ML16204A039
| ML16204A039 | |
| Person / Time | |
|---|---|
| Site: | Prairie Island |
| Issue date: | 06/10/2016 |
| From: | Mcneil D NRC/RGN-III/DRS/OLB |
| To: | Northern States Power Company, Minnesota |
| Shared Package | |
| ML15274A272 | List: |
| References | |
| 50-282/OL-16-301, 50-306/OL-16-301 | |
| Download: ML16204A039 (1) | |
Text
ES-201 Examination Preparation Checklist Form ES-201-1 Facility: _Prairie Island Nuclear Generating Plant U1/U2 Date of Examination: _06/09/2016 Developed by: Written:
Facility NRC
//
Operating Facility NRC Target Date*
Task Description (Reference)
Chief Examiners Initials
-180
- 1.
Examination administration date confirmed (C.1.a; C.2.a and b) dm
-150
- 2.
NRC examiners and facility contact assigned (C.1.d; C.2.e) dm
-150
- 3.
Facility contact briefed on security and other requirements (C.2.c) dm
-150
- 4.
Corporate notification letter sent (C.2.d) dm
[-120]
- 5.
Reference material due (C.1.e; C.3.c; Attachment 3) n/a
{-90}
- 6.
Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1, ES-401-1/2, ES-401N-1/2, ES-401-3, ES-401N-3, ES-401-4, and ES-401N-4, as applicable (C.1.e and f; C.3.d) dm
{-85}
- 7.
Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e) dm
{-60}
- 8.
Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, ES-401N-6, and any Form ES-201-2, ES-201-3, ES-301-1, or ES-301-2 updates), and reference materials due (C.1.e, f, g and h; C.3.d) dm
-45
- 9.
Written exam and operating test reviews completed. (C.3.f) dm
-30
- 10.
Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202) dm
-21
- 11.
Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) dm
-21
- 12.
Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dm
-14
- 13.
Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202) dm
-14
- 14.
Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) dm
-7
- 15.
Facility licensee management queried regarding the licensees views on the examination. (C.2 j) dm
-7
- 16.
Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; ; ES-202, C.2.e; ES-204) dm
-7
- 17.
Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) dm
-7
- 18.
Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) dm
- Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
[Applies only] {Does not apply} to examinations prepared by the NRC.