ML16341D450

From kanterella
Jump to navigation Jump to search
Insp Rept 50-323/85-27 on 850810-16 & 0904.No Violation Noted.Major Areas Inspected:Status of Fire Detection/Alarm Sys for One Fire Zone & Procedures Used to Identify Operational Status of Equipment in Need of Repair & Maint
ML16341D450
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 09/19/1985
From: Chaffee A, Crews J, Huey R, Andrea Johnson, Polich T, Waite R, White R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341D451 List:
References
50-323-85-27, NUDOCS 8510090350
Download: ML16341D450 (14)


See also: IR 05000323/1985027

Text

'

a

.

'I

f

I

a

a

U.'.

NUCLEmARI REGULATORY COMMISSION

,, "REGION V

I

I

Iii

Ii

Report'No.

50-323/85;,27;

"

I

I'

~ ri

License'No.

DPR-82

Licensee: Pacific Gas"'and'lectric

Company

77 Beale Street,

Room 1451

San Francisco,

California

94106

Facility Name:

Diablo Canyon, Unit 2

II

(

I

Inspection at:

Diablo Canyon Site

Inspection Conducte

Au

st 10-16 and September

4,

1985

Inspectors:

J..

e

S

'or

a

gineer

and

Team Leader'

.D

e

'ned

A

D

o

s

Enfo ce

tOff cer

Da

'gned

R. F

San

n

enior

sident Inspector

Da

e

S gne

T.

Dia

o

C

, Resi

nt Inspector

Da

e

igned

R.

, Reside

Inspector,

WNP-2

Other Accompanying Personnel:

Da

e

igned

R. E. Schreiber,

Consultant, Battelle Pacific Northwest Laboratories

R. L. Gruel, Consultant, Battelle Pacific Northwest Laboratories

Approved By:

A.

. Chaffee,

Chief

Reactor Projects

Branch

g </~~

Date Signed,

~Summa

Ins ection on Au ust 10-16 and

Se tember

4

1985

(Re ort No. 50-323/85-27)

Areas

Xns ected:

Enhanced

Team Inspection of operating

crews

and operational

readiness

of Diablo Canyon, Unit 2.

This inspection involved 246 inspection

hours by five NRC personnel

and

112 inspection hours by two NRC consultants

including 210 hours0.00243 days <br />0.0583 hours <br />3.472222e-4 weeks <br />7.9905e-5 months <br /> of backshift inspection.

During this inspection,,topics

in inspection procedures

71707,

72302 and 71710 were covered.

--~-1-0-O9 Pygmy'85O919

pDR

ADOCt '0

@DR.

4

II

'

!'

k

W

I a.

t

I

ft

lf

tl

-2"

~Findin s:

No violations of NRC requirements

resulted

from this inspection.

The

NRC Resident Inspection staff is, however, continuing to examine the

circumstances

regarding the status of the fire detection/alarm

system for one

fire zone (containment) of the plant.

Additional information is necessary

to

determine if the condition observed

by the Special Inspection

Team involves

a

violation of NRC requirements.

Observations

by the Special Inspection

Team

were discussed

with licensee

management

and actions

were taken,

and are

expected to continue, to improve operational activities.

These observations

are discussed

throughout the report;

and relate principally to needed

improvements in (1) the procedures

used to identify the operational

status of

equipment in need of repair,

maintenance

or other corrective actions,

(2)

operator alertness

to status lights or other indication of equipment

malfunction (particularly in areas

behind control room panels),

(3)

determination of the operability of fire detection/alarm

system,

(4)

housekeeping

during maintenance

and (5) the review of changes

to test

procedures.

rs

s

fl

I

'1 .,1

"1'J

ffe

1 r

(

s

jc

r

1

I

ps

e fsr

1

n

f

f

II

  • s

~ If

H

f,

~

I

I

I'I

',\\, /

Ij f

lf

1

1

p

II

II

n

H C.'

r

1

r

i.

J

h

Hr

1

'I

I'

I

I(*

I

a

I

I

r~

. t-

I

1

c

I

I(

(I

'I

I(

J

l

I

Ij-- <

I

3

I

(3(l

II

13

I

t

I

(3(

(

V

j3

3(

I

J

II~

3 A

I

I"

3

'pl

I j

Ii

I

I

I

f.

DETAILS

Persons

Contacted

  • G.

-VJ

R

"-"R.

J.

D.

"~R.

J.

R.

A. Maneatis,

Executive Vice President

D. Shiffer, Vice President

Nuclear Power Generation

C. Thornberry, Plant Manager

Patterson,

Assistant Plant Manager/Superintendent

M. Gisclon, Assistant Plant Manager/Technical

Services

A. Taggart, Director (}uality Support (Site)

P. Flohaug,

Supervisor (}uality Support

(Reactor Operations)

A. Sexton,

Operations

Manager

L. Fisher,

Senior Power Production Engineer

The inspectors

also held discussions

with and observed

the performance

of

numerous

other licensee

employees

during the course of the inspection;

these

included Shift Managers, Shift Foremen, Shift Technical Advisors,

Senior Control Room Operators,

Control Room Operators,

unlicensed

operations

peisonnel,

and maintenance

technicians.

2.

+Attended Management

Meeting on September

4, 1985.

~-"Attended Management

Meeting on August, 3.6,

1985.

I

Enhanced Ins ection Team

Com osition and Pattern of Ins ection

'I

The inspection

was carried out by senior

members of the Region V staff,

Senior Resident, and Resident Inspectors

ass'igned

to operating

power

reactors in Region V, and, two consultants

from the 3attelle Pacific

Northwest Laboratories

(PNL)'.

The PNL consultants

are certified operator

license examinators,

and currently provide contract assistance

to the

NRC

in this capacity.

\\*

To evaluate

the performance of the operating

crews,

members of the

Enhanced

Inspection ~Team were assigned

to around-the-clock

coverage of

shift, operations

commencing

on August 10 and continuing through August

16,

1985.

During this period preoperational

testing

was completed

and

preparations

were in progress for initial criticality of Unit 2,

and

Unit 1 was operating at 100/'power in commercial operation.

I

This pattern of inspection permitted

members of the inspection

team to

observe

several shift crews in the operation of both Unit 1 and

2 from

the dual unit control room.

3.

Assessment

of 0 eratin

Crew Performance

Operating

crew performance

was assessed

based

upon the inspection team's

observation of (1) the conduct of scheduled plant evolutions,

(2) crew

response

to unplanned

events

(including an Unusual Event on August 14,

1985 involving a fatal auto accident

on the plant access

road and ensuing

range fire which threatened

an off-site source of electrical power)

and

(3) thorough discussions

with individual operating

crew members.

I

I

il

I

J,

4

D

I

I

'I

I

r

I

V

P

P

P

I.

I'l

I

I-

4

I

5

I

I

,P

e

P

P

I

Jp

The overall performance of the operating

crews

was judged by the

inspection

team to be above average in terms of their knowledge of plant

systems,

operating procedures

and adherence

to procedures.

Shift turnover procedures

and practices

were observed

to be of

particularly high quality.

Control room manning and shift coordination during periods of activity on

both Units

1 6 2 were given close attention by the inspection

team,

particularly to those positions of Senior Control Operator

and Control

Operator which are

common to both units.

Good discipline and practices

were observed at all times to insure that sufficient operator attention

was given to each unit, particularly during periods of unusual activity

on either Unit.

A specific example

was during an event on Unit 2 on

August 10,

1985 when unanticipated plant response

occurred during

a

planned test of the turbine automatic

runback system.

During the event

an unanticipated unit trip, auto transfer of startup power from the 500

KV to 230 KV offsite power source,

and spurious

auto start of an

emergency diesel generator

occurred.

Coordination

among the operating

crew was observed to be effective and disciplined in responding to the

unanticipated

events

on Unit 2, while maintaining proper attention to

Unit

1 operations.

Observations

of E ui ment Status

Examination of control room panels

by the inspection

team revealed

numerous miniature sticker labels (called

"AR stickers")

on individual

components.

Discussions with licensee personnel

revealed that these

labels were utilized as part of a system recently implemented (for trial

use) by a draft procedure to indicate

components

which were the subject

of Action Request

reports

(AR) or Nuclear Plant Problem Reports

(NPPR's),

indicating that such components

were in need of repair,

maintenance

or

other corrective action.

A,comparison of the status of two of the'AR stickers

revealed that the

AR

associated

with the sticker was closed out without the sticker being

removed.

This observation

was brought to the attention of licensee

supervision who,undertook

a 100/ check of similar stickers in both the

Unit 1 and Unit 2 a'reas of the control room.

The results of the

licensees verification revealed

approximately

35 percent of a total of

more than thirty, stickers did not,'reflect the accurate

status of the

equipment to which they were attached,

in that the associated

AR or NPPR

had been

completed.,

A review of the draft procedure

governing use of the

AR stickers revealed

one potential

cause

os the stickers not accurately reflecting the status

of equipment to which they were at'tached

to be

a provision within the

procedure which requiies that the

AR sticker be removed only by the

person

who applies. the sticker-;

This appears

to be

a carryover practice

which is consistent with the procedures

for equipment clearance

tags,

where personnel

safety is a prime consideration.

1

I

I

'I

I

I

I'

II I

H

II

11

I

I

I

1

I'%

I I

L

Ik(

1

~ I

kl

}I

I

1(1 k

v

I

II

(

4,

l.

k(}

\\I

,1

j

'I

, I..

J

+

I Wk

I

h

I

}

I

I

'i

k

k

II

1 3

I

J

1

Licensee

maiiagement indicated, that changes

would be made to the

AR

procedure to'equire that the stickers

be removed from equipment

when the

associated AR'r NPPR is 'complete

and closed out.

The status of electrical j'umpers, 'caution tags

and man-on-the-line

tags

were exa'mined 'during sever'al tours of plant areas.

Logs and other

controlling documents-for 'such tags

and jumpers

were also examined

on

several occasions.

No discrepancies

of, the nature discussed

above were

identified with regard,to 'these. tags

and jumpers.

Discussions

were 'also held with .Quality Assurance

(QA) personnel

regarding audits conducted'by'them

on the status of tags

and the

AR

stickers

used to indicate the status of plant systems.

These discussions

revealed that

a recent audit had been conducted

by QA of 100/ of the tags

in Units

1 6 2.

The audit had not, however, included the

AR stickers

discussed

above.

0 erator Alertness

and Matchstandin

Practices

Two observations

by the inspection

team revealed

the need for continuing

attention by licensee

management

and supervision to improve the alertness

and watchstanding practices

of plant operators.

One such instance

involved an observation

on August 13,

1985 of a failed

fuse indicator light on the rear of a control room vertical panel.

Subsequent

investigation revealed that the failed fuse was in a redundant

solenoid circuit for a main steam isolation valve in loop 4 of Unit 2.

In response

to this observation,

licensee

management

took prompt action

to correct the condition and include this area of the control room panels

in routine panel walkdown procedures.

Another instance

involved an observation

on August, 13,

1985 regarding

a

pressure

gauge

on the Diesel Generator

1-3 lube oil filter which

indicated

a differential pressure

across

the filter of approximately

55

psig.

The normal pressure

across

the filter is 2-3 psig.

A subsequent

check showed that the gauge was,defective,

thus indicating an erroneous

differential pressure.

The defective

gauge

had not been identified by

plant operators.

These observations

were discussed with licensee

management

at the time of

Management

Meetings

on August

16 and September

4, 1985.

Plant Housekee in

and Radiation Control

During tours of the plant Auxiliary, Turbine and Containment Buildings

plant housekeeping

practices

were observed

to be generally quite good.

The posting

and control of radiation and contaminated

areas

were observed

to be effective.

An exception to the above

was

one instance while touring the

Diesel-Generator

Room 1-3. It was observed that in the course of

maintenance

a ladder

was left leaning on equipment near the diesel

governor

and fuel rack linkage.

Immediate steps

were taken by the

Ifhl

h

t

g

'

lf

I

IP ~

'I

hf

'IP

F.,

I

1

1

I

h

I

P f

P

N

W

1

licensee

to have the ladder

rem'oved from the area.

This observation

was

discussed

with licensee

management,

in the context of the type of

conditions operations

and other plant, staff should be alert to in their

periodic tours of the plant.

Fire Detection

S stem, Alarm 0 erabilit

On August 11,

1985 a,member of the inspection

team observed that an alarm

annunciator

wasactuated

on the,.control

room Fire Alarm Control Panel

A.

The actuated

annunci.ator

was for Zone 12, Containment Building.

This observation

was brought to the attention of licensee

management for

investigation.

The licensee's

investigation revealed that the

annunciator

was actuated

due to 2 of 21 detectors in Zone

12 being

inoperable.

The licensee'ook

steps

to repair the two inoperable

detectors,

thus clearing the annunciator.

This observation is to be followed up by the

NRC resident inspection

staff to determine if the condition observed

by the inspection

team

rendered

the fire alarm system inoperable,

and if so that appropriate

compensatory

measures

were taken by the licensee.

This is an Unresolved

Item.

(50-323/85-27-01)

Control Circuit Groundin

From 1am

Base Short

Reactor Coolant

Pump

(RCP 2-1) tripped unexpectedly

on August 11,

1985.

Subsequent

investigation by the licensee

revealed that the cause of the

trip was the loss of control power to the pump breaker.

The loss of

control power had resulted

from the shorting of adjacent indicating lamp

bases in the control room panel for the pump.

Further investigation by the licensee,

in response

to concern expressed

by the inspection

team,

revealed that

a potentially generic problem for

such shorting existed in other areas of the control room panels

where

a

"three or more" configuration of indicating lamps existed.

In such

a

configuration the close proximity of lamp bases

coupled with one or more

loose

lamp bases

could cause

contact between the electrical connectors

of

adjacent

lamp bases.

The licensee

subsequently

conducted

an examination of all similar lamp

configurations

(approximately 70) in the Unit 2 area of the control room.

Four additional instances

of potential shorting, either loose

lamp bases

or near contact between

connectors

on adjacent

lamp bases,

were

identified and corrected.

A similar examination is to be made of the indicating lamp bases in the

Unit 1 area of the control room during plant shutdown.

Test Procedure

Inade uac

During the conduct of a test of the turbine runback system unanticipated

plant response

was experienced

as discussed in paragraph 3., above.

Evaluation by the licensee

revealed that the unanticipated plant response

resulted from a deficiency in the test procedure.

The deficiency in the

~F

1

I

I

t'g

.4.

" I.*

I

h II

I

I"

I

I

I

p

li

I

iJ

I

  • I

'i

'F

I

I

II

F

I

'f

p

t

I

1

hl I

I'

1

I

<< "If

'I If"

ff

I

I

1

I

11

1

I

I 'I

h

5

procedure

had resulted

when changes

were made to the procedure to reflect

changes in the initial conditions to the test from cold shutdown to hot

standby conditions.

Licensee

management

directed that the test be discontinued until the

procedure deficiencies

were thoroughly reviewed

and corrected.

This experience

was discussed

at the Management Meetings, with particular

emphasis

on the need to review changes

to procedure

as thoroughly as the

initial procedures

themselves.

10.

Licensee

Mana ement Involvement

During the week prior to the current inspection licensee

corporate

and

site functional managers

were assigned

to around-the-clock

coverage of

plant operations.

This practice,

which will continue for an indefinite

period during the initial startup of Unit 2>is similar to that

implemented by the licensee

during initial startup of Unit 1.

ll.

Unresolved Items

12.

An unresolved

item is

a matter about which more information is required

in order to ascertain

whether it's an acceptable

item,

an open item,

a

deviation," or a violation.

S

Mana ement Meetin

s

The findings, of the inspection were discussed

with those licensee

representatives

indicated in paragraph

1. at the site

on August 16 and

the c'orporat'e offices'n September

4, 1985.

.e

I'

n

1>,

C

8

'L

I I

Pl-

o

?

I

f.

/I

,

t

t

ll

ll

c

a

li

I

l

I

1