Calvert Cliffs Operating Exam Comments:

Admin JPMs:

R01- appears to be a typo regarding Tavg. JPM says "and Tavg is less than 250°F" Initial condition states 100% power.

R0 Removed 2-CD-277 as a Critical task when reviewing tagout Added mechanical tagging points for 11/12 AFW Mini-Flow lines to critical task R04- Determine the best place (classroom or simulator) to conduct this JPM.

SR01- Classroom checked, but simulator setup information is given. Typo.

Corrected reference in Component Cooling Water cue SR02- Removed 2-CD-277 as a Critical task when reviewing tagout Added mechanical tagging points for 11/12 AFW Mini-Flow lines to critical task Moved cue for Technical Specification from body of JPM to Examinee's Cue Sheet SR03- Revised Critical Task values for dose calculations to include conservative calculation of highest dose rate (i.e. highest dose rate for entire duration)

SR04- Increased Containment Radiation Monitors readings on Examinee's Cue Sheet Transferred cue information from the body of the JPM to the Examinee's Cue Sheet Added that a Hostile Action is not in progress to the Examinee's Cue Sheet Downgraded two Critical Tasks due to adding information to the Examinee's Cue Sheet SR05- same typo as R01.

Put page 7 cues into the initial conditions.

In-Plant JPMs:

ln-Plant1 - Added panel name of 2C43 to cue.

ln-Plant2 - Added Off position to standard in steps N.1 and N.2.

Added panel name of 1C43 to cue.

Page 1of3

Simulator JPMs:

Sim1 - Added cue regarding Chemistry surveillance to Examiner's Cue Sheet Revised standard for step 6.2.A Revised standard for step 6.2.1 for CEA position Removed duplicate cue prior to AOP-1 B Sim2 - Changed details of Task Standard Changed standard from Step Q to Step R for EOP-5 Step R Changed standard to 12 LPSI in Step S.1.a.1 ( 1)

Added band of 450-600 GPM to standard for Step S.1.a.1 (2)(b)

Sim3 - Deleted redundant portion of element in Step Vl.B.4 Added information to Examinee's Cue Sheet regarding ERPIP Personnel Emergency Attachment Sim4 - Added Simulator setup instruction to ensure PZR level is -160" at start of JPM Copied Initial conditions to Examinee's Cue Sheet Sim5 - Revised standard for Step 1.1.a to reflect power condition of CACs Revised standard for Step 1.2 SIAS to reflect MOV indications Added Evaluator Note prior to Step 3.1 stating 01-58 may also be referenced during execution of the step Added Cues for ESFAS verification reports Sim6 - Revised Examinee's Cue Sheet instructions to use the normal breaker to repower the 21 4Kv bus and removed cue from JPM Revised Standards on Steps 1, 2, and 3 for only the busses required to support the normal breaker as the power supply Added Simulator Setup instructions to ensure Unit-2 EOP Attachments are available Sim? - Removed Sim Setup instructions to chain RPS Cabinets A,C, & D and CCV tags on breakers Added Evaluator Note for Simulator Driver to leave Annunciator Horn unacknowledged following the loss of 1Y02 Page 2 of 3

Scenarios:

Scenario 1

  • Changed to 23 AFW pump OOS to match equipment OOS in other scenarios
  • Added time trigger to insertion of Event 9
  • Enhanced Responses to Crew Requests
  • Removed required action, Increases Charging flow, from Event #5
  • Changed HR-2 to met in Event 9 and ensured CE-1 met
  • Added directions to shut 12 MSIV based on scenario trigger
  • Added potential EOP-5 actions to Event 8 Examiner Notes Scenario 2
  • Added summer conditions to turnover
  • Changed timeline of 1A DG STP to indicate that 30 minutes are left on test
  • Corrected typo on Event #1 regarding 11 Charging Pump
  • Provided options in Event #4 using boration and/or CEAs
  • Removed Shuts CVC-501-MOV from Event #5 due to power loss
  • Enhanced Responses to Crew Requests
  • Added briefing requirement for loss of MCC 101 AT/BT as part of turnover
  • Enhanced MCC-104/114 guidance to the Examiner Scenario 3
  • Changed to 23 AFW pump OOS to match equipment OOS in other scenarios
  • Changed wisping ADV to 12 ADV
  • Corrected typo on Event #8 Critical Task AFW Block valves
  • Enhanced Responses to Crew Requests Page 3 of 3