ML16228A408
Letter Sequence Other | |
---|---|
CAC:MF6776, (Open) | |
Initiation Administration Questions
| |
MONTHYEARL-15-297, Submittal of 10 CFR 50.55a Request for Alternative Repair Methods for Reactor Vessel Head Penetrations and J-Groove Welds (Request 2-TYP-3-RV-04)2015-09-30030 September 2015
[Table View]Submittal of 10 CFR 50.55a Request for Alternative Repair Methods for Reactor Vessel Head Penetrations and J-Groove Welds (Request 2-TYP-3-RV-04) Project stage: Request ML15293A6032015-10-20020 October 2015 NRR E-mail Capture - Beaver Valley, 1 and 2 - Acceptance of Requested Licensing Action 10 CFR 50.55a Req for Alternative Repair Methods for Reactor Vessel Head Penetrations and J-GROOVE Welds (Request 2-TYP-3-RV-04) Project stage: Acceptance Review ML16147A3622016-06-17017 June 2016 Relief Request No. 2-TYP-3-RV-04, Revision 0, Regarding Repair Activities for Reactor Vessel Head Penetration Nozzles and Associated J-Groove Welds Project stage: Other ML16228A4082016-10-21021 October 2016 Correction to Relief Request 2-TYP-3-RV-04, Revision 0, Regarding Repair Activities for Reactor Vessel Head Penetration Nozzles and Associated J-Groove Welds Project stage: Other 2015-09-30 |
ML16228A408 | |
Person / Time | |
---|---|
Site: | Beaver Valley |
Issue date: | 10/21/2016 |
From: | Doug Broaddus Plant Licensing Branch 1 |
To: | Richey M FirstEnergy Nuclear Operating Co |
Broaddus, D, NRR/DORL/LPL1-2, 415-8124 | |
References | |
CAC MF6776 | |
Download: ML16228A408 (3) | |
Similar Documents at Beaver Valley | |
---|---|
Category:Code Relief or Alternative
MONTHYEARML24226A3652024-05-13013 May 2024
[Table view]Approval of Request for Alternative from Certain Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 ML22082A2532022-03-29029 March 2022 Correction Letter - Issuance of Authorization of Proposed Alternative to Use ASME OM Code Case OMN-27 ML22012A2972022-01-21021 January 2022 Proposed Alternative to Use ASME OM Code Case OMN-27 L-20-256, Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2020-09-28028 September 2020 Request to Use Provision in Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ML20223A0142020-08-20020 August 2020 Issuance of Relief Request SSR-1, Revision 0, from the Requirements of the ASME Code (EPID L-2020-LLR-0050 (COVID-19)) ML20206K8652020-08-0707 August 2020 Relief Requests 2-TYP-4-RV-06 and 2-TYP-4-RV-07 from the Requirements of the ASME Code (EPID L-2020-LLR-0053 and EPID L-2020-LLR-0054 (COVID-19)) ML20145A0002020-06-0303 June 2020 Relief from the Requirements of the ASME Code for Requests VRR6 and VRR5 (EPID L-2020-LLR-0049 and EPID L-2020-LLR-0051 (COVID-19)) ML20100N3222020-04-0909 April 2020 Verbal Relief for Penetration Evaluation and Hot Leg Nozzles - Delivered 4/9/2020 at 10:00 Am ML20099B2572020-04-0808 April 2020 Verbal Relief Unit 2 CIV ML20098F3012020-04-0707 April 2020 Verbal Relief for Appendix I Safety Relief Valves ML20095J2192020-04-0404 April 2020 Email Beaver Valley Power Station, Unit 2 - Verbal Relief for MOVs - Delivered 4/4/2020 at 4:00 Pm ML20095J0992020-04-0404 April 2020 Email Beaver Valley Power Station, Unit 2 - Verbal Relief for Snubbers - Delivered 4/4/2020 at 4:00 P.M L-20-117, 10 CFR 50.55a Request Number 2-TYP-4-RV-06, Hardship for Hot Leg Nozzle Inspections2020-04-0303 April 2020 10 CFR 50.55a Request Number 2-TYP-4-RV-06, Hardship for Hot Leg Nozzle Inspections L-20-118, CFR 50.55a Request Number SRR-1, Revision 0, Snubber Testing2020-04-0303 April 2020 CFR 50.55a Request Number SRR-1, Revision 0, Snubber Testing L-20-060, CFR 50.55a Request Number: VRR4, Revision 0, Containment Isolation Valve Test Frequency2020-04-0202 April 2020 CFR 50.55a Request Number: VRR4, Revision 0, Containment Isolation Valve Test Frequency L-20-116, CFR 50.55a Request Number VRR6, Revision 0, Motor-Operated Valve Test Frequency2020-04-0101 April 2020 CFR 50.55a Request Number VRR6, Revision 0, Motor-Operated Valve Test Frequency ML20079F8162020-03-26026 March 2020 Relief Requests 1-TYP-4-C2.21-1 and 1-TYP-4-RA-1 Regarding Weld Examination Coverage for the Fourth Inservice Inspection Interval ML19275E2942019-10-16016 October 2019 Issuance of Relief Request Proposed Alternative to Reactor Vessel Nozzle Weld Examination Frequency Requirements in Lieu of Specific ASME Code Requirements L-19-107, Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2019-08-27027 August 2019 Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements ML19051A1082019-02-20020 February 2019 Request Alternative Examination Frequency for Reactor Vessel Nozzle to Safe-End Welds (Request 2-TYP-4-RV-05, Revision 0) ML18227A7332018-08-27027 August 2018 Request for Relief from the Requirements of the ASME Code ML18004A1222018-01-22022 January 2018 FENOC-Beaver Valley, Davis-Besse, and Perry - Alternative for the Use of ASME Code Case N-513-4 (CAC Nos. MG0120, MG0121, MG0122, and MG0123; EPID L-2017-LLR-0088) L-17-317, Request to Extend Certain Reactor Vessel Inspections from 10 to 20 Years (Request 1-TYP-4-BN-01)2017-11-15015 November 2017 Request to Extend Certain Reactor Vessel Inspections from 10 to 20 Years (Request 1-TYP-4-BN-01) L-17-308, 10 CFR 50.55a Request for Alternate Reactor Vessel Nozzle Flaw Depth Sizing Criteria (Request 2-TYP-4-RVSE-2)2017-10-25025 October 2017 10 CFR 50.55a Request for Alternate Reactor Vessel Nozzle Flaw Depth Sizing Criteria (Request 2-TYP-4-RVSE-2) ML17167A0672017-06-26026 June 2017 Requests for Alternatives and Requests for Relief Fourth 10-Year Inservice Test Program Interval (CAC Nos. MF8333-MF8356). Note: Correction Safety Evaluation See ML17255A526 ML17159A4422017-06-26026 June 2017 Requests for Alternatives and Requests for Relief Fifth 10-Year Inservice Testing Program Interval (CAC Nos. MF8332 Through MF8357). Note: Correction Safety Evaluation See ML17255A508 ML17047A6102017-03-0202 March 2017 Relief from the Requirements of the American Society of Mechanical Engineers Code ML17041A1852017-03-0202 March 2017 Relief from the Requirements of the ASME Code ML17048A0042017-03-0202 March 2017 Relief from the Requirements of the ASME Code ML16328A1252017-01-23023 January 2017 Relief from the Requirements of the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code) (TAC No. MF7780 - MF7783) ML16190A1332016-12-27027 December 2016 Relief from the Requirements of the ASME Code ML16319A0572016-12-0101 December 2016 Acceptance of Requested Licensing Action Relief Request for Proposed Alternative to Perform As-Found Set-Pressure Test ML16257A6212016-11-21021 November 2016 Relief Request BV2-PZR-01, Regarding Alternative to Requirements for Components Connected to the Steam Side of the Pressurizer ML16228A4082016-10-21021 October 2016 Correction to Relief Request 2-TYP-3-RV-04, Revision 0, Regarding Repair Activities for Reactor Vessel Head Penetration Nozzles and Associated J-Groove Welds ML16147A3622016-06-17017 June 2016 Relief Request No. 2-TYP-3-RV-04, Revision 0, Regarding Repair Activities for Reactor Vessel Head Penetration Nozzles and Associated J-Groove Welds ML14363A4092015-01-28028 January 2015 Relief Request No. 1-TYP-4-RV-04 Regarding the Examination Requirements of Code Case N-729-1 ML1202702982012-02-0707 February 2012 Relief Request VRR3 Regarding Solenoid Operated Valve Remote Position Verification Frequency ML1131304282011-11-22022 November 2011 Relief Request VRR5 Regarding Turbine Driven Auxiliary Feedwater Valve Test Frequency for the 10-Year Inservice Testing Program Interval ML1126404122011-09-20020 September 2011 Acceptance Review Results for VC Summer Relief Request (ME6879) ML1107705512011-04-26026 April 2011 Relief Request VRR2 Regarding the 10-Year Inservice Testing Program Interval ML1104705572011-02-25025 February 2011 Relief Request Regarding an Alternative Weld Repair Method for Reactor Vessel Head Penetrations J-Groove Welds ML1006807812010-03-12012 March 2010 Third 10-Year ISI Interval Relief Request (ME2608) L-08-362, Beaver, Units 1 and 2, Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Paragraph IWA-5244 Examination Requirements2008-12-0202 December 2008 Beaver, Units 1 and 2, Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Paragraph IWA-5244 Examination Requirements L-08-207, Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Inspection Period Extension Requirement2008-09-24024 September 2008 Proposed Alternative to American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Inspection Period Extension Requirement L-08-069, Impractical American Society of Mechanical Engineers Code Section XI Weld Examination Requirements (Request Nos. 1-TYP-3-RA-1, 1-TYP-3-RA-2, 1-TYP-3-RA-3)2008-04-0909 April 2008 Impractical American Society of Mechanical Engineers Code Section XI Weld Examination Requirements (Request Nos. 1-TYP-3-RA-1, 1-TYP-3-RA-2, 1-TYP-3-RA-3) ML0720504882007-09-17017 September 2007 Relief Request No. BV1-PZR-01 Regarding Weld Overlay Repairs on Pressurizer Nozzle Welds ML0705905552007-04-30030 April 2007 Relief, Relief Request No. BV2-PZR-01 Regarding Weld Overlay Repairs on Pressurizer Nozzle Welds L-07-056, Requests Approval of Proposed Alternatives and Relief for Inservice Testing Program Ten-Year Update2007-03-28028 March 2007 Requests Approval of Proposed Alternatives and Relief for Inservice Testing Program Ten-Year Update ML0625801202006-10-0202 October 2006 (BVPS-1 and 2), Inservice Inspection (ISI) Program, Alternative Examination of Reactor Coolant Pipe Welds, Request for Relief No. BV3-RV-2 2024-05-13 Category:Letter MONTHYEARIR 05000334/20240112024-10-17017 October 2024
[Table view]License Renewal Phase IV Inspection Report 05000334/2024011 L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 05000334/LER-2024-004, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 05000334/LER-2024-003, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations 05000334/LER-2024-002, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation 05000334/LER-2024-001, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000334/20240102024-05-15015 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000334/2024010 and 05000412/2024010 L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee 05000412/LER-2023-003-01, Missile Barrier Door Left Open Resulting in a Loss of Safety Function2024-02-20020 February 2024 Missile Barrier Door Left Open Resulting in a Loss of Safety Function IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection 2024-09-17 |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 21, 2016 Mr. Marty L. Richey Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
CORRECTION TO BEAVER VALLEY POWER STATION, UNIT 2- RELIEF REQUEST 2-TYP-3-RV-04, REVISION 0, REGARDING REPAIR ACTIVITIES FOR REACTOR VESSEL HEAD PENETRATION NOZZLES AND ASSOCIATED J-GROOVE WELDS (CAC NO. MF6776)
Dear Mr. Richey:
By letter dated June 17, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16147A362), the U.S. Nuclear Regulatory Commission (NRC) authorized Relief Request 2-TYP-3-RV-04, Revision 0, requested by FirstEnergy Nuclear Operating Company (the licensee) in its letter dated September 30, 2015 (ADAMS Accession No. ML15273A066). Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(z)(1 ), the relief request was for an alternative to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, associated with repair activities for reactor vessel head penetration nozzles and associated J-groove welds at the Beaver Valley Power Station, Unit 2 (BVPS-2).
This letter corrects errors in the NRC's letter issued on June 17, 2016. The letter mistakenly referred to 10 CFR 50.55a(a)(3)(i) and Unit 1 (i.e., BVPS-1) in its authorization of the alternative.
The licensee's request for the use of the alternative requested in its September 30, 2015 letter is authorized for BVPS-2 pursuant to 10 CFR 50.55a(z)(1 ).
M. Richey If you have any questions, please, contact the Project Manager, Taylor A. Lamb, at (301) 415-7128 or by e-mail at Taylor.Lamb@nrc.gov.
Sincerely, Douglas A. Broaddus, Chief Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412 cc: Distribution via Listserv
ML16228A408 OFFICE DORL/LPLl-2/PM DORL/LPLl-2/PM DORL/LPLl-2/LA DORL/LPLl-2/BC DORL/LPLl-2/PM NAME MMarshall Tlamb LRonewicz DBroaddus Tlamb DATE 08/17/2016 08/18/2016 08/17/2016 10/21/2016 10/21/2016