ML16040A345

From kanterella
Jump to navigation Jump to search
Response to Disputed Non-Cited Violation Hope Creek Generating Station - Component Design Bases Inspection Report 05000354/2015007
ML16040A345
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 02/09/2016
From: Ray Lorson
Division of Reactor Safety I
To: Davison P
Public Service Enterprise Group
References
Download: ML16040A345 (5)


See also: IR 05000354/2015007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BLVD., SUITE 100

KING OF PRUSSIA, PA 19406-2713

February 9, 2016

Paul J. Davison

Site Vice President - Hope Creek

PSEG Nuclear, LLC - S05

P.O. BOX 236

HANCOCKS BRIDGE, NJ 08038

SUBJECT: RESPONSE TO DISPUTED NON-CITED VIOLATION HOPE CREEK

GENERATING STATION - COMPONENT DESIGN BASES INSPECTION

REPORT 05000354/2015007

Dear Mr. Davison:

We received your response [ADAMS No. ML15362A564] to our inspection report

05000354/2015007 [ADAMS No. ML15329A157] issued on November 25, 2015, concerning

activities conducted at your facility. In your response, you denied a Non-Cited Violation (NCV)

contained in the inspection report. Specifically, PSEG contends that the weaknesses identified

in the inspection report regarding classification, evaluation and corrective actions are not more

than minor in that PSEGs conclusion on operability and corrective actions were not impacted.

The NRC conducted a detailed review of your response and the applicable inspection guidance.

Region I staff who were not involved with the initial inspection effort performed this review. After

careful consideration of the bases for your denial of the NCV, we determined that the violation

and characterization of the finding were properly described in the inspection report. Specifically,

the inspection team identified that your staff failed to conduct operability determinations in

October 2013 following the improper installation of a service water system valve and a

subsequent event where the valve failed to operate due to a high torque condition. In response

to the inspection teams questions, your staff, with support from an external engineering

organization, performed an operability review and determined that the valve was able to perform

its safety function for a limited number of operating cycles. You subsequently scheduled a

maintenance activity to fully restore the valve during the October 2016 refueling outage. Our

review determined that this finding was appropriately characterized as more than minor as

there was a reasonable basis for questioning operability of the valve following the October 2013

events described above. We have provided a summary of our evaluation and conclusions as an

enclosure to this letter.

P. Davison 2

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter, its

enclosure and your December 24, 2015, response will be available electronically for public

inspection in the NRC Public Document Room or from the NRC's document system (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Raymond K. Lorson, Director

Division of Reactor Safety

Docket No. 50-354

License No. NPF-57

Enclosure: as stated

cc w/encl: Distribution via ListServ

SUMMARY

Non-Cited Violation (NCV)05000354/2015007-02

Restatement of the Violation:

The team identified a Green NCV of 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, because PSEG did not provide adequate work order instructions

for the installation of service water (SW) pump discharge isolation valve 2198C following

planned valve maintenance in October 2013. Specifically, the inadequate work order

instructions contributed directly to maintenance technicians installing the valve in the opposite

orientation compared to the intended orientation.

Licensee Response (Summary):

PSEG denies that the NRC identified any new information that impacted the licensees

conclusions regarding operability or corrective actions. The improper re-installation of the valve

EAHV-2198C was promptly identified by the licensee and entered in CAP, and the additional

analyses performed in response to NRC questions supported the licensees initial conclusions.

In addition, PSEG contends the identified weaknesses associated with the classification,

evaluation, and corrective actions of EAHV-2198C do not meet the threshold for more than

minor.

NRC Evaluation:

The NRC Region I staff performed an independent review of the documented NCV in Inspection

Report 05000354/2015007, using PSEGs basis for denial for comparison, and made the

following observations:

1) Notification (NOTF) 20626219 was initiated by the PSEG staff on October 22, 2013,

identifying the installation of valve 2198C 180 degrees different than when removed.

This NOTF was subsequently updated by the PSEG maintenance staff to reflect

inadequacies in the applicable Work Order (60112463-410) as compared to the valve

drawing (M-10-1) and the associated vendor manual. The NCV properly refers to

10 CFR 50, Appendix B, Criterion V, as the appropriate violation of regulatory

requirements.

2) The Component Design Bases Inspection (CDBI) report states (page 6) that there was

no documented evaluation of the impact of this misalignment and configuration error

prior to operations declaring the C SW pump operable following the 2198C maintenance

on October 23. As stated in the report and further clarified by interview with the

inspection team leader, PSEG did not complete an operability evaluation prior to

restoration of the C SW pump to service on October 23, 2013, in spite of the improper

installation of the outlet valve. Further, PSEG acknowledged this deficiency by initiating

NOTF 20705874 (also documented in the report). The inspection report (page 7)

identified a second instance where PSEG failed to properly assess a valve operational

anomaly, an unexpected high opening torque (compared to the valves weak link

analysis and Limitorque limits) and its potential adverse impact on system operability.

This condition was identified during troubleshooting of valve 2198C on October 27,

2013, but no corresponding operability evaluation was documented.

1

Enclosure

3) The teams observations documented in the report and highlighted in 2) above, form the

basis for the inspection teams conclusion that the NRC added value to a licensee-

identified finding or violation. The absence of an operability evaluation, for either of the

above referenced conditions, was documented as a weakness in the licensees

classification, evaluation, or corrective action (page 9) and was the basis for the team to

conclude there was a reasonable doubt of operability, with respect to the valve being

able to function under all design basis conditions. In order to conclude that the valve

was operable and to answer questions from the inspection team, PSEG performed an

operability determination for the issue of the valve being installed in the wrong

orientation (NOTF 20705874), performed a technical evaluation to determine that the

valve actuator was capable of opening the valve under all required design basis

conditions based upon actual measured data (NOTF 20704783), and contracted with

Kalsi Engineering to perform an H4BC gear box torque analysis for the valve actuator.

This team conclusion was documented in the Analysis Section of the inspection report

(page 9-10) in reference to the basis for the observations (and underlying performance

deficiency) being more than minor. The team cites Example 3.j of IMC 0612,

Appendix E, as justification of the more than minor determination.

4) PSEGs Basis for Denial did not address the Appendix E more than minor example

referenced in the CDBI inspection report. Rather, PSEG stated that the weaknesses

identified by the team regarding classification, evaluation and corrective action were not

more than minor. Further, PSEG contends that the additional analyses performed in

response to NRC team questions did not change the original operability determination

outcome. Neither the subjective contention of the weaknesses being minor nor the final

determination of operability being maintained provide a sufficient basis for denial. The

NRC determined that the Appendix E example established the basis for determining that

this performance deficiency was of more than minor significance.

5) In the Basis for Denial, PSEG opines that the CDBI teams challenge of the operability

impact of the above conditions was unfounded without knowledge of the actual operating

conditions of the system (system alignment, flowrates, and valve differential pressure

were not recorded and were unknown). PSEG contends that without knowing actual

system operating conditions, data cannot be extrapolated with any certainty. The NRC

considers that the uncertainties associated with the valve operating parameters highlight

the reason why PSEG was required to perform an operability determination following

improper installation of the valve and its failure to operate due to a high torque condition.

6) Additionally, PSEG took exception to the observation in the inspection report that the

maintenance work instructions lacked sufficient detail. On page 6 of the inspection

report, the inspection team noted that PSEG maintenance personnel identified and

documented in NOTF 20626219, that the desired orientation of the 2198 valve was not

specified in valve drawing M-10-1 or in the vendor manual. The inspection team also

noted that the work order contained several diagrams which depicted the wrong valve

orientation. The NRC determined that the maintenance work instructions given to the

maintenance staff lacked sufficient detail to ensure that the valve was installed in the

proper orientation.

For the above reasons, the staff concludes that the violation occurred as described in Inspection

Report 05000354/2015007.

2

Enclosure

P. Davison 2

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter, its

enclosure and your December 24, 2015, response will be available electronically for public

inspection in the NRC Public Document Room or from the NRC's document system (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Raymond K. Lorson, Director

Division of Reactor Safety

Docket No. 50-354

License No. NPF-57

Enclosure: as stated

cc w/encl: Distribution via ListServ

DISTRIBUTION:

DDorman, RA (R1ORAMail) FBower, DRP PKrohn, DRS

DLew, DRA (R1ORAMail) RBarkley, DRP JKulp, DRS

MScott, DRP (R1DRPMail) MDraxton, DRP WCook, DRS

JColaccino, DRP (R1DRPMail) JHawkins, DRP, SRI JSchoppy, DRS

RLorson, DRS (R1DRSMail) SHaney, DRP, RI JBrand, DRS

BSmith, DRS (R1DRSMail) COtt, DRP, AA CSantos, RI, OEDO

RidsNrrPMHopeCreek RidsNrrDorlLpl1-2

DOCUMENT: G:\DRS\Engineering Branch 2\PSEGCDBINCVChallengeJan2016.docx

ADAMS ACCESSION NUMBER: ML16040A345

SUNSI Review Non-Sensitive Publicly Available

OFFICE RI/DRS RI/DRS RI/DRS

NAME WCook JKulp RLorson

DATE 02/08/2016 02/08/2016 02/09/2016

OFFICIAL RECORD