ML16127A208

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/88-13,50-270/88-13 & 50-287/88-13 on 880509-13 & 19-27.Violations & Observations Noted.Major Areas Inspected:Qa Effectiveness in Areas of Operations & Surveillance Testing,Maint & Design Control
ML16127A208
Person / Time
Site: Oconee  
Issue date: 07/25/1988
From: Belisle G, Shannon M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16127A206 List:
References
50-269-88-13, 50-270-88-13, 50-287-88-13, NUDOCS 8808150264
Download: ML16127A208 (24)


See also: IR 05000269/1988013

Text

10

gREGjZq

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

Report Nos.:

50-269/88-13, 50-270/88-13, and 50-287/88-13

Licensee:

Duke Power Company

422 South Church Street

Charlotte, NC

28242

Docket Nos.: 50-269, 50-270,

License Nos.: DPR-38, DPR-47, and

and 50-287

DPR-55

Facility Name:

Oconee 1, 2, and 3

Inspection Conducted:

May 9-13 and 19-27, 1988

Inspectors:

&____________

___

7

'

M. Shannon, Team Lfidir

Date Signed

Team Members

T. Cooper

K. Jury

E. Lea

L. Mellen

Approved by:

G. A. Belisl6, Chief

ate

igned

Quality Assurance Programs Section

Operations Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, announced inspection of quality assurance effectiveness

was conducted in the areas of operations and surveillance testing, maintenance,

and design control.

Results:

Although a number of violations were identified, the licensee's

various work practice and procedural controls in the areas inspected were

generally acceptable.

Licensee personnel were knowledgeable of their work

activities.

Within the areas inspected, the following violations were identified.

-

Failure to provide accurate IST and firewatch records, paragraphs 3.b

and 3.c.

-

Failure to measure the full stroke time of ASME Section XI valves,

paragraph 3.d.

8806150264 880803

PDR

ADOCK 05000269

G

PNU

2

-

Failure to identify valves required to be tested pursuant to ASME

Section XI requirements, paragraph 3.g.(3).

-

Failure to follow procedural requirements of Station Directives relating

to maintenance work requests and cleanliness controls, paragraphs 4.d and

4.e.

-

Failure to document the bases for 10 CFR 50.59 determinations, paragraph

5.b.

-

One unresolved item was identified involving configuration control

inadequacies in the ES and RPS cabinets, paragraphs 4.b and 4.e.

-

A weakness (IFI) relative to acceptance criteria for valves moving freely,

paragraph 3.g.(1).

-

A weakness (IFI) relative to corrective actions for valve 1LP-21 multiple

failures, paragraph 3.e.

Within the areas inspected,.the following observations were noted:

-

The number of value stroke time failures was very small.

-

Maintenance history records did not indicate repetitive failures.

-

Based on the low component failure rate and few repetitive failures the

licensee's corrective and preventive maintenance programs appeared to be

better than average.

-

The licensee's maintenance engineering program,

with emphasis towards

component engineers,

appeared to be a effective method of resolving

component failures.

-

The requirements of ASME 45.2.11 Design Control appeared to be adequately

implemented for most engineering activities.

REPORT DETAILS

1. Persons Contacted

Licensee Employees

J. Bowers, Production Specialist I

  • R. Brackett, Station QA Manager
  • M. Clardy, Maintenance/P&S Engineer

B. Davis, Nuclear Production Engineer

D. Denard, Performance Supervisor

T. Dwyer, Nuclear Production Engineer

P. Forrester, Nuclear Production Engineer.

B. Foster, Superintendent of Maintenance

E. Frampton, Design Engineer

  • A. German, Design Engineering/Site Office

R. Harris, Design Engineer

D. King, Design Engineer

R. Knoerr, Project Services Engineer

R. Ledford, QA Surveillance Supervisor

  • T. Mathews, Production Specialist II (Licensing)

W. McAlister, Support Engineer

B. Millsaps, Maintenance Services Engineer

  • F. Owens, Regulatory Compliance

K. Rhode, Nuclear Production Engineer

N. Riddle, Project Support Engineer

  • D. Sweigart, Operations Superintendent

D. Taylor, Project Support Engineer

R. Todd, Project.Support Engineer

  • M. Tuckman, Station Manager

Other licensee employees contacted included engineers, operators,

technicians, maintenance personnel, and office personnel.

NRC Resident Inspectors

  • P. Skinner, Senior Resident Inspector

L. Wert, Resident Inspector

  • Attended exit interview

Acronyms and initi.alisms used throughout this report are listed in the

last paragraph.

2. Quality Assurance Effectiveness (TI.2515/78)

The objective of this inspection was

to

assess quality assurance

effectiveness.

For this report, quality assurance effectiveness is

defined as the ability of the licensee to identify, correct, and prevent

2

recurrence of similar problems.

The term quality assurance effectiveness

used in this application was not limited to the licensee's QA Department;

it was the total of all efforts needed to achieve quality results.

This was a performance-based rather than a compliance-based inspection.

In.stead of verifying compliance with programmatic

requirements,

the

principal effort was to determine whether results were actually achieved

that the quality assurance program was designed to accomplish.

However,

when problems were identified, appropriate regulatory requirements were

enforced.

The inspection effort was divided into the following areas, each of which

is addressed in separate report details.

Operations and Surveillance Testing

Design Control.

Maintenance

3. Operations And Surveillance Testing

The licensee's quality assurance effectiveness in the area of operations

and surveillance testing was assessed by observing plant operating

personnel, observing surveillance testing, reviewing surveillance results,

reviewing normal and emergency procedures,. reviewing component equipment

histories, and conducting personnel interviews.

a.

Surveillance Testing

The

inspectors

witnessed

Performance

Test

PT/2/A/0150/22A,

Operational Valve Functional Test.

This consisted of stroke time

testing IST categorized valves for Unit 2, while at power. The test

was conducted satisfactorily; however, valve 2-LP-16 failed to stroke

open as required and valve 2-LWD-1 had a stroke time increase. These

and other discrepancies noted during the course of the inspection

will be discussed later in this report.

After witnessing valve stroke time testing, reviewing valve stroke

time histories, and reviewing maintenance histories, the inspectors

concluded that the licensee's program for ASME Section XI valve

testing was above average. There were no indications of repetitive

failures or of common component failures. The preventive maintenance

program and MOVATS testing program appear to have created high

operational reliability for plant power operated valves.

b. Documentation Falsification

While witnessing PT/2/A/0150/22A on May 11,

1988,

the inspectors

noted that on the Reactor Building Normal

Sump Isolation valve,

2LWD-1, stroked closed in eight seconds; its previous stroke time was

five seconds. Acceptance criteria 11.3.3 of the performance test

states that in order to meet the acceptance criteria, valves with

3

previous stroke times equal to or greater than five seconds and less

than or equal to ten seconds must not increase 50 percent from the

previous test. The inspectors then witnessed the recording of the

stroke time into the test data as eight seconds and verified this

time via the control room printer. The performance technician was

unaware that the as-found stroke time did not meet acceptance

criteria 11.3.3, and initialed procedure step 12.16.5 which verified

acceptance. The inspectors were aware that the stroke time did not

meet the applicable acceptance criteria; however,

the inspectors

wanted to ensure this test discrepancy would be identified during the

procedure review and approval cycle. On May 25, 1988, the inspectors

reviewed the completed test procedure for verification that the

stroke time discrepancy had, in fact, been identified by the licensee

during the review cycle. The inspectors identified that the stroke

time of eight seconds (previously entered in the completed procedure)

had been changed to five seconds,

which now met the acceptance

criteria. Upon verification of the original recorded stroke time,

the inspectors asked for documentation of any retest that may have

been performed. Unaware of any retest performance, the licensee then

verified the computer recorded stroke time of eight seconds and

retested the valve on May 25, 1988; the retested stroke time was also

eight seconds. Upon examination by the inspectors, it appeared that

initials on the procedure page in question were not consistent with

the same initials on other test pages. The licensee stated that they

would investigate and determine the cause of the discrepancies and

take appropriate corrective actions.

The licensee contacted the responsible performance technician, who

admitted to replacing the completed page in question and to changing

the measured stroke time from eight seconds to five seconds.

The

licensee also identified that the previous (prior to May 11)

stroke

time for valve 2LWD-1

had been recorded as five seconds and the

computer had shown the actual stroke time to be eight seconds. This

surveillance test was also-performed by the same individual.

The actions of the performance technician in changing the TS

surveillance data violate NRC requirements. 10 CFR 50.9(a),

Completeness and Accuracy of Information,

states that information

required by

the Commission's regulations, orders, or license

conditions to be maintained by the licensee shall be complete and

accurate in all material respects.

Failure to meet the 10 CFR 50.9(a). requirements is collectively

combined with an additional example as discussed in paragraph 3.c and

is identified as Violation 269, 270, 287/88-13-01.

c. Falsification Of Records Associated With Fire Barrier Penetration

Patrols

On May 18,

1988,

the DE group identified that some fire barriers

between the control room,

cable room,

equipment room,

and turbine

4

buildings were inoperable. The fire barriers consisted of 10 inches

of a foaming agent with metal plates on

each side which was

determined by test results to be

inadequate.

The test results

identified that a 12 inch thickness of foam was required. As a result

of the notification by DE, the penetrations were declared inoperable

and the actions of TS 3.17.6.1 were entered.

The TS LCO requires a

fire watch patrol to inspect the affected areas hourly.

On May 19,

the resident inspector reviewed the security print-out of the cable

room card-key doors and identified several periods that exceeded the

specified time

interval required by

TS.

Since the NEOs were

responsible for this surveillance, the inspector also reviewed the

logs maintained by the assigned personnel.

The logs for all three

units indicated the required hourly watches were performed,

even

though the computer listing indicated the individuals had not entered

the prescribed areas

in the required time.

This conflicting

information was provided to Operations management.

Subsequent

licensee investigations identified 5 times in a continuous 28 hour3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br />

period that the fire patrols were not performed in the prescribed TS

time requirements, where as the logs indicated that the patrols were

performed. The licensee concluded that three personnel were involved

in this occurrence. The failure to perform these required activities

resulted in violating TS 3.17.6.1.

This

falsification of

documentation is collectively combined with an additional example as

discussed in paragraph 3.b and is identified as Violation 269, 270,

287/88-13-01.

d. Valve Stroke Time Testing

While witnessing valve stroke time testing, the inspectors noted that

valves were being tested utilizing the time between actuations of the

limit switches, i.e. the "light to light" method. It was also noted

that for certain valves the time delay between valve actuation and

first limit switch actuation was as much as eight seconds.

The

"light to light" method does not measure the full stroke time of the

valve.

The 1980 ASME Boiler and Pressure Vessel Code,Section XI, Rules for

Inservice Inspection of Nuclear Power Plant Components,

Article

IWV 3412,

Exercising Procedure,

requires that valves tested under

this section shall be full-stroke exercised. Article IWV-3413, Power

Operated Valves, defines full-stroke time as that time interval from

initiation of the actuating signal to the end of the actuating cycle;

however, the licensee measures the time between actuations of the

limit switches.

The licensee's failure to meet the

1980 ASME

Section XI valve stroke testing requirements -is identified as

Violation 269, 270, 287/88-13-02.

e.

Valve 1LP-21 Discrepancies

During the equipment maintenance history review, the inspectors noted

that multiple maintenance work request had been completed for valve

5

1LP-21 because it was unable to meet its acceptance criteria. 1LP-21

is the "A" train LPI

system suction valve from the

BWST.

The

following is a failure and repair history for 1LP-21 for the last two

years:

On April 4, 1986, 1LP-21 failed to meet its acceptance criteria

of a maximum stroke time of 15 seconds, in that, it stroked in

16 seconds. The licensee apparently did not recognize that the

valve did not meet its acceptance criteria, consequently, a

discrepancy was not written.

Unit 1 started up on May 6, 1986,

and again on May 27,

1986,

without knowledge of the valve not meeting its acceptance

criteria.

On June 3, 1986,

1LP-21 again failed to meet its

acceptance criteria when it

was found-to stroke in 16 seconds.

At this time the licensee recognized that the previous test did

not meet its acceptance criteria and took corrective actions by

counseling the personnel

involved.

Corrective action was to

reset the limit switch and the valve actuated in 15 seconds.

On

November 17,

1986,

1LP-21 failed to meet its acceptance

criteria and stroked in 16 seconds. The valve stem threads were

lubricated and the valve stroked in 15 seconds.

On May 20,

1987,

1LP-21 failed to meet is acceptance criteria

and Work Request 91757C was written and stated that the valve

had a bent stem, a packing leak, and failed to meet the stroke

time acceptance. A deficiency written on PT/1/A/0150/22A stated

that the 'stroke time was inconsequential and that 1LP-21 would

be repaired during the next Unit 1 outage.

The unit was shut

down

on

September 2, 1987,

and repairs were

completed on

October 8, 1987. These repairs reset the limit switch.

On October 31,

1987,

1LP-21 failed to meet its acceptance

criteria and the threads were lubricated without issuing a work

request.

Work Request 50209F was written to perform MOVATS

testing and called for replacing the torque switch; however, the

torque switch was not replaced.

These identified discrepancies with the 1LP-21 stroke times did not

present an operability concern but they do raise a concern with the

licensee's adherence to acceptance criteria.

The licensee's IST

program acceptance criteria lists the acceptable stroke time as 15

seconds; however,

on May 20,

1987, a work request stated that the

valve failed to meet its stroke time acceptance and repairs were not

performed

on the valve for over three months.

The licensee's

statement that the stroke time was inconsequential,

presented an

attitude that the acceptance criteria is only a guideline and not a

requirement. It was also noted that the limit switch was reset on

two occasions as corrective action for obtaining proper valve stroke

time.

6

The resetting of limit switches as corrective action for stroke

failures, for 1LP-21 is considered to be a weakness and is identified

as Inspector Followup Item 269/88-13-08. This item is applicable to

Unit 1 only.

f.

Valve 2LP-16

While witnessing PT/2/A/0150/22A,

Valve 2LP-16 failed to stroke.

Valve 2LP-16 is the Train "B" LPI System supply valve for HPI pump

suction and RBS system cooling. This valve is opened during various

emergency procedures

by the

RO.

It

is commonly

known

as the

piggyback valve and is opened after the BWST has been drained during

a loss of coolant accident.

After the valve failure, the supply

breaker was verified closed and a work request was written. No other

licensee initiated reviews or evaluations were performed at this

time.

The control room operators were

questioned by the inspectors

concerning HPI and RBS system operability with 2LP-16 being out of

service.

An informal discussion determined that the HPI and

RBS

systems were not inoperable and the reasoning used was that: (1) the

valve could be manually opened if required, and (2) the RCS could be

depressurized for the accident condition when this valve is required.

The next shift was also questioned concerning HPI and RBS system

operability with 2LP-16 out of service.

They also stated that the

valve could be manually opened and the RCS could be depressurized.

It was noted that licensee personnel had not verified that the valve

could be manually operated after its initial failure.

There were

also discussions concerning possible area radiation levels during the

accident scenario for which the valve would be required and it

was

determined by the operators that area radiation levels would be

prohibitive for manual operation of this valve.

At this point the

Operating Engineer was contacted in order to determine if any further

action was required.

The following day,

the day shift operators were also questioned

concerning system operability. They also stated that the valve could

be manually operated and the RCS could be depressurized. A shift RO

walked through the emergency procedures with the inspector and

determined that under conditions when 2LP-16 required opening, the

RCS would be saturated and could npt be depressurized as previously

thought.

The licensee was again questioned about HPI and RBS system operabili

ty and it

was stated that the HPI

suction could be manually

cross-tied to supply Train "A" LPI to both trains of HPI and RBS.

Again the licensee did not account for accident radiation levels for

entry to manipulate various valves.

Three different shifts made assumptions that were not valid.

The

valve was not checked for manual operation, area radiation levels

7

during accident scenarios were not considered, and it

was assumed

that the RCS could be depressurized.

The IST Engineer was contacted concerning the valve failure. He, in

turn, contacted ,the

Maintenance

Department

and

personnel

were

assigned to perform the work request.

An electrician physically

lifted the motor starting relay and the valve cycled. The valve was

then cycled from the control room,

the performance group timed the

valve, and the work request was closed.

The root cause for the

failure was not determined,

in that, the failure mechanism was not

identified. At this time the licensee stated that ASME Section XI

allows 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> before they were required to declare a non-operating

valve inoperable and thus the HPI

and RBS systems were not

inoperable. The licensee further stated that the HPI pump suctions

were cross-tied and suction flow to all three pumps could be supplied

from the "A" Train LPI pump and therefore the HPI trains were both

operable.

During the inspection,

the licensee communicated to the NRC

a

preliminary LER concerning LPI supply to HPI and RBS. The LER stated

an analysis indicated that under certain conditions during the

recirculation phase, both trains of LPI may not be able to provide

adequate HPI pump suction pressure and this could result in the loss

of HPI system capability. It is apparent that if both LPI trains are

unable to supply adequate suction pressure, that only one LPI train

available would be even more restrictive.

The licensee did not take a conservative approach in addressing the

issue of system operability when 2LP-16 failed to open; however, the

valve was repaired, satisfactorily tested, and returned to service

within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. A more desirable action would have been to declare

the HPI and RBS Train "B" systems inoperable, enter the appropriate

TS action statements, make the necessary repairs,

and perform the

appropriate retesting for operability.

g. Miscellaneous Items

(1) PT/1,2,&3/A/0150/22A,

Section 11.0,

Acceptance

Criteria,

Step 11.

1, states that all valves move freely and without

restriction or. binding over a complete cycle.

This acceptance

criteria was not verified during the course of the surveillance

test even though the steps verifying acceptance were signed as

acceptable. This item was considered to be a weakness in the

IST program and needs further management attention. It will be

identified as Inspector Followup Item 269,270, 287/88-13-07.

(2) The inspectors observed the following actions by control room

personnel;

horseplay

(jostling,

joking,

bumping,

etc.)

whistling, backs to panels, feet on desk, crowded conditions,

and the burning of an insect. Most items occurred on one shift.

The licensee was notified by the inspectors that all of these

items conveyed a less than professional appearance. The Station

8

Manager discussed this situation with cognizant operation's

personnel and corrective actions were taken.

During subsequent

observations, this situation did not recur.

This was also

discussed during the management meeting on June 7, 1988.

(3) During a review of various system flow diagrams it

was noted

that certain power operated valves were not included in the IST

program. ASME Section XI, Article IWV 100, Scope, requires that

Class 1, 2, and 3 valves required to perform a specific function

in mitigating the consequences of an accident, are to be tested

to verify operational readiness.

Valves exempted

from this

requirement are valves used for operating convenience, system

control, or for maintenance.

The following valves:

LPSW-772, LPSW-773, and LPSW-774, which

are power operated and are the first isolation valves-outside

containment, were not included in the IST program.

They would

be

used as containment isolation valves for mitigating

radioactive release.

HP-98 is a power operated valve in the HPI suction header. This

valve would be used to provide ECCS HPI train separation on a

suction header fault.

ASME Section XI, IWV-1400, requires that each valve to be tested

in accordance with ASME requirements shall be categorized by the

owner and listed in plant records.

10 CFR_50 Appendix B,Section XI,

Test Control,

states that a

test program shall be established to assure that all testing

required to demonstrate that structures, systems and components

will

perform satisfactorily in service is identified and

performed in accordance with written test procedures.

Contrary to the above requirements, the IST program failed to

assure that components required to be tested were identified.

Valves HP-98, LPSW-772, LPSW-773 and LPSW-774 were not included

in the ASME Section XI valve testing program.

The licensee's

failure to identify valves required to be tested pursuant.to the

1980 ASME Section XI requirements is identified as Violation

269, 270, 287/88-13-03.

4. Maintenance

The inspectors reviewed predictive, preventive, and corrective maintenance

to determine the licensee's ability to identify and correct adverse

trends. This review included field verifying maintenance activities in

progress and reviewing previously completed maintenance activity records.

The maintenance activity review focused primarily on EFW,

FDW,

RPS,

ES

Logic,

HPI,

RVLIS,

LPI,

and

RC

system,

although other systems were

included to a lesser extent.

9

a.

Predictive Maintenance

The inspector reviewed plant procedures and station directives to

identify any mechanism used for identifying potential problems that.

could lead to equipment failure.

The inspector also interviewed

responsible personnel and reviewed history files on equipment

identified in the predictive maintenance program.

Engineers in the Maintenance Service section were responsible for

identifying potential problems and for specifying corrective actions.

They reviewed work requests and Nuclear Plant Reliability Data System

information

on a periodic basis to identify potential problems.

Maintenance directives.were used to provide special instructions for

monitoring

specific

equipment.

Maintenance

Directive

5.3.4,

Predictive.Maintenance and Monitoring Program (PM-2),

was used as a

mechanism for identifying problems with rotating and reciprocating

equipment. Maintenance service engineers utilize statistical failure

analysis, oil analysis, and vibration analysis to identify potential

problems per PM-2.

Maintenance Directive 5.3.5, Valve and Valve

Operation Program, provided information

on

the valve program

established at Oconee.

A review of the items identified under the

PM-2

and

the valve operation

program indicated that adequate

monitoring and corrective actions were taken to prevent recurring

problems. The inspector also. noted that those persons responsible

for the vibration and valve program were very knowledgeable of the,

subject matter.

b.

Preventive Maintenance

The

inspector

witnessed

the performance of

IP/O/A/310/12A,

Engineered Safeguards System Logic Sub System 1,, High Pressure

Injection and Reactor Building Isolation, Channel 1, on Line

Instrument Calibration for Channels

1 and 2. The technician

performing the maintenance activity was knowledgeable of the

procedure and the effects of performing the procedure on associated

plants systems.

The procedure was technically correct, however, it

was necessary to perform several steps out of sequence which made its

use somewhat cumbersome.

While witnessing IP/O/A/310/12A, the inspector observed that a jumper

was installed across a power transformer in the cabinet which housed

some of the Channel 1 Engineered Safeguards Instrumentation on Unit 3

(ES Analog Cabinet). The jumper was.not shown on any of the system

drawings.

The jumper was removed by the system engineer when the determination

was made that the jumper served no apparent function.

The system

engineer did not document removing this jumper on a work request or a

modification request, i.e. the jumper was removed without proper

authorization. Several days later, after being questioned by the

inspector, the system engineer documented an evaluation to remove the

10

jumper which included taking meter readings and inspecting similar

cabinets. The licensee believed that the jumper may have been left

in the cabinet after a surveillance, or stored in the cabinet by an

instrument technician rather than returning the jumper to the

appropriate storage location.

The jumper had no effect on system

operability; however, this is considered an example of inadequate

configuration control and is combined with additional examples in

paragraph 4.e. to constitute Unresolved Item 269, 270, 287/88-13-06.

c. Corrective Maintenance

The inspector witnessed licensee personnel performing work requests

55365B, 55366B, and 55367B, performance of PM on the Magnex Valves in

the RVLIS on May 19, 1988. The purpose of the Magnex valves in the

RVLIS is to provide a means of calibrating or replacing a faulty

transmitter with the reactor at elevated pressure. While performing

the maintenance test, the inspector witnessed the technicians

striking the Magnex valves with a nylon hammer and heating the valves

with a portable heater when two valves on Unit 3 could not be

operated manually. This action was in accordance with a hand written

procedure change that was appropriately documented and approved.

The inspector questioned the technicians involved in this activity to

determine how this type of corrective action had been approved. The

inspector was informed that the vendor had recommended this method of

corrective action; the inspector then contacted the vendor.

Vendor

personnel stated that the original request to heat the valves came

from the licensee without mentioning striking or mechanically

disturbing the valves. The vendor concurred with heating the valves;

however,

the licensee did not evaluate the effects of heating or

striking the valves. As a result of the inspector's observations and

discussions with the vendor and licensee, the inspector contacted the

valve manufacturer,

Autoclave,

and spoke with one of the valve's

designers.

He stated that these valves had sensitive internal

components and a light coating of a vacuum grease and were not

designed for the methods of corrective actions taken by the licensee.

The valve manufacturer also stated the preferred orientation of the

valves was in the vertical direction with the operator directly above

the valve body. This allows the ball of the valve to rotate in the

valve cup assembly. The orientation of the valves observed by the

inspector is in the horizontal direction which causes the valve to

rotate against the valve seat. Both valves in question have failed

to close during the last three surveillances.

The first two valve

failures were not identified on the Component Malfunction/Maximum

Tolerance Limit Exceeded sheet as required by the PM procedure and as

such did not receive an appropriate engineering review. The licensee

could not find an evaluation or any objective evidence to justify

their method of corrective action.

There are additional examples of

similar failures and similar corrective actions on Units 1 and 2.

The current method of corrective actions will not ensure the valves

will remain open after the valves that bind are cycled.

Other than

magnetic valve actuator position,

there are

no direct ways to

determine the valves' position.

The valves are not essential to

system operability. The only requirement for the Magnex valves is to

remain open when the RVLIS is required.

Until a satisfactory method of correcting the valve binding problem

can be determined,

the licensee agreed to suspend the practice of

striking and h.eating the valves and pursue a course of corrective

action that will not have the potential of.damaging the valves or the

valves' internals.

d. Work Requests

The inspector reviewed selected samples of the approximately 2900

(1080 open and 1725 closed) QA Condition 1 work requests issued since

January 1, 1987. The review was focused primarily in the area of

retest and functional test requirements, environmental qualification

determinations,

clearances, QA

condition

determinations,

and

adherence to the procedural requirements during the performance of

the maintenance-tasks. Additionally, the inspector reviewed Station

Directive 3.2.1,

Work

Request,

dated February 18,

1988.

Minor

problems were found in the majority of the Work Request packages

reviewed. Selected examples of the discrepancies are as follows:

Work Request No.

12514,

Repack 2LP-76.

On sheet 1 of the Post,

Maintenance Testing section, the inspection for packing leakage

and inspection for general leakage were identified as required

but were not performed. The work request also required Red Tags

to be installed but procedure MP/O/A/1200/01, Valves - Adjusting

and Packing, step 12.1, was marked N/A for the applicability of

clearing the Red Tags.

Work Request No.

14665,

Loop B Feedwater Valve Delta Pressure

Instrument Repair. The QA condition, retest requirements,

and

functional verification were

not correctly identified in

accordance with Oconee Nuclear Station Directive 3.2.1, Sections

6.1, 6.2 and 6.3 respectively.

Work Request No. 03535, 2LP-63. The clearance to begin work was

not given. Sheet 1 of the Post Maintenance Testing section, the

inspection for packing leakage,

and inspection for general

leakage were identified as required but were not performed.

The work requests listed below were for performing

PMs on

Control Rod Drive Breakers:

Not considered EQ related

EQ determination not made

55161B

55154B

55163B

55162B

55155B

55165B

55013A

55156B

55170B

55171B

55157B

55159B

55449A

55158B

55173B

12

The work requests without EQ determinations were not consistent

with the requirements of Station Directive 3.2.1, Work Requests, Section 6.13, Environmentally Qualified Equipment.

Work Request 92265C, Repair 1LPSW-566. The retest requirements

were changed without appropriate initials and date, making it

impossible to determine when or by whom the change was made or

who reviewed the change.

The

following work requests for refurbishing limitorque

operators did not include either determining or documenting that

required retests were performed:

51638G

51659G

51689G

51644G

51687G

51652G

51688G

Note 1

51608G

Note 1

Note

1:

In addition, the appropriate electrical functional

verification test was not specified.

The following work requests involved performance of the Doble

test on 4160 volt breakers and transformers:

57791B

Note 2

58035C

57046C

Note 2

57048C

57044C

Note 2

57045C

57762B

Note 2

.57042C

57435D

Note 2

57033C

Note 3

57043C

52005G

Note 4

57035C

52006G

Note 5

Note 2:

The computer generated retest requirements were

incorrect, however the work planner corrected the work request

prior to commencing work.

Note 3: The clearance for the breaker was not completed and the

systems were returned to service without documentation.

Note 4:

The functional verification test was

incorrectly

specified.

Note 5:

The work request specified a retest which could not

physically be performed. As a result, no retest was performed.

The following work orders had either incorrectly specified

retest requirements or retest requirements were not specified:

96178C

Drain in 2FW-130

53030G

Replace limit switch on 2RC-3

53033G

2FDW-16

52922G

2PT-17P

15

Work Request 12514C,

Repack 2LP-76,

and Work Request 03535C,

Repack 2LP-63.

On the Post Maintenance Testing sheet, the

inspection for packing leakage and inspection

for general

leakage were identified but were not performed.

The examples noted above were not considered all inclusive and were

considered a programmatic lack of attention to detail in completing

work requests. These examples are collectively combined with another

example of a failure to follow procedures,

paragraph 4.e,

and

constitute Violation 269, 270, 287/88-13-04.

The following work orders were reviewed with no discrepancies noted:

55451A

55449A

52308G

At the licensee's request, the inspector reviewed a sample of work

requests that were not microfilmed or were not completed.

Some of

the same type of problems existed in the additional sample reviewed.

The review results were inconclusive. It was generally not possible

to determine if

the work had been completed correctly since all the

associated paper work had not been finished. Some of the preplanning

work; however, appeared to demonstrate improvement.

The inspector witnessed maintenance activities in progress

and

interviewed selected maintenance personnel to determine the effect of

the maintenance work order discrepancies on actual maintenance work

performed. The consensus of the maintenance personnel interviewed

and the conclusions of the

inspector,

based upon maintenance

activities witnessed,

are that the actual work activities were

performed in accordance with applicable station directives and

applicable procedures. Based on this conclusion, Violation 269, 270,

287/88-13-03

is directed only to the completion of required

documentation and does not indicate a lack of quality in the

maintenance work performed.

e.

Reactor Protection System and Engineered Safeguards Logic

The

inspectors

verified

the

terminated

wiring,

installed

configuration, and logic wiring of selected portions of the RPS and

ES.

A number of discrepancies were identified; the licensee

subsequently reviewed these. discrepancies.

The following are the

specific discrepancies and the licensee's evaluations.

(1) Debris was found primarily in the ES cabinets which included

numerous unattached plastic wiring tags, metal strips, a bag of

termination screws, a box of light bulbs, paper, and a styrofoam

tobacco expectorant receptacle which contained a soiled paper

towel and an apple core. The expectorant receptacle and the

associated contents were wedged in the rear portion of the ES

wiring harness.

14

(2)

Unit 3 ES Analog Cabinet #1, Terminal Block 2, Row 9. A landed

lead from terminal 12 was attached to terminal 9 instead of

terminal 8 as shown on approved drawings or as connected on the

other units.

Licensee evaluation: terminal 8 is the common

ground for the -15 VDC power supply for ES Analog Cabinets 1 and

4. Although the ground was not connected in accordance with the

drawing,

the power supply for cabinets 1 and 4 are operable

based on monthly surveillance results. The licensee stated that

a PIR will be initiated to evaluate the landed lead not attached

in accordance with the termination drawing.

This item was

specifically discussed

on June 14

and June 28,

1988, with

licensee personnel.

The licensee verified that the existing

ground connection to the ES Cabinet would perform the function

of the instrument ground.

(3) Unit 1 ES Analog Cabinet #1, Terminal Block 3, Row 9. Terminals

1 and 2 have landed leads which are not designated on controlled

drawings. Licensee evaluation: although the connections are not

on controlled drawings, they go to the test panel control point.

(4) Unit 2 ES Analog Cabinet #1, Terminal Block 3, Row 9. Terminals

6 and 7 have

landed leads which are not on the ,terminal

drawings. Licensee evaluation:

although the terminations are

not shown

on the appropriate termination drawings,

they are

shown on the test panel control board drawings.

(5) Unit 2 ES Analog Cabinet #1, Terminal Block 3, Row 9. Terminals

1 and 2 have landed leads which are not designated on controlled

drawings. Licensee evaluation: although the connections are not

on controlled drawings, they go to the test panel control point.

(6)

Unit 1 ES Analog Cabinet #1, Terminal Block 3, Row 9. Terminals

6 and 7 have landed leads which are not on the terminal

drawings. Licensee evaluation: although the terminations are

not shown on the appropriate termination drawings, they are

shown on the test panel control board drawings.

(7) Unit 3 ES Analog Cabinet #1, Terminal Block 3, Row 9. Terminals

6 and 7 have landed leads which are not on the terminal

drawings. Licensee evaluation: although the terminations are

not shown on the appropriate termination drawings, they are

shown on the test panel control board drawings.

(8) Unit 3 RPS Channel D-2 cabinet contains a jumper from Terminal

Block 6, Row 8, terminal 2 to Terminal Block 6, Row 9, terminal

3, which is not designated on controlled drawings. The licensee

was in the process of evaluating this discrepancy.

(9) Unit 3 RPS

Channel

A-1 cabinet,

Terminal

Block 3, Row 8,

terminal

12 has a landed lead which is not designated on

controlled drawings. Licensee evaluation: the function of these

15

wires has not been determined and will require tracing the

circuit in the RPS cabinet.

(10) Unit 3 RPS Channel A-2 cabinet, jumper shown on drawing going

from Terminal Block 6, Row 8, terminal 1 to Terminal Block 6,

Row 9, terminal.3 actually goes from Terminal Block 6, Row 8,

terminal 2. Licensee evaluation: this supplies the ground for

the manual bypass switch, and is the result of rolled wires on

the back plane of the terminal strip.

(11)

Unit 3 RPS Channel A-2 cabinet, terminals 9 and 10 have parallel

connections not shown on the termination drawings.

Licensee

evaluation: these wires go to the B&W test panel

and are

reflected on drawing 0-2715 H1.

(12) Unit 3 RPS Channel

B-1 cabinet,

Terminal

Block 5,

Row 9,

terminals 4, 5, 9, and 10 and Terminal Block 6, Row 9, terminals

1, 2, 4, and 5 have parallel connections which are not on the

termination drawing. Licensee evaluation: these wires to the

B&W test panel and are reflected on drawing 0-2715 HI.

(13) Unit 3 RPS Channel C-2,

cabinet jumper shown on drawing going

from Terminal Block 6, Row 8, terminal 3 to Terminal Block 6,

Row 9, terminal 3 actually goes from Terminal Block 6, Row 8,

terminal 2. Licensee evaluation: this supplies the ground for

the manual bypass switch, and is the result of rolled wires on

the back plane of the terminal strip.

(14) Unit 2 RPS Channel C-2 cabinet has a jumper between terminals 10

and

12

that does not appear on the termination drawing.

Licensee evaluation: this supplies the ground for the manual

bypass switch, and is the result of rolled wires on the back

plane of the terminal strip.

(15) On all three units in the A-1, B-1, C-1 and D-1 RPS cabinets, a

metal test jack assembly and the associated test leads were not

considered in the seismic design of the RPS cabinets and were

not shown on the system drawings.

The test jacks are used to

measure RC flow transmitter signals.

(16) Numerous test connections are in the ES and RPS cabinets that

are not shown on the wiring drawings.

Items 2-14 and 16 are examples of configuration control inadequacies

in the ES and RPS cabinets.

Until these configuration control

inadequacies are resolved by the-licensee, this-is combined with an

additional example of a configuration control inadequacy as discussed

in paragraph 4.b to constitute Unresolved Item 269,

270,

287/88-13-06.

Item 1 contains examples of failure to maintain adequate housekeeping

controls in the

ES cabinets.

The failure to maintain adequate

16

housekeeping is contrary to the requirements of Maintenance Directive

3.2.5, Maintenance Housekeeping Program, and is collectively combined

with other examples of failure to follow procedures, paragraph 4.d.,

and constitutes Violation 269, 270, 287/88-13-04.

Item 15 resulted in portions of the RPS being in a seismic configura

tion which was previously unanalyzed.

After the identification of

the concern

by the inspector,

the licensee performed a seismic

analysis of the cabinets which demonstrated the cabinets were

seismically qualified in their current configuration.

This is

considered as an additional example of Unresolved Item 269,

270,

287/88-13-06. Another example is discussed in paragraph 4.b.

f. Quality Assurance Involvement In Maintenance

To determine the extent that QA was involved in the work request

process the inspector interviewed the QA Work Request Controller.

The Work. Request Controller delineated the work request flow path

through the QA organization. The inspector then interviewed selected

QA personnel and reviewed selected QA audits and surveillances.

The

inspector concluded that while QA only reviewed portions of the work

requests, the work request discrepancies should have been detected by

QA. This area needs additional attention by the

QA audit and

surveillance programs.

To determine the extent that QA was involved in the configuration

control of the ES and RPS,

the inspector interviewed selected QA

personnel.

The results of the interviews indicated that QA was not

directly involved in modifications that were considered to be

non-safety related and were not part of the decision process to

determine if the modifications were

safety

related.

Since

documentation

did not exist to indicate how the

specific

discrepancies noted in paragraph 4.e occurred,

QA was not aware of

the activities that

may

have

caused the

specific discrepant

conditions. Additionally,

QA does not have a specific audit or

surveillance program which required the field verification of RPS or

ES terminations or system logic. The lack of QA involvement in the

determination of whether a modification is safety related or not and

the lack of a program to verify ES and RPS terminations and logic,

were considered contributing factors which led to the findings noted

in paragraph 4.e. The licensee has agreed to include inspections of

this type in future QA surveillances or audits.

5. Design Control

The inspector reviewed the station modification program and examples of

SPRs, DSs, ECs,-TMs, Alarm and Setpoint Changes, and NSMs.

Interviews

were conducted with personnel in Project Services, Maintenance Services,

Instrument and Electrical, Training, and Compliance.

a. Modification Controls

17

The inspector reviewed a sample of open and closed NSMs,

for the

period since January 1987 and identified that documentation required

by the Nuclear Station Modification Manual, Station Directive 2.3.4,

Nuclear Station Modification Program, revised October 8, 1987,

and

Project Services Manual,'Section 4.6, Nuclear Station Modification,

revised April 8, 1988,

was present.

The station has identified the

open NSM backlog as a problem and established goals to reduce that

backlog. Between April 1986 and April 1988, the number of open NSMs

decreased from approximately 1150 to approximately 450. The goal of

450 was expressed to the inspector as approximately two years worth

of work.

The inspector

reviewed approximately

120

ECs

to assure that

modifications were not being handled as ECs,

which receive a lesser

level

of approval, review, schedule, and documentation.

The

inspector reviewed

OE-1239 which performed

steam generator tube

sleeving and modified the primary system boundary, and OE-1227 which

installed nozzle dams and.nozzle dam hold down rings in the steam

generators. The review of OE-1227 and OE-1228 by the individual NSRB

members resulted in the following concern:

"These exempt change VNs were to install nozzle dam hold down

rings in the "A" & "B" OTSGs for Unit 1.

Why was this done

using an exempt change VN instead of issuing an NSM? What's the

basis for this meeting the exempt change VN criteria?"

The response to this concern stated the following:

"It

was the Superintendent of Maintenance's decision to handle

this

modification

as a VN

rather than

an

NSM.

The

Superintendent is no longer at Oconee, but it.is speculated that

his decision was based on the fact that the modification could

be done quicker."

These examples received what appeared to be complete and technically

accurate reviews and evaluations, but the potential to mistreat the

modification control program appears to exist.

The inspector reviewed approximately 25 TMs from January 1987 to the

present, and identified that all requirements for evaluation, review,

and approval were present.

The three month re-evaluations were

present for TMs open greater than this period.

b.

10 CFR 50.59 Evaluations

10 CFR 50.59(b)(1) states that the licensee shall maintain records of

changes in the facility, including a written safety evaluation which

provides the bases for the determination that the change does not

involve an unreviewed safety question.

The safety evaluation is only required for changes to the facility

which alter the design,

function,

or method of performing the

18

function of a structure, system, or component described in the Safety

Analysis

Report either by text or drawing.

Since structures,

systems, or components which are not explicitly described in the

Safety Analysis Report clearly have the potential for affecting those

systems which are explicitly described, this affect must be

considered in the performance of either safety evaluations or the

screening process utilized in determining if

an unreviewed safety

question is required.

The NSMM, Appendix E, Guidance for 10 CFR 50.59 Evaluations, Section

7.1,

provides the criteria for determining if

a 10 CFR

50.59

evaluation is required.

Among the criteria listed are requirements

for a review of the possibility of degradation of equipment important

to safety during events such as seismic, fire, tornadoes, missiles,

flood, security, etc., and for changes which actually result in a

different physical appearance.

Section 7.1 also provides guidance

for the written justifi.cation which must be provided whenever a

10 CFR 50.59 evaluation has been determined to not be required.

The inspector reviewed Nuclear Station Modifications, Exempt Changes,

Temporary Changes, and Alarm and Setpoint Changes to determine the

adequacy of the attached 10 CFR 50.59 evaluations.

The following

exempt changes pertaining to valve replacements were determined by

site personnel to not involve an unreviewed safety question; however,

they did not have a 10 CFR

50.59 evaluation performed,

nor a

documented basis other than a generic statement that the replacement

component met or exceeded original design specifications and that the

component had been approved by DE (this is not an inclusive list):

OE No.

OE No.

OE No.

OE No.

1341

1347

1190

1355

1359

1360

1312

1313

1606

1607

1608

1609

1620

1621

1622

1609

1658

1344

1200

The licensee determined that the following exempt changes required a

10 CFR 50.59 evaluation and determined that an unreviewed safety

question was not involved, but did not include the bases for the

determination that an unreviewed safety question was not involved.

This list is not intended to be all inclusive.

OE No.

OE No.

OE No.

OE No.

1349

1339

1188

1192

1218

1179

The licensee informed the inspector that since the DE group had

approved the replacement valves, this was justification for not

providing a complete 10 CFR 50.59 evaluation, as the DE group did a

19

complete analysis prior to approving the replacement valves.

The

engineer who

approved the

replacement

valves

stated

that

acceptability of the new valves was based on pressure, temperature,

and application of the valves.

He also stated that the failure

mechanisms of the old valves were reviewed to select a valve less

susceptible to the failure.

The engineer was asked to supply the

records of the evaluations for the valve replacements but he stated

that no records were available and that he had not been told to

maintain them.

The inspector reviewed the NSRB review sheets for NSRB meetings dated

September 21,

1987,

November 20,

1987,

and February 5, 1988.

The

NSRB members continually expressed concern as to the adequacy of the

10 CFR 50.59 evaluations for the ECs used for valve replacements.

The NSMM, Section 9.0, Subsection 9.2.1.3, Exempt Changes for

Electrical and Instrumentation Systems

and Components,

included

instrumentation setpoints as an item to be handled under the EC

process. The site Project Services Manual, revised June 26, 1987,

Section 4.4, Exempt Changes, referenced the NSMM as the source to be

used in determining when a change requires an EC.

Oconee Nuclear Station Directive 2.1.3, revised April 14, 1987, Alarm

and Setpoint Control,

stated that setpoint changes were

made

utilizing the

Procedure Major Change Process Record form.

This

directive did not include the DE group in the development and review

of proposed changes. The Station Directive did not require that a

10 CFR 50.59 evaluation be performed, even though the change form has

a section titled, Safety Evaluation; it

required only that four.

questions be answered yes or no. These questions include:

Involves an unreviewed safety question?

Requires completion of a Nuclear Safety Evaluation Check List?

The

Nuclear Evaluation Check List is a detailed 10 CFR 50.59

evaluation, but none of the changes since January 1987, required that

one

be completed.

This included two changes that required TS

revisions.

The revisions to the TS themselves had 10 CFR 50.59

evaluations attached, but the setpoint change documents did not.

The inspector reviewed the change packages for instrumentation

setpoints generated since January 1987.

Changes to the Alarm and

Setpoint document do not include 10 CFR 50.59 evaluations other than

a statement that an unreviewed safety question is not involved. The

determination of the existence of an unreviewed safety question, as

described in both the NSMM and 10 CFR 50.59, was performed; however,

the bases for the determination that an unreviewed safety question

was not involved was not documented.

The

inspector reviewed procedure

changes

that implemented the

setpoint changes to determine if the 10 CFR 50.59 procedure

20

evaluations would satisfy the requirements for the actual setpoint

changes.

The evaluations addressed the impact of revising the

procedures,

not the impact in changing the actual setpoint.

The

inspector was informed that the Station Directive governing Alarm and

Setpoint Control would supposedly be revised by June 1, 1988,

to

include instructions to complete 10 CFR 50.59 evaluations.

Since early 1987,

the licensee has been working to upgrade their

10 CFR 50.59 program.

The program for procedure revisions is

scheduled to be implemented June 1, 1988; however, the program for

the modification program was implemented in early 1987,

with the

latest revision being implemented December 1,

1987.

The valve

replacement program discrepancies identified by the

inspector

occurred after the implementation of the new program. The alarm and

setpoint changes were handled as procedure revisions; however,

even

the old program would have required a 10 CFR 50.59 evaluation.

While the inspector noted an increase in the quality of the 10 CFR

50.59 evaluations performed for NSMs and

TMs,

the evaluations

performed for the valve replacement ECs and the Alarm and Setpoint

Changes do not satisfy the requirements of 10 CFR 50.59(b)(1).

The

failure to adequately document the bases for the determination that

changes did not involve an unreviewed safety question is contrary to

10 CFR 50.59 requirements and is identified as Violation 269,

270,

287/88-13-05.

6.

Exit Interview

The inspection scope and findings were summarized on May 27,

1988, with

those persons indicated in paragraph 1.

The inspectors described the

areas inspected and discussed in detail the inspection findings listed

below. The licensee did not identify as proprietary any of the material

provided to or reviewed by the inspectors during this inspection.

Dissenting comments were not received from the licensee.

Item Number

Description and Reference

269,270,287/88-13-01

Violation - Failure to provide accurate

IST and fire watch records, paragraphs 3.b

and 3.c.

269,270,287/88-13-02

Violation -

Failure to measure the full stroke

time of ASME Section XI valves paragraphs 3.d.

269,279,287/88-13-03

Violation -

Failure to identify valves to be

tested pursuant to ASME Section XI requirements,

paragraph 3.g.(3).

21

269,270,287/88-13-04

Violation

-

Failure

to

follow

procedural

requirements of Station Directives relating to

maintenance work

requests

and

cleanliness

controls, paragraphs 4.d and 4.e.

269,270,287/88-13-05

Violation -

Failure to document the basis for

10 CFR 50.59 determinations, paragraph 5.b.

269,270,287/88-13-06

URI -

Configuration control inadequacies in the

ES and RPS cabinets, paragraphs 4.b and 4.e.

269,270,287/88-13-07

IFI -

Acceptance criteria for valves moving

freely, paragraph 3.g.(1).

269/88-13-08

IFI

-

Corrective actions for valve 1LP-21

multiple failures, paragraph 3.e.

7. Acronyms and Initialisms

ASME

-

American Society of Mechanical Engineers

B&W

-

Babcock and Wilcox

BWST

-

Borated Water Storage Tank

CFR

-

Code of Federal Regulations

DE

-

Des'ign Engineering

DS

-

Design Studies

EC

-

Exempt Changes

EFW

-

Emergency Feedwater

EQ

-

Environmentally Qualified

ES

-

Engineered Safeguard

FDW

-

Feedwater

HP/HPI

-

High Pressure Injection

IFI

-

Inspector Followup Item

ISI

-

Inservice Inspection

IST:

-

Inservice Testing

LCO

-

Limiting Condition for Operation

LER

-

Licensee Event Report

LP/LPI

-

Low Pressure Injection

LPSW

-

Low Pressure Service Water

LWD

-

Liquid Waste Disposal

MOVATS

-

Motor Operator Valve Testing

N/A

-

Not Applicable

NEO

-

Nuclear Equipment Operator

NRC

-

Nuclear Regulatory Commission

NSM

-

Nuclear Station Modification

NSMM

-

Nuclear Station Modification Manual

NSRB

-

Nuclear Safety Review Board

OE

-

Oconee Exempt Change

OTSG

-

Once Through Steam Generator

P&S

-

Planning and Scheduling

PIR

-

Problem Investigation Report

PM

-

Preventative Maintenance

PT

-

Periodic Test

22

QA

-

Quality Assurance

RBS

-

Reactor Building Spray

RC/RCS

-

Reactor Coolant System

RO

-

Reactor Operator

RPS

-

Reactor Protection System

RVLIS

-

Reactor Vessel Level Indicating System

SPR

-

Station Problem Report

SRO

-

Senior Reactor Operator

TB

-

Terminal Block

TI

-

Temporary Instruction

TM

-

Temporary Modification

.TS

-

Technical Specification

VN

-

Variation Notice

  • 0