ML16161A988

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/88-11,50-270/88-11 & 50-287/88-11 on 880425-0505.No Violations or Deviations Noted.Major Areas Inspected:Review of Adequacy of Emergency Operation Procedures
ML16161A988
Person / Time
Site: Oconee  
Issue date: 06/07/1988
From: Julian C, Lawyer L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16161A987 List:
References
50-269-88-11, 50-270-88-11, 50-287-88-11, NUDOCS 8807120257
Download: ML16161A988 (25)


See also: IR 05000269/1988011

Text

NUCLEA

EULATRS COMMSO

REGION if

0 VASTTA STREET, N .V

1

TLANTA, GEORGIA 30E23

Licensee:

Duke Power Company

422 South Church Street

Charlotte NC 28242

Docket Nos.:

50-269, 50-270, 50-287

License Nos.:

DPR-38, DPR-47, DPR-55

Facility Name:

Oconee Nuclear Station

Inspection Conducted: April Z2-

May 5, 19,8&.

Inspection Team Leader:

LA3

.

t--

f

A

L. Lawyer

Date Signed

Inspection Team Members: M. Archer

M. .DeGraff

P. Kellogg

G. Bryan

P. Skinner

Approved By:

!

C. A. Julia ,/}Chief

Date Signed

Operations Branch

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection was conducted in the area of review

of the adequacy of Emergency Operation Procedures.

Results:

No violations or deviations were identified.

807120:257 880628

PDR

ADOCK050006

P DC

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • R. Bugert, Manager Operations Training
  • M. Carter, Design Engineer
  • D. Deatherage, Operating Engineer
  • C. Harlin, Compliance Engineer
  • R. Ledford, QA Surveillance Supervisor
  • R. Lingle, Operations Engineer
  • R. Morgan, Production Engineer
  • F. Owens, Shift Supervisor
  • M. Patrick, Operations Engineer
  • P. Stovall, Lead Simulator Instructor
  • R. Swiegart, Superintendent Operations
  • M. Tuckman, Station Manager

Other licensee employees contacted included engineers, technicians,

operators and office personnel.

NRR Attendees

  • W. Regan, Chief, Human Factors Assessment Branch
  • H. Pastis, Project Manager

NRC Resident Inspectors

  • P. Skinner, Senior Resident Inspector.
  • L. Wert, Resident Inspector
  • Attended exit interview on May 5, 1988.

2.

Exit Interview

The inspection scope and findings were summarized on May 5, 1988, with

those persons indicated in paragraph 1.

The

NRC described the areas

inspected and discussed in detail the inspection findings listed below.

Although proprietary material was reviewed during this inspection,

no

proprietary material is contained in this report.

Those items on which

dissenting comments were received from the licensee are identified by a

marginal asterisk in the detailed discussion which follows.

Note: A list of abbreviations used in this report is contained in

Appendix E.

2

Item Number Status

Description/Reference Paragraph

IFI 269,270,287/88-11-01

Open

Resolution of QA review

effectiveness (paragraph 4)

IFI 269,270,287/88-11-02

Open

Resolution of OP references in the EP

(paragraph 5)

IFI 269,270,287/88-11-03

Open

Correction of labeling discrepancies

between EOPs and panel indication as

outlined in Appendix D (paragraph 6)

IFI 269,270,287/88-11-04

Open

Correction of technical discrepancies

contained in the EOPs as outlined in

Appendix B (paragraph 6)

IFI 269,270,287/88-11-05

Open

Correction of human factors discrep

ancies contained in EOPs as outlined

in Appendix C (paragraph 6)

IFI 269,270,287/88-11-06

Open

Review Natural Circulation Cooldown

with vents open (paragraph 6)

IFI 269,270,287/88-11-07

Open

Review simulator

effectiveness

in

training on EOPs (paragraph 7)

IFI 269,270,287/88-11-08

Open

Review writer's guide training to

increase operator awareness of terms

(paragraph 8)

3.

Background Information

Following the TMI accident, the Office of Nuclear Reactor Regulation

developed the "TMI Action Plan" (NUREG-0660 and NUREG-0737) which required

licensees of operating reactors to reanalyze transients and accidents and

to upgrade Emergency Operating Procedures (EOPs) (Item I.C.1).

The plan

also required the NRC staff to develop a long-term plan that integrated

and expanded efforts in the writing, reviewing, and monitoring of plant

procedures (Item I.C.9).

NUREG-0899, "Guidelines for the Preparation of

Emergency Operating Procedures," represents the NRC staff's long-term

program for upgrading EOPs, and describes the use of a "Procedures

Generation Package" to prepare EOPs.

The licensees formed four vendor

type owner groups corresponding to the four major reactor types in the

United States; Westinghouse, General Electric, Babcock & Wilcox, and

Combustion Engineering.

Working with the vendor company and the NRC,

these owner groups developed Generic Technical Guidelines (GTGs) which

are generic procedures that set forth the desired accident mitigation

3

strategy. These GTGs were to be used by the licensee in developing their

PGPs.

Submittal of the PGP was made a requirement by Confirmatory Order

dated July 6, 1984. Generic Letter 82-33,

"Supplement 1 to NUREG-0737

Requirement for Emergency Response Capability," requires each licensee to

submit to the NRC a PGP which includes:

a.

Plant-specific technical guidelines with justification for differ

ences from the GTG

b.

A writer's guide

c.

A description of the program to be used for the validation of EOPs

d.

A description of the training program for the upgraded EOPs.

From this PGP, plant specific EOPs were to have been developed that would

provide the operator with directions to mitigate the consequences of a

broad range of accidents and multiple equipment failures.

Due to various circumstances,

there were long delays in achieving NRC

approval of many of the PGPs.

Nevertheless,

the licensees have all

implemented their EOPs.

To determine the success of the implementation, a

series of NRC inspections are being performed to examine the final product

of the program; the EOPs. The objective is to perform table top reviews,

simulator exercises where possible,

and in-plant walk-throughs of the

EOPs with licensed operators to verify their adequacy.

The

EOPs are

considered to be adequate for use if they can be understood and performed

successfully by the operators and they incorporate the accident mitigation

strategy developed by the appropriate vendor specific owner groups.

This inspection report represents findings, observations, and conclusions

regarding the adequacy of the EOPs.

It

did not,

as a matter of intent,

review whether the EOPs thus prepared conformed to the NRC staff's long

term program for upgrading EOPs and whether those EOPs had been properly

prepared using a PGP.

The success level of licensees in following the

PGP submitted to NRC

is a regulatory issue that will be dealt with on a case-by-case basis.

Although some licensees'

EOPs strayed far from their PGP,

that issue is

of secondary importance to this inspection effort.

The purpose of this

inspection is to verify adequacy of the EOPs for continued safe operation

of the facility.

4.

EOP/GTG Comparison

The NRC reviewed the relationship between the Oconee EOPs and the plant

specific EPGs. The approved Oconee ATOG and the B&W owners' group TBD are

generic technical guidelines that form the basis for the Oconee plant

specific technical guidelines detailed in the EPG document (Figure 1).

An

"EPG

-

TBD Deviations Document"

(2/12/88)

details specific deviations

between the EPG document and the TBD.

4

Figure 1

Development of the Oconee EOPs

B&W OG

Generic Technical

l

Plant Specific

l

Emergency Operating

Guidelines

l

Technical Guidelines I

Procedures

(ATOG +

TBD)

=>

Oconee EPGs

=>

Oconee EP & APs

(Deviation Document)

The EPG document serves as the plant specific technical guideline from

which Oconee EOPs and their changes are developed.

The Oconee emergency

procedure (EP/1/A/1800/01)

very closely parallels the EPG document, but,

as appropriate, provides greater operational detail.

The licensee uses

plant specific APs to supplement the EP.

The Oconee EP and APs together

compose the licensee's emergency operating procedures.

The NRC reviewed emergencies and other significant events covered by the

Oconee

EP

and APs.

Taken together the EP and AP procedures cover the

broad range of emergencies and other significant events listed in RG 1.33,

section 6. At Oconee the EP and AP procedures together constitute the

EOPs.

A Quality Assurance department individual was interviewed and selected

records were reviewed to verify that QA had been properly involved in the

initial preparation

of the

EP

and

APs.

QA

audit NP-87-14(ON)

was

conducted on operations activities from 8/24/87 to 9/18/87.

This audit

encompassed the EP and APs. There were no deficiencies noted by that QA

audit.

A review of the EP and APs was conducted by QA during the procedure

preparation phase.

While the purpose of this review was

to verify

adherence to the writer's guide,

findings produced by this review were

minimal and many failures to conform to the writer's guide were missed

(see Appendix C). Three specific examples of this were AP/1/A/1700/7, Loss

of Low Pressure Injection System, AP/1/A/1700/22, Loss of Instrument Air,

and AP/1/A/1700/23, Loss Of 1KI (NNI).

The QA review of these had listed

only a small fraction of the writer's guide deficiencies such as unapproved

abbreviations, incorrect

spelling

and capitalizations

which

were

identified in a spot check

by the

NRC.

A licensee representative

5

committed to review the effectiveness of this QA

review and take

appropriate corrective action.

Resolution of this

issue will

be

identified as IFI 50-269, 270, 287/88-11-01.

No violations or deviations were noted in this area.

5.

Independent technical adequacy review of the EOPs.

  • The NRC determined by review of the procedures listed in Appendix A that

generally the vendor recommended step sequence was followed except where

deviations were documented in the EPG-TBD Deviations Document.

Review of

the EOPs established that the ATOG guidance was contained within the EOPs

whenever applicable. The general priority of treatment and order of steps

was maintained in the procedures. However, in order to reduce the bulk of

the EOP,

on occasion the operator was referred to an entire operating

procedure, of which only a small portion was applicable (e.g.,

Appendix

C, item la,

1c1,

1c2,

1d,

etc.).

The licensee should review the OP

references to determine if

the applicable portions of the OPs could be

included as steps within the EP or as a separate enclosure.

Resolution

of this issue will be identified as IFI 50-269,270,287/88-11-02

Placekeeping deficiencies were identified during simulator and control

room walk-throughs of the EOPs and are documented in Appendix C. These

include:

  • a.

Portions of the

EP and APs were removed from their binders to

hand to other operations personnel.

This caused several delays in

the completion of procedures. An additional copy of the APs should

be provided in the control room or other steps should be taken to

avoid the need for doing this.

b.

Many operators inappropriately made use of random objects

(fingers,

pencils,

and a stapler) as placekeeping aids.

However,

one

SRO

employed an appropriate solution to this problem.

He used yellow

stick-ups to mark

WHEN

statements to remind himself of future

actions. This placekeeping technique worked successfully and should

be encouraged.

The inspectors verified that entry conditions to the procedures were

generally clear.

The

scenarios postulated during

the procedure

walk-throughs resulted in multiple transfers and instances of simultaneous

use of the EOPs; no significant errors were identified.

Cautions and notes were generally clear and properly placed within the

EOPs. The priority of accident mitigation appeared to be maintained in the

Oconee EOPs.

The degree of adherence to the B&W guidance available in the ATOG and the

TBD was found to be appropriate.

The licensee has identified major

deviations as required between the ATOG/TBD and the EPG in the Emergency

Procedure Guidelines Technical Basis Document Deviations Document.

The

6

inspectors were unable to confirm that safety significant deviations were

reported to the NRC due to time constraints.

ONS unique operator action parameter values were established in the ONS

setpoint document and were used in the EOPs except for the infrequent

occasions noted in the appendices.

Control room drawings were inspected to verify that management controls

were effective and that plant changes were reflected in interim and final

drawings in a timely manner.

The inspectors found that the number of

outstanding NSMs requiring drawing changes did not appear to be excessive,

and the number appeared to be decreasing.

There were no violations or deviations noted in this area.

6.

Review of the EOPs by In-Plant and Control Room Walk-throughs

In-plant and control

room walk-throughs of the emergency and abnormal

procedures listed -in

Appendix A were conducted.

Generally,

the

nomenclature appears to be consistent between the instrumentation and

control labeling on the control board and the procedures.

Those few

discrepancies noted are enumerated in Appendix D. The licensee committed

to review these and make changes as appropriate. Resolution of this issue

is identified as IFI 50-269,270,287/88-11-03.

Indicators, annunciators and controls referenced in the EOPs were found to

be available to the operators. There is one set of emergency and abnormal

procedures maintained in the control room at all times for each unit.

These procedures were verified to be of the latest revision and free of

any handwritten changes.

While the result of these walk-throughs was generally positive, a few

discrepancies in the areas of technical adequacy, writer's guide adherence

and human factors were noted.

Technical discrepancies are identified in

Appendix B, while writer's guide and human factors discrepancies are noted

in Appendix C. The licensee has committed to correct the discrepancies

identified in the aforementioned appendices except where specifically

excepted by marginal asterisk.

Appendix B discrepancies will be identi

fied as IFI 50-269,270,287/88-11-04, and Appendix C discrepancies will -be

identified as IFI 50-269,270,287/88-11-05.

In response to Generic Letter 81-21, the licensee committed to perform a

natural circulation cooldown without forming a void in the reactor vessel

head. The licensee's method of accomplishing this is to open the reactor

vessel head vent prior to initiating the cooldown. While this will help to

prevent void formation this will also open the reactor coolant system to

the reactor building. This could result in excessive contamination of the

reactor building and possibly limit access for some time.

7

It

should be noted that at the time Generic Letter 81-21 was issued,

procedures for natural circulation cooldown with upper head voids were not

generally available.

The

NRC staff's technical position on upper head

voiding has changed accordingly. Controlled voiding into the reactor

vessel upper head is

now an acceptable strategy provided that it

can be

done using all safety grade equipment with NRC approved procedures and

licensed operators trained in the use of these procedures.

The licensee

committed to review the use of head vents in light of this position and

request a change to allow cooldown with the head vents closed. Resolution

of this issue will be identified as IFI 50-269,270,287/88-11-06.

Due to time constraints many of the aspects of the validation and

verification program that were applied to the development of the EP and

APs were not inspected in depth.

Some deficiencies are identified in

connection with the licensee's ongoing evaluation of EOPs in paragraph 8.

There were no violations or deviations noted in this area.

7.

Simulator Observations

The

NRC

observed

two different crews performing

the following six

scenarios on the Oconee simulator:

a.

Loss of Electrical Power

b.

Overcooling

c.

Loss of HPI and RCP Seal Failure

d.

Loss of all Feedwater

e.

Steam Line Break with SG Tube Rupture

f.

Small Break LOCA

The procedures provided operators with sufficient guidance to fulfill

their responsibilities and required actions during the emergencies, both

individually and as a team.

The procedures did not cause the operators -to physically interfere with

each other while performing

the

EP

and APs.

However,

the operator

concurrently performing APs and OPs was loaded with tasks.

The procedures did not duplicate operator actions unless required (e.g.,

for independent verification).

When a transition from one

EOP to another EOP or other procedure was.

required,

precautions were taken to ensure that all necessary steps,

prerequisites, initial conditions, etc. were met. Operators were found to

be knowledgeable about where to enter and exit the procedures.

However,

there were a number of problems related to placekeeping in the procedures

(see Appendix C, Writer's Guide and Human Factors discrepancies).

8

Activities that should occur outside the control room were initiated by

the operators and proper confirmation of their completion was given.

These actions were

inspected during

in-plant walk-throughs

of the

procedures.

The EOP lesson plans cover both the technical basis behind the procedures

and their structure and format. The training scenarios provide sufficient

coverage of the EOPs (with the exceptions noted below), including multiple

malfunctions.

In addition, operators were

trained on

significant

revisions of the EOPs prior to their implementation.

The training simulations should duplicate actual plant operations whenever

possible.

The extent of simulation should be such that the operator is

required to take the same action on the simulator to conduct an evolution

as on the reference plant using the same procedure. Three deficiencies in

this aspect of EOP training program were noted:

a.

Operators are encouraged in training not to check the placekeeping

check-off spaces in the EP,

while they are expected to do so in an

actual emergency.

  • b.

The PORV operating switch (1RC-66)

in the simulator is not a spring

return to auto switch as it is in the plant.

Because of this, the

simulator does not accurately simulate plant procedures involving

opening the PORV.

c.

The simulator cannot model the use of the diesel air compressor as

an emergency supply of instrument air.

Simulator training in EOP usage should model the reference plant as nearly

as possible. The licensee should review EP and AP simulator training and

retraining, and assure that discrepancies such as these are eliminated.

Resolution of, this item will be identified as IFI 50-269,270,287/88-11-07.

No violations or deviations were noted in this area.

8.

Ongoing Evaluation of the EOPs

Administrative controls were reviewed to determine if

the licensee has

an acceptable program in place for a continuing evaluation of the EOPs.

These were OMP 4-2, The Validation Process; APM Section 4.2, Administra

tive Instructions for Permanent Station Procedures; and procedure MNSA-103,

Workplace

Procedure for Technical Review and Verification of Nuclear

Station Emergency Procedure and Guidelines. While these procedures were

used to verify the EP, only selected APs received full V&V. Since the NRC

did not consider the number of discrepancies listed in Appendices B, C,

and D to be indicative of a serious V&V problem,

no corrective action is

proposed for existing EOP revisions. However, the licensee has committed

to apply V&V to future revisions of the EOP.

9

There were no violations or deviations noted in this area..

9.

EOP User Interviews

Ten interviews were conducted by the NRC inspection team and it

was

determined that the current EOPs satisfy the needs of the operational

personnel.

The operators felt the EOPs were adequate and compatible with

the level of knowledge of the typical operator,

and the operations staff

were confident that the EOPs would function effectively during an actual

event.

One discrepancy that was noted during these interviews was that

confusion appeared to exist among the operators interviewed as to the true

meanings of the terms "available","excessive", "go to",

"refer to" and

"complete".

These inconsistencies indicate a need for further operator

training in the terminology used in the EOPs and/or definitions contained

in the Writer's Guide. The licensee should review this area and provide

retraining as necessary. Resolution of this issue will be identified as

IFI 50-269,270,287/88-11-08.

There were no violations or deviations noted in this area.

APPENDIX A

PROCEDURES REVIEWED

NUMBER

TITLE

EP/1/A/1800/01

EMERGENCY OPERATING PROCEDURE

04/08/88

AP/1/A/1700/01

LOAD REJECTION

04/08/88

AP/1/A/1700/02

EXCESSIVE RCS LEAKAGE

04/08/88

AP/1/A/1700/03

BORON DILUTION

04/08/88

AP/1/A/1700/05

EARTHQUAKE

04/08/88

AP/1/A/1700/06

NATURAL DISASTER

04/08/88

AP/1/A/1700/07

LOSS OF LOW PRESSURE INJECTION SYSTEM

AP/1/A/1700/08

LOSS OF CONTROL ROOM

04/07/88

AP/1/A/1700/09

SPENT FUEL DAMAGE

04/07/88

AP/1/A/1700/10

UNCONTROLLABLE FLOODING OF TURBINE BUILDING 04/08/88

AP/1/A/1700/11

LOSS OF POWER

01/29/88

AP/1/A/1700/12

LOOSE PARTS IN REACTOR COOLANT SYSTEM

04/07/88

AP/1/A/1700/13

LOSS OF CONDENSER CIRCULATING WATER INTAKE 04/07/88

CANAL/DAM FAILURE

AP/1/A/1700/14

LOSS OF NORMAL MAKEUP OR LETDOWN

AP/1/A/1700/15

DROPPED CONTROL RODS

AP/1/A/1700/17

LOSS OF CONTAINMENT INTEGRITY

04/13/88

AP/1/A/1700/18

ABNORMAL RELEASE OF RADIOACTIVITY

04/22/88

AP/1/A/1700/19

LOSS OF MAIN FEEDWATER

02/29/88

AP/1/A/1700/20

LOSS OF COMPONENT COOLING

04/12/88

AP/1/A/1700/21

HIGH ACTIVITY IN RC SYSTEM

04/25/88

AP/1/A/1700/22

LOSS OF INSTRUMENT AIR

03/31/88

AP/1/A/1700/23

LOSS OF 1KI (NNI)

04/14/88

AP/1/A/1700/24

LOSS OF LPSW

PROCEDURES REFERRED TO BY EP OR APs THAT WERE REVIEWED (IN FULL OR IN PART)

CP/1&2/2002/05

POST ACCIDENT CAUSTIC INJ INTO LPI

03/14/88

.OP/0/A/1102/22

RB HYDROGEN ANALYZER SYSTEM

10/03/85

OP/O/A/1102/23

OPERATION OF CONTAINMENT HYDROGEN RECOMBINER 03/01/87

OP/O/A/1102/25

SHUTDOWN FOLLOWING A FIRE

10/20/87

OP/O/A/1103/05

PRESSURIZER OPERATION

08/16/84

OP/O/A/1106/31

CONTROL OF SECONDARY CONTAMINATION

01/22/87

OP/O/A/1600/11

SSF EMERGENCY OPERATING PROCEDURES

12/10/87

OP/1/A/1102/04

OPERATION AT POWER

02/03/88

OP/1/A/1102/10

CONTROLLING PROCEDURE FOR UNIT SHUTDOWN

11/24/87

OP/1/A/1103/06

RCP OPERATION

04/13/87

OP/1/A/1104/04

LPI SYSTEM

10/21/87

OP/1/A/1106/01

TURBINE GENERATOR

01/18/88

Appendix A

2

PT/1/A/1103/15

REACTIVITY BALANCE

10/09/87

  1. Procedures are in the review process and have not yet been approved

for use.

-APPENDIX B

TECHNICAL COMMENTS.

This appendix contains technical comments, observations and suggestions for EOP

improvements made by the NRC.

Unless specifically stated, these comments are

not regulatory requirements. However,

the licensee agreed in each case to

evaluate the comment and take appropriate action. These items will be reviewed

during a future NRC inspection as noted in paragraph 6.

1. EP/1/A/1800/01 Section 504,

SG Tube Leak

a. Step 9.1 has the operator open 1RC-159 and 1RC-160, but does not

inform the operator that SKL Breaker 8 in the Cable Room must be

closed to open these valves.

The breaker is normally kept open

during operation. A number of operators were not aware of this. The

need to close the breaker should be noted in the EP or a warning

label placed next to the valve switches on the control panel.

b. Step 11.2 The order of the items is important, but they are not

numbered as required by the writer's guide.

2.

EP/1/A/1800/01 Section CP-603, HPI Cooling Cooldown

a. step 5.0; In order to open either the high point vents or the

reactor head vent the local breaker must be closed and then the

"power on" button must be depressed on the main control board.

This

required action is not addressed in the procedure.

The licensee

should revise the procedure accordingly.

b. step 26; A note should be included in the step to feed only the

unaffected generator unless the affected steam generator is required

for heat transfer.

3.

AP/1/A/1700/03, Boron Dilution

The licensee should consider revising the AP and supporting

OP/1/A/1103/04 to recognize those AP cases and symptoms which are

severe enough to warrant immediate boron injection without waiting

for chemistry sample results. As written, the procedures currently

follow a process of:

AP entry to a particular case,

chemistry

sampling, exit to the OP,

await sample results, determine desired

concentration, compute, lineup, and then add boron.

An example of a case that warrants immediate boron injection is AP

case D. With the reactor critical at power and control rod insertion

to a position to the left of the safety limit curve,

the procedure

Appendix B

2

should add boron immediately. When rod position has been restored to

at least the 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> LCO region, a final predetermined addition can be

made in the normal manner.

The

NRC concluded that immediate boration was applicable in other

cases such as AP case A,B and C.

4.

AP/1/A/1700/13,

Loss of Condenser Circulating Water Intake

Canal/Dam Failure.

a. Pg. 3, step 5.4;

This step waits until secondary heat removal

systems are "exhausted" before sending personnel to the SSF.

The procedure should be revised to man the SSF prior to exhaustion.

b. Pg 7, step 4.4; The licensee should consider adding a note

following 4.4 explaining that if all four CCW pumps were running,

CCW 10-13 would be open. To reestablish pump flow, an NLO must

close one discharge valve prior to start of that pump in step 4.5.

5.

OP/1/A/1103/06, Reactor Coolant Pump Operation

Enclosure 4.3, section 2.5; This section requires "start RCPs using

enclosure 4.1." If

enclosure 4.1 was used in strict conformance to

this step, i.e. establish the seal injection prior to the start of

the pump, the intent of this section would not be met. The intent is

to start the pump without seal injection and gradually bring seal

injection into operation.

Appendix C.

WRITER'S GUIDE AND HUMAN FACTORS DISCREPANCIES

This appendix contains comments, observations and suggestions for EOP improve

ments made by the

NRC.

Unless specifically stated,

these comments are not

regulatory requirements.

However, the licensee agreed in each

case to

evaluate the comment and take appropriate action. These items will be reviewed

during a future NRC inspection as noted in paragraph 6.

1. EP/1/A/1800/01, Emergency Operating Procedure

a.

Section

502,

Loss

of

Heat Transfer;

The

reference to

OP/O/A/1102/25, Shutdown Following a Fire, for operation of the

atmospheric dump valves is inappropriate. The EP should specify

which section of the enclosure to use or the specific steps

should be put into the EP from the OP.

b.

Section 503,

Excessive Heat Transfer; Step 2 refers to a SG

level of greater then 92%. The

EPG references a 95% setpoint

for this condition.

The licensee should resolve this conflict

to reflect the actual plant value.

c.

Section 504, SG Tube Leak

(1) Step 5.0 refers the operator to OP/1/A/1102/4,

OPERATION

AT

POWER,

but does not specify a step number.

The only

applicable step is 3.4. This should be referenced in the

EP.

(2) Step

6.1

refers

the

operator

to

OP/1/A/1102/10,

CONTROLLING

PROCEDURE

FOR

UNIT

SHUTDOWN,

but does

not

specify a step number.

The only applicable step is 3.2

(Turbine Generator Shutdown).

This step number should be

referenced in the EP.

(3) Steps 11.0 and 26 contain a list of valves to be closed to

isolate the SG. There is no action statement to inform the

operator that he should close the valves. This step should

be rewritten to conform with the writer's guide.

(4) Page 83.

In the Unit Status Summary "using on

SG with

forced circulation" appears to be a typographical error.

d.

Section 507, Inadequate Core Cooling; In step 14 the intentions

are to start a Reactor Coolant Pump.

The caution and first

bullet reference support systems and the operating procedure.

The initial conditions of the operating

procedure

may

be

contradictory to the current plant condition at the time this

step is

being

implemented

and could

be confusing

to the

operator. This step should be modified to clearly state which

section of the OP would be applicable.

Appendix C

2

e.

Section CP-601, Cooldown Following a Large LOCA

(1) Step

2.4.2;

This

step

refers

the

operator

to

OP/0/A/1102/25,

Shutdown

Following a Fire,

to provide

direction on the use of the atmospheric dump valves. From a

review of this procedure it

appears that only one step in

this OP is applicable to the operation of the atmospheric

dump valves. The licensee should revise the EP to include

the applicable information from the OP.

(2) Step 8.1; This step requires the operator to verify RB

isolation but the step provides no guidance on which valves

need to verified closed nor does the step address any

specific valve line-ups. The licensee should provide

additional guidance denoting valves which

need to

be

verified.

(3) Step 8.1; This step is lacking in two other respects.

Step 12 of the same procedure requires,. when initiating

make-up

to the

BWST,

that the boron concentration be

greater than T.S. values. Additionally, step 12 references

OP/1/A/1104/04, Low Pressure Injection System for the

correct make-up

procedure

given

the

current

plant

configuration. Step 8.1 contains neither the concentration

requirement nor the reference.

The licensee should revise

step 8.1 to be consistent with other steps completing the

same action.

(4) Step 9.0; Within this step there are two separate actions.

The first action requires chemistry to sample the RB

emergency sump for boron concentration.

The second action

(if

necessary)

requires operations to isolate possible

sources of sump dilution. The licensee should revise the

procedure to separately state these group responsibilities.

f. Section CP-602, SG Cooldown With Saturated RCS

(1) Step

17 includes a list of valves to close.

One line

lists the RCP seal return valves, the next states "(If RCPs

NOT operating)," and the following line lists the Quench

Tank Vents. This use of a conditional is unclear, and not

in accordance with the Writer's Guide. This step should be

rewritten to clarify the meaning of the conditional

and

conform to the writer's guide.

(2) Step

39; This step includes a list of "bullets"

for

alternative methods to be used to reduce

RCS pressure.

This list is intended to provide alternative actions to be

taken in order of preference, not an indication that the

operator should

always perform all the actions (the

Appendix C

3

meaning of bullets is described in the writer's guide).

This step should be rewritten to clarify the meaning of

these bullets and to conform to the writer's guide.

g.

Section CP-603, HPI Cooling Cooldown

(1) Step 2.0 requires that when subcooling margin is greater

than

50 degrees F and CETCs are decreasing,

RCS P/T be

maintained in the proper region of enclosure 7.1.

To be

consistent with other steps referencing the same action the

licensee should include a statement to throttle HPI.

(2) Step 16; Same comment as CP-601, step 9, above.

h.

Section CP-604, Solid Plant Cooldown

(1) Step 4.0;

To

be

consistent with other

steps which

reference maintaining RCS P/T within the proper region of

enclosure 7.1, the licensee should include a statement to

throttle HPI when subcooling margin is greater than 50

degrees F.

(2) Step 11; Under verify RB isolation the phrase "if RCPs are

not operating" appears. It is unclear

as

to

the

applicability of this statement. The licensee should revise

the procedure to clearly identify which valves need to be

verified closed if the RCPs are not operating.

2. AP/1/A/1700/01, Load Rejection

a.

Step 3.0;

Main steam relief valve position indication is not

available in the control room. The procedure should be revised

to indicate that confirmation of valve position is required from

external observation.

b.

Step 5.3;

396" is near the upper range limit of the instrument

(400")

and is too precise to be read from the installed meter.

If this value is correct (see comment below) and the precision

is required, the step should be revised to direct the operator

to verify level from a computer point.

c.

Step 5.3;

Change 396" to be consistent with other documents.

This

step

reacts

to pressurizer solid conditions.

Both

EP/1/A/1800/01

(step

5.17.4)

and the

EPG Setpoint

Document

(pg.9)

use 375" as the licensee's definition of pressurizer

solid.

396" does not appear in the setpoint document.

Appendix C

4

3. AP/1/A/1700/02, Excessive RCS Leakage

Step 5.6.1; This step refers to any subcooling margin " less than or

equal to zero."

To be consistent with other steps the reference to

subcooling margin should be changed to " equals zero."

4. AP/1/A/1700/03, Boron Dilution

Step 5.1 of Case A, B, C, & D; In this step, the reader is directed

to "Refer to the Emergency Plan."

Where appearing, this should be

changed to "Refer to AP/O/B/1000/01, Classification of Emergencies."

The decision to implement the EP plan is made from that procedure.

5. AP/1/A/1700/07, Loss of Low Pressure Injection

a.

Steps 5.2, 5.5 and 5.5.4 case B; All these steps address

make-up to the RCS; however, they are not consistent with each

other. The licensee should revise these steps such that make-up

to the RCS is done the same way each time.

b.

Step 5.5.4.2; There is a typographical error. The licensee

needs to change "fo" to "to".

6.

AP/1/A/1700/08,

Loss of Control Room

Case A; In Step 4.8, an operator is sent to the Unit 1 and 2 WDP with

directions to establish communications with the Auxiliary Shutdown

Panel as soon as possible. Although there is a telephone at the WDP,

no phone number is listed in the procedure,

posted by the telephone

or otherwise quickly available to allow the operator to establish

this communication.

7. AP/1/A/1700/11, Loss of Power

a.

Step 6.1, THEN statement. Add a reference to OP/1/A/1104/12.

b.

Step 11.0.

Add "Verify" to the last 4 bullets of the IF

statement.

c.

Step 4.2;

Position a copy of OP/O/A/1106/27 at the diesel air

compressor. Currently,

an in plant NLO tasked to start the

compressor must go to the Control

Room for a copy of the OP,

then to the diesel compressor.

On a loss of instrument air,

time is too precious to accept the lost time involved in pulling

a copy of the procedure from the control room before proceeding

to the diesel.

d.

Step 5.3.1;

Valve label plate is missing on 1CCW- 79 and

should be replaced.

Appendix C

5

e.

Enclosure 6.2, step 1.0;

This step involves high voltage

hazards and should be done by experienced I&E personnel.

At

present there is no procedural requirement for I&E staffing on

back shifts.

The licensee should consider establishing a

minimum I&E manning level in plant procedures.

f.

Step 8.0;

1HP-26 is an infrequently operated valve. The

procedure should be revised to include the physical location of

the valve.

g.

Step 3.0;

Provide a racking tool at or near the auxiliary

service water switchgear.

h.

Step 3.6;

ASW 600V Load Center label plate is missing and

should be replaced.

8. AP/1/A/1700/13, Loss of Condenser Circulating Water Intake Canal/Dam

Failure

a.

Case A & B, Step 2.0;

The same parameter value should apply in

both lake level bullets (now shown as -775' and decreasing less

than 775' respectively).

b.

Case B, Step 4.1.1.

Delete the last bullet. "Continue

concurrently with ...

" is redundant to "REFER TO."

c.

Case B, Step 4.3; The procedure should be revised to direct the

operator to obtain 1CCW-20 through 25 valve positions from the

control room computer point readout or by local verification.

d.

Case B, Step 4.6;

The last bullet states security will

energize the lock. Operators indicate that normal practice is

to send a guard directly to the gate and that some problems have

arisen when

guards did not know-where

to go.

Additional

training and possible procedure changes should be considered.

e.

Enclosure 6.1, Step 1.0;

Install a chain on LPSW-139 or

provide a nearby ladder.

The nearest ladder is -150'

away

through a dimly lighted area,

an area which may be flooded if

this procedure is operative.

f.

Enclosure 6.1, Pg 12;

After step 4.0, direct the reader back

to pg. 9 to continue with step 5.6.2 of Case B.

9. AP/1/A/1700/23 -

Loss of IKI Bus (NNI)

Step 5.7 instructs an operator to proceed to the equipment room to

bypass the 1KI inverter by changing switch positions. These switches

are located above the KI panel so that a ladder would be required to

safely operate these switches.

A ladder should be

staged in the

room.

Appendix C

6

10. AP/1/A/1700/20, Loss of Component Cooling

Step 4.4 requires that all heat exchangers be checked for temperature

increase. The licensee should revise this step to include the maximum

values to assist the operators in determining when a limit is being

approached.

11. AP/1/A/1700/22, Loss of Instrument Air

a.

Section 2.0, symptoms; The statalarm location, (2SA-4 D-5)

should be (2SA-4 C-5). Typographical error.

b.

Step 5.3.1; The second bullet requires the operator to remain

in the

area

of

1CC-8. Radiation

levels

need

further

consideration. The present stationing of an operator in this

area would be unacceptable under certain accident conditions.

The licensee should revise the procedure to include a caution

statement as to the presence of high radiation levels under

certain accident conditions when manual operation of 1CC-8 is

required.

c.

Step 5.5; The labels attached to 1FDW-315 and 1FDW-316 are

color coded incorrectly, i.e. red versus black.

12.

OP/1/A/1103/06, Reactor Coolant Pump Operation

a.

Step 2.7; Several sub steps reference seal leakage flow rates

of 8.5 gpm or greater. The maximum flow rate that can be read on

the instrumentation provided to the operators is read on a chart

recorder that can only read a maximum of 6 gpm.

b.

Step 2.7.5; Where the term " seal return valve " is used, the

actual valve designators should be used.

c.

Enclosure 4.1, step 2.1; A tolerance should be provided to the

operator to provide practical adjustment of the flow to an RCP.

d.

Enclosure 4.1, step 2.4; Locations should be provided for

1HP-277 and gage 1PG-102. In addition, labels should be attached

to the gage.

e.

Enclosure 4.3, section 2.2; This section requires the operator

to slowly reestablish component cooling flow to all reactor

coolant pump thermal barriers. This section should be clarified

to provide details on how this action is to be accomplished.

APPENDIX D

NOMENCLATURE DISCREPANCIES IDENTIFIED

BY

NRC EOP INSPECTION TEAM

Step/

Procedure

Page

Procedure Nomenclature

Label on Equipment

EP/1/A/1800/01

3.0

SU Block Vlv

SU FDW Block Vlv

SU Control Vlv

SU FDW Control Vlv

MS to SSRH

MS to 2A1 & 2B2

TD EFDWP Disch Vlv

To 2A/2B OTSG Blk

6.1

1HP-25 (lB HPI BWST

1 HP-25

Suction)

6.1

1HP-27 (lB HP Injection)

1 HP-27

7.3.1

Reference to SG

OTSG on Board

Section 504

3.3.1

'lB' HPI BWST Suction

No Name on Label

3.3.3

'lB' HP Injection

No Name on Label

8.1

Subcooling Margin

Saturation Margin

11&26.0

Main FDW Control Vlv

Main FDW Control

SU Control Vlv

Startup FDW Ctl

MD EFDWP Disch Vlv

No Name on Label

TD EFDWP Disch Vlv

TDEFDWP Disch to

1A(1B) OTS 6 Blk

13.7.3

'lA' HPI Header Flow

Emerg HP Inj Flow

19.2.1

"High"

HI

19.2.2

"OFF"

Stop

27.7.7

RBNS Isol

RB Normal Sump Isl

28

SG Secondary Pressure

Main Steam Prss.

Section 505

1.1

HPI Header Flow

Emerg HP Inj'Flow

Appendix D

2

2.2

LPI Header Flow

DH Removal Flow

2.3

LPSW Flow

LPSW to Decay Hx

3.1

LPSW Flow

Reactor Bld, Vent

4.0

RB Spray Flow

RBS Flow

Section 602

1

HPI Header Flow

Emerg HPI Ind Flow

36

LPI Header Flow

DH Removal Flow

OP/O/A/1600/11 2.3

Diesel Engine Service

Diesel Engine

Water Flow

Service Pump

Discharge Flow

2.13

PORV Block Vlv

PORV Block

2.13

Pzr Water Space Sample

Pzr Water Sample

2.13

RC Pumps Seal Return

RCP Seal Return

2.21

TH-103 (SSF ASW Suction

No Label on

Temperature)

Component

2.21

SSF-CCW-285

No Descriptive

Label

AP/1/A/1700/01

1/3.0

Turbine Master

Turbine Header

Pressure

AP/1/A/1700/02 5.5

1RC-66 (PORV)

1RC-66 (PORV

Pilot Valve)

AP/1/A/1700/03 4/5.6.1

1LPSW-7(RCP Coolers

Channel 6 Label

Supply)

Plate Missing

AP/1/A/1700/05 5.5

Red Phone Notification

No Procedure So

Procedure

Designated

AP/1/A/1700/11

4/2.0

...

channel A &

Bus 1 and Bus 2

channel B ...

7/4.1

SLI LEE STBY BUS

Transformer CT5

1 FDR

Bus No. 1

7/4.1

SL2 LEE STBY BUS

Transformer CT5

2 FDR

Bus No. 2

7/4.2

SK1 KEOWEE STBY

Transformer CT4

BUS 1 FOR

STBY BUS No. 1

Appendix D

3

7/4.2

SK2 KEOWEE STBY

Transformer CT4

BUS 2 FDR

BUS No. 2

8/5.2

SL1 LEE STBY BUS

Transformer CT5

1 FDR

STBY Bus 1.

8/5.2

SL2 LEE STBY BUS

Transformer CT5

2 FDR

Bus 2.

8/5.3

LEE BUS BKR

CT5 Bus 1 Auto/

Xfer SWs

Manual; ...

Bus 2

8/5.3

SL1 ....

(w/o SL1)

8/5.3

SL2 ....

(w/o SL2)

11/4.2

RCP Seal Injection Flow

Seal Inlet Header

14/7.3

(HWPs ....

)

Hotwell Pump

14/7.4

CBP

Cond Booster Pump

14/7.6

CSAE

STM to STM Air

Eject A (or B or C)

14/8.1.4

CC Total Flow

Comp Cool Header

Flow

29/3.6

SF Priming Pump

Ul & U2 Emerg.

Cooling Water

Priming Pump

AP/1/A/1700/13

1/2.0

Lake Level

Forebay Level (w

700' Correction)

3/5.2

1LPSW-138 (TD EFDWP

1LPSW-138 & 184 to

Cooling Bypass Valve)

EFWP Pump Cooling

Bypass

3/5.3.1

ESWT

Storage Tank Level

11/1.0

2CCW-70 (LPSW to

2CCW-70 Service

Unit 3 .....

)

Water Return to

Unit 3 .....

11/1.0

2CCW-71 (LPSW Return

2CCW-71 Service

to .....

Water .....

11/2.0

1LPSW-19 (lB RBCU

1LPSW-19 lB RBCU &

Inlet)

Aux Fan CLR Inlet

Appendix D

4

11/2.0

2LPSW-19 (2B RBCU

2LPSW-19 2B RBCU &

inlet)

Aux Fan CLR Inlet

AP/1/A/1700/20

5.2

CC Surge Tank

Comp. Cool. Surge

Tank Level

AP/1/A/1700/24 --

LPSW Pump Discharge

LPSW Serv H20 Hdr

Note:

1. Specific discrepancies between procedure and equipment nomenclature

may occur more than once in the same procedure. To avoid repetition,

they are only identified once.

2.

This appendix lists identified nomenclature differences between

procedures and installed equipment.

Nomenclature requirements for

the EP and APs are stated in the writer's guide; for OPs they are

stated in APM section 4.2.3.4.

APPENDIX E

LIST OF ABBREVIATIONS

AP

Abnormal Procedure

ASW

Auxiliary Service Water

ATOG

Abnormal Transient Operating Guidelines

B&W

Babcock & Wilcox

BWST

Borated Water Storage Tank

CCW

Condenser Circulating Water

CETC

Core Exit Thermocouples

EOP

Emergency Operating Procedure

EP

Emergency Operating Procedure

EPG

Emergency Procedure Guidelines

GTG

Generic Technical Guidelines

HPI

High Pressure Injection

I&E

Instrument & Electrical

LCO

Limiting Condition of Operation

LOCA

Loss of Coolant Accident

NLO

Non-licensed Operator

NRC

Nuclear Regulatory Commission

NSM

Nuclear Station Modification

OG

Owners Group

ONS

Oconee Nuclear Station

OP

Operating Procedure

PGP

Procedure Generation Package

PORV

Power Operated Relief Valve

P/T

Pressure/Temperature

QA

Quality Assurance

RB

Reactor Building

RCP

Reactor Coolant Pump

RCS

Reactor Coolant System

RG

Regulatory Guideline

SG

Steam Generator

SRO

Senior Reactor Operator

SS

Shift Supervisor

SSF

Safe Shutdown Facility

TBD

Technical Basis Document

TMI

Three Mile Island

V&V

Validation and Verification

WDP

Waste Disposal Panel