APPENDIX H Evacuation Regions
H EVACUATION REGIONS This appendix presents the evacuation percentages for each Evacuation Region (Table H-i and Table H-2) and maps of all Evacuation Regions. The percentages presented in Table H-i and Table H-2 are based on the methodology discussed in assumption 5 of Section 2.2 and shown in Figure 2-1.
Note the baseline ETE study assumes 20 percent of households will not comply with the shelter advisory, as per Section 2.5.2 of NUREG/CR-7002.
Pilerim Nuclear Power Station H-i KLD Eneineerine. P.C.
Evacuation Time Estimate Rev. I
Table H-i. Percent of Sub-area Population Evacuating for Each Region Basic Regions I
Region Site PAR Description Sub-area I
Description 1112 1 54I 6 I 7 I 8 I 9 I 10o l 11 l 2 1 Rl2-Mile Radius 2-Mile Ring R0S-Mile Radius
- j.
5-Mile Ring Site PAR Rein Wind Direction From:
Description
- R4NW, NNW, N 3060 - 0190
- RSNNE, NE, ENE 0200 -0690 R6E 0700 - 1220
- R7ESE, SE 1230 - 1400
- RSSSE, S
1410 - 1830 Sub-area r
I 1112131 415 6
7 8
9 10 11 I 12 I
I 4
4-4
+
+
20%
20%
20%
20%
20%
20%
20%
2% 2%2%2%20%,2%2010 20%
20%
20%
20%
20%
20%
20%
4
+
4
+
4 4
20%
20%
20%
20%
20%
20%
20%
2%
20%
20%_ 20%120%2%
0 N/A SSW, SW, WSW, W, WNW 184°-3o5° I
Refer to Region R01 Region Wind Direction From:
Description 1
2 3
4 5
6 7
8 9
1 1
1 R09 I
NW, NNW, N 319°- 0190 RIO 0200-021° Rll NNE, NE 022°-~056° R12
-I2002072-020620 R13 I
0670 -0690 R14 IENE 070°-103° RiS E, ESE 104°- 1090 R16 1°15 R17 1160-1290 R8IS SE13
-32 R19 I
1330 -1400 R20
- ISSE, S14
-75 R21 I
1760°-1790 N/A I5SW, SW, WSW, W, WNW 1800°-3180 Refer to Region R02 Pilgrim Nuclear Power Station Evacuation Time Estimate H-2 KLD Engineering, P.C.
Rev. 1
Table H-2. Percent of Sub-area Population Evacuating for Each Staged Region
____Staged Evacuation.- 2-Mile Region Evacuates, then Evacuate Downwind to 5 Miles Region Wind Direction From:
Description 1
2 3
4 5
6 7
8 9
10 11 1
R242NEEoEne00 5-M 1220R20%
20%
20%
20%
20%
20 20%
20%
R26 ESE, SE 1410 - 1830 0
0 0
0 0
R27 SSE, S 1840 - 35052%
0 20%
20%
20%
20% 20%
20 2%
N/A SSW, SW, WSW, W, WNW 2-Mile Ring Refer to Region R01 Sub-area(s) Shelter-in-Place Pilgrim Nuclear Power Station Evacuation Time Estimate H-3 KLD Engineering, P.C.
Rev. 1
Figure H-1. Region R01 Pilgrim Nuclear Power Station Evacuation Time Estimate H-4 KLD Engineering, P.C.
Rev. 1
Figure H-2. Region R02 Pilgrim Nuclear Power Station Evacuation Time Estimate H-5 KLD Engineering, P.C.
Rev. 1
J Figure H-3. Region R03 H-6 KID Engineering, P.C.
Pilgrim Nuclear Power Station Evacuation Time Estimate H-6 Rev. 1
Figure H-4. Region R04 Pilgrim Nuclear Power Station Evacuation Time Estimate H-7 KLD Engineering, P.C.
Rev. 1
Figure H-S. Region R05 H-8 KLD Engineering, P.C.
Pilgrim Nuclear Power Station Evacuation Time Estimate H-S Rev. 1
Figure H-6. Region R06 Pilgrim Nuclear Power Station Evacuation Time Estimate H-9 KLD Engineering, P.C.
Rev. 1
Figure H-7. Region R07 Pilgrim Nuclear Power Station Evacuation Time Estimate H-bO KLD Engineering, P.C.
Rev. 1
Figure H-8. Region R08 Pilgrim Nuclear Power Station Evacuation Time Estimate H-li KLD Engineering, P.C.
Rev. 1
Figure H-9. Region R09 Pilgrim Nuclear Power Station Evacuation Time Estimate H-12 KLD Engineering, P.C.
Rev. 1
Figure H-lO. Region RIO Pilgrim Nuclear Power Station Evacuation Time Estimate H-13 KLD Engineering, P.C.
Rev. 1
Figure H-11. Region Rll Pilgrim Nuclear Power Station Evacuation Time Estimate H-14 KLD Engineering, P.C.
H-14 Rev. 1
Figure H-12. Region R12 Pilgrim Nuclear Power Station Evacuation Time Estimate H-15 KLD Engineering, P.C.
Rev. 1
Figure H-13. Region R13 Pilgrim Nuclear Power Station Evacuation Time Estimate H-16 KLD Engineering, P.C.
Rev. 1
Figure H-14. Region R14 H-17 KLD Engineering, P.C.
Pilgrim Nuclear Power Station Evacuation Time Estimate H-17 Rev. 1
Figure H-15. Region R15 Pilgrim Nuclear Power Station Evacuation Time Estimate H-18 KID Engineering, P.C.
Rev. 1
Figure H-16. Region R16 Pilgrim Nuclear Power Station Evacuation Time Estimate H-19 KLD Engineering, P.C.
Rev. 1
Figure H-17. Region R17 Pilgrim Nuclear Power Station Evacuation Time Estimate H-20 KLD Engineering, P.C.
Rev. 1
Figure H-18. Region R18 Pilgrim Nuclear Power Station Evacuation Time Estimate H-21 KLD Engineering, P.C.
Rev. 1
Figure H-19. Region R19 Pilgrim Nuclear Power Station Evacuation Time Estimate H-22 KID Engineering, P.C.
Rev. 1
Figure H-20. Region R20 Pilgrim Nuclear Power Station Evacuation Time Estimate H-23 KID Engineering, P.C.
Rev. 1
Figure H-21. Region R21 Pilgrim Nuclear Power Station Evacuation Time Estimate H-24 KLD Engineering, P.C.
Rev. 1
Figure H-22. Region R22 Pilgrim Nuclear Power Station Evacuation Time Estimate H-25 KID Engineering, P.C.
Rev. 1
Figure H-23. Region R23 Pilgrim Nuclear Power Station Evacuation Time Estimate H-26 KLD Engineering, P.C.
Rev. 1
Figure H-24. Region R24 Pilgrim Nuclear Power Station Evacuation Time Estimate H-27 KLD Engineering, P.C.
Rev. 1
Figure H-25. Region R25 Pilgrim Nuclear Power Station Evacuation Time Estimate H-28 KID Engineering, P.C.
Rev. 1
Figure H-26. Region R26 Pilgrim Nuclear Power Station H-29 Evacuation Time Estimate KLD Engineering, P.C.
Rev. 1
Figure H-27. Region R27 Pilgrim Nuclear Power Station Evacuation Time Estimate H-30 KLD Engineering, P.C.
Rev. 1
APPENDIX H Evacuation Regions
H EVACUATION REGIONS This appendix presents the evacuation percentages for each Evacuation Region (Table H-i and Table H-2) and maps of all Evacuation Regions. The percentages presented in Table H-i and Table H-2 are based on the methodology discussed in assumption 5 of Section 2.2 and shown in Figure 2-1.
Note the baseline ETE study assumes 20 percent of households will not comply with the shelter advisory, as per Section 2.5.2 of NUREG/CR-7002.
Pilerim Nuclear Power Station H-i KLD Eneineerine. P.C.
Evacuation Time Estimate Rev. I
Table H-i. Percent of Sub-area Population Evacuating for Each Region Basic Regions I
Region Site PAR Description Sub-area I
Description 1112 1 54I 6 I 7 I 8 I 9 I 10o l 11 l 2 1 Rl2-Mile Radius 2-Mile Ring R0S-Mile Radius
- j.
5-Mile Ring Site PAR Rein Wind Direction From:
Description
- R4NW, NNW, N 3060 - 0190
- RSNNE, NE, ENE 0200 -0690 R6E 0700 - 1220
- R7ESE, SE 1230 - 1400
- RSSSE, S
1410 - 1830 Sub-area r
I 1112131 415 6
7 8
9 10 11 I 12 I
I 4
4-4
+
+
20%
20%
20%
20%
20%
20%
20%
2% 2%2%2%20%,2%2010 20%
20%
20%
20%
20%
20%
20%
4
+
4
+
4 4
20%
20%
20%
20%
20%
20%
20%
2%
20%
20%_ 20%120%2%
0 N/A SSW, SW, WSW, W, WNW 184°-3o5° I
Refer to Region R01 Region Wind Direction From:
Description 1
2 3
4 5
6 7
8 9
1 1
1 R09 I
NW, NNW, N 319°- 0190 RIO 0200-021° Rll NNE, NE 022°-~056° R12
-I2002072-020620 R13 I
0670 -0690 R14 IENE 070°-103° RiS E, ESE 104°- 1090 R16 1°15 R17 1160-1290 R8IS SE13
-32 R19 I
1330 -1400 R20
- ISSE, S14
-75 R21 I
1760°-1790 N/A I5SW, SW, WSW, W, WNW 1800°-3180 Refer to Region R02 Pilgrim Nuclear Power Station Evacuation Time Estimate H-2 KLD Engineering, P.C.
Rev. 1
Table H-2. Percent of Sub-area Population Evacuating for Each Staged Region
____Staged Evacuation.- 2-Mile Region Evacuates, then Evacuate Downwind to 5 Miles Region Wind Direction From:
Description 1
2 3
4 5
6 7
8 9
10 11 1
R242NEEoEne00 5-M 1220R20%
20%
20%
20%
20%
20 20%
20%
R26 ESE, SE 1410 - 1830 0
0 0
0 0
R27 SSE, S 1840 - 35052%
0 20%
20%
20%
20% 20%
20 2%
N/A SSW, SW, WSW, W, WNW 2-Mile Ring Refer to Region R01 Sub-area(s) Shelter-in-Place Pilgrim Nuclear Power Station Evacuation Time Estimate H-3 KLD Engineering, P.C.
Rev. 1
Figure H-1. Region R01 Pilgrim Nuclear Power Station Evacuation Time Estimate H-4 KLD Engineering, P.C.
Rev. 1
Figure H-2. Region R02 Pilgrim Nuclear Power Station Evacuation Time Estimate H-5 KLD Engineering, P.C.
Rev. 1
J Figure H-3. Region R03 H-6 KID Engineering, P.C.
Pilgrim Nuclear Power Station Evacuation Time Estimate H-6 Rev. 1
Figure H-4. Region R04 Pilgrim Nuclear Power Station Evacuation Time Estimate H-7 KLD Engineering, P.C.
Rev. 1
Figure H-S. Region R05 H-8 KLD Engineering, P.C.
Pilgrim Nuclear Power Station Evacuation Time Estimate H-S Rev. 1
Figure H-6. Region R06 Pilgrim Nuclear Power Station Evacuation Time Estimate H-9 KLD Engineering, P.C.
Rev. 1
Figure H-7. Region R07 Pilgrim Nuclear Power Station Evacuation Time Estimate H-bO KLD Engineering, P.C.
Rev. 1
Figure H-8. Region R08 Pilgrim Nuclear Power Station Evacuation Time Estimate H-li KLD Engineering, P.C.
Rev. 1
Figure H-9. Region R09 Pilgrim Nuclear Power Station Evacuation Time Estimate H-12 KLD Engineering, P.C.
Rev. 1
Figure H-lO. Region RIO Pilgrim Nuclear Power Station Evacuation Time Estimate H-13 KLD Engineering, P.C.
Rev. 1
Figure H-11. Region Rll Pilgrim Nuclear Power Station Evacuation Time Estimate H-14 KLD Engineering, P.C.
H-14 Rev. 1
Figure H-12. Region R12 Pilgrim Nuclear Power Station Evacuation Time Estimate H-15 KLD Engineering, P.C.
Rev. 1
Figure H-13. Region R13 Pilgrim Nuclear Power Station Evacuation Time Estimate H-16 KLD Engineering, P.C.
Rev. 1
Figure H-14. Region R14 H-17 KLD Engineering, P.C.
Pilgrim Nuclear Power Station Evacuation Time Estimate H-17 Rev. 1
Figure H-15. Region R15 Pilgrim Nuclear Power Station Evacuation Time Estimate H-18 KID Engineering, P.C.
Rev. 1
Figure H-16. Region R16 Pilgrim Nuclear Power Station Evacuation Time Estimate H-19 KLD Engineering, P.C.
Rev. 1
Figure H-17. Region R17 Pilgrim Nuclear Power Station Evacuation Time Estimate H-20 KLD Engineering, P.C.
Rev. 1
Figure H-18. Region R18 Pilgrim Nuclear Power Station Evacuation Time Estimate H-21 KLD Engineering, P.C.
Rev. 1
Figure H-19. Region R19 Pilgrim Nuclear Power Station Evacuation Time Estimate H-22 KID Engineering, P.C.
Rev. 1
Figure H-20. Region R20 Pilgrim Nuclear Power Station Evacuation Time Estimate H-23 KID Engineering, P.C.
Rev. 1
Figure H-21. Region R21 Pilgrim Nuclear Power Station Evacuation Time Estimate H-24 KLD Engineering, P.C.
Rev. 1
Figure H-22. Region R22 Pilgrim Nuclear Power Station Evacuation Time Estimate H-25 KID Engineering, P.C.
Rev. 1
Figure H-23. Region R23 Pilgrim Nuclear Power Station Evacuation Time Estimate H-26 KLD Engineering, P.C.
Rev. 1
Figure H-24. Region R24 Pilgrim Nuclear Power Station Evacuation Time Estimate H-27 KLD Engineering, P.C.
Rev. 1
Figure H-25. Region R25 Pilgrim Nuclear Power Station Evacuation Time Estimate H-28 KID Engineering, P.C.
Rev. 1
Figure H-26. Region R26 Pilgrim Nuclear Power Station H-29 Evacuation Time Estimate KLD Engineering, P.C.
Rev. 1
Figure H-27. Region R27 Pilgrim Nuclear Power Station Evacuation Time Estimate H-30 KLD Engineering, P.C.