ML16341C955

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-275/79-12 & 50-323/79-07 on 790430-0503. Noncompliance Noted:Tubing Support Installed on Another Support Exceeded Max Specified Weight Limit & Conduits Not Installed as Required by Procedures & Drawings
ML16341C955
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 06/01/1979
From: Dodds R, Hutson T, Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341C954 List:
References
50-275-79-12, 50-323-79-07, 50-323-79-7, NUDOCS 7908150233
Download: ML16341C955 (16)


See also: IR 05000275/1979012

Text

50-275/79-12

Report

No. 50-323/79-07

,Doc(get

No

50-275

q 50-323

U. S.

NUCLEAR REGULATORY COMMISSION

OFFICE

OF INSPECTION AND ENFORCEMENT

REGION V

Licese

No

CPPR-39,

CPPR-69

Safeguards

Group

Pacific Gas

and Electric Company

77 Beale Street

San Francisco,

California

94106

Feei] ity Naze

Diabl o Canyon Units

1 and

2

In'spection at

"

Diablo Canyon Site,

San Luis Obispo

County,

Ca 1 ifornia

, Inspection

conducted:

April 30 - May 3,

1979

Inspectors:

D. F. Kirsch, Reactor Inspector

I a

T.

W. Hutson,.Reactor

Inspector

Date Signed

Date Signed

Approved

R. T. Dodds, Chief, Engineering Section,

Reactor

Construction

and Engineering

Support Branch

Date Signed

7

c'-'te

Signed

Sunmary:

Ins ection durin

eriod of A ril 30 - Ma

3,

1979

Re ort Nos.

50-275/79-12

and 50-323 79-07

~A<<d:

R i,

'di

p

Ci

ty

gi

11

d

inspectors

of constructi'on activities including:

licensee action

on

previous inspection findings; licensee action

on IE Bulletins and

Circulars; physical protection of safety-related

equipment; allegations

of improper raceway support installation; Unit 2 volume control tank

overpressure

corrective actions;

NDE examiner,

gC inspector,

and welder

performance qualifications; welding materia~l control; and steam generator

preservice

examination results.

The inspection involved 46 inspector-

hours

by two

NRC inspectors.

Results

Of the eight areas

inspected,

no items of noncompliance

or

deviations

were identified in six areas,

one item of noncompliance

was

identified in each of the areas of pipe supports

(infraction

tubing

support installed

on another support

exceeded

the maximum specified

weight limit - Paragraph

4.a)

and electrical

raceway supports (infraction-

failure to install conduit as required

by procedures

and drawings-

Paragraph

7.b.(4))

and one unresolved

item was identified in the arg,

pffo

p]9 (p)

electrical

raceway supports

(Paragraph 7.b.(3)).

'f96:as%

e

lt

DETAILS

1.

Persons

Contacted

'a

~

Pacific

Gas

and Electric

Com an

PGSE

f

M.

R. Tressler,

Assistant Superintendent

- General

Construction

R.

D. Etzler, Project Superintendent

  • N. N.

Norem, Startup

Engineer

  • D. A. Rockwell, Resident Electrical

Engineer

~V. L. Killpack, Resident

Mechanical

Engineer

  • R.

K. Rhodes,

Instrumentation

Supervisor

  • M. E. Leppke,

QA Supervisor

  • S. J. Foat,

QC Engineer

J.

R. Bratton,

QC Engineer

H. Yianegold,

Hanger Engineer

C. Braff, Pipe Support Supervisor

F. J.

Cucco,

Instrumentation

Engineer

0.

G. Crass,

Tubing Installation

and Valve Maintenance

Coordinator

F.

M. Russell, Acting Resident Civil Engineer

V. Smart, Electrical Field Engineer

R. llhited, Electrical Field Engineer

G. Hegli,

QA Engineer

R. Johnson,

Civil Field Engineer

b.

Pullman-Kello

Kello

D. Geske,

QA/QC Manager

R. A. Richardson,

Receiving Inspector

K. ll. Melin, Rod

Room

QA Inspector

  • Denotes

those attending

the exit interview.

2.

Gener al

The licensee anticipates

readiness

for operating license

issuance

and fuel load for Unit

1

on or about July 6; 1979.

3.

Punch List

The licensee's

punch list of incomplete work contained

235 items at

the time of inspection

and efforts were underway to complete the

work.

The licensee

stated that, to assure

readiness

for licensing

and

fuel load,

an instruction would be written detailing (a) individuals

responsible for document

reviews to assure

completion of and/or

identification of incomplete work, (b) documents

required to be

reviewed

and (c) appropriate

interface requirements

necessary

for

General

Construction,

Operations Division, and Engineering.

AI

-2-

4.

Licensee Action on Previousl

Identified Followu

Items

a.

0 en

Unresolved

Item - Unistrut hlelded to Su

ort 49-12V

323/79-, 05-03

During the inspection

conducted

on March 26-29,

1979,

the

inspector

noted that

a section of unistrut associated

with

instrument tubing support 2-FT-640 was welded to the bottom of

hanger

49-12V in Unit 2.

Paragraph

10 of Drawing 049237,

Revision

4 (Piping and Mechanical

Pipe

Hanger

and Snubber

Supplementary

Installation Instructions)

gives three criteria

for determining the acceptability of attaching

a tubing

support to a large bore hanger .

These criteria specify

a

maximum 25 pound attachment

weight.

Subsequent

to i'nstal'lation

and inspector identified concerns,

calculations

by

PGSE

showed that the weight of support 2-FT-640, attached

to 49-

12V, was

28 pounds.

The tubing support installation contractor,

H.

P. Foley. installs supports

in accordance

with Drawing

049238,

Change

5, Instrument Tubing Supports.

This drawing

did not contain the three acceptance

criteria in Paragraph

10

of Drawing 049237.

Drawing 049237

had not been

issued to

H.

P. Foley.

This appears

contrary to the requirements of

10 CFR 50,'Appendix B, Criterion V, which states

in part that,

"Activities affecting quality shall

be prescribed

by documented

~ instructions,

procedures,

or drawings, of a type appropriate

to the circumstances

and shall

be accomplished

in accordance

with these instructions,

procedures,

or drawings."

b.

This is an apparent

item of noncompliance.

0 en

Isolation of Mutuall

Redundant Circuits

275/79-07-02

In order to determine if non-safety related wiring crossed

protection set or vitality boundaries,

the inspector

examined

the licensee's circuit schedule

and

a number of mechanical

panels

housing class

1 instr~ments in the Unit

1 containment

and

made the following observations.

(1)

Common non-vital heater circuits cross

the following

circuits with less

than 5-ipch air separation.

(a)

Steam Generator

1-3 level circuits in protection

se~

1

(PNL46) and protection set

3 (PNL54): Heater

circuit No.

PJ7116

(b)

Steam Generator

1-4 steam flow circuits in protection

set

1

(PNL47) and protection set

2 (PNL51):

Heater

circuit No.

PJ7107

(c) 'team Generator

1-4 level circuits in protection set

2 (PNL51) and protection set

4 (PNL59):

Heater

circuit No.

PJ7107

(d)

Pressurizer

level circuits in protection set

1

(PNL22), protection set

3 (PNL20) and protection set

2 (PNL89):

Heater circuit No. PJ7104

(e)

Reactor Coolant System loop 1-2 flow circuits in

protection set'

(PNL22), protection set

3 (PNL20)

and protection set

2 (PNL89):

Heater circuit No.

PJ7104

(f)

Steam Generator

1-2 level circuits in protection set

1

(PNL45) and protection set

3 (PNL53):

Heater

circuit No.

PN7114

(2)

In addition, wires at the heater

end in panel

57 had been

removed from the heater

element

and were hanging free.

The'ire

ends

had been

taped with electrician tape

and

were visible inside the tape.

This item is open pending evaluation of additional information

to be submitted

by the licensee.

5.

Licensee Action on Bulletins and Circulars

Bulletin 78-04

NAI'1CO Stem t1ounted Limit Switches

The inspector

examined

the Unit.l installation of five environ-

mentally qualified

NAMCO Snaplock switches,

EA 180 series,

model

No. EA-180-11302

on valves

8149A, 8149B, 8149C,

LCV 459 and

LCV 460.

At present

14 of 18 switches

in Unit

1

had

been replaced with the

exception of installation of the

LOCA seal

connections

to the limit

switches.

The

LOCA seals

had

been ordered

from the

Conax

Company,

Drawing No.

25K191S, Revision A, Part

No.

02 and certified as

meeting

the applicable

environmental qualifications.

The inspector

has

no further questions

on this item.

6.

Ph sical Protection of Safet -Related

E ui ment

During a tour of the Auxiliary Seawater

System

(ASM) pump and gate

operator area,

located in the intake structure, it was observed

that

a large screen

wash water line was suspended

above the Unit

1

and

2 ASM suction gate operating motors.

The line did not appear

to be supported

by seismically qualified supports.

In addition,

the redundant

gate operators for each unit had

no physical barriers

installed.

The licensee

noted that this problem

had

been previously identified

in Plant Design

Comment

No.

16.

The followup of this item has

been

remanded

to the cognizance of the Resident

Inspector,

who was

following the licensee's

resolution of plant design

comments.

In

addition, this question

was addressed

to the Project Engineer

who

stated

that this observation

would be examined

and that licensee

actions

deemed

necessary

or already

taken to assure

adequate

physical

protection of safety-related

equipment would be identified.

e

7.

Alle ations of Im ro er Racewa

Su

ort Installation

~

~a.

Alle ations

as understood

b

the

NRC

Allegations of improper Unit

1

raceway. support installations

were received

by the Resident

Inspector who, in turn, referred

them to the regional office for resolution.

Specifically, the

allegations

were:

Support

No. K-115-4-100

had

no side brace support to the

wall; FE/FM-2-249

had holes in unistrut welds;

and

- FE/Fkl-1-260 welds were not to detail.

(2)

(3)

(4)

Support

Nos. C-104-3-7

and 3-8 had

a unistrut

beam

on

piece S-6 which was not to detail.

Support

Nos.

K-100-7-115

and 116'ad concrete

anchor

bolts installed which were not separated

from adjacent

concrete

anchor bolts

by the required distance.

Conduit Nos.

K-9424,

9430 and

9652 in K-100 area,

run

above vital conduit and did not have class

1 supports

installed.

b.

NRC Construction

Branch Findin

s

(2)

(3)

The allegation

was substantiated,

however, support

Nos.

K-115-4-100,

FE/FM-2-249 and FE/FM-1-260 had

been pre-

viously identified by the licensee

as discrepant

and

entered

onto work package

G-93:E-84 for repair

by the

PG&E cleanup

crew.

The allegation

was substantiated;

however, examination

indicated, that support

Nos.

C-104-3-7

and 3-8 were con-

structed in a manner which exceeded

design detail require-

ments.

The design details called for- a P-3300 unistrut

beam attached

to piece

S6.

A P-1000

beam was attached

to

the

S6 members for both supports.

The P-1000

beam is

a

heavier,

more substantial

member than P-3300.

The allegation

was substantiated.

The inspector

examined

the concrete

anchor bolt installations for supports

K-

100-7-115,

116 and about

100 other supports

located in

various areas of Unit l.

In addition to the supports

identified by the alleger, it appeared

that supports

Nos.

K-100-7-100,

K-100-7-165

and K-100-7-118 (in K-85 area of

Unit 1) had anchor bolts which did not meet the specified

anchor bolt spacing

requirements

of Foley procedure

gCP-

9.

All of the identified supports

had

been inspected

and

accepted

by Foley in the conduct of the raceway support

inspection/inventory

program

and

none of the Support

Inspection

Mork Sheets,

for the above supports, identified

anchor bolt spacings

as

a discrepancy.

0'

Foley procedure

QCP-9,

Paragraph

4.4.1, requires that

"center-to-center

anchor spacing shall not be less

than

12 nominal diameters of the largest anchor bolt unless

directed

by PG&E design

documents."

The supports

noted

above utilized 1/2 inch diameter concrete

anchor bolts

which were spaced

between

2-1/2 and

3 inches

from adjacent

anchor bolts.

The licensee's

Resident Electrical

Engineer

believed that

Foley had

been provided with additional

PG&E direction,

based

upon an inspection of all anchor bolt installations

by Engineering

Department in 1975 and the results

of'

PG&E study performed to establish

anchor bolt installation

acceptance

criteria.

This is an unresolved

item pending

examination of the additional

PG&E directions supplied to

the contractor.

(275/79-12-01)

The allegation

was substantiated.

An examination of

numerous

raceway

and support installations

on May 1,

1979

in the K-100 area of Unit

1 identified the following

discrepancies:

(a)

Non-vital conduits

K-9424,

K-9430 and

K-9652 were

installed

above

and crossing vital conduits without

having

a class

1 support provided

on each side of

the intersection.

(b)

Non-vital conduits

KHT-52 and

53 were both suspended

from support

K-115-6-47 (a vital bus

F support)

and

an unnumbered vital bus

H support of detail

number

397, without having

an intermediate

class

1 support

provided.

Foley procedure

QCP-9 (Quality Control Procedure for

Installation of Raceways,

Junctions

and Terminal

Boxes

for Hire Pull), Paragraph

4.2.5 (implementing

PG&E Drawing

050029,

conduit note 60) states

that "Hhere non-class

1

conduit shares

supports withNore than one class

1 raceway,

vital or protection channel,

an intermediate

class

1

support shall

be provided."

Foley, procedure

QCP-9,

Paragraph

4.1.8 (implementing

PG&E

Drawing 050030,

note 3) states

that where raceways,

other

than those identified as class

1, "cross

a class

1 raceway,

a class

1 support shall

be constructed

on, each side of

the intersection."

This is an apparent

item of noncompliance.

(275/79-12-

02)

Unit 2 Volume Control Tank

The hydrostatic test records,

visual examination

and liquid penetrant

test records for the Unit 2 Volume Control

Tank were reviewed

by

the inspector for compliance with the requirements

of ASttE Section

XI, through

Summer

1975 Addendum.

The visual

and liquid penetrant

examinations

disclosed

surface

defects

such

as slag left on welds

during fabrication,

excessive

weld reinforcement

and

a misalignment

of the shell to head which exceeded

allowable code limits.

Non-

conformance report DC2-79-gC-P0054

was written to document

the

deficiencies

noted

and all data

taken

had

been turned over to

Westinghouse

engineering for evaluation

and disposition.

The

resolution of this item wi.ll be followed through the normal review

of NCR's.

No items of noncompliance

or deviations

were identified.

Nondestructive

Examiner

and

C Ins ector

uglification

The inspector

reviewed

one Level II NDE examiner's qualifications

and five Level II gC inspectors'ualifications

for conformance

to

the requirements

of SNT-TC1A, Kellogg Procedures

ESD-235

(Non'-

destructive

Examination

Personnel

gualification and Certification

Procedure)

and

ESD-237 (guality Assurance

Inspector Training

Program) .

No items of noncompliance

or deviations

were identified.

Wel din

tlateri al Control

The filler material

withdrawal

and issue operations

and material

storage in the Kellogg rod room were examined for,compliance with

Procedure

ESD 202 ('eld Material Distribution and Control).

The

holding ovens

were properly marked with the contents

and the

temperature

gauges

had

been- calibrated.

All portable rod warmers

had

been

checked for operation

and temperature

at the required

frequency.

The rod room was clean

and neat with all cans of

moisture sensitive

weld rod undamaged

and hermetically sealed.

The

rod withdrawal slips for Hay 2,

1979 were randomly reviewed

and

appeared

to be properly completed.

The receiving inspection reports

and certified material test reports. fdr the following heats of weld

rod being issued

were reviewed.

Heat Number

Rod. T

e and Size

E7018-

E7018-

E7018-

E308-16

ER308-

ER308-

3/16"

5/32"

1/8"

1/8"

3/32"

II

07L150

412E-0271

422E-1681

29963

48116

482584

1/8

No items of noncompliance

or deviations

were noted.

~

~

'

-7-

Wel'der Performance

ua1 ification

Ten welders performing welding on Hay 2,

1979 were checked for

proper qualifications using the welders qualification matrix issued

for the period tray

1 through Hay 31,

1979.

These ten welders

appeared

qualified by use of the matrix.

To verify the accuracy of

the matrix, the inspector

compared

two welders

performance qualifi-

cation records with the matrix.

The review showed, that the limit

of thickness

stated for a specific welding procedure

had

been

rounded

up to the nearest

quarter inch over the

2T (T-thickness of

test plate) limit required

by Section

IX of the

ASME code.

For

example,

a

2T limit of 0.636 inches

had been

rounded

up to 0.750

inches

in numerous

cases.

The inspector also found that

a procedure

qualification record for a welder,

symbol

BR, was missing from his

qualification folder.

This item is open

and will be examined

during

a future inspection.

(275/79-12-03)

12.

Steam Generator

Preservice

Examination

In 'the course of liquid penetrant

preservice

examinations,

the

licensee

reported that indications of crazing were identified on

the outer diameter of Unit

1

Steam Generators

1 and

2 cold leg ring

dams.

The indications

appeared

in the clad area at the edge of the

weld material

and not in the weld material.

Steam Generator

1

had

an indication about 3/8 inches

long and Steam Generator

2 had

a

number of large indications.

The licensee

was still in the process

of investigation to determine

the exact nature

and depth of the

indications

on Steam Generator

2.

Westinghouse Electric Corporation,

the

HSSS supplier,

had initiated

a Field Discrepancy

Report and submitted this to their Tampa office

for resolution.

Westinghouse

personnel

noted that all previous

studies

determined that the indications

had never gone into base

metal.

This item will be examined further during

a future in-

spection.

(275/79-12-04)

13.

Unresolved

Items

Unresolved

items are matters

about which more information is required

in order to ascertain

whether they are acceptable

items,

items of

noncompliance,

or deviations.

One unnesolved

item was identified

during this inspection

and is discussed

in Paragraph 7.b.(3).

14.

Exit Interview

The inspectors

met with licensee

representatives

(denoted in Para-

graph

1) on Hay 3,

1979 and summarized

the inspection

pur'pose,.

scope

and findings.

The licensee

was informed of those matters

considered

as items of noncompliance

and unresolved.

Ay

<v