Text
1P,R A60II
,
E~JPldj)
+w*w+
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION V
SUITE 202, WALNUTCREEK PLAZA
1990 N. CALIFORNIA BOULEVARD
WALNUT CREEK, CALIFORNIA 94596
Docket Nos. 50-275
50-323
Pacific Gas
and Electric Company
77 Beale Street
San Francisco,
California 94106
Attention:
tlr. Philip A. Crane
Assistant
General
Counsel
Gentlemen:
Subject:
NRC inspection of Diablo Canyon Unit Nos.
1 and
2
This refers to the inspection
conducted
by Messrs.
D. F. Kirsch and
L. E. Vorderbrueggen of this office on August 24 through September
22,
1978 of activities authorized
by
NRC Construction
Permits
No. CPPR-39
and CPPR-69,
and to the discussion of'ur findings held with Messrs.
R. D. Etzler and T. G. DeUriarte and other members of your staff at the
conclusion of the inspection.
Areas
examined during this inspection
are described
in the enclosed
inspection report.
Within these
areas,
the inspection .consisted of
selective examinations of procedures
and representative
records,
.
interviews with personnel,
and observations
by the inspectors.
Based
on the results of this inspection, it appears that one of
your activities was not conducted in full compliance with the
NRC
requirements,
as set forth in the Notice of Violation, enclosed
herewith as Appendix A.
This item of noncompliance
has
been cate-
gorized into a level as described
in our correspondence
to all
NRC
licensees
dated
December
31, 1974.
.This notice is sent to you pursuant to the provisions of Section
2.201
of the NRC's "Rules of Practice," Part 2, Title 10,
Code of Federal
Regulations.
Section
2.201 requires
you to submit to this office,
within thirty (30) days of your receipt of this notice,
a written
. ~
Pacific Gas
and Electric Company
-2-
OCT
> S)S
statement
or explanation in reply including:
(1) corrective steps
which have
been taken
by you and the results achieved;
(2) corrective
steps
which will be taken to avoid further violations;
and
(3) the
date when full compliance will be achieved.
In accordance
with Section
2.790 of the
NRC's
"Rules of Practice,"
Part 2, Title 10,
Code of Federal
Regulations,
a copy of this letter
and the enclosed
inspection report will be placed in the
NRC's Public
Document
Room.
If this report contains
any information that you be-
. lieve to be proprietary, it is necessary
that you submit
a written
application to this office, within 30 days of the date of this letter,
requesting that such information be withheld from public disclosure.
The application must include a full statement of the reasons
why it
is claimed that the information is proprietary.
The application
should
be prepared
so that any proprietary information identified is
contained in an enclosure to the application,
since the application
without the enclosure will also
be placed in the Public Document
Room.
If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document
Room.'hould
you have any questions
concerning this inspection,
we will be
glad to discuss
them with you.
Sincerely,
Enclosures:
l.
Appendix A Notice of Violation
2.
IE Inspection
Report
Nos. 50-275/78-12
50-323/78-12
cc w/o enclosure
2:
R. P. Mischow,
PGKE
J.
D. Worthington,
PGSE
Reactor Construction
and
Engineering
Support Branch