Other: ML16187A261, ML16248A001, ML18057B298, NG-15-0361, Six-Month Status Report and Phase 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, NG-16-0241, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), NG-17-0121, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109), NG-17-0250, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (EA-13-109), NG-18-0066, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, NG-18-0138, NextEra Energy Duane Arnold, LLCs Completion of Required Action for NRC Order Number EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions
|
MONTHYEARML16054A2312015-10-0808 October 2015 E-44108 Attachment 2 E-mail from J. Michael Davis (NextEra Energy Duane Arnold) to Don Shaw (Areva) for Duane Arnold Energy Center Project stage: Request NG-15-0361, Six-Month Status Report and Phase 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2015-12-22022 December 2015 Six-Month Status Report and Phase 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Project stage: Other ML16187A2612016-06-30030 June 2016 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) Project stage: Other ML16248A0012016-09-13013 September 2016 Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 2 of Order EA-13-109 (Severe Accident Capable Hardened Vents) Project stage: Other NG-16-0241, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)2016-12-22022 December 2016 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) Project stage: Other NG-17-0121, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109)2017-06-29029 June 2017 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109) Project stage: Other NG-17-0250, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (EA-13-109)2017-12-19019 December 2017 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (EA-13-109) Project stage: Other ML18057B2982018-03-0505 March 2018 Report for the Audit of Licensee Responses to Interim Staff Evaluations Open Items Related to NRC Order EA-13-109 Project stage: Other NG-18-0066, Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2018-06-26026 June 2018 Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Project stage: Other NG-18-0138, NextEra Energy Duane Arnold, LLCs Completion of Required Action for NRC Order Number EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2018-12-19019 December 2018 NextEra Energy Duane Arnold, LLCs Completion of Required Action for NRC Order Number EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Project stage: Other ML19168A1302019-06-21021 June 2019 Safety Evaluation Regarding Implementation of Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Related to Order EA-13-109 (CAC No. MF4391; EPID No. L-2014-JLD-0039) Project stage: Approval 2017-12-19
[Table View] |
Text
E-44108 E-mail from J. Michael Davis (NextEra Energy Duane Arnold) to Don Shaw (AREVA) for Duane Arnold Energy Center
1 WILLIFORD Dennis (BE/LO)
From:
Davis, J.Michael <J.Michael.Davis@nexteraenergy.com>
Sent:
Thursday, October 08, 2015 3:37 PM To:
SHAW JR Donis (BE/LO)
Cc:
WILLIFORD Dennis (RS/IB); Swenzinski, Laura
Subject:
Voluntary Agreement to Implement CoC 1004 Amendment Revisions Which Remove the Requirement for a Spent Fuel Pool To: Don Shaw, AREVA TN Licensing Manager From: J. Michael Davis, Licensing Manager, NextEra Energy Duane Arnold
Reference:
AREVA Inc. letter E-42575, from Paul Triska (AREVA) to NRC Document Control Desk, Application for Revision to the Standardized NUHOMS System - CoC 1004, Amendments 0 through 11 and Amendment 13, Docket 72-1004, dated August 24, 2015 The purpose of this communication is to confirm the following:
- NextEra Energy Duane Arnold, LL is aware of and understands the proposed AREVA Inc. changes to the CoC 1004 Standardized NUHOMS System Technical Specifications and the associated UFSAR changes, which are detailed in the letter referenced above for all approved amendments.
- We understand that these changes will result in Revision 1 to each currently approved CoC 1004 amendment.
- We understand that the previous version of the associated amendments will be superseded in their entirety by Revision 1.
- We agree to voluntarily implement these changes for our general licensee independent spent fuel storage installations (ISFSIs) at the following sites, which operate CoC 1004 Standardized NUHOMS Systems under one or more amendments:
- Duane Arnold Energy Center, Palo, Iowa
- In order to allow sufficient time to incorporate these changes in a quality manner, we request that AREVA work with the NRC to provide its general licensees a maximum 180-day period after the effective date of the revised amendments during which we can complete incorporation and begin storage operations under the revised amendments.
Sincerely, Mike Davis Licensing Manager NextEra Energy Duane Arnold 319-851-7032 Michael.Davis@nexteraenergy.com
E-44108 E-mail from J. Michael Davis (NextEra Energy Duane Arnold) to Don Shaw (AREVA) for Duane Arnold Energy Center
1 WILLIFORD Dennis (BE/LO)
From:
Davis, J.Michael <J.Michael.Davis@nexteraenergy.com>
Sent:
Thursday, October 08, 2015 3:37 PM To:
SHAW JR Donis (BE/LO)
Cc:
WILLIFORD Dennis (RS/IB); Swenzinski, Laura
Subject:
Voluntary Agreement to Implement CoC 1004 Amendment Revisions Which Remove the Requirement for a Spent Fuel Pool To: Don Shaw, AREVA TN Licensing Manager From: J. Michael Davis, Licensing Manager, NextEra Energy Duane Arnold
Reference:
AREVA Inc. letter E-42575, from Paul Triska (AREVA) to NRC Document Control Desk, Application for Revision to the Standardized NUHOMS System - CoC 1004, Amendments 0 through 11 and Amendment 13, Docket 72-1004, dated August 24, 2015 The purpose of this communication is to confirm the following:
- NextEra Energy Duane Arnold, LL is aware of and understands the proposed AREVA Inc. changes to the CoC 1004 Standardized NUHOMS System Technical Specifications and the associated UFSAR changes, which are detailed in the letter referenced above for all approved amendments.
- We understand that these changes will result in Revision 1 to each currently approved CoC 1004 amendment.
- We understand that the previous version of the associated amendments will be superseded in their entirety by Revision 1.
- We agree to voluntarily implement these changes for our general licensee independent spent fuel storage installations (ISFSIs) at the following sites, which operate CoC 1004 Standardized NUHOMS Systems under one or more amendments:
- Duane Arnold Energy Center, Palo, Iowa
- In order to allow sufficient time to incorporate these changes in a quality manner, we request that AREVA work with the NRC to provide its general licensees a maximum 180-day period after the effective date of the revised amendments during which we can complete incorporation and begin storage operations under the revised amendments.
Sincerely, Mike Davis Licensing Manager NextEra Energy Duane Arnold 319-851-7032 Michael.Davis@nexteraenergy.com