ML16342A842

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/99-06 & 50-323/99-06 on 990418-0529.Two Violations Noted & Being Treated as Noncited Violations. Major Areas Inspected:Aspects of Licensee Operations,Maint, Engineering & Plant Support
ML16342A842
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 06/25/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML16342A843 List:
References
50-275-99-06, 50-275-99-6, 50-323-99-06, 50-323-99-6, NUDOCS 9907060172
Download: ML16342A842 (28)


See also: IR 05000275/1999006

Text

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket Nos.:

License Nos.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved By:

50-275

50-323

DPR-80

DPR-82

50-275/99-06

50-323/99-06

Pacific Gas and Electric Company

Diablo Canyon Nuclear Power Plant, Units 1 and 2

7 ~/a miles NW of Avila Beach

Avila Beach, California

April 18 through May 29, 1999

David L. Proulx, Senior Resident Inspector

Dyle G. Acker, Resident Inspector

James

F. Melfi, Project Engineer

CliffordA. Clark, Reactor Inspector.

Linda J. Smith, Chief, Project Branch E

ATTACHMENT: Supplemental Information

'P'P070b0i72

990b25

PDR

ADQCK 05000275

8

PDR

EXECUTIVE SUMMARY

Diablo Canyon Nuclear Power Plant, Units

1 and 2

NRC Inspection Report No. 50-275/99-06; 50-323/99-06

This inspection included aspects of licensee operations, maintenance,

engineering, and plant

support.

The report documents inspection performed during a 6-week period by the resident

inspectors.

~Oerations

Two examples of a noncited violation of Technical Specification 6.8.1.a, in accordance

with Appendix C of the NRC Enforcement Policy, were identified for failure to follow

procedures.

In the first example, carpenters installed a scaffold that blocked a fire

suppression sprinkler in the area of a component cooling water pump, in violation of the

scaffolding procedure.

In the. second example, operators improperly implemented

Equipment Control Guideline 18.4, after declaring the fire suppression

system

inoperable in the area of component cooling water Pump 1-3. Operators initiated an

hourly fire tour instead of a continuous firewatch as required by Equipment Control

Guideline 18.4. The fire protection engineer performed a subsequent

review that

determined that the fire suppression

system was degraded,

but operable.

Four other

recent operator errors, with respect to implementation of the Equipment Control

Guidelines, indicated that improvement was necessary

in this area.

These two

examples of the violation were placed in the corrective action program as Action

Requests A0485075 and A0484540 (Section F1.1).

Maintenance

Maintenance and surveillance activities observed were performed properly

(Sections M1.1 and M1.2).

~En ineerin

I

The design change package associated

with the auxiliary saltwater vault drain system

was an example of sound enginee'ring and was designed to improve the reliability of the

associated

check valves.

The licensee installed y-strainers and low-point drains to help

remove foreign material from the drain system to minimize fouling of the check valve

seating surfaces (Section E1.1).

A noncited violation, in accordance with Section VII.B.1 of the NRC Enforcement Policy,

was identified for failure to implement Technical Specifications 4.0.5 and 3.7.3.1.

Specifically, in July 1997, the licensee used pump curves instead of the required

reference values in development of acceptance

criteria for inservice testing of the

component cooling water pumps.

The licensee subsequently submitted a relief request

to correct this violation (Section E8.2).

-2-

Plant Su

ort

Routine radiation protection practices were performed well in that personnel donned

protective clothing and dosimetry properly apd that radiological barriers were properly

posted (Section R1.1).

Routine security activities were performed well in that the security officers were alert at

their posts, security boundaries were being maintained properly, and screening

processes

at the Primary Access Point were performed properly (Section S1.1).

Summa

of Plant Status

Unit 1 began this inspection period at 100 percent power.

Unit 1 continued to operate at

essentially 100 percent power until the end of this inspection period.

Unit 2 began this inspection period at 100 percent power.

On April25, 1999, operators reduced

power to 50 percent to support cleaning in the circulating water tunnels.

Following completion

of the circulating water tunnel cleaning, operators returned Unit 2 to 100 percent power on

May 1. Unit 2 continued to operate at essentially 100 percent power until the end of this

inspection period.

I. ~Oerattone

01

Conduct of Operations

01.1

General Comments

71707

The inspectors visited the control room and toured the plant when on site, including

periodic backshift inspections.

Overall, the performance of plant operators reflected a

focus on safety.

Operators frequently implemented self- and peer-checking

in the

performance of routine duties. The use of three-way communications continued to

improve, and operator responses

to alarms were observed to be prompt and appropriate

to the circumstances.

The inspectors noted that operators carefully conducted power maneuvers to support

the Unit 2 circulating water tunnel cleaning, in accordance with procedure requirements.

II. Maintenance

M1

Conduct of Maintenance

a.

Ins ection Sco

e 62707

The inspectors observed portions of work activities covered by the following work

orders:

Work Order

C0161922

~Deacri tion

Centrifugal Charging Pump 2-1 Attempt to Correct Gear Oil Hl

Temperature

-2-

R0189573

R0167678

Calibration of Centrifugal Charging Pump 2-1 Gauge Pl-782

Inspection and PM of CS-2-9001B, with Replacement of Torque

Limiter Plate Per MMD M000073

R0187659

C0128646

Preventive Maintenance on Containment Spray Pump 2-2

Install Splice Plates for Residual Heat Removal Pump 2-1 Seismic

Supports

b.

Observations and Findin s

The inspectors concluded that the applicable work orders were performed properly.

Operators initiated the clearances

properly, and probabilistic risk assessments

were

satisfactorily performed prior to the work.

M1.2

Surveillance Observations

a.

Ins ection Sco

e 61726

The inspectors obse'rved portions of the performance of Procedure STP M-9A, "Diesel

Generator Routine Surveillance Test," Revision 53A, and Procedure STP M-89,

"Emergency Core Cooling System Venting," Revision 28.

b.

Observations and Findin s

The inspectors found that the licensee performed these surveillance tests properly and

documented the data properly. Operators satisfactorily performed risk assessments

'rior

to removing the applicable systems from service.

M8

Miscellaneous Maintenance Issues (92700, 92902)

M8.1

Closed

Licensee Event Re ort LER 50-323/97-005-00:

Reactortripandsafety

injection caused by inadvertent main steam isolation valve closure because of personnel

error.

This issue was discussed

in detail and dispositioned in NRC Inspection Report

50-275; 323/97-19.

No new issues were revealed upon review of this LER.

-3-

E1

Conduct of Engineering

E1.1

Desi

n Chan

e Packa

e Review

a.

Ins ection Sco

e 37551

The inspectors reviewed Design Change DCP P-49392 to determine if the proper

design controls were implemented.

b.

Observations and Findin s

The licensee implemented Design Change DCP P-49392 during Refueling Outage 1R9.

The purpose of this design change was to install newly designed check valves,

y-strainers, and low-point drains on the Unit 1 auxiliary saltwater pump vault drains to

improve the reliability of the associated

check valves.

NRC Inspection Report 50-275;

323/97-14 identified several issues associated

with the auxiliary saltwater pump vault

drain check valves.

These valves were noted to be unreliable, since these check valves

were found to be stuck in the open position during periodic surveillances because

of

foreign material on the seats.

This rendered the check valves unable to perform their

intended safety function of preventing back flow into the auxiliary saltwater pump vault

during postulated intake structure flooding. Design Change DCP P-49392, which

installed y-strainers and low-point drains upstream of the check valves, was developed

to help minimize the deposition of foreign material on the check valve seating surfaces.

The inspectors also reviewed the as-built drawings and applicable preventive

maintenance

instructions and noted that these items were satisfactorily revised to reflect

Design Change DCP P-49392.

From these reviews, the inspectors determined that

Design Change DCP P-49392 was an example of sound engineering.

c.

Conclusions

The design change package, associated

with the auxiliary saltwater vault drain system,

'as

an example of sound engineering and appeared to improve the reliability of the

associated

check valves.

ES

Miscellaneous Engineering Issues (92700)

E8.1'losed

Ins ection Followu

Item

IFI 50-275 323/97003-01:

periodic testing required

for main feedwater pump turbine stop valves.

This foilowup item was opened after a loss of main feedwater Pump 2-1 and a reactor

trip on March 29, 1997, when the licensee discovered that the main feedwater pump

turbine stop valves had a design basis specification to close within 5 seconds, but were

not tested to verify this criterion. This followup item involved reviewing the licensee's

resolution for testing of the stop valves.

-4-

Backcaround

After a reactor trip, the licensee identified an equipment problem with the main

feedwater Pump 2-1 governor valve, in which it did not shut promptly because

of

particulates in the main feedwater Pump 2-1 control oil system.

The licensee resolved

this problem, but also questioned other aspects of the main feedwater pump control

system, including whether this failure could affect the main feedwater turbine stop

valves.

A quality assurance

audit determined that certain design basis

accident'equences

relied upon these turbine stop valves to close to limitthe amount of

. feedwater entering containment by stopping the main feedwater pumps.

Further review

identified that the main feedwater pump stop valves were not tested to verify that they

would satisfy the design basis requirements.

The inspectors opened the followup item

to assess

the licensee's resolution of not testing these stop valves.

Assessment

At the time of the reactor trip, the licensee performed a prompt operability assessment

that concluded that the valves were operable based upon startup tests performed on the

main feedwater pumps.

The inspectors found that the licensee implemented

surveillance procedures to test these valves and issued License Amendment Request

98-05 on August 10, 1998, to include a trip response time for the main feedwater

pumps.

The licensee tested these valves using'Procedure

STP V-3P7, "Timing Test-

Main Feedwater Pump Stop Valves." The inspectors considered the licensee's actions

appropriate.

The licensee had Technical Specifications (TSs) that did not assure that the design

basis was maintained for the plant. Title 10 CFR 50.36(c)(2)(ii)(C) states that a TS

limiting condition for operation must be established, for each item that is a structure

.

system or component that functions to mitigate a design basis accident or transient that

presents a challenge to the integrity of a fission product barrier.

Limiting how much

feedwater enters containment was considered important for a postulated feedwater line

or steam line break in containment to limitthe height of water in containment or the

extent of a cooldown of the reactor coolant system.

However, 10 CFR 50.36(c)(2)(iii)

states that licensees are not required to revise TSs issued prior to April 1995 to meet

the requirement concerning the proper content of limiting conditions for operation.

Because the TSs were initiallyissued without including the surveillance of the main feed

pump turbine stop valves, no violation of NRC requirements occurred and this followup

item is closed.

Closed

LER 50-275/97-012-00:

TSs 3.7.3.1 and 4.0.5 not met because

of personnel

error.

In July 1997, the licensee identified that the inservice testing requirements were not met

for component cooling water (CCW) Pump 1-3, because

of an inadequate test

procedure.

This error occurred, in part, because

of changes

in code requirements for

the second 10-year inservice testing interval and a failure to implement required

procedure changes before the next required inservice test.

The CCW pump test

-5-

F

procedure did not comply with TS 4.0.5 and ASME Operations and Maintenance Part 6

requirements as clarified by NUREG-1482. The licensee used pump curves instead of

reference values in determining the acceptance

criterion.

The licensee revised the surveillance test procedures for the CCW pumps to comply

with ASME Operations and Maintenance Part 6, prior to subsequent surveillance tests.

~

Anaiysis of the test results did not show any actual degradation of CCW Pump 1-3.

As corrective actions for this LER, the licensee submitted a relief request to allow using

pump reference curves for the CCW pump testing and performed an Independent

assessment

of the inservice testing program to ensure that all required relief requests

have been submitted.

The licensee received approval for the relief request for the CCW

pumps on February 25, 1998. The licensee has also submitted a relief request for the

auxiliary saltwater pumps.

The inspectors determined that the failure to test CCW Pump 1-3 in accordance

with the

ASME code was a violation of TSs 4.0.5 and 3.7.3.1.

This nonwillful, licensee-identified

and corrected violation is being treated as a noncited violation consistent with

Section VII.B1 of the NRC Enforcement Policy (50-275/99006-01).

E8.3

Closed

LER 275 323/97-003-00:

Reactor vessel level indication system outside

design basis due to personnel error and inadequate vendor communication.

This LER identified an error with their calibration of their reactor vessel level indication

system during an evaluation for the transition to a 24-month fuel cycle. This situation

was discussed

in NRC Inspection Report 50-275;323/97-02.

The inspectors reviewed

this LER and did not identify any new issues, and concluded that the

licensees'orrective

actions were adequate.

This LER is closed.

R1

R1.1

Radiological Protection and Chemistry Controls

T

General Comments

71750

S1

S1.1

The inspectors evaluated radiation protection practices during plant tours and work

observation.

The inspectors determined that routine radiation protection practices were

performed well in that personnel donned protective clothing and dosimetry properly and

that radiological barriers were properly posted.

Conduct of Security and Safeguards Activities

General Comments

71750

During routine tours, the inspectors assessed

the conduct of security and safeguards

activities. The inspectors concluded that routine security activities were performed well

in that the security officers were alert at their posts, security boundaries were being

maintained properly, and screening processes

at the Primary Access Point were

performed properly. During backshift inspections, the inspectors noted that the

protected area was properly illuminated.

Control of Fire Protection Activities

Scaffoldin

Controls

Ins ection Sco

e 71707

The inspectors evaluated the effect of installed scaffolding on safety-related structures,

systems, and components.

Observations and Findin s

Scaffolding Installation

During tours of the facility, the inspectors evaluated the effect of installed scaffolding on

safety-related systems with respect to fire protection.

On May 19, 1999, the inspectors

noted that carpenters erected a scaffold above CCW Pump 1-3. The licensee used this

scaffold for work on penetration seals.

The inspectors noted that the scaffold had the

appropriate seismic qualification and did not interfere with CCW system operation.

However, the inspectors noted that the carpenters installed the scaffold platform such

that the platform blocked the fire suppression sprinkler nozzle above CCW Pump 1-3.

The inspectors were concerned that the fire suppression

capabilities were impaired

without compensatory measures

and notified the shift supervisor of this deficiency..

The shift supervisor inspected the scaffold and agreed that the scaffold impaired the

functionality of the fire suppression system.

The shift supervisor initiated Action

Request (AR) A0485075 to e'nter this item into the corrective action system.

In addition,

the shift supervisor added the impaired sprinkler to the hourly firewatch tour.

The inspectors noted that Procedure AD7.ID5, "Scaffold Material Structures,"

Revision 4A, Section 6.3.7.g, stated that scaffold structures shall not block

passageways,

walkways, fire suppression

equipment, emergency lighting, or personnel

exits. Because carpenters erected a scaffold that obstructed a sprinkler near CCW

'Pump 1-3, the licensee did not comply with this procedure.

TS 6.8.1.a requires the

licensee to implement procedures as recommended

in Regulatory Guide 1.33,

Appendix A, Revision 2. Regulatory Guide 1.33, Appendix A, recommends

administrative procedures,

and Procedure AD7.ID5 partially implemented this

requirement.

Therefore, failure to implement Procedure AD7.IDS is the first example of

a violation of TS 6.8.1.a.

However, this Severity Level IVviolation is being treated as a

noncited violation, consistent with Appendix C of the Enforcement Policy. This violation

example is in the corrective action program as AR A0485075 (50-275/99006-02,

Example 1).

-7-

Licensee investigation of this issue revealed that Procedure AD7.ID5 provided thorough

instructions for the carpenters to follow to ensure that safety-related systems were not

impaired during scaffold installation.

However, Procedure AD7. ID5 contained only

vague direction with respect to operator and engineering walkdowns of scaffolds. The

licensee was evaluating enhancements

to Procedure AD7.ID5 at the end of the

inspection period.

b.2

Operator Response

to Scaffold Problem

The inspectors subsequently reviewed the operator response

to the deficient scaffold.

The inspectors noted that operators considered the fire suppression system for the

vicinityof CCW Pump 1-3 inoperable and implemented Equipment Control

Guideline 18.4, "Sprinkler/Spray Systems."

Equipment Control Guideline 18.4 required

that, if a fire suppression sprinkler system was inoperable in an area containing fire

protection safe shutdown equipment, a continuous firewatch was required.

If a fire

suppression sprinkler or spray system was inoperable in an area without safe shutdown

equipment, an hourly firewatch tour of the area was required.

The licensee's safe

shutdown analysis credited the CCW pumps; therefore, upon discovery that the fire

suppression sprinkler was inoperable, a continuous firewatch was required.

However, operators mistakenly directed that the area of CCW Pump 1-3 be added to

the hourly firewatch tour because of insufficient knowledge of Equipment Control

Guideline 18.4. AR A0484540 and Quality Evaluation Q0012134 were updated to

include this operator error. Quality Evaluation Q0012134 contained four additional

examples of operators failing to properly implement Equipment Control Guidelines.

The

licensee addressed

these errors on a generic basis.

The inspectors considered the

licensee response

to operator performance issues appropriate.

Procedure OP1.DC16, "Control of Plant Equipment not Required by the Technical

Specifications," Revision 2A, Section 5.4.4, stated that the required actions of the

Equipment Control Guidelines shall be implemented.

Because the operators failed to

properly implement Equipment Control Guideline 18.4 when the fire suppression system

was inoperable, this procedure requirement was not met.

TS 6.8.1.a requires the licensee to implement procedures as recommended

in

Regulatory Guide 1.33, Appendix A, Revision 2. Regulatory Guide 1.33, Appendix A,

recommends administrative procedures,

and Procedure OP1.DC16 partially

implemented this requirement.

Therefore, failure to implement Procedure OP1.DC16 is

the second example of a violation of TS 6.8.1.a.

However, this Severity Level IV

violation is being treated as a noncited violation, consistent with Appendix C of the

Enforcement Policy. This violation example is in the corrective action program as

AR A0484540 (50-275/99006-02, Example 2).

The licensee's fire protection engineer evaluated the as-found condition of the scaffold.

The fire protection engineer noted that, although the sprinkler above the scaffold

platform could not perform its function, another sprinkler head existed in the area of the

pump. Therefore, the fire protection engineer determined that the fire suppression

0

-8-

system in the area was degraded but operable.

The fire protection engineer directed

that, as a prudent compensatory'measure,

an hourly firewatch tour be in place and no

combustible materials be allowed in the vicinityof CCW Pump 1-3. The inspector

determined that these measures

were appropriate.

Conclusions

Two examples of a noncited violation of TS 6.8.1.a, in accordance

with Appendix C of

the enforcement policy, were identified for failure to followprocedures.

In the first

example, carpenters installed a scaffold that blocked a fire suppression sprinkler in the

.

area of a CCW pump, in violation of the scaffolding procedure.

In the second example,

operators improperly implemented Equipment Control Guideline 18.4, after declaring the

fire suppression system inoperable in the area of CCW Pump 1-3. Operators initiated

an hourly firewatch tour instead of a continuous firewatch as required by Equipment

Control Guideline 18.4. The fire protection engineer performed a subsequent

review

that determined that the fire suppression

system was degraded but operable.

Four

other recent operator errors, with respect to implementation of the Equipment Control

Guidelines, indicated that improvement was necessary

in this area.

These two

examples of the violation were placed in the corrective action program as

ARs A0485075 and A0484540.

V. Mana ement Meetin s

X1

Exit Meeting Summary

L

The inspectors presented the inspection results to members of licensee management at the

conclusion of the inspection on June 9, 1999. The licensee acknowledged the findings

presented.

The inspectors asked the licensee whether any materials examined during the inspection

should be considered proprietary.

No proprietary information was identified.

ATTACHMENT

SUPPLEMENTAL INFORMATION

PARTIALLIST OF PERSONS CONTACTED

Licensee

J. R. Becker, Manager, Operations Services

W. G. Crockett, Manager, Nuclear Quality Services

R. D. Gray, Director, Radiation Protection

T. L. Grebel, Director, Regulatory Services

D. B. Miklush, Manager, Engineering Services

D. H. Oatley, Vice President and Plant Manager

R. A. Waltos, Manager, Maintenance Services

L. F. Womack, Vice President, Nuclear Technical Services

INSPECTION PROCEDURES (IP) USED

IP 37551

IP 6-1 726

IP 62707

IP 71707

IP 71750

IP 92700

IP 92902

IP 92903

Onsite Engineering

Surveillance Observations

Maintenance Observation

Plant Operations

Plant Support Activities

Onsite Follow up of Written Reports of Nonroutine Events at Power

Reactor Facilities

Follow up - Maintenance

Follow up - Engineering

ITEMS OPENED AND CLOSED

~Oened

None.

Closed

50-323/97-005-00

LER

Reactor trip and safety injection caused by inadvertent main

steam isolation valve closure because of personnel error

(Section M8.1)

50-275; 323/

97-003-01

IFI

Periodic testing requirements for main feedwater pump

turbine stop valves (Section E8.1)

50-275/97-012-00

50-275; 323/

97-003-00

LER

TSs 3.7.3.1 and 4.0.5 not met because

of personnel error

(Section E8.2)

LER

Reactor vessel level indication system outside design basis

(Section E8.3)

0 ened and Closed

50-275/99006-01

NCV

50-275/99006-02

NCV

Failure to properly implement the inservice testing program

for a component cooling water pump (Section E8.2)

Two examples of failure to followadministrative procedures

'Section F1.1)

i

LIST OF ACRONYMS USED

ASME

AR

CCW

IFI

IP

LER

NCV

NRC

PDR

TS

American Society of Mechanical Engineers

action request

component cooling water

inspection followup item

inspection procedure

licensee event report

noncited violation

Nuclear Regulatory Commission

Public Document Room

Technical Specification

)

I