Section 8.3.
The team reviewed the load sequencing
timers, starting time of the safety motors
under
various
bus voltage
conditions,
and the starting capability of the
EDGs.
The load sequencing
of
the
EDGs appeared
to meet applicable
licensee
commitments.
Table 8.3-5 of the
FSAR, Revision 5, dated 9/89, provided
a listing of the
maximum steady state
EDG load
demand following a
LOCA.
The team noted that
several
motor loads listed in the table were not representative
of the maximum
demand
by the motors listed in the table.
The team questioned
the licensee
regarding
the worst case
loading versus
the
EDG ratings.
The licensee
confirmed the maximum steady state
load
demand
on each safety
bus following a
LOCA, and identified the two hour rating of the
as
3000
kW, the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br />
rating
as
2750
kW, and the continuous rating of 2600
kW.
The revised
loading
data indicated
the following:
In response
to team .questions
regarding
the above
noted condition, the
licensee
stated that the
EDG bus loading included
147
kW for the fire pumps.
DCPP design basis
does
not require analysis for a
LOCA and loss of offsite
power coincident with a fire.
The only condition that could cause
the running
of the fire pumps coincident with
a
LOCA and loss of offsite power would be if
an earthquake
caused fire protection
pi pi ng fai lure, consequent
low fire
'rotection
piping pressure
and resultant initiation of the fire pumps.
The
licensee's
emergency
response
procedure for an earthquake,
EP M-4, Revision
11
dated ll/5/90, required
an inspection of fire protection piping within two
hours following an earthouake
and the isolation of any damaged fire protection
piping.
This in turn would result in securing
the fire pumps if they
were not needed.
This would reduce
the
EDG bus
(F and
H) loads approximately
147
kW each.
The licensee
stated that corrected
EDG bus
loads would be
reflected in the next normal
FSAR update.
Pending submittal of an
FSAR change
to more accurately reflect
EDG bus loadings
and subsequent
NRR review and
acceptance,
this
was identified as Unresolved
Item 50-275/91-07-03.
2.3.2
Protective
Re~la in
EDG trips were provided for overspeed,
engine
low lube oil pressure,
and
generator current differential; in addition,
the
EDG was protected
from
reverse
power, loss of field, and overcurrent during routine testing.
A
review of the settings
and the control logic indicated that they were
generally designed
in accordance
with IEEE 387 standard.
a
12
Under
normal
system operating conditions
and during
EDG monthly testing,
a
ground fault inside the
EDG or along the
EDG cable
up to the 4160
V
breaker would not be detected.
However, during the
18 month
EDG surveillan'ce
testing,
performance of high voltage insulation resistance
testing
(meggering)
would reveal
the ground fault.
The 4160
V system cable were identified as
5 kV, 133$ insulating level 'cable
that met the requirements
of ICEA-S-66-516
and
ICEA S-68-524.
The team noted
that Table 3-1 of those
standards
required
a ground fault clearing
time of not
more than
one hour.
Because
of the apparent limitations of the ground fault
detection
scheme for the ungrounded
EDGs,
and the cable insulation
requirements,
the
team was concerned
with the adequacy of the
DCPP ground
fault detection
scheme.
In response
to team concerns,
the licensee
agreed
to
review the design
and consider modifying the
scheme
as appropriate.
2.3.3
EDB L
d~5
The
EDG load sequencer
was designed with two sets of individual timing relays
instead of a single multiple function timer.
One set of relays
was
used for
plant shutdown
on unit trip, or on loss of offsite power, or on degraded
grid
voltage.
The other set
was
used
when
a safety injection signal
occurs..
These
timers were
powered
by the secondary
winding of
a potential
transformer which
was connected
to the 4160
V safety
bus.
The voltage operating
range of these
timers
was within the operating
range of the 4160
V safety bus.
The load
sequencer
timer relay scheme
appeared
to be capable of performing its intended
function.
The, licensee
uses
a high resistance
ground system for the 4160
V system.
'he
EDGs are not grounded.
Mhen the
EDGs provide power to the 4160
V safety
~buses,
'the entire
4160
V safety
system
becomes
an ungrounded
system.
The
existing ground fault detection
system
measures
the residual
ground fault
current
and would not detect
ground fault in an ungrounded
system.
Should
a
ground fault exist in an .ungrounded
system,
the licensee
would not be
'mmediately
aware of the fault until the fault developed into a phase
to phase
fault that could then result in a trip of the. faulted circuit.
2.3.4
Voltage
and
F~ne
uenc~ Re~elation
t
A 1972 manufacturer's
shop test report
and
a sample of recent routine test
results of the
EDG were reviewed.
The data indicated that the
EDG could start
a 800
hp motor while maintaining the voltage dip and frequency drop within the
recommended
limits of Regulatory
Guide 1.9 and
The voltage
and
frequency recovery
time was within 2 seconds,'hich
was less
than
60K of the
sequencing
time interval
between
two load groups
as required
by Regulatory
Guide 1.9.
The shop test result also indicated
the voltage regulation
and
frequency were within the limits of the Regulatory Guide.
The steady state
and transient voltage regulation
and frequen'cy regulation of
the
EDG appeared
to be acceptable.
13
,2.3.5
Re~souse
to
NRC Information Notice 91-06 "Lock-Uo of
s~o
ns
douse
Circuit Preven~tin
Restart of Tr~sed
NRC Information Notice (IN) 91-06, dated 1/31/91,
informed all operating
reactor plant licensees
of potential
problems involving the restart of a
tripped emergency
diesel
generator
(EDG) because
of "lockup of EDG or load
sequencer
control circuits.
The incidents at Vogtle-1 and. Kewaunee raised
concerns
regarding
the understanding
of EDG and load sequencer
control
'circuits and their interfaces,
and the adequacy of procedures
for EDG restart
following expected trips.
The licensee
evaluated this
IN on 4/16/91
and documented
the result in a
memorandum
from Nuclear Engineering
and Construction
Services
to Nuclear
Operations
Support..
The
highlights of this evaluation
are
as follow:
Instead of a master
se'quencer,
the licensee
used separate
timing relays
for response
'to an accident signal
and to
signal.
Each time delay relay controls
a safeguard
load.
These
120 Vac
relays
are
powered
by
a potential
transformer
on the
EDG 4160
V bus.
Thus, if the
EDG is tripped
and the timing sequence
is interrupted,
these
relays
are de-energized
and
become self-resetting.
Mhen the bus
is re-energized,
the sequence
is automatically reini tiated.
A Safety Injection or loss of offsite power condition automatically
, sta'rts
each
EDG-.
The
EDG is automatically loaded, if offsite power is
not.available. 'fter starting, if the
EDG is tripped,
a shutdown relay
.
(SDR) is activated
by the following four protective features:
a)
Generator differential overcurrent (short circuit).
b)
Low-lube oil pressure
( lack of lubricant).
c)
d)
Emergency
manual
stop.
The
SDR locks out
EDG restart
and trips the
EDG output breaker.
These
protective features
include the minimum protection to prevent catastrophic
damage
to the
EDG while ensuring
maximum availability.
They do include
jacket water temperature
which caused
the spurious trip at Vogtle.
Operating
Procedure
OP J 6-8: I, "Diesel Generator
1-1 t1ake Available,"
provides specific instruction
on resetting
a locked out
EDG.
The inspectors
assessed
the licensee's
evaluation
by review of drawings
and
operating
procedures,
walkdown of the control boar'd,
and interviews with the
operators.
The inspectors
found that the
EDG protective trips included only
re-energizing
the
EDG bus,
and the operators
are provided adequate
instructions
to restart
a locked out
EDG.
The licensee
concluded that the
concern,
outlined in IN 91-06 was not an issue for DCPP.
Based
on the team's
review, this appeared
to be
a valid conclusion.
,14
III
2.4
480 Volt AC Class
1E~Sstem
N
The inspection
team reviewed the design of the 480 Vac Class
1E System.
For each of the
two units of the power plant, three separate
and independent
load centers
and associated
distribution equipment'ere
provided.
Each load
center consisted
of a 4. 16 kV-480
V transformer,
close coupled to
a motor
control center,
served
from a separate
4.16
kV Class
lE bus.
The motor control
center construction generally consisted of combination circuit breaker,
and control transformer
units for motor loads,
and circuit
breaker-only units for non-motor loads.
Safety related
loads
were assigned
to
the load centers
such that
a minimum of two load centers
could provide power,
'o the minimum required safety related'oads.
in order to mitigate the impact
of a design basis
accident.
The largest .loads
connected
to the 480 Volt Class
IE system
were the two-speed
300/100
hp containment -fan cooler motors.
Features
and characteristics
of the design
reviewed
by the
team included
equipment ratings, short circuit duty, voltage regulation
and equipment
protection.
These attributes
appeared
to the team to be adequate.
However,
voltage regulation,
under degraded
230
kV system conditions,
posed
a concern
as discussed
in Section 2.2.5 of this report.
2.4. 1
480 Volt Load Center
P
Loadings
on the 480 volt Class
lE load centers
under all postulated
plant
conditions,
including startup,
normal
power operation,
shutdown,
and emergency
operation
under design
basis
accident conditions,
were demonstrated
by the
licensee's
calculations
15-DC, Revision 5, dated 4/25/91
and 96-DC, Revision
2, dated 4/22/91.
The latter calculation
was performed using
a certified
computer
program identified as
ELIvIS-AC.
The
team reviewed both calculations
and
noted that'here
was approximately
a
20K margin between
the transformer
and motor control center
bus ratings
and the worst case
loading "requirements
of each
load center.
Spare circuit provisions
were noted
on the motor control
centers
which would allow future load additions.
The team also observed that
the feeder circuit breakers
and contactors
used in the motor control centers
had continuous
ampere ratings compatible with their loads.
The team noted
two minor error s in calculation
15-DC, Revision 5.
The first
related to the
kVA load imposed
by the containment
fan cooler motors during
a
LOCA.
The total loadings
on 'the buses for the
LOCA, as calculated,
considered
a motor power factor of 0.9.
However, the documented
power factor value for
slow speed,
loss-of-coolant
accident operation
was 0.497.
This resulted
in an
error of approximately
74
kVA per containment
fan cooler.
The second error
involves the load
imposed
by the backup battery charger
ED121..
The
calculation
assumed
that the backup charger
would not be in operation.
However, it could have
been in use if either battery charger
ED11 or ED12 were
out of service.
In the latter case,
approximately
79
kVA (64
KW) would have
been
on 480 volt bus
1H.
The safety significance of these
two errors
on the
480 volt load center
equipment
was considered
by the team to be minor because
of the
20% margin in equipment ratings
and should
be corrected
in the next
revision of the calculations.
2.4.!
8~0V 1<<Sh
Ci
.
C
9
The
team reviewed the licensee's
calculation
96A-DC, Revision
0 dated 4/19/91
15
which was intended to determine
the short circuit current duty to which the
'.16
kV and 480 volt buses
could have
been
exposed.
The calculations
'considered
the maximum anticipated
480 volt bus voltage in determining the
fault level.
This calculation determined that the short circuit current duty
on the three
480 volt Class
1E load center
buses
was approximately
20 kA,
which appeared
to be
well within the capability of the specified short
circuit current interrupting rating of 25
kA for this equipment.
R.'l.3
480 ~15 ~iR g
1
Calculation 96-0C, Revision 2, determined
steady state
480 volt,bus voltages
under various supply voltage conditions
and plant operating
modes.
The
team
review of the calculation identified that the running and starting voltages
at
the terminals of the -480 volt safety related
motors
had not been determined.
The licensee
responded
by stating that their design practice
was
based
on
a
2X
steady state voltage"drop in load feeder cables.
A'conservative starting
current of 6 times running current would result in
a
12 percent voltage drop
during motor starting.
The licensee
provided the
team with copies of their
drawings
053994,
Change
2, dated 5/12/78,
and 053995,
Change
2, dated 4/19/78,
both titled "Thermal Electric Design Standard,
Power Circuits for Induction
Motors."
The drawings
showed conductor size
and length limitations for
various motor loads, for a steady state voltage drop of 2 percent of
460 volts in a 40'C ambient.
At the request of the team,
the licensee
performed
an informal bounding calculation for the longest
480
V ac power
cable.
This calculation analyzed
the 2472 ft. long,
k2AWG cable for the
auxiliary salt water cross-tie
motor operated
valve FCV-601.
Steady state
voltage drop was
shown to be 1.45
and starting voltage drop was
shown to be
6.3X.
The methodology
used
and the results of the calculation
appeared
to be
acceptable.
The team reviewed the licensee's
calculation
192-DC, Revision 0, dated 5/8/91,
which was intended to determine
the maximum allowable length of the
120
Vac
control wires associated
with the 480 volt motor control centers.
Individual
480-120 volt control transformers,
for each motor-starter control circuit,
were provided in the motor control centers.
Since the licensee
evaluated
these control circuits with the 480 volt system,
the team included this
calculation in the 480 volt system design review.
The licensee
appeared
to
have
used acceptable
methodology in determining
maximum control circuit
lengths for both
810
AWG and
812
AWG conductors
used in the plant design.
~
Further,
the calculation
addressed
the bounding case
which was the control
circuit for the previously mentioned auxiliary salt water
pump discharge
cross-tie valve,
FCV-601.
The methodology
used
by the licensee
to demonstrate
voltage conditions in the
480 volt system
appeared
to be acceptable.
However,
a concern
regarding
the
satisfactory
performance of 480 volt safety related motors
and motor operated
valves
u'nder degraded
230
kV grid conditions is di'scussed
in Section 2.2.5 of
this report.
2.4.4
480 Volt System
and E~uipment Protection
The
team reviewed
the overcurrent protection applied. to the 480 volt Class
1E
system
and its loads.
Short circuit protection
was provided
by molded case
breakers
using magnetic trips.
Overload protection
was provided for motor
loads
by thermal
overload devices
in conjunction with contactors.
The protection
16
for non-motor loads
was provided
by molded case circuit breakers
using thermal
and magnetic trips.
The 'team reviewed the licensee's
calculations
Revision 0, dated 9/ll/90; 1958-DC, Revision 1, dated 10/ll/90; 195C-DC,
Revision 0, dated
11/2/90;
1950'-DC, Revision 1, dated 4/4/91;
and
Revision 0, dated 2/5/91 that evaluated
the various breaker magnetic
and thermal
trip settings
and thermal overload device trip setting or selection.
The trip
settings
appeared
to .be established
with all uncer'tainties
resolved
such that
the protected
devices
completed their safety related functions, including worst
case
voltage conditions for motor starting
and running and for trip setting
tolerances.
The team also noted that fuses
were used in the circuits for
480-120 volt control transformers
and potential
transformers.
The application
of protective devices
and their trip settings
appeared
to be acceptable.
l.l" lll1
ACC1
~AEE<<
The team reviewed
the design of the
120 Vac Class
1E system.
Each of the
, two
DCPP units
had four 120 'volt vital instrument
buses
and two supplemental
120 volt vital instrument
buses.
Each
bus
was served
by a separate
and
independent
7.5
kVA, Class
1E inverter.
A backup supply which consisted
of a
7.5
kVA, 480-120 volt transformer
and voltage regulator
was also provided.
The
backup supply was provided to facilitate maintenance
of any one of the
units'ix
Class
lE inverters.
Each inverter 's
normal or preferred
power supply was
from the
125 volt DC Class
lE system with an alternate
supply,
upon loss of
its
DC input from the 480 Vac Class
1E system.
The four vital instrument
buses of each unit served
the four redundant
channels
of the nuclear
steam
supply system's
instrument,
control
and protection
systems.
The supplemental
vital instrument
buses
served
loads
not specifically related to safety
systems
actuation
and safe shut
down.
Features
and characteristics
of the design
reviewed included equipment sizing versus
loading, voltage regulation,
and
inverter input requi rements
.
These attributes
appeared
to the
team to be
adequate.
/
2.5.1
E~ui ment
S~izin
The team reviewed the licensee's
calculation
93-DC, Revision 3, dated 12/1/89,
which was intended
to demons'trate
the loading'n the four vital instrument
bus
inverters
and
two supplemental
vital instrument
bus inverters.
The
'alculation
was
based
on detailed individual circuit load tables.
Individual
device
loads
had
been obtained
from vendor documentation
including bills of
materials,
elementary or schematic
diagrams,
and instruction manuals.
The
calculation demonstrated
that the individual inverter loadin'gs
ranged
from
approximately
78% to 97K of the nameplate
ratings.
The inverters
and .backup
voltage regulator
appeared
to have
been adequately
sized for the loads.
2.5.2
Voltage Regulation
The
team noted in the licensee's
design basis
document
DCN No. S-65, Revision
0, dated 9/30/90,
"120
VAC Systems,"
that voltage requirements
for the system
were listed
as
118 volts +,5W.
However,
the nuclear
steam
supply system
vendor information (E-Spec
677138
and
E-Spec
677414 for Nuclear
and Process
.
Instrumentation)
referenced
in the design
basis
document indicated
a-
requirement for 118 volts
+ 2X.
The
team noted that Section 7.6.2. 1 of
17
the plant's
updated
FSAR, Revision 6, dated 9/90, stated that the inverters
were designed. for an output of 118 volts
+ 2X, which agreed with the voltage
regulation informatio'n noted in the inverter. manufacturer's
published data.
In response
to the team's
concern for this anomaly the licensee
provided
a
copy of a telex from the nuclear
steam
supply system vendor,
dated 7/29/75, in
which the voltage regulation'f
+ 5X was indicated
as acceptable.
The
licensee's
response
to- this voltage regulation concern
appeared
to be
.
acceptable.
Based
on information contained
in
DCN No. S-65
and the manufacturer's
published data,
the inver ters will provide
+ 2X regulation with an input of
105 to 140 Vdc or 414 to 506 Vac.
In response
to the team's
request,
the
licensee
performed
an informal calculation to demonstrate
acceptable,
worst
case
input voltage from the preferred or normal supply at the end the battery
duty cycle, at which time the battery terminal .voltage would be
114 volts (see
Section 2.6.1).
This calculation indicated that inver ter terminal voltage
would be approximately
113 Vdc, which would be within the inverters
required
input range.
Based
on the design
and documents
inspected,
the
120 Vac Class
1E system
voltage regulation
appeared
to be acceptable.
2.6
125 Volt DC Class
1E System
The team reviewed the design of the
125 Vdc Class
lE system which, for
each of the
two units of the power plant, included three
independent
and
separate
buses.
Each
bus
was served
by its
own 125 volt, 60 cell, lead-acid
type battery
and battery charger.
A spare
charger
was provided to serve-
either
one of two buses,
while a second
spare
charger
was provided for the
third bus.
Each
normal battery charger for each of the three battery
buses
was supplied from a separate
480 Volt=Class
IE bus.
Loads were assigned
to
each battery
bus to support
and complement
the safety related
loads
served
by
-its associated
480 Volt Class
1E bus
and 4. 16
kV Class
1E bus.
Each of the
three battery
buses
served
two 120
VAC Class
1E instrument
bus inverters.
The
team reviewed the features
and characteristics
of the design,
including
battery
and battery charger sizi ng, short circuit duty and voltage conditions
for 125
Vdc motor operated
valve functions.
The team gave particular
attention to calculations relating to the portions of the system associated
with battery
12, since it was
on the team's
selected
load path for the
inspection.
These features
and characteristics
appeared
to be adequate.
2.6.1
Batter~and
Hattery Cha~rer
Sizing
The design
basis
document
DCN No. S-67, Revision 0, dated 9/30/90,
"125/250
Volt Direct Current System," stated
that the design criteria for battery
sizing was that the
end of duty cycle or minimum allowable voltage
was 1.9
volts per cell
(114 volts total).
Further,
the duty cycle for the design
basis
accident
was
2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
and the duty cycle for station blackout was
4
hours.
The
team reviewed
the licensee's
calculation
2328-DC, Revision 2,
dated 2/15/91, for Class
1E battery
12, which was intended to verify that the
battery
was sized for the
2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> duty cycle.
The
methodology
used
employed
the computer
program
ELMS-DC, which was
based
on
IEEE Standard
485-1978,
"Recommended
Practice for Sizing Large
Lead Stora'ge Batteries for Generating
Stations
and Substations."
The results
indicated
an existing battery capacity
18
margin of 3.8/ for battery
12, with a 2-hour duty cycle and
a minimum voltage
to be not less
than
114 V.
Acceptable
margins
were also noted in calculations
232A, Revision
2 and
232C, Revision 1, both dated 6/1/90, for the other two
Class
1E batteries.
The team noted that the licensee's
calculation
144-DC, Revision 1, dated
3/19/90,
performed to verify that the batteries
were adequate
for the 4-hour
blackout duty cycle,
had used
data
from calculations
superseded
by calculations
232A,
B and
C-OC discussed
above.
In response
to the team's
concern for the
impact, the. licensee
provided the results of preliminary calculations
235A,
B
and
C - OC, which were intended to supersede
calculation
144-OC,
and used
data
from calculations
232A,
B and
C-DC.
These preliminary results
appeared
to
indicate acceptable
margins for the 4-hour duty cycles.
The licensee
had
no formal calculation for verification of battery charger
sizing.
However, the
team agreed that the 400 amperes
nominal rating (440
amperes
maximum) for the chargers
appeared
to be acceptable
based
on
a
continuous
charger
load (i.e., without battery charging) of approximately
210
amps,
as implied by calculation
2.6.2
i 5~V l
0
S <<
Sh
Ci
i
C
The team reviewed the licensee's
calculation
233B-DC, Revision 1, dated
9/5/90,
which was intended to determine
the short circuit current duty on the portion
of the system
served
by battery
12.
The calculation, considering fault
current contribution from both the battery
and charger,
determined
that the
fault curi ent at the battery terminals
was approximately
14.4
kA and
approximately
14. 1
k
kA at the main bus.
These
values
were well below the main
bus breaker interrupting ratings of 25
kA and the distribution panel
breaker
ratings of 20 kA.
The battery fuses
were reported to have
a 200
kA
interrupting rating.
The team found the methodology
and results of the
calculations
to be acceptable.
Similar results for the portions of the system
associated
with the other
two batteries
were. demonstrated
by calculations
233A, Revision
1 and
233C, Revision 2, both dated 9/5/90.
The methodology
and
results of these calculations
appeared
to be acceptable.
2.6.3
Voltage to 125 Vdc Motor 0~crated
Valves
(MOVs)
The
OC motor operators
at
DCPP were purchased
and sized to develop
rated torque at 70K of motor terminal voltage.
The inspection
team reviewed
calculations
126-DC dated 7/25/83,
and
1956-DC, dated 5/17/91, which were
performed to determine
the worst case
expected
motor terminal voltage at motor
operated
valve FCV-95.
The calculations
assumed
an ambient temperature
of
163'
and the minimum expected
end of life battery voltage of 114 volts.
The calculation also
assumed
a maximum motor unseating
current of 19.31
amps,
which was taken
from test data
performed using the Westinghouse
Vital System
for a test performed
on 5/17/91, at
a pressure
of 775 psi,
and with an unknown
differential pressure
and flow.
Review of this test data indicated
inrush
currents of approximately .32 amps,
running current of 7.35
amps,
and
an
end
current of 19.31
amps.
It was unclear to the inspection
team as to whether
these
tests
were performed at design basis conditions
or whether currents
in
excess
of 19.31
amps
would be required for unseating
the valve in the open
direction.
Using the
19.31
amps,
the licensee
then developed
an equivalent
-19
circuit for this motor operated
valve using cable resistances
at 20'
and
a
motor resistance
at 163'.
Correcting for the motor resistance
but
'not for the feeder cable resistance
for high 'temperatures
was
non-conservative,
because
the resultant voltage available
to the motor under
these conditions
appeared
to be greater.
In addition, this methodology
assumed
that the motor torque
was
a pure function of terminal voltage.
This
is not true if motor resistance
increases
due to elevated
temperatures.
The
resultant calculation
showed that 82.25 voltage would be available across
the
motor shunt windings
and 78.34% voltage would be available
across
the motor
series windings, which is greater
than the stated
70K voltage requirement.,
The methodology
and inconsistencies
in this calculation brought into question
the validity of the results.
Due to the existing margin, there did not appear
to be
an operability concern with this valve.
However, the team was concerned
that similar errors might have
been
made for other valves
where adequate
margin was not available.
'In addition, true thrust requirements
for these
'valves
based
on design. basis testing,
o'r its equivalent,
need to be
established
in accordance
with the licensee's
Generic Letter 89-10 program.
This issue will be reviewed during
a future, Generic Letter 89-10 inspection.
P'ending further review, this was identified as Unresolved
Item 50-275/91-07-04.
2.7
Protection
and Protection Coordination
The
team reviewed the licensee's
various calculations
and coordination curves
that established
protective relay and tripping device settings,
and
demonstrated
coordination of circuit protection devices .applied in the power
plant's
Class
1E
EDS.
Particular attention
was given to relay
and tripping
device settings
associated
with the team's
selected
load path,
and included
the 4. 16
kV system,
from the startup
and auxiliary transformers,
through the
4.16
kV switchgear
and the 480 volt load center outgoing feeders.
The team
also reviewed protection
and coordination
as applied to the
125 volt DC 'Class
lE system,
starting at the battery
and battery charger terminals
through the
DC system main buses.
The relay and device settings that were'reviewed,
demonstrated
protection coordination of tripping devices for bus main
supplies,
bus ties, motor feeders,
load center transformer feeders,
diesel
generator
protection
and for battery
and for battery charger protection.
Protection and,protection
coordination
appeared
ac'ceptable.
2.8
Containment Electrical Penetrations
The team reviewed the licensee's
calculations
which were intended to
demonstrate
the application of penetration
assemblies
with regard to
current capability and overcurrent protection provided in'ompliance
with Regulatory
Guide 1.63,
Rev.ision
1, dated 5/77.
Primary and backup
overcurrent protection
were provided
by the licensee
in cases
where the
maximum anticipated fault currents
could exceed
the" capabilities
of the
assemblies.
Circuit breakers
were usually provided
as -primary and
backup protection devices.
Fuses
were used in som'e
low voltage circuits.
Primary and backup overcurrent protection devices
reviewed were physically
separated
from each other.
However,
team walkdowns
and subsequent
design
review identified
a containment penetration for a non-Class
1E emergency
lighting
DC circuit that appeared
to be
r outed in
a manner that jeopardized
20
its protection.
The loadside
leads for the circuit from the backup breaker
were routed
back through the panel
containing
the primary breaker
and then to
the penetration.
A catastrophic failure of, or within, this non-class
1E
panel
could have resulted
in shorting of conductors
which would bypass
both
primary and backup protection.
In the event of a design
basis
accident,=an
emergency lighting circuit fault within the containment, without circuit
overcurrent protection,
could have r'esulted
in a fai lure of the associated
electrical penetration
and
a challenge to the containment integrity.
The team
discussed
this condition with the licensee.
The licensee
did not consider
the
noted condition to be
a problem.
They considered that
a type of failure that
could bypass all the overcurrent protection for the penetration
was highly
improbable.
The conductor insulation
and the spacing
between
conductors
tended
to preclude
a short circuit that would bypass
the protection.
The team
concurred with the licensee's
position
and agreed that
a safety concern did
not exist.
However,
the
team felt that routing the load side conductors
from
the backup protection
back through the panel
contain'ing the primary protection
was not in keeping with prudent design practices for redundant
protection
schemes.
(N
The team noted that penetration
assemblies,
including their conductors,
and
the protective devices,
appeared
to be adequately
sized.
Coordination of 2
protective device trip characteristics
with the thermal characteristics
( I t)
of the penetration
assemblies
appeared
acceptable.
2.9
Auxiliar~Feedwater
(AFW) Electrica~lS
stem
The power supplies
to the
AFW pumps
and their associated
instruments
and
valves,
and the automatic initiating signals
to start the
AFW pumps
under
various
normal
and
abnormal
operating conditions
were reviewed.
Each of the
instruments
in
a given
AFW train was
powered
from the battery backed
inverters.
No inverters
supplied
power to instruments
and control valves in
more than one
AFW train.
The sequencer
timer relay used in the
AFW system logic circuit was the
same
type used in the
EDG sequencing
logic circuit.
The minimum voltage allowed by
the Agastat timers, cat.
no.
2412AO,
was
120
V - 132 V, which corresponded
to
3570
V - 4620
V at the 4160
V bus.
3570
V was higher than the second
level
relay
(SLUR) set point and the 4620
V was higher than the
10'X
allowance for the 4160
V system.
The application of this timer appeared
to be
acceptable.
The initiation of a safety injection actuation
signal
(SIAS)
appeared
to inhibit all other
AFW automatic actuation signals.
AFW pumps
would not start simultaneously with other
pumps during the
EDG load
sequencing.
The design of the electrical portion of the
AFW system
appeared
to be
acceptable.
3.0
Mechanical
Systems
The
team reviewed calculations
and documentation
and conducted
walkdowns of
EDG fuel oil storage
and transfer,
lubricating oil, starting air,
and diesel
heating
and cooling equipment,
on
a sampling basis,
to determine
the ability
of mechanical
systems
supporting
the
EOGs to perform their design
basis
~functions during postulated
accident conditions.
The team reviewed equipment
associated
with the heating, ventilating,
and air conditioning
(HVAC) of the
'diesel
generator
room, battery
rooms, essential
switchgear
rooms,
and selected
EDG and
HVAC design modifications.
The team reviewed the translation of
various mechanical
loads of selected
pumps to,electrical
loads for input into
design basis calculations.'
3.1
E ~Di
i
G
ill~E~
3. 1.1
Fuel Oil Storage
Capacity
FSAR Section 9.5.4.1,
Revision
6 dated 9/90, required availability of
sufficient
EDG fuel oil storage
capacity for 7 days of EDG operation while
providing power for minimum LOCA loads in one unit and
power for operation of
equipment in a second unit that was in hot or cold shutdown conditions.
Technical Specification (TS) 3.8. 1. 1 required that
a minimum of 52,046
gallons-of
EDG fuel
be available for both units in Modes 1-4.'CPP
had
two 40,000 gallon
EDG fuel oil storage
tanks.
The
team reviewed
EDG fuel oil requirements
and licensee calculations
to
verify compliance with those requirements.
Calculation M-786, Revision
1
dated 4/22/91,
determined
the amount of fuel oil required for 7 days
operation at
The calculation determined
that the
amount of fuel oil for two unit operation
(one unit experiencing
a
LOCA and
the second unit shutdown)
was 51,963 gallons.
The calculation also
determined that the
two
EDG fuel oil tanks
had
an unusable
volume of
972.4 gallon each for a total
two tank usable capacity of 78055 gallons.
The tanks were usually allowed to be depleted
by 7500 gallons before
additional fuel oil is ordered.
The team noted that calculation
M-786 used
a fuel oil average
specific gravity-
of 0.88.
TS surveillance
requi rement 4.8. 1. 1.3.c( l)(a) allowed
a minimum
specific gravity of 0.83.
Use of the minimum TS allowed specific gravity would
have
been
more appropriate
and would have resulted
in
a
EDG fuel oil storage
requirement of 54,975 gallons.
The noted non-conservative
calculation
was
discussed
wit% the licensee.
In response
to the
teams
concern,
the licensee
.
performed additional calculations
and demonstrated
that conservatisms
in the
assumed
fuel consumption for various
ESF loads could be revised
and
approximately
4000 gallons of fuel oil consumption
could be removed
from the
calculation.
'The licensee
agreed
to review and establish
a documented
basis
for the
TS fuel oil capacity requirements,
and submit any necessary
TS change.
The team acknowledged
the licensee's
response
but still considered
the lack of
conservatism
in the calculation to be
a. weakness.
The
team felt that the
calculation
lacked sufficient consideration for the
TS
EDG fuel oil specific
gravity requirements.
Furthermore,
the team noted that the
verification/checking
process
had not caught the non-conservative
assumption.
Supervision
had inappropriately
approved
the non-conservative
calculation.
During the review of the
EDG fuel oil capacity calculations,'he
team
was
informed of a licensee
prepared Justification
For Continued Operations
(JCO)
relevant to DCPP's
EDG fuel oil storage
capacity.
JCO 89-01 for Units
1 and
2
had
been
in effect since 2/89.
The
JCO was
implemented
to provide increased
fuel oil storage
requirements
to meet minimum loads for seven
days,
per the
22
FSAR,
due to increased electrical
load
and
added surveillance
requirements
of
Regulatory
Guide
(RG) 1. 137,
"Fuel Oil System for Standby Diesel'enerators,"
Revision 1, 10/79.
The
JCO was,still in effect and the fuel oil storage
capacity requirements
needed
to close out the
JCO were still unresolved at the
time of this
EDSFI inspection (4/91), the team 'felt that there did not appear
to be proper
and timely resolution of the still open (2/89)
JCO fuel oil inventory
issue with respect
to determination of the technical
basis
and resolution of
potential
TS licensing issues.
As noted above,
the licensee
agreed
to more
expeditiously pursue
the resolution of the
JCO issue
and potential
EDG fuel
oil TS change
requirements.
The team considered
the lack of prompt
resolution of this issue to an additional
example of the licensee's
weakness
in achieving timely corrective actions.
3.1.2
EDG Air Start
System
FSAR Section 8.3. 1. 1. 13.2 described
the
EDG air start system.
The
section stated,
"Both of the two air-start
systems
operating together
are
capable of starting
and accelerating
the engine generator
set to rated
speed
and voltage in less
than
10 second's.
In the event that one of the air-start
systems fails or is unavailable,
the redundant air -start system is capable of
starting
and accelerating
the engine generator
set to rated
speed
and voltage
in less
than
12 seconds."
The section continued to describe
the
boost system."
Although the
FSAR section discussed
the
need
for the turbocharger
boost system, it did not clearly state that it was
necessary,
in addition to the start air system, for the capability to start
and load the
EDGs to rated
speed
and voltage within ten seconds.
Preoperational
test records
reviewed
by the
team confirmed that need.
The
licensee
confirmed the team's
observation
and stated
that the
FSAR would be
clarified in the next normal
FSAR update submittal.
3. 1.3
Jacket
Water/Lube Oil Temperature
The team reviewed licensee calculations that evaluated
the
EDG cooling
capabilities.
DCPP Calculation 82-13 determined that at the maximum design
ambient temperature
of 91'F, the
EDG room temperature
would be 123'F.
The
design
temperature
of the diesel
generator
room was 120'F in accordance
with
FSAR Section 9.4.
The team questioned
the licensee
regarding
the long term
and short term effects of the higher temperature
on mechanical, electrical,
and electronic
components
located in the room.
The licensee
performed
an
evaluation
in response
to the team's
questions
and concluded that the 123'F
room temperature
would still be acceptable
(AR A0229031).
Acceleration of
aging
on
some
components
would occur;
however,
no short term failures were
expected.
The
team noted that the
had upper limits on jacket water
and lube oil
temperature,
above which premature
wearing of components
and deterioration of
performance
could occur.
The
EDG vendor provided the licensee with a 205'F
upper limit for EDG water jacket temperature
and
a 185'F upper limit for lube
oil temperature.
The
team noted that at diesel
room temperatures
of 123'F,
which corresponded
to the maximum
FSAR stated
design
ambient temperature
of
91'F,
no design calculation
had
been
performed to determine
the jacket water
and lube oil temperatures.
The licensee
agreed
to obtain jacket water
and
lube oil temperature
calculations
from the
EDG vendor at 123'F diesel
room
23
,temperature
to ensure that the jacket water
and lube oil upper temperature
limits would not be exceeded.
In addition to the above:commitment,
the licensee
stated that alarms
were
provided to warn the operator
of, the high temperature
condition before the
upper limits were reached.
.The li.censee
provided the annunciator
response
procedure
(AR PK16-08), that ensured'hat
the
EDG room temperature
would not
increase
appreciably
beyond 120'F.
The
EDG room west doors were normally
open for EDG room cooling and the east
doors were normally closed for fire
protection.
The annunciator
response
procedure
checked that the west doors
had not inadvertently shut
and were still open.
The procedure
did not
require the opening of the east
doors to increase
EDG room ventilation flow.
The licensee
committed to review and change
the annunciator
response
procedure
as necessary'o
ensure sufficient diesel
room cooling on high room
temperature
annunciation.
Pending further licensee
evaluation
and
performance of any annunciator
response
procedure
change,
this was identified
as Unresolved
Item 50-275/91-07-05.
The day before the
team exit meeting,
the
team was
made
aware of, and
reviewed test records for performance of STPN-96. for EDG 1-1 performed
on
November
16,
1989.
The test records
showed that both high lube oil and high
jacket water temperatures
of 195'F (upper limit of 185'F
as described
in
Section
3. 1.3 (b) and 183'F, respectively,
were observed
before the licensee
was able to open the east roll-up door to cool
the room.
The
room
temperature,
at the time of high temperature
alarms,
was only at 92'F.
This
was well below the 123'F
room temperature" expected at maximum
FSAR stated
design
ambient temperature
of 91'F.
Test records
showed that lube oil, jacket
water
and
room temperature
went down, but drifted u'p again to higher values
after
a period of about six hours
and reached
values
higher than previously
recorded.
Since the
team obtained
these test records
near the end of the
inspection,
the
team
had insufficient time to appropriately
review the
information.
However,
on the basis of the information reviewed,
the team
had
the following concerns:
The cause of high lube oil and high jack water temperature
at only 92'F
diesel
room temperature
should
be determined.
The team noted that
maximum diesel
room temperature
could
be 123'F, which would result in
higher lube oil and jacket water temperatures.
An evaluation
should
have
have
been
performed to determine
the consequences
of the observed
condition should it occur during operation of the
EDGs under accident
conditions.
b.
Lube oil temperature
during this test
exceeded
the upper limit of 185'F
set
by ALCO.
An evaluation
should
have
been
performed to determine if
possible, deterioration of the
EDG occurred.
Pending further
NRC inspection
to review the licensee's
evaluation or
analysis,
determination of cause,
and performance of any necessary
corrective
actions for the
November
16,
1989, high temperature
alarms during performance
of
EDG testing, this was identified as
an additional
item for Unresolved
Item 50-275/91-07-05..
24
314
3
~it
E
EDGs could derate
due to high ambient temperature
and insufficient engine
warming.
The team noted:that
the diesel
engines
were rated at an ambient
temperature
of approximately 90'F.
The team noted that the maximum recor'ded
OCPP
ambient temperature
was 96'F.
The
team questioned
the licensee
regarding
the
possible derating of the
EOGs
due to ambient
temperatures
that were higher than
its rated ambient temperature
and possible insufficient engine warm-up during
its initial operating period.
The licensee
responded
that the diesel
package
was designed
by ALCO to compensate
for warm-up of engine 'inclusive of
support
systems
to operating
temperature
and for ambient temperature
above
rated temperature.
The input of fuel oil to the engine is varied to
compensate
for increasing
and decreasing
loads
and other variable conditions
which govern the output of the engine (load, ambient temperature,
air manifold
.pressure,
exhaust
pressure,
etc.).
The amount of derating
due to the
increase
in ambient temperature
to 96'F or insufficient warming of the engine
would be compensated
by increasing
fuel supply to the engine.
The team
had
no
further concerns
in this area.
3.1.5
1
1
4
1fff
1
f
1
133
The
EDG room west roll-up doors
were normally left open to provide for EDG
room cooling.
These
doors
were designed
to be closed
by means of fusible
links that sensed
high temperatures if a fire occurred in the room.
The team
reviewed the seismic qualifications of the doors
and the fusible links.
Calculation
E(jP 304. 1,
OCP N-34398 Rl showed that both the mechanical
and
electrical
components
of the fusible link and other mechanical
parts of the
doors
had
been seismically qualified.
The team concluded that seismic
qualification of the west roll-up doors were acceptable.
3.1.6
Pin~in
Stre~ss
Anal sis - Air Starting System
Q
The
EDG air start system
was
a seismically analyzed
system.
The team reviewed
selected
models of piping stress
analysis for the Air Starting
System.
The
analysis
was performed utilizing Bechtel
stress
analysis
program NE101.
The
analysis
assumptions
and methodology
seemed
to be acceptable
and the allowable
stresses
were well within code limit.
3.1.7
Fuel Oil and Jacket
Water Chemistry
The
team reviewed selected
samples
of fuel oil and jacket water chemistry
sample reports
to ascertain
that appropriate
chemistry controls were being
implemented
by the licensee.
The team noted that the licensee
had established
acceptance
criteria that were within TS allowable limits.
The team review of
the chemistry sampling records
indicated that results of the sampling
reviewed
were acceptable.
3.2
3.2,1
Heat~in
and Ventilation
Battery
Room Ventilation
The team reviewed
the ventilation design of the battery
room to ascertain
that
sufficient ventilation existed to preclude
a hydrogen explosion hazard
under
various postulated
design conditions.
Calculation 83-46 determined
the
25
.adequacy of natural ventilation to the battery
room on loss of fans
and the
hydrogen concentration
in the
room was calculated.
Based
on an ambient
'temperature
of 78'F and
room temperature
of 104;F, the natural ventilation
flow was calculated
to be
68
CFN and air flow required to maintain
2X
H
by
volume in accordance
with Regulatory
Guide 1. 128 was
1 CFN.
Although t(e
calculations
raised
several
questions
from the team,
licensee
response
to the
questions
and conservatisms
in the calculations
confirmed that the battery
room ventilation met licensee
commitments
and requirements.
3.3
Power
Demand for Major Loads
The
team checked selective
samples of vital 4.16
kV mechanical
loads to
ascertain
that the loads
were being appropriately
accounted for in the
EDS
design.
Review of the mechanical
loads indicated that actual
pump
characteristics
were
used
and were conservative.
The team noted however,
that loads listed in
FSAR Table 8.3-5,.Revision
5 were outdated
and not
conservative
as discussed
in Section 2.3. 1 of this report.
As previously
noted,
an
FSAR change will be accomplished
and the loads listed in Table 8.3-5
of calculation
150C, Revision
5 would be followed, except for the component
cooling water
pumps load which required further change
to 342
kW(e) instead of
318 kM(e).
3.4
Auxi'liar~Feedwater
System
3.4. 1
.
AFW Pump Runout Protection
Runout protection
was provided to the motors of the Auxiliary Feedwater
(AFW)
pumps to prevent motor overloading.
The team reviewed runout protection
design calculations
to 'verify that appropriate
design considerations
were
utilized.
Calculation
ISP-1-03 determined
low, AFM discharge
pressure
setpoints
and
AFW level control valves position to limit runout of AFW pumps.
For
a feedwater line break scenario,
low pump discharge
pressure
would
position the
AFM level control valves
to
a predetermined
position
and limit
the
AFW flow.
The
AFW motor power was limited to 600 hp by controlling the
AFW flow.
The team reviewed selected
calculation assumptions
and methodology
and concluded that the calculation assumptions
and methodology
appeared
to be
acceptable.
3.4.2
(uglification and Separation
of AFW Level Control Valves
~LCVs)
The team reviewed the
AFM system to determine
the effects of a feedwater line
break
and possible effects of steam
on the
AFM LCVs. The team reviewed
the
qualifications
and separation
of the
AFW LCVs in relation to their ability to
cope with a feedwater line break
and to ascertain
that
AFW would still be
available to the steam generators.
The team review indicated that the system
design
met licensee
commitments
and applicable
requirements.
4.0
Eq~ui ment Testing, Surveillance,
and Maintenance
4.1
EDG Testi~n
The
team observed
the performance of the monthly
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> surveillance
on
1-3,
as required
by TS and
implemented
by Procedure
N9H.
The operators
appeared
to follow the procedure appropriately.
An additional
EDG start
was
26
immediately performed after completing the surveillance
procedure
because
one
of the times recorded for the
EDG appeared
to be inappropriately short in in
comparison to previous experience for starting
and loading the
EDGs.
Shortly after
EDG 1-3 was shut down, the inspector discovered
the radiator
door of EDG 1-2 open about 80 degrees.
The inspector
informed an operator,
who promptly obtained
keys,
locked the door,
and checked that the other
radiator doors were locked.
The door was required
by Revision
10 Procedure
OP
J-6B: II, "Diesel Generator
1-2, Nake Available" to be locked shut.
This is to
prevent personnel
entry and to prevent
bypass
flow around the
EOG water jacket
radiator coils, which could result in inadequate
cooling of the water jacket.
The licensee
stated
that the configuration of the door is such that
an open
door would have blocked the walkWay past the radiator, resulting in quick
discovery
by an operator during operator
rounds.
Also, unless
the door was
fully open,
the airflow into the radiator would have
caused significant
differential pressure
across
the door, causing
the door to slam shut.
In
either case,
the licensee
stated that the safety significance of the open door
was minimal.
As corrective action;
the licensee
planned to review applicable
work instruction references
to include
a precaution
to close
and lock the door
after the activity, and to install warning signs
on the door that it must be
locked while the
The team considered
this assessment
to be
appropriate.
Therefore, this apparent violation of TS 6.8. l.a, which requires
that plant procedures
be implemented,
was identified as
a non-cited violation,
50-275/91-07-06,
in accordance
with 10 CFR 2, Appendix C, V.A., -since the
safety s.ignificance
appeared
minimal, and the licensee corrective action
appeared
to be prompt and appropriate.
The
team noted that the
EDG 1-3 room temperature
gage TI-99 appeared
to be
reading
about
10 to 15'F high.
The licensee
observed
the gage
and initiated an
Action Request
(AR) to have the calibration checked.
The gage is scheduled
for 18 month calibrations,
and
had
been calibrated
about nine months prior to
the inspection.
The licensee
stated
that this was not an immediate
operability concern,
because
the instrument bias
was in a conservative
direction.
The
team reviewed the records of the last two calibrations of the
gage.
The gage calibration records
reviewed did not indicate excessive drift
or bias
and that the calibration frequency
appeared
to be appropriate.
The team compared
the
TS surveillance
requirements
with the surveillance
testing
implemented
by plant procedures.
Three
EDG surveillance
procedures
contained
acceptance
criteria which only partially implemented
the
TS
requirements.
1.
TS 4.8. 1. 1.2.b(7)(b) required that, for
a simulated
loss of offsite
power, in conjunction with a Safety Injection test signal,
the
EDG must
energize
accident
loads
and operate for
greater
than or equal
to five minutes
while loaded.
After energization of these
loads,
the
EDG must maintain steady
state voltage
and frequency of the emergency
buses
at 4160
+ 420V and
60 +
1.2
Hz during this test.
However, Revision
14 of Procedure
N-15,
" Integrated
Test of Engineered
Safeguards
and Diesel Generators,"
Step
15. 1.7, referred to
Attachment 8.6 of the procedure.
Attachment 8.6 required information on
voltage,
frequency values and-stability
to be recorded at one minute, although
the body of the procedure
required this to be at five minutes.
This was
considered
a weakness.
'I
~ It
27
2.
TS 4.8.1.1.2.b(8)
required that, within five minutes after completing
a 24
hour
EDG operating test,
the requirements
of TS 4.8.1. 1.2b(5)(b)
be performed.
~ This required simulating
EOG auto start,
and
energization of emergency
loads.
After energization,
the steady state voltage
and frequency of the emergency
buses
shall
be maintained at 4160
+ 420
V and
60 + 1.2
Hz during this test.
- Revision
12 of Procedure
N-9G, "Diesel Generator
24 Hour
Load Test," Steps
12.3.2.m
and n, referenced
by Step.15.
1 as the acceptance criteria, required
that the voltage
and frequency
be verified to be steady.
However, the length
of time for this stability was not specified in the data sheets.
Although
the body of the procedure i'ndicated'hat
the scope of the procedure
was to
demonstrate
the stated condition, the
team considered
this to be
a second
example of poorly written surveillance test procedures
and identified this as
another licensee
weakness.
3.
TS 4.8. 1.'1.2,
and Table 4.8-1 requirements
concerning
EOG testing,
require, in part, that the criteria of Regulatory
Guide 1. 108 be used to
determine validity of
EDG failures'.
The
Reg Guide required,
in part, that
an
EOG start
be considered
successful if it met the design accident requirements.
This included design
basis
times to start
and load to the bus.
Con'sequently,
a failure to meet design basis
times would be considered
an unsuccessful
start.
Revision
3 of Procedure
N-9I stated that it implemented
the above requirement
to determine
the validity of the start
as defined
by Reg Guide 1. 108.
Steps
8.4 and 8.5 of the procedure
only require the diesel start
and load
1300
kW.
No specific time limits for starting
and loading are contained
in the,
procedure,
even
though the diesel
is required
to start
and load within 10
seconds
in order to be considered
a valid start.
There did not appear
to be
acceptance
criteria documented
in the procedure
which addressed
the time in
which the
EDG was required to start
and load to the bus.
For the three procedures
discussed
above,
the licensee
plans revisions to
specifically address
the
TS requirements.
For the first two instances,
the
licensee
stated that Procedures
N-15 and
N-9G wi'll be revised to contain
a
step which explicitly addresses
the five minute stabilization requirement
as
implemented in procedure
N-16Al, in order
to make the surveillance tests
consistent.
For the third procedure,
N-9I, the licensee
planned to review the
procedure"and clarify the acceptance
criteria.
The above
examples of inadequate
procedural
implementation of surveillance
requirements
appeared
to be
a violation of TS 6.8. l.a, referencing
Regulatory
Guide 1.33, regarding
adequate
implementation of Technical Specification
surveillance
requirements.
This was identified as Violation 50-275/91-07-07.
4. 1. 1
EDG Air Start
System Testing
The Emergency
Diesel
Generator
(EDG) air start
system provided the means for
starting the
EOG's.
The system consisted
of 'two separate
trains of starting
air and
an additional train of turbo air start for each
EDG.
Each train
consisted
of a compressor,
after cooler, filter/dryer components,
an air
receiver,
pressure
reducer, air start solenoid valves
and air start motors.
Each train included
a check valve which served
as
a means for passively
isolating the
non safety-related,
non seismically analyzed
compressor,
after
28
cooler, filter/dryer piping from the safety-related,
seismically analyzed
piping system
up to the
EDG air start motors.
The 'licensee
tests
the
EOG air start system
OEG-214,
225, 236,
247,'58
and
269 using Procedure
STP V-302 Revision
1.
The most recent
testing of those valves at the time of the inspection
was performed in April
of 1'989 for Unit
1 and in Yiarch of 1990 for-Unit 2.
STP V-302 and the results
of recent tests
were reviewed.
The inspector
had the following observations:
(1)
The tests
measured
receiver pressure
drop while piping upstream of the
check valve was vented.
The mechanism
used for venting the upstream
piping was
by manual lifting of a relief valve.
Filter drains
and
a
drain valve were available for performing this function but were not
required to be used
by the procedure.
(2)
The tests
were 'required to be conducted for only 10 seconds.
The
relatively short duration of the tests
appeared
to be susceptible
to
error.
(3)
The acceptance
criteria for the test
was that
no more than
a 30 psig drop
in receiver pressure
be observed
during the
10 second test.
Recent tests
indicated that
a maximum actual
leak rate of 2 psig in 10 seconds
was
observed
during testing of all the check valves.
However,
the acceptance
criteria would allow a check valve to pass this test with a leak rate
that would, within one minute, preclude
the air receive
s from having
sufficient air to start
an
EOG.
(4)
The licensee
had
no documented
basis for the check valve leakage
acceptance
criteria.
(5)
The check valves were not included in the licensee's
ASNE Section
XI
Inservice Test
( IST) Program.
NUREG 0675 Supplement
31, Safety
Evaluation Report, related
to the operation of DCPP,
dated August 1985,
Section 5.2.8. 1,
Item
12 required that valves in the diesel air start
system that perform
a safety function be full-stroke exercised quarterly
in accordance
with the requirements
of subsection
IMV of Section
XI of
the
ASYiE code.
The licensee
response
to the
SSER
31
NRC question
indicated that the
IST program
had
been revised to include testing
of EDG air start valves.
Subsequent
discussions
with the licensee
regarding
the above observations
resulted in the initiation of Action Request
A0231186 to establish
the
acceptance
criteria
and bases for EDG air start check valve leakage.
The
licensee
also stated
that
V302 would be revised to utilize a more
appropriate
vent path other than the relief valve.
Criterion
V requires,
in part, that instructions,
procedures,
or drawings
include appropriate
quanti tative or qualitative acceptance
cri teria for
determining that important activi ties
have
been satisfactorily accomplished.
OCPP
FSAR, Revision 2, Section 8.3. 1.1. 13.2 states,
in part, that each air
start
system provide
45 seconds
of continuous
engine cranking.
The acceptance
criteria of 30 psig/10
second
would not ensure
45 seconds
of continuous
cranking
with the system
leakage
and still be able to start the
EOG to rated
speed
and
voltage
and load within 10 seconds.
This appeared
to be
a violation of 10 CFR 50, Appendix B, Criterion V, and
was identified as another
example for
Violation 91-07-07.
29
4.2
~Rela
Calibratio~nPro
ram
'The team reviewed relay calibration records
to verify that setpoints
conformed
to those specified in the setpoint calculations.
The team inspected
the relay
settings of devices within the selected
load path
on
a sampling basis.
The
calibration of the protective relays
appeared
to be completed during .each
refueling cycle by the electrical
maintenance
department.
Work activiti'es
were usually monitored
by system engineers
and controlled by administrative
calibration procedures.
The team noted that
a top tier administrative
procedure
describing
the relay calibration program did not exist.
However, it
was noted that controlled procedures
for each
type of relay describing
guidance for calibration
and maintenance
were available.
The .team noted that
the licensee
appeared
to have
a good centralized electrical setpoint
document
.
which identified the setpo'ints
and the design'basis.
4.3
Setpoint Control
Program
The licensee's
program for establishing
and controlling safety-related
instrument setpoints
was described
in Administrative Procedure
AP-C-lS6,'
"Electrical
and Mechanical
Device Setting
and Instrument Setpoint
Change
Control Program,"
Revision 0.
The procedure
described
the requirements
and
methods for initiating, analyzing, controlling and documenting
changes
.,to
electrical
device setpoints.
Requests
for setpoint 'or device setting
changes
were documented
and tracked
by
action requests
(ARs).
The request
forms were routed to the engineering
manager
or his designee
(usually the system engineers)
for review and
. concurrence.
This initial review was intended to ensure
that the proposed
setpoint
change
was reasonable
and would not adversely effect system operation
or compromise
TS operability requirements.
4.4
llolded Case Circuit Breaker~Testin
The
team reviewed maintenance
procedure
MPE-64. 1A, "Electrical Maintenance
Procedure
AC and
DC Molded Case Circuit Breaker Test Procedure,"
which was
used
for verifying the operability of molded. case circuit breakers.
Acceptance
criteria .for the testing were contained
on the licensee "List of Electri'cal
Devices for Protection
and Control Circuits" drawing b'050024-15
and were
transcribed
by the craftsmen
on to the data
sheets
of MPE-64. 1A.
The
maintenance
procedure
contained specific sections for testing ma'gnetic only
breakers,
thermal
magnetic
breakers
with adjustable
magnetic trips,
and
thermal
magnetic
breakers
with fixed magnetic trips.
The team reviewed the specified
acceptance
criteria and results of testing for
circuit breaker
a thermal
magnetic
breaker with a fixed magnetic
trip, which was
used to supply the
ED121 battery charger.
The allowable trip
time for the breaker
was required to be 20-132
seconds
at 450 amps,
which was
+ or - 20K of the times specified
on the manufacturers trip curve for the
thermal
element of this breaker.
For the fixed magnetic
element,
the testing
verified that the breaker
would not trip at
a value lower than the lowest
value of the minimum trip range
(750 amps),
and that the breaker
would trip
instantaneously
within the upper
bounds of trip range for the magnetic
element
(2700 amps}.
No adverse
findinas were noted
by the team with regard. to this
procedure.
30
4.5
Fuse Control
The licensee's
fuse control
program
was governed
by a policy letter dated
April 5,
1991 from the Electrical
Maintenance
and Instrument Control Managers,
titled "DCPP
Fuse
Replacement
Policy."
This policy letter replaced
previous
Electrical,
ISC and Operations policy memoranda
issued in 1987..
This policy letter required that:
an Action Request
(AR) be initiated for all
blown fuses,
affected
equipment
be inspected
before replacement,
appropriate
documents
be reviewed
to determine correct replacement
fuses,
proper selection
for containment penetration circuits
be verified, all fuses that may have
been
subject 'to
a fault be replaced
even if they did not blow, and replacement
fuses
be obtained for safety related
equipment
from approved locations.
The team verified that fuse replacement
was controlled by plant approved
work
orders.
The inspector walked
down
some of the accessible
fuses
on
some of the
safety related battery chargers.
The installed fuses
appear ed to be correct.
Based
on review of the above policy letter
, control of fuse replacement
by
approved
work orders,
and sample
walkdown, the
team concluded that the
licensee's
fuse control
p'rogram
was adequate.
4.6
Char er and Inverter Testin
, Surveillance
and Maintenance
The inspecto~
reviewed
sample
surveillance
and maintenance
procedures
and
records for Class
1E battery chargers
and inverters.
.These
procedures
and
records
appeared
to contain
key attributes,
parameters
and acceptance
criteria
to assure
the functionality of the
EDS.
One of the completed
maintenance
procedures
reviewed
was flaintenance
Procedure
(YiP) E-67.3A, Revision ll
"Routine Preventive
Maintenance of Station Battery.Chargers,"
performed
on
Charger ll under
Work Order Number
R72236
on April 8, 1991.
The inspector
found that in Section 7.30, "Voltage Ripple," the acceptance
criteria
specified
was less
than or equal
to
100
mVAC.
The actual ripple voltage
measured
was
108,
650
mVAC.
The Maintenance
Engineer identified that he was
verbally notified about this, per Step 7.30. 1 of the procedure.
However,
there
was
no documented
evidence *that this out of specification condition was
formally dispositioned.
Upon further revigw, the'nspector
learned that two other charger s were tested
previously using the
same
procedure.
Charger
231
was tested
on September
7,
1990,
and Charger
12 was tested
on February 9,
1991.
higher
than
100
mVAC were observed
on these
two chargers.
These
nonconforming
conditions
were documented
in the test reports,
and the Maintenance
Engineer
was notified.
In addition,
AR4 A0202659
and A0217639 were initiated for these
discrepancies.
The System Engineer considered
that the chargers
were
operable'lso,
the Maintenance
Engineer
noted that
a third AR was not
generated
because. of the two pending
ARs for the other
two chargers.
In response
to inspectors
question,
the System Engineer
generated
another
AR8
A0217639 to expedite
the resolution of the two pending
ARs.
On Nay 17,
1991,
the licensee
completed
the evaluation
and concluded that the
100
mVAC
criterion was in fact, overly conservative.
The
new acceptance
criteria was
revised
to
1% of the output voltage (i.e.,
1200
mVAC) per
EPRI guidelines.
The team reviewed this evaluation
and 'concurred with the licensee that the "as
found" ripple voltage
appeared
to have
been acceptable
"as is" and the
, I
31
identified condition
appeared
to have minor safety consequences..However,
~
~
~
~
~
~
failure to generate
an
AR for the third case of out of specification ripple
~voltage
was not in accordance
with Procedure
C-3, "Conduct of Plant
and
'quipment
Tests",
step 4;5.2.a.2.
The inspector considered this to be an
exampl,e of the following weaknesses:
( 1)
The
AR program procedure
NPAC C-12,
"NonConformances,"
did not clearly
require workers to formally document
nonconforming conditions
found
during testing (i.e. quanti tative acceptance
criteria not met) in an
AR.
(2)
The procedure
NPAC C-3, "Performance of Tests
and Surveillances," clearly
required
an
AR to be initiated upon failure to meet
an acceptance
criteria during
a test.
However,
NPAC C-12 and C-3 were not consistent
in this requirement.
(3)
The original
100
mVAC acceptance
criteria was unrealistically
conservative.
The industry standard
was
1% of line voltage
(1200
mV ac
for Diablo Canyon).
The basis
did not appear
to have
been
documented.
(4)
Similar discrepancies
had
been
found
on three chargers
since
September
1990.
The licensee
resolved it after the inspector questioned
the test
report.
The resolution did not appear to have
been timely.
The failure to document
the above
noted nonconforming condition was'identified
as non-cited violation 50-275/91-07-09.
The licensee
took prompt corrective
action
and the safety significance of the nonconforming condition was minimal.
The violation was considered
non-cited in accordance
with 10 CFR 2, Appendix
C, Section
V.A.
4.7
Batt~er
Testing, Surveillance,
and Maintenance
The inspector
reviewed the battery test procedures.
This included the
performance test conducted
every
60 months to assure
the battery capacity is
greater
than or equal
to 80% of the manufacture's
rating,
and the service
tests
conducted
every
18 months
to assure
the batteries
are capable of meeting
the load profile.
These
procedures
appeared
to include the necessary
acceptance
criteria and the.
proper testing steps.
The inspector also
sampled
a report for a recently
completed service test for Station Battery
12.
The service profile defined in
the
DCN appeared
to have
been appropriately
used for the test.
The licensee's
battery testing
program appeared
to be adequate.
4.8
Equipment
Malkdown Inspection
The team inspected
plant equipment within the
EDS 'and
compared
the installed
configurations of the components
with the requirements
of design
documents.
The team verified such attributes
as location, rating, size,
and type.
Additionally, the
team reviewed maintenance
and calibration activities
associated
with the selected
equipment.
32
4.8.1
Transformers
.The team inspected
the unit auxiliary transformer,
standby startup transformer
and load center transformer
on
Bus
1G.
The loading, rating, 'capacity,
and tap
settings
appeared
to be in accordance
with plant drawings
and design
do'cumentation.
However, the
team noted a'ifference
between
Drawing SK
437518,
Revision
12A and the
1G load center transformer.
This drawing
indicated the load center transformer
(1G) impedance
to be 6.75%.
The
nameplate
data indicated this value to be 6.8X.
The licensee
stated that the
6.75%
impedance
was rounded off on the
name plate to 6.8% and the 6.75K
impedance
on the drawing agrees
with the transformer test report data
(Document 663336-8).
4.8.2
Switchgear
and Motor Control Centers
Switchgear
and motor control centers
appeared
to be labeled correctly, easily
identifiable,
and well maintained.
For cabinets
which could be opened
by the
licensee without degrading
seismic qualifications during operation,
compartment
internals
inspected
were free of dust
and debris,
and internal wiring
harnesses
were secured
and not apparently
in the way of moving parts.
4.8.3
Circuit Breakers
'
A comparison of nameplate
data with the design
drawings for General Electric 4
kV and
12
kV magna-Blast circuit breakers
showed that the installed circuit
breakers
appeared
to conform to the documented
requirements
for loads,
voltage,
and interrupting capaci ties.
Visual inspection of accessible
circuits
showed
the breakers
to be clean
and well maintained.
Test procedures
appeared
to be'ell
developed
and contained pertinent vendor test
and
maintenance
requirements.
The data record
package of the procedures
appeared
to provide comprehensive
documentation
of as-found
and as-left conditions.
4.8.4
Cable
and
Race~wa
The team examined
the installation of Class
1E cable to verify that the
installation complied with the requirements
of Section 8.3 of the
FSAR.
The
cable train separation
in trays
and conduit in the cable spreading
room and
switchgear
rooms
appeared
to be maintained in accordance
with the
FSAR.
During this inspection
the
team noted that the licensee
had issued Quality
Evaluation
(QE) Q0008100 identifying circuit and raceway schedule
inconsistencies.
These inconsistencies
included:
raceway routing errors,
missing cable
codes,
duplication of sequence
numbers,
lack of circuit routing
to locations,
locations
not in file, and raceway overfills.
The licensee
stated that the root. causes
for"this quality problem included:
( 1) defects
in
the existing program (wire route), which allowed blank data fields (missing
data)
to be input into the system;
and (2) the responsibilities for design
and
data entry were previously in one area of responsibility.
This concept did
not allow for checks
and balances
to assure all data
had
been
entered
correctly.
To correct these deficiencies,
the licensee
was implementing
a
new program
entitled
"SET Route."
Data is presently
being converted
and transferred
from
the old wire route program to the
new
SET route program.
The licensee
plans
to complete
the conversion
and
have all deficiencies
resolved within 24
~
't
~
Ss
33
months.
The team inspected
portions of the
SET route program
and noted that
corrective actions
were being completed
and the concerns
noted
above
appeared
to be'encompassed
by this corrective action.
4.8.5
Low VoltaSeeS
stems
.
The team inspected
the
1E and,non-lE
120
V ac and
125
V dc systems,
including
chargers,
inverters,
and batteries.
Equipment condition and configuration
appeared
to be adequate,
and plant condition and cleanliness
appeared
good.
4.8.6 ~8~i
The team inspected
several
of the safety related
pump areas,
including the
auxiliary sa)t'ater
pump, auxiliary feed water
pump,
component cooling water
pump',
and safety injection
pump
rooms.
In addition, it appeared
that plant
cleanliness
was generally
good.
Seismic tie downs, were observed
to be. in
place for temporary
equipment
and tools.
4..7
~6 ~i1
6
The team inspected
the five EDGs.
Except for specific concerns
documented
earlier in this report,
the material condition of the
EDGs appeared
to be
good.
4.9
E ui ment Hodification Review
4.9.1
DCP-41644-Install
Cable~Sread~in
Room Air Condi tion~in
System
DCP-41644 involved installation of an air conditioning unit for the cable
spreading
room to provide
a relatively constant
temperature
for electronic
devices,
in order to promote service life.
The team reviewed the
DCP and
concluded that the changes
appeared
to be acceptable.
4.9.2
Transformer
V~olta e-Chandte
The team reviewed the unit auxiliary and startup transformers'ap
change
modification package,
DCP E-44355,
Revision
1, dated 2/22/90.
The subsequent
effect of the. change
had
been factored into the load flow and voltage drop
calculations,
96 A-DC and
96 8-DC.
The modification appeared
to be
acceptable.
4
.8 ~Eil
I
ET "I
I de
5. 1
Identi fi ca tion of Noncon formi no Condi tions
The team reviewed the procedures
which identify an'd evaluate
nonconforming
conditions,
and require documentation
of the identification of a problem.
As noted earlier in the report,
Procedure
C-3, "Conduct of Plant
and Equipment
Tests" stated
that observations
found outside of acceptance
require that
an
Action Request
(AR) be written to document
the nonconformance.
However,
a
higher tier procedure,
C-12,
"Nonconformances,"
which listed several
examples
of instances
requiring initiation of an
AR, did not note the specific
situation where procedural
acceptance
criteria were not met.
This is an
.example of a lack of consistency
in the requirements
to document
a
nonconforming condition or to initiate a problem identification document.
As noted earlier in this:report,
the team identified two occurrences
where
problems
were identified without prompt formal documentation.
Specifically,
these
included
the- open
EDG radiator door and the inverter ripple voltage that
did not meet its acceptance
cri teria.
Each of these
instances
appear
to be
violations of 10 CFR 50, Appendix B, Criterion XVI , which requires,
in part,
that conditions adverse
to quality be promptly identified. In each of these
cases,
the licensee
appeared
to have taken prompt, appropriate corrective
action,
and the safety significance
was minimal.
These violations were
identified as non-cited in accordance
with 10 CFR 2, Appendix C, Section
V.A.
5.2
Review of Selected
and Root Cause Analysis
The team reviewed several
Nonconformance
Reports
(NCRs) written
on the
EOS.
lJith the exception of instances
documented
elsewhere
in this report,
the
appear
to have
been dispositioned appropriately,
and the associated
safety
evaluations
appeared
to be adequate.
During the
teams
review of electrical related
NCRs,
two NCRs that concerned
failures of an
EDG to start
and load within TS requirements
were identified.
In the first case,
documented
in
NCR DCI-91-TN-N032,
EDG 1-1 took
approximately
19.8 seconds
to start
and load after offsite power was lost on
March 7,
1991.
In this instance diesels
1-2 and 1-3 started
and were loaded
to the vital buses within the ten second
requirements.
In the second
case,
documented
in
NCR DCI-91-TN-N035,
EDG 1-2 took 19.6
seconds
to start
and load
during the performance of Surveillance
Test Procedure
M-15, "Integrated Test
of Engineered
Safeguards
and Diesel
Generators".
on March 18,
1991.
TS 4.8. 1. 1.2.a requires,
in part, that
EDG starts
be verified by the
EOG
accelerating
to at least
900
RPM in less
than or equal
to 10 seconds
and
voltage
and frequency
be 4160
+ or - 420 volts and
60 + or - 1.2
Hz within 13
seconds
after
the start signal.
TS 4.8.1. 1.2.a also requires,
in part, that
EDG testing frequency
be in accordance
with TS Table 4.8-1.
TS Table 4.8-1 requires
EDG testing frequency that is dependent
on the number
of valid tests
and test fai lures.
TS Table 4.8-1 requires that the criteria
for determining
the
number of valid tests
and failures
be in accordance
with
Position c.2.e of Regulatory
Guide
(RG) l. 108, Revision
1.
RG 1. 108, Revision
1, defines "Failure" as the failure to start, accelerate,
and
assume
the
design rated
load within the 'time prescribed
during an emergency
or valid
test.
Position C.2.e of
RG 1. 108, Revision 1, requires,
in part, that all
start attempts
that result in failure to start,
be considered
valid tests
and
failures except if the fai lure can
be definitely attributed to
a malfunction
of equipment that is not
a part of the defined
EOG unit design.
Although the licensee
performed extensive testing relative to these failures,
the exact cause of the first fai lure has yet to be determined'.
The second
failure has
been attributed to the first level instantaneous
relay which detects
the loss of power to the vital bus.
The inspection
team
expressed
several
concerns
as
a result of the review of the two NCR's.
35
~
~
~
~
~
~
(1)
Although the cause of failure for diesel
generator l-l has yet to be
determined,
this failure was incorrectly classified
by the licensee
as
being
"non valid".
The basis of the licensee's
classification,
as
documented
in paragraph
IV.B.2 of NCR DCI-91-TN-N032, and as explained
initially by the licensee,
was that draft Regulatory
Guide 1.9 states
that if a diesel fails to load, but eventually loads in a few minutes
without any corrective maintenance,
the failure should
be considered
non-valid.
This appeared
to the
team
as
a licensee
interpretation
of Regulatory
Guide 1.9 based
on guidance
contained
in a
NUMARC paper
that was contrary to the
NRC position
on this subject.
In addition,
paragraph
C.2.e.(2) of NRC Regulatory
Guide 1.108 states
that an
unsuccessful
start or load attempt should
be considered valid unless
the
unsuccessful
start or load attempt
can definitel
be attributed to spurious
operation of a trip that is bypassed
in t e emergency
operating
mode, or
malfunction of equipment that is not operational
in the emergency
mode or
is not part of the defined diesel
generator unit design.
The determination
that the
EDG 1-1 failure to load within 10 seconds
on March 7,
1991
was
an invalid failure was identified as Violation 91-07-10.
(2)
The similarity of both failures which occurred within 11 days of each
other brings into question
the reliability of the circui try and logic
associated
with starting the, diesel
generators.
Although one of the
failures
has
been attributed to
a faulty first level undervoltage
relay,
the inability of the licensee
to determine
the
ca'use of the other
failure,
and the potential for a
common
mode failure with respect to
starting the diesels
was of concern to the inspection
team.
(3)
As noted in paragraph
4. 1 of this report, surveillance
test procedure
M-9I, which is used
by the licensee
for documenting
and evaluating diesel
starts,
did not contain adequate
acceptance criteria.
Paragraphs
8.4 and
8.5 of the procedure
only required that the diesel start
and load
1300
Kw.
No specific time limits for starting
and loading are contained
in
the procedure,
even
though the diesel
is required to start
and load
within 10 seconds
in order to be considered
a valid successful
start.
5.
5
1
d
d
Based
on the team consensus
and specific inspection in the area,
the licensee
appears
to have
a strong
program for control
and evaluation of vendor
information.
Based
on response
to industry
and
NRC generic concerns,
and based
on
aggressive
evaluation of the
NRC EDSFI findings at other utilities with
respect
to applicability at
OCPP,
the licensee
appears
to have
implemented
an
effective program to control
and evaluate
industry information.
6.0
General
Conclusions
The Diablo Canyon
EDS and supporting
systems,
with exceptions
noted in the
report,
appeared
to be capable of fulfilling its design function requirements.
Except for instances
noted in the report,
the engineering
and technical
support staff appeared
to be well trained
and appeared
to be fulfillingthei r
required functions.
4
36
7.0
Unresolved
Items
Unresolved
items are matters
about which more information is required to
determine, whether they are acceptable
or
may involve violations or
deviations.
Unresolved
items identified during this inspection
are
listed in Attachment 2.
"
8.0
Exit Meeting (30703)
The inspection
scope
and findings were summarized
on Nay 24,
1991 with
those
persons
indicated in Attachment
1 of this report.
The areas
inspected
and the inspection findings listed in Attachment
2 were
discussed.
The licensee
acknowledged
the
team findings.
~g
37
Attachment
1
Persons
Contacted
Pacific
Gas
and Electric
C~om an~
- N. Angus, Technical
Services
Manager
- R. Anderson,
Nuclear Engineering
and Construction
Services
Manager
W. Barkhuff, Quality Control Manager
- N. Basu,
Senior Electrical Engineer
T. Bennett,
Mechanical
Maintenance
Manager
- J. del Nazo, Senior Mechanical
Engineer
R.
Domer, Engineering
and Construction
General
Vice
President
- T
- W
T.
- B
- J
C.
- p
- D
- G
D.
R.
- H
- W
- B
- D
- D
- J
- N
- A.
NRC
Fetterman,
Electrical
Group Supervisor
Fujimoto,
NTS Vice President
Grebel,
Regulatory
Compliance Supervisor
Giffin, Maintenance
Services
Manager
Griffin, Regulatory
Compliance Senior Engineer
Groff, System Engineering
Manager
Lang, Quality Control Senior Engineer
Niklush, Manager of Operations
Services
Norris, Response
Team Consultant
Oatley,
Support Services
Manager
Ortega, Electrical
Plant'System
Engineer
Phillips, Electrical Maintenance
Manager
Rapp,
On Site Review Group Chairman
Smith, Supervising Electrical
Engineer
Spalding,
Mechanical
Engineer
Taggert,
OPIA Director
Townsend,
Vice President
and Manager of Operations
Tresler,
Nuclear Engineering Project Engineer
Young, Senior Quality Assurance
Supervisor
- R. Zimmerman, Division Director, Region
V
J. Dyer, Director,
PDV,
- D. Kirsch, Branch Chief, Region
V
P. Narbut, Senior Resident
Inspector
- K Johnston,
Resident
Inspector
The inspectors
also held discussions
wi th other licensee
and contractor
personnel
during the course of the inspection.
- Attended the exit meeting
on Nay 24,
1991.
~P
tq
~e
~
~
38
~
~
~
~
~
~
~
Appendix
2 - EDSFI
Team Inspection
Findings
I
' 1..
MEAKNESS - 2. 1.3. 1 - Numerous modelling inaccuracies
contained
in the
load flow and voltage drop calculations
resulted in the validity of the
calculations
being questioned.
The inaccuracies
also resulted
in the
questioning of the adequacy of the licensee's
calculation review process.
i
2.
3.
4.
5.
7.
8.
9.
10.
WEAKNESS - 2.2. 1(c) - Non-conservative
cable resistance
value
was
used
for the 4160
V short circuit calculation
(96A-DC).
However sufficient
margin existed
, as demonstrated
by the calculation,
to compensate
for
the non-conservative
assumption.
UNRESOLVED ITEM 91-07-01 - 2.2.2 - A documented
technical
basis for the
increased
short circuit interrupting current rating for the 4160
V ac
breakers
needed
to be obtained
by the licensee
from the vendor.
UNRESOLVED ITEM 91-07-02 - 2.2.5 - An analysis
to determine
the effects
of degraded
grid voltage
on the operability of YiOVs and
120
V ac
needed
to be completed
and any .necessary
setpoint
changes
determined
by the analysis
needed
to be implemented.
UNRESOLVED ITEM 91-07-03 - 2.3. 1 - An
FSAR change
needed
to be submitted
to NRR,
and reviewed
and approved
by NRR, to reflect differences
between
EDG loads listed in the
FSAR and
EDG loads established
in licensee
ca 1 cul ations.
WEAKNESS - 2.4.1 - Minor errors
were noted in calculation
15-DC, Revision
5, regarding
the loads
imposed
by the containment
fan coolers
and the
backup battery charger.
The 20 percent margin in the load center
equipment rating,
however,
compensated
for the errors.
UNRESOLVED ITEM 91-07-04 - 2.6.3 - The methodology
and inconsistencies
contained
in calculations
126-DC, 7/25/83,
and
1956-DC, 5/17/91, for MOVs
require further review during future
MOV inspections.
VEAKNESS '- 2.8 - Routing of emergency lighting going to
a containment
did not appear to be well engineered
in that the routing was
such that overcurrent protection
was jeopardized.
MEAKNESS - 3.1.1 - The
EDG fuel oil consumption calculation,
M-786,
Revision
1, used
a non-conservative
fuel oil specific gravity
average
value in lieu of the minimum allowed by Technical Specifications.
The
non-conservatism,
however,
was compensated
by the sites
EDG fuel oil
storage
inventory requirements.
k'EAKNESS - 3.1.1 - A licensee "Justification for Continued Operation"
(JCO), established
in February,
1989, to assure
adequate
EDG fuel oil
inventory was maintained, still needed
to be resolved during the May,
1991 inspection.
UNRESOLVED ITEM 91-07-05 - 3. 1.3 - The licensee
needed
to perform or
obtain calculations
to establish
maximum
EDG jacket water
and lube oil
temperatures
under
maximum design
ambient
temperatures
to ensure
that
vendor established
limits would be met.
In addition,
an evaluation of
~
~
39
the
need to change
the high
EDG jacket water and lube oil temperature
response
procedure
was
needed.
Further inspection
was also
required,
to determine
the adequacy of licensee
nonconforming condition
identification, evaluation
and performance of any analysis,
and
performance of any resultant corrective action, for high
EDG jacket water
and lube oil temperature
alarms that were experienced
during
EDG 1-1
STPM-96 surveillance
testing performed in November,
1989.
12.
NON-CITED VIOLATION 91-07-06 - 4.1 -
EDG 1-3 radiator door was required
to be shut
and locked but was found open.
The licensee
took prompt
corrective action
and the safety significance
appeared
to be minimal.
13.
VIOLATION 91-07-07 - 4. 1 - Acceptance criteria contained
in an
surveillance test procedure
did not fully implement Technical
Specifications
surveillance test requirements.
Two other
surveillance test procedures
data
sheets
were poorly written in relation
to the acceptance
criteria
and were considered
h'EAKNESSES.
14.
VIOLATION 91-07-07 - 4. 1. 1 - Additional example - Procedure
STP-V302,
Revision 1, allowed
EDG air start system
check valves to leak 30 psig
in 10 seconds.
No documented
technical
basis
existed for the acceptance
criteria.
The licensee
needed
to establish
a leak rate
and
a documented
technical
basis for the leak rate.
15.
NON-CITED VIOLATION 91-07-08 - 4.6 - Battery Charger
11
had
a ripple
voltage slightly above
the acceptance
criteria during performance of
preventative
maintenance
on April 18,
1991
and
was not identified in an
appropriate
nonconforming condition report.
However,
the acceptance
criteria was determined
by the licensee
to be overly conservative,
the
condition had minimal safety significance,
the licensee
took prompt
corrective action
and it appeared
to be
an isolated
case.
16.
VIOLATION 91-07-09 - 5.2 -
EDG 1-1 did not start,
get to rated
speed
and
voltage
and load within the
10 second
Technical Specification
time limit
during the March 7,
1991 Unit
1 loss of offsite power event.
The failure
was considered
an invalid failure, although
the cause
had not been
definitely determined,
contrary to Technical Specification 4.8. 1. 1. 1.2.a
and Regulatory
Guide
1. 108.
4~