FPL-032R

  • I=PL.

January 23, 2015 Ms. Karin Smith Section Leader South Florida Water Management District 3301 Gun Club Road West Palm Beach, FL 33416-4680 RE: Florida Power & Light Company- Turkey Point Plant Water Use Permit Application Cooling Canal Augmentation P.-oject

Dear Ms. Smith:

Florida Power & Light Company (FPL) is requesting authorization from the South Florida Water Management District (SFWMD) to access the District's right of way, connect to the L-31E canal, and seasonally transfer excess stormwater (above the 254 cubic feet per second required for the Comprehensive Everglades Restoration Project (CERP) Biscayne Bay Coastal Wetlands restoration project) from the L-31E canal to the Turkey Point Plant to aid in reducing temperature and salinity in the Cooling Canal System (CCS).

On August 28, 2014 the SFWMD issued EO No. 201-078-DAO-WU/ROW/ERP (Attachment A) allowing for the temporary installation and removal of piping and pumping systems for transfer of water from the L-31E Canal to the CCS. In accordance with the conditions of the EO, FPL divetied surface water from the L-31E Canal which would have otherwise been discharged to tide. via the S-20F, S-20G, and S-21A coastal structures and was in excess of the flows reserved for protection of fish and wildlife (Rule 40E-10.061, F.A.C.). Withdrawals were tenninated on October 15, 2014.

In lieu of requesting another EO for short-term coverage, FPL is requesting a recurring annual diversion of water from the L-31E under the SFWMD Consumptive Water Use Program. FPL proposes to utilize a similar design (Attachment B) and comply with conditions consistent with those that were approved under EO No. 201-078-DAO-WU/ROW/ERP. Enclosed are the applicable SFWMD Water Use Application Forms and supporting documentation (Attachments C and D) and a check for the Water Use Permitting fee of $6,200.

The proposed work is necessary for the continued safe and reliable operation of the Turkey Point Plant.

FPL appreciates your expedited review of the enclosed drawings and details. Please contact me at 561-691-2808 (Matthew.Raffenberg@fpl.com) or Stacy Foster at 561-691-7065 (stacy.foster@fpl.com) ifyou have any questions.

Sincerely,

~ )11, ~~ /2r HJt(

Matthew J. Raffenberg Director of Environmental Licensing and Permitting

Attachments: Attachment A- SFWMD EO No. 201-078-DAO-WU/ROW/ERP Attachment B - CCS Augmentation Construction Drawings Attachment C- Water Use Permit Application and Supporting Documents Attachment D- Water Use Supplemental Form F and Suppmting Documents

AT'FACl!IMEN1' A s.-.-:mm N~. ZOl~OI18-D~-WU/OOW/ERP

BEFORE THE GOVERNING BOARD OF THE SOUTH FLORIDA WATER MANAGEMENT DISTRICT SFWMD No. 2014-078-DAO-WU/ROW/ERP IN RE:

EMERGENCY FINAL ORDER ISSUED TO FLORIDA POWER AND LIGHT FOR THE PURPOSE OF AUTHORIZING TEMPORARY PUMP INSTALLATION AND WATER WITHDRAWAL ALONG AND FROM THE LN31 E CANAL SYSTEMj MIAMI-DADE COUNTY, FLORIDA

--~------------------------~'

EMERGENCY FINAL ORDER The Executive Director of the South Florida Water Management District (District),

pursuant to Sections 120.569 and 373.119(2), Florida Statutes (Fla. Stat.), after considering the recommendations of District staff and being otherwise fully appraised of the matter, issues the following Emergency Order (Order) containing Findings of Fact, Ultimate Facts and Conclusions of Law:

FINDINGS OF FACT

1. The District is a public corporation of the State .of Florida, existing pursuant to Chapter 25270, Laws of Florida, 1949, and operating pursuant to Chapter 373, Fla. Stat., and Title 40E, Florida Administrative Code (Fla. Admin. Code), as a multi-purpose water management district with its principal office at 3301 Gun Club Road, West Palm Beach, Florida. The District has the power and duty to protect Florida's water resources and to administer and enforce the provisions of Chapter 373, 1

Fla. Stat., and the rules promulgated there under, Title 40E, Fla. Admin. Code. The District has jurisdiction over the matters addressed in this Order.

2. Florida Power and Light (FPL) is a subsidiary of NextEra Energy, Inc. As a regulated utility, FPL is granted an exclusive franchise by the Public Service Commission to provide reliable and cost-effective electric service to customers, including critical infrastructure, within its service territory in Florida. FPL's service territory covers all or parts of 35 Florida counties and serves approximately nine million customers.
3. The customers particularly at issue in this matter are those residing In Miami-Dade and Broward counties. In these counties, FPL provides electrical service to two million customer accounts, including critical infrastructure.
4. FPL owns and operates the electric power generating facility known as the Turkey Point Power Plant (Turkey Point) that is the subject of this emergency authorization request.
5. Turkey Point is located in unincorporated southeast Miami~Dade County, east of Florida City and the City of Homestead. The Turkey Point site covers approximately 11 ,000 acres. Turkey Point is located approximately 25 miles south of Miami and about nine miles east of Florida City. Properties adjacent to Facility are almost exclusively undeveloped land. Turkey Point is bordered to the east by Biscayne Bay and Card Sound. A Turkey Point location map is attached and incorporated as Exhibit A.
6.
  • Turkey Point consists of five steam electric generating unHs: three fossil fuel-fired units (Units 1, 2, and 5) and two nuclear units (Units 3 and 4). Units 1 and 2 2

constructed in the late 1960s each have a continuous generating capacity of approximately 404 megawatts {MW). Operations of units 1 and 2 are on a standby basis and not routinely in service. Unit 5 has a continuous generating capacity of approximately 1150 MW. Units 3 and 4 each have continuous generating capacity of approximately 820 MW.

7. Units 3, 4, and 5 are certified under Florida's Power Plant Siting Act (PPSA). Units 1 and 2 pre-date the PPSA and are not certified.
8. FPL owns and operates a cooling canal system ("CCS"), an approximately 5,900-acre network of unlined canals at Turkey Point, to provide cooling water.

Construction of the CCS was completed in 1973, and the CCS was closed from the surface waters of both Biscayne Bay and Card Sound. The CCS facilities pre-date the PPSA and are not certified. Under routine operations, there are no active surface water inflows utilized to maintain ccs water levels, temperature, or salinity.

9. The L~31 E Canal system is of particular import to FPL's emergency authorization request. The L-31 E Canal system is part of the Central and Southern Florida Flood Control Project (C & SF Project) for which the District is the designated local sponsor pursuant to Section 373.1501, Fla. Stat. As local sponsor, the District operates C&SF Project components, including the L-31E Canal system and the surface water flow to tide from the ass_ociated basins consistent with the guidance provided in the United States Army Corps of Engineers Master Water Control Manual, East Coast Canals, Volume 5.
10. The L~31 E Canal system is a borrow canal and levee system that stretches north - south both intercepting water as it flows eastward to tide in southeast 3

Dade County and providing storm surge protection. A map depicting. the L-31 E Canal system is attached and incorporated as Exhibit B. The L-31 E Canal runs parallel to the South Central Biscayne Bay and across several drainage basins, six of which are named for the associated major east-west canals: Canal 100 (C-100), C-1, C-1 02, C-103, North Canal and Florida City Canal. This canal network and coastal levee system is operated for several C & SF Project purposes, including reducing the potential for flood and storm surge damage as well as limiting saline water intrusion. Water from the L-31 E is discharged to Biscayne Bay at several coastal structures, as depicted on Exhibit B.

11. Operation of the C & SF Project coastal structure gates in this canal network controls the quantity and timing of water discharged into this portion of Biscayne Bay. Overall, these surface water inflows comprise the largest input of fresh water to Biscayne Bay in this area.
12. In the 1990's the U.S. Army Corps of Engineers and the District developed the Comprehensive Everglades Restoration Program (CERP) which was approved by Congress in the Water Resources Development Act of 2000 (WRDA 2000). A component of CERP includes the Biscayne Bay Coastal Wetlands Phase 1 Project.

This project component aims to restore the overland sheetflow in an. area of up to 11,000 acres, and to improve the ecology of Biscayne Bay, including its freshwater and saltwater wetlands, nearshore bay habitat, marine nursery habitat, and the oyster reef community.

13. Implementation of the Biscayne Bay Coastal Wetlands Phase 1 Project will. impound and redistribute freshwater runoff from the existing canal discharges into 4

the coastal wetlands adjoining Biscayne Bay to provide a more natural and historical overland flow pattern through existing coastal wetlands and tidal creeks. This redistribution of freshwater runoff will improve the temporal and spatial distribution of inflows to Biscayne Bay.

14. The WRDA 2000 requires that water be reserved from allocation as an assurance that each CERP project component will meet its goals and objectives. Water is to be reserved consistent with the objectives and information contained within the Central and Southern Florida Project Comprehensive Everglades Restoration Plan Biscayne Bay Coastal Wetlands Project Phase I Final Integrated Project implementation Report and Environmental Impact Statement (PIR) and other sources of information.
15. To this end, the District conducted technical studies identifying water to be reserved for the protection of fish and wildlife within the western near-shore portion of Central Biscayne Bay, engaged in rule development, and adopted the Nearshore Central Biscayne Bay reservation rule and associated implementation rules. (Exhibit C)

The location of the Nearshore Central Biscayne Bay as well as the associated; Project canal system is depicted in Figure 3-1 of the attached and incorporated Exhibit C.

16. The determination of the amo.unt of water needed for protection of fish and wildlife in the Nearshore Central Biscayne Bay reservation rule is based on meeting a year-round salinity target for the nearshore area of central Biscayne Bay of 20 (practical salinity scale) given in the PIR. More detailed analyses were performed to determine the locations and quantities of surface water for the reservation rules. This information is contained in the District's Technical Document to Support a Water Reservation Rule 5

for the Comprehensive Everg1ades Restoration Plan Biscayne Bay Coastal Wetlands Project (July 2013).

17. Rule 40E-1 0.061, Florida Administrative Code, is the water reservation rule for the Nearshore Central Biscayne Bay. Pursuant to this rule, surface water flowing into the Nearshore Central Biscayne Bay, as derived from various and listed contributing canal reaches, is reserved from allocation. Figure 3-4A depicts surface water flow from the C-102 + Military+ C-103 Canal through S-21A + S-20G + S*20F into Biscayne Bay during the Wet Season and is the relevant reservation for this Order; the reserved Target Flow to the Bay is 504 acre-ft I day or 254 cubic feet per second (cfs).
18. On August 27, 2014, FPL requested the District issue an Emergency Order for temporary authorization to utilize the District's right of way and to divert and use water, above that reserved in Rule 40E-10.061, F.A.C., from the L-31E Canal System to help moderate unusually high temperatures and salinity that are occurring in the CCS. A copy of FPL's request and related correspondence between FPL and the Nuclear Regulatory Commission is attached and incorporated as Composite Exhibit D.

In summary, FPL seeks to divert water that is available, above the water reserved by Rule 40E-10.061, F.A.C., which would otherwise be discharged to tide via the S-20F,S-20G and S-21A coastal structures. District staff reviewed and considered FPL's request, the District's right of way, the infrastructure proposal, historic data, District statutory authorizations and rules, and the potential water availability and provided input to the District's Executive Director.

6

19. In support of their emergency authorization request, FPL provided the following information which is contained in Composite Exhibit D and summarized below:
a. United States Nuclear Regulatory Commission (NRC) Operating Licenses for Turkey Point and CCS Temperature Requirements: Turkey Point Power Plant Units 3 & 4 operate under a license from the Nuclear Regulatory Commission. The original operating license included a requirement that the maximum allowed CCS water temperature on the intake or inlet side of Units 3 &

4 cannot exceed 100°F. During July 2014, numerous factors contributed to higher than usual inlet temperatures in the CCS that approached 100°F. Also, during July- August, intake temperatures approached 102°F. After analysis, FPL requested and received temporary approval from the NRC to temporarily deviate from the water temperature requirement as is pursued a permanent change to the plant's operating license. In parallel, FPL submitted and received (August 8, 2014) approval for a License Amendment Request (LAR) that permanently increases the CCS intake water temperature limit from 100°F to 104°F. (Composite Exhibit D) This LAR is conditioned such that if the NRC license timit is exceeded and certain conditions met, both Turkey Point Units 3 and 4 will be required to commence shut down within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> which could impact grid reliability. If Units 3 and 4 were required to shut down, an important piece of FPL's power generation portfolio will not be available to meet the current and anticipated high electricity demand, potentially impacting electrical service to more than 2 million customer accounts in Miami-Dade and Broward Counties, including critical infrastructure.

7

b. CCS Temperatures and Record-Breaking Power Demand: Peak demaRd for electric generation in south Florida is directly related to high temperatures and humidity which generally occur in the summer and early fall.

Beginning in July 2014, Turkey Point's CCS experienced higher than usual temperatures as well as record breaking electricity demand. By the end of July, CCS Plant intake temperatures exceeded 100°F and have continued to exceed 100°F during afternoon peaks, recently reaching a high of 102°F, as depicted in Composite Exhibit D.

c. Factors Contributing to CCS Temperatures:* A number of factors are contributing to higher than usual temperatures in the CCS. These factors include: high summer temperatures; significantly less rainfall in the vicinity of Turkey Point, including rainfall at the CCS; elevated salinity; and an algae bloom.
i. Temperature Data: For the Miami-Dade and Broward areas, the average high in September is 89°F and in October it is 86°F. CCS temperatures exceeded 100°F during July and August, 2014.

ii. Rainfall, Evaporation, Salinity, and Seepage Data: FPL* reports typical annual rainfall at Turkey Point totals range between 50 inches to 75 inches. Normally, summer rainfall is effective in moderating the CCS water temperature and salinity, In 2013, the annual rainfall accumulation at Turkey Point measured at the CCS was less than 20 inches. As of the end of May, 2014, there had been less than 3 inches of rain at the rain station within the CCS.

Although additional rainfall has occurred in June and July, the 8

overall rainfall remains less than 26 inches at the CCS, compared to* 40 inches at the Miami Airport during the same timeframe .

. Moreover, FPL data indicates that the high evaporation, averaging 34 MGD, and losses to groundwater, averaging 12 MGD, have resulted in more water leaving the CCS than is being provided from the aquifer or rainfall and ultimately concentrating salinity in the CCS. FPL reports the CCS salinity has reached levels near 90 ppt, compared to historic levels of approximately 60 ppt.

iii. Algae Bloom: FPL indicates the above described conditions have allowed an algal bloom in the CCS to persist and affect Plant operations. The algae concentration, prior to treatments beginning

. mid-summer, was as high as 1.8 million cells per milliliter, far exceeding the historic average values of 50,000 cells per milliliter.

Recent FPL treatments have reduced the algae concentrations.

However, the turbidity associated with the algae bloom has caused u*nusual amounts of solar energy to be absorbed in the CCS, thereby Increasing CCS temperatures. FPL reports effective treatment of the algae will require the salinity to be reduced to bring the dead algae out of suspension, which is nec~ssary to reduce CCS temperatures and, thereby, restore the heat exchange capacity of the CCS. Detailed information concerning the CCS algae bloom are contained in Composite Exhibit 0, particularly the correspondence between FPL and the NRC.

9

d. FPL's Request for Temporary, Emergency WatE?r Supply: In summary, FPL requests an immediate, temporary emergency authorization kom the District to allow FPL to access the District's right of way, connect to the L-31 E canal, and conditionally withdraw stormwaier from the L-31E Canal, and convey this water to the CCS with above-ground piping. Composite Exhibit 0 contains the design details for FPL's request. FPL's proposed operational plan synchronizes the volumes and rates of its northern and southern pumping operations so as to avert dewatering of wetlands adjacent to the L-31E canal. A portion of the proposed Infrastructure involves temporary installation of pipes across wetlands.
20. Temporary installation of the pipes within wetlands, as shown in Exhibit D, will have only minimal or insignificant individual or cumulative adverse impacts on the water resources of the District. Based on the design proposed in Exhibit 0, FPL's proposed, temporary installation qualifies for an exemption from the requirement to obtain an environmental resource permit pursuant to subsection 373.406(6), Florida Statutes.
21. Water levels in the L-31 E Canal system, the proposed water supply source, are influenced by the operation of coastal canal structures. Operation of the S-20F, S-20G and S-21A are performed consistent with guidance from the United States Army Corps of Engineers regulation schedule and Master Water Control Manual, East Coast Canals, Volume 5. Under normal operating conditions for April 30- October 15 the S-20F, S-20G, and S-21A structures are operated in the "high range" meaning discharges to tide are conditionally made when stages upstream of the structure 10

including stages within the L-31 E Canal are 2.2 ft. NGVD or higher an.d the gates are closed when headwater stages drop to 1.8 ft NGVD.

22. Operational records of the District show combined average daily flow from the C-1 02, Military, C-1 03 canals through Structures S-21A, S-20G, and S-20F, respectively, into this portion of Biscayne Bay are 481 cfs during the month of August (1993 - 2013) and 620 cfs for the month of September (1993 - 2013), with daily combined flows ranging from 0 to more than 3,000 cfs during these months.
23. The combined reserved target flow for structures S-21A, S-20G, and S-20F is 254 cfs suggesting that there is a reasonable expectation that daily flows exceeding the reservation target flows will occur during the months of August and September.
24. Based on FPL's request and the above-described facts, the Executive Director of the District has considered this matter and finds that an emergency exists and the emergency measures proposed herein are necessary to protect the public health, safety or welfare.

ULTIMATE FACTS AND CONCLUSIONS OF LAW

25. Section 373.119(2), Fla. Stat., and Rule 28~106.501, Fla. Admin. Code, authorize the Executive Director of the District, in the event of an emergency requiring immediate action to protect the public health, safety or welfare, with the concurrence of the Governing Board, and without prior notice, to issue an order reciting the existence of such an emergency and requiring that such action be taken as deemed necessary.

Section 120.569, Florida Statutes, also authorizes issuance of emergency authorizations. Moreover, the District is authorized, in summary, to regulate 11.

connections and use of the District's rights of way, use of water, construction of new diversion facilities, initiation- of new water uses, diversion and withdrawal facilities pursuant to a variety of statutes. (e.g.: §§373.083, 373.085, 373.086, 373.1501, 373.171, 373.219, Florida Statutes) The proposed activities are exempt from the requirement to obtain an environmental resource permit pursuant to subsection 373.406(6), Florida Statutes.

26. As to right of way matters, Rules 40E-6.451 and 40E-6.481, Fla. Admin.

Code, further provide an emergency exists when immediate action is necessary to protect lives or property.

27. Pursuant to statutory authorizations, FPL's request and supporting documents, and the facts described herein, the Executive Director finds that an emergency exists requiring immediate action necessary to protect the public health, safety, or welfare. The Executive Director also finds the wetland impacts identified in Exhibit D and authorized by this Order qualify for a Section 373.406(6), Fla. Stat.,

exemption.

28. The action authorized by this_ Emergency Order is appropriate to address this emergency situation:
29. The L-31 E Canal system is part of the C&SF Project for which the District is the designated local sponsor pursuant to Section 373.1501, Fla. Stat. Pursuant to Sections 373.085 and 373.086, Fla. Stat., the District is authorized to operate the C&SF Project, including the S-20 Structure and the L-31 E Can~l system.

12

ORDER Based u~on the Findings of Fact, Ultimate Facts and Conclusions of Law, the Executive Director orders FPL is authorized to undertake the following, *temporary actions in accordance with the conditions stated herein:

30. Temgorary Utilization of District Right of Way:
a. Authorized Facilities and Installation: FPL is authorized to install the infrastructure depicted in Exhibit D on the District's L-31 E Canal right of way.

The design details, including facility description and location, authorized by this Order are contained in the attached and incorporated Exhibit D. To the extent the information contained in Exhibit D conflicts with the terms and conditions of this Emergency Order, this Emergency Order shall control. FPL shall install, operate, and maintain the temporary withdrawal facilities and associated equipment in accordance with this Order. Any deviations from the design schematics identified in Exhibit D shall be presented to the District for approval prior to installation of the modified design. These facilities are temporarily authorized for the purpose of diverting and use water from the L-31 E Canal system to help meet its cooling water needs pursuant to the following conditions.

b.* Right of Way Installation Conditions:

i. Installation
  • Coordination; Prior to commencement of construction or utilization of *the District's right of way and, again, upon completion of the installation of the authorized facilities, FPL is required to contact the District's Field Representative, Mike Worley of the District's Homestead Field Station, (954)410-7383, and schedule a pre-construction 13

meeting and final inspection. The District's Homestead Field Station Superintendent is authorized to make field changes to installations or operations described herein to better achieve the District's objectives; such changes shall be subsequently documented in writing and communicated by the District to FPL.

ii. Site Security: The pumps at both the north and south pumping sites shall be manned continuously throughout the entire time the pumps are deployed pursuant to this Order. The south pumping site shall be manned by a pump operator provided by the pump manufacturer.

iii. Right of Way Conditions: FPL is required to comply with all Right of Way conditions contained in the body of this Order and attached and incorporated Exhibit E.

31. Temporary Water Withdrawal Authorization:

a.. Authorization to Withdraw and Use Water. if available, from the L~

31 E Canal System:

i. Water Availability Restriction: FPL is prohibited from withdrawing and using water from the L~31 E Canal system that is reserved for fish and wildlife by Rule 40E-10.061, F.A.C., for the Nearshore Central Biscayne Bay. The only water available for the purpose of this Order is that water which would otherwise be discharged to tide from either the S-20F, S-20G, and S-21A struCtures and is in excess of the flows reserved for protection of fish and wildlife in Rule 40E-1 0.061, F.A.C. This available surface water may, temporarily, be withdrawn and used within FPL's 14

cooling canal system in accordance with the conditions as set forth herein.

Tl1ere are no assurances provided by this Order that water will be available for FPL's withdrawal and use on any given day.

ii. District's Daily Determination of Water Availability and FPL Pump Operation: On a daily basis, the District will determine the amount and timing that FPL may operate the pumps and facilities authorized herein to withdraw water from the L-31 E Canal system. Only when the combined flows to tide through coastal structures S~20F, S-20G, and Sw21A exceed 254 cfs will the District determine the amount and timing water available for a FPL pump operation. The rate and volume of a potential FPL withdrawal, if any, shall be determined by the District, no later than 10:00 a.m., each day and for the duration of this Order. The District's daily determination of water availability shall cover a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period and last until no later than 9:59a.m. the next day. In the event the District does not provide any written direction to FPL in accordance with t~is paragraph, then FPL shall cease all pumping until further notice.

iii. Communication of Water Availability Determination: The District's Operation Control Center will communicate its daily water availability determination to FPL by e-mail, to the FPL's designated contact(s): Matthew Raffenberg, or his designee, at Matthew.Raffenberg@fpl.com. The District's Operation Control Center may be contacted 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day, 7 days a week at: 561-682~6116 and 15

occ@sfwmd.gov.

  • FPL may not commence any daily withdrawal operations prior to this District communication confirming water availaiJility.

iv. Monitoring and .Reporting: FPL shall monitor and report the amount of water diverted from the L-31 E Canal system to its cooling canal system. When FPL withdraws water, then FPL must generate a daily report including the following detailed information: (1) the water availability determination for each day as provided by the District's Operational Control Center, (2) identification of which pump(s) were used over the course of the day; (3) time on and time off, per pump; (4) RPM setting, per pump, if variable; (5) calculated volume of water pumped, per pump; and (6) cumulative log flows at each pump station. fn addition, the report shall include hourly stage data for the L-31 E Canal measured at TPSW~1 and TPSW~2 for the weekly reporting period, whether or not the pumps operated. Water quality grab samples consisting of conductivity, turbidity, total kjedahl nitrogen, nitrate nitrite as N, phosphorus, ortho phosphorus, ammonia, and TRPH (total recoverable peteroleum hydrocarbons, also known as Florida Petroleum Residual Organic or "FL-PRO") shall be collected prior to initiation of pumping pursuant to this Order and once a week thereafter for the duration of this Order. These samples shall be collected at TPSW-1 and TPSW-2. FPL shall make the sampling logs. and lab reports available upon request. The report shaH*

reference this Order and be submitted by noon, Tuesday of each week for all withdrawals occurring during the preceding week. (The preceding week 16

-reporting period is considered Monday at 1:00 a.m. through Sunday midnight.) The- report shall be e-mailed to both the District's Assistant Executive Director, Len Lindahl at llindahl@sfwmd.gov and Terrie Bates, Division Director - Water Resources, at tbates@sfwmd.gov. Upon Executive review of the weekly report, conference calls may be required.

Additionally, the District may request available monitoring data at any time and FPL shall provide the same within two hours of the District's request.

v. Special Pump Station Criteria:

(a) The District may require FPL to terminate pumping at any time. Upon receipt of any oral or written request from the District to terminate pumping, FPL must cease pumping within two (2) hours.

(b) FPL shall wirelessly coordinate the pumping at both stations to assure that, from a non-flow condition, the north station pumps shall be started first The south station pumps shall be started within 5 minutes of the north station pumps start, with an equivalent flow. Similarly, when pump operation ceases, the south station pumps shall cease first and the north station pumps shall cease within 5 minutes.

vi. Pump Requirements:

(a) Pump On I Off Switches: Each pump authorized pursuant to this Order shall be equipped with an operable, 17

remote .pump operational device prior to initiating pump operations.

(b) Pump discharge curves:- Pump discharge curves used in determining rates of discharge while pumps are operating, as deployed in the field, shall be provided to the District prior to pump operation for the purpose of calculating flow rates and volumes.

(c) Totalizing Hour Meters: FPL shall install totalizing hour meters at each pump authorized by this Order and such meters shall be available for periodic District inspection and verification.

32. Section 373.406(6), F.S., Exemption Conditions:
a. No permanent fill shall be placed in the wetland area described in Exhibit D.
b. All activities which qualify for the subject exemption shall be conducted and operated using appropriate best management practices and in a manner which does not cause a violation of water quality standards, pursuant to Chapter 62-302, Florida Administrative Code.
c. The District's determination that the proposed temporary placement of pipes, pymps, and associated infrastructure qualifies as an exempt activity may be revoked if the installation is substantially modified from that described in Exhibit D, if the basis for the exemption is determined to be materially incorrect, or if the installation results in violation of state water quality standards. Any 18

changE;}s made in the construction plans or location of the project may necessitate a permit from the District. Therefore, FPL is advised to contact the District before beginning any work in wetlands or surface waters which is not specifically described in Exhibit D.

d. Upon termination of this Order, all pipes, mats, other materials and equipment shall immediately be removed from the wetland to allow the wetland vegetation to recover.
33. Immediate Facility Removal and Reinstallation:
a. Prior to a Storm Event: FPL shall remove the temporary withdrawal facilities authorized by this Order located within the District's right of way within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of receipt of notice from the District. The temporary withdrawal facilities should be maintained and secured so as to not impede the District's ability to make flood control releases in advance of a storm event.
b. After a Severe Storm Event: FPL shall notify the District of its intent to reinstall the temporary withdrawal facilities in the District's right-of-way at least three (3) business days before such reinstallation is scheduled to occur.
34. All documents, plans, and reports required by this Order shall be submitted to Len Lindahl via email at llindahl@sfwmd.gov and Terrie Bates via email at tbates@sfwmd.gov.
35. Miscellaneous Conditions:*
a. This Order authorizes FPL to take actions under Chapter 373, Fla.

Stat., as provided herein. This Order does not relieve FPL from the requirements to obtain any other federal, state, or local authorizations.

19

b. This Order does not constitute a-water use or right-of~way permit or grant any legal right to water as set forth in Chapter 373 Fla. Stat., and associated District rules and regulations over the water intercepted and stored under this Order.
c. This Order does not convey any property right to FPL, nor any rights and privileges other than those specified in this Order. This Order shall not be construed as an abandonment or any other such impairment or disposition of the District's property rights.
d. This Order shall not be construed as a substitute for, or waiver of, any right-of-way, surface water management, water use, or other permits required of FPL under the District's rules and regulations.
e. FPL shall insure that harmful impacts to the water resources, off-site land uses, or existing legal uses of water do not occur as a result of this Order. In the event such harmful impacts result from actions authorized by this Order, FPL shall implement all actions, as directed by the District, to cease. such harmful impacts and, if necessary, to mitigate such impacts. Failure to comply with this requirement shall be considered a violation of this Order.
f. Failure to comply with the terms of this Order shall constitute a violation of a District Order under Chapter 373, Fla. Stat., and enforcement proceedings may be brought in any appropriate administrative or judicial forum.
g. The District reserves the right to initiate appropriate legal action, to impose civil penalties, and collect attorney's fees and costs to enforce the terms of this Order.

20

h. This Order may be modified or amended at any time, as appropriate for the protection of the public health, safety, and welfare and the water resources of south Florida by the Governing Board, Executive Director, or Executive Director's designee.
i. The Executive Director or Executive Director's designee may require FPL to remove all or part of the authorized facilities and cease withdrawal and I or use activities under this Order at any time.
j. The District's immunity from liability under Section 373.443, Florida Statutes, for any damages that might result from the activities authorized under this Order, shall not be diminished by the terms of this Order, or any activities taken pursuant to this Order.
k. Failure to comply with 1he conditions contained within this Order shall constitute a violation of a District Order under Chapter 373, Florida Statutes, and enforcement proceedings may be brought in any appropriate administrative or judicial forum.

I. If the District petitions or sues for enforcement of the terms of this Order, the District reserves the right to initiate appropriate legal action, to impose civil penalties and collect attorney's fees and costs.

36. Termination: This Order shall terminate on the earliest of: (1) failure to receive Governing Board concurrence at their next regularly scheduled meeting, (2)

October 15, 2014, or (3) at any time upon written notice from the District's Executive Director or the Executive Director's designee.

21

37. Required Facility Removal: Within 30 days of termination of this Order, FPL shall remove all temporary withdrawal facilities and associated infrastructure authorized by this Order, inoludin.g the pipes buried under 344th Avenue. Moreover, FPL shall properly restore the right-of~way to the District's satisfaction. In the event of failure to so comply within the specified time, the District may remove the temporary withdrawal facilities and associated infrastructure authorized by this Order and associated equipment and FPL shall be responsible for all removal and restoration costs.
38. A Notice of Ri_ghts attached hereto as Exhibit F.
39. This Order shall take effect upon execution by the Executive Director of the District and shall expire as provided herein. This Order is subject to the Governing Board's concurrence at its next regularly scheduled Governing Board meeting.

DONE AND SO ORDERED in West Palm Beach, Florida, on this 28th day of August, 2014.

SOUTH FLORIDA WATER MANAGEMENT DISTRICT By its Executive Director Blake C. Guillory,,£:.~

Executive Director Legal Form Approved:

f:Kl .&~ cr~~

Elizabeth D. Ross, Esq.

22

A'fTACIIM1£NT B fef>NS1'RtTCTION JI)RA,WENGS

Temporary Cooling Canal Wetland ID Habitat Type Acreage Augmentation Pipeline & Equipment HW 510- Canal 0.04 f:Z2J Area of Temporary Wetland Impact p 612 - Mangro\.e Swamps 0.32 PROJECT 510- Canal 0.04 FPL TURKEY POINT R 641 - Frestwtater Marshes 0.03 COOLING CANAL 6411- Marsh Smvgrass 0.02 FRESHWATER RECHARGE Grand Total 0.45 TITLE PROJECT OVERVIEW MAP NOTES PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING CONSULTANT YYYY-MM-DD 2015-01-20 TRANSMITTED FOR AG ENCY REVIEW PREPARED NRL

'SEE ATTAC HED SHEETS FOR DETAIL DESIGN NRL REFERENCE ( j tGolder

Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 AP PROVED KAB TEMPORARY WETLAND IMPACTS, GOLDER ASSOC IATES INC., 2014 PROJECT CONTROL Rev. FIGURE 1412354 001 0 1

I I

I I

I (ii u

c Ill I

I D Intake Pipes w

~

<')

~

I I

o-------- Powerpak (TYP)

I I

I I

I Wetland HW-510 0.04Acres~ I D I I

0 I \

I \

Wetland R-641 /

0.03 Acres /

/

/

/

/

Wetland R-510 I

0.02Acres

(

Discharge I Pipes I I

(ii c I u

Ill I <

~

w

~

<') I  :!

~

~ 0 u I 0

"',0

~

~ I 0

!* 20 40 I m

~

~

  • 0

§ ~~5iiiiiiil

~ ~1~:4llB~O~________JF~e~eLI____________-=~~-=~==~~::~~---=:::=:::::::::::=:==:=:::::::::::::::::::::::::=::::::::j

~ LEGEND TABLE 1- TEMPORARY WETLAND CLIENT -

<o, IMPACT ACREAGE FPL ~,

Temporary Cooling Canal *

~ - - - Augmentation Pipeline & ~

, Equipment

~_.~ L_l Wetland Line PROJECT ~~*

~ FPL TURKEY POINT ~

~ [::::_~] Area of Temporary Disturbance COOLING CANAL ~

~ ffiEII Limits of Temporary Construction FRESHWATER RECHARGE ~

~o:. rz:zJ Area Matting ofTemporary Wetland T INITLTEAKE SYSTEM ~_.~,

!, NOTE;pact TEMPORARY WETLAND IMPACTS ~

~<

PRELIMINARY DRAWI NGS: THESE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING TRANSMITTED FOR AGENCY REVIEW CONSULTANT YYYY*MM-DD 2015-01-21 ~£ t

~

.: REFERENCE

(!~Golder PREPARED DESIGN NRL NRL

' Associates REVIEW KAB

~~ PIPELINE ROUTE , TAYLOR ENGINEERING INC., 2014 TEMPORARY WETLAND IMPACTS, GOLDER ASSOCIATES INC., 2014 APPROVED KAB FIGURE (j PROJECT CON TR OL Rev.

1412354 002 0 2

I I

I I

I I

I I

I I

I I

I Wetland R-510 0.02Acres Gvetland R-6411

!!/

I I

< 0.001 Acres I

I --* \

\

I Modular Work Platform )J I

I \

(Typical Each Side of Pump/'

\

--, \

"' \"

\

\

I I

I I

I I

I I Wetlal/d R-6411 I

o.opAcres I

I I I I 20 40 \

.1 I I I l!!!!!!!!!!!!li~!!!liiiiiiiiil )

I I I I TABLE 1 -TEMPORARY WETLAND CLIENT IMPACT ACREAGE Temporary Cooling Canal FPL Wetland ID Habitat Type Acreage

- - Augmentation Pipeline &

HW 510- Canal 0.04 Equipment p 612- Mangro"' Swamps 0.32 L_l Wetland Line 510- Canal PROJECT 0.04 FPL TURKEY POINT

[=~J Area ofTemporary Disturbance R 641 - Freshwater Marshes 0.03 COOLING CANAL EEEBJ Limits of Temporary Construction 6411 -Marsh Sawgra ss 0.02 FRESHWATER RECHARGE Matting Grand Total 0.45 TITLE r::zzJ Area of Temporary Wetland DISHCARGE SYSTEM Impact TEMPORARY WETLAND IMPACTS NOTES PRELIMINA RY DRAWINGS: THE SE DRAWI NGS ARE NOT FINAL FORM , BUT ARE BEING CONSULTANT YYYY-MM- DD 2015-01 -2 1 TRANSMITTED FOR AGENCY REVIEW PREPARED NRL DESIGN NRL REFERENCE REVIEW KAB PIPELINE ROUTE. TAYLOR ENGINEERING INC., 2014 APPROVE D KAB TEMPO RARY WETLAND IMPACTS, GOLDER ASSOCIATE S INC., 2014 PROJECT CONTROL Rev. FI GURE 1412354 002 0 3

~Edge of Wetland I

i I

I I

I I .----'

i I I _ " \." r Edge of Wetland Wetlald R-6411 "'-/ ~ Wetland P-612 o.f Acres 0.04Acres Wetland P-612 I 0.28Acres i

I I

I I

I I

20 40 TABLE 1. TEMPORARY WETLAND IMPACT ACREAGE Temporary Cooling Canal Wetland ID Habitat Type Acreage

- - Augmentation Pipeline &

HW 510- Canal 0.04 Equipment p 612- Mangro\e Swamps 0.32 L_l Wetland Line PROJECT 510- Canal 0.04 FPL TURKEY POINT

[::::_~] Area ofTemporary Disturbance R 641 -Freshwater Marshes 0.03 COOLING CANAL H.:J:Ill Limits of Temporary Construction 6411 -Marsh Sawgrass 0.02 FRESHWATER RECHARGE Matting Grand Total 0.45 TITLE

[ZZJ Area of Temporary Wetland DISHCARGE SYSTEM Impact TEMPORARY WETLAND IMPACTS NOTES PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM , BUT ARE BEING CONSU LTANT YYYY-MM-DD 2015-01-21 TRANSMITTED FOR AGENCY REVIEW PREPARED NRL DESIGN NRL REFERENCE { f tGolder PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 Associates REVIEW KAB APPROVED KAB TEMPORARY WETLAND IMPACTS, GOLDER ASSOCIATES INC. , 2014 PROJECT CONTROL Rev. FIGURE

~ 1412354 002 0 4

~ L_--------------------------------------------------------------------------~0

Edge of Wetland Wetland P-612 f 0.04Acres Wetland P-612 0.04Acres Edge of Wetland Wetland P-612 0.28Acres Wetland ID Habitat Type Acrea ge HW 510 - Canal 0.04 p 612- Mangro\e Swamps 0.32 PROJECT 510- Canal 0.04 FPL TURKEY POINT

[=~J Area o fTempora ry Disturbance R 641 - Freshwater Marshes 0.03 COOLING CANAL lffiJI Limits of Temp orary Construc tion 6411 - Marsh Sawgrass 0.02 FRESHWATER RECHARGE Matting Grand Total 0.45 TITLE IZZl Area Impact o fTemporary Weiland DISHCARGE SYSTEM TEMPORARY WETLAND IMPACTS NOTES PRELIMINARY DRAWINGS: THE SE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING CONSULTANT YYYY-MM-DD 2015-01-21 TRANSM ITTED FOR AGENCY REVIEW PREPARED NRL DESIGN NRL REFERENCE ( j t Golder Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 APPROVED KAB TEMPORARY WETLAN D IMPACTS, GOLDER ASSOCIATES INC., 2014

I I

I I

Wetland P-612 I

0.04Acres I I

I I

I I

I

--- J Edge of Wetland

--~

--~

--~

'--.._1 I

i I

I I

i Wetland ID Habitat Type Acreage HW 510- Canal 0.04 p 612- Mangrow Swamps 0.32 PROJECT 510- Canal 0.04 FPL TURKEY POINT

[=~J Area ofTemporary Disturbance R 641 - Freshwater Marshes 0.03 COOLING CANAL tEBJI Limits of Temporary Construc tio n 6411 -Marsh Sawgrass 0.02 FRESHWATER RECHARGE Mailing Grand Total 0.45 TITLE

[ZZJ Area of Temporary Weiland DISHCARGE SYSTEM Impact TEMPORARY WETLAND IMPACTS NOTES PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM , BUT ARE BEING CONSULTANT YYYY-MM-DD 2015-01-21 T RANSM ITTED FOR AGENCY REVIEW PREPARED

(!/~Golder NRL DESIGN NRL REFERENCE Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 APPROVED KAB TEMP ORARY WETLAND IMPACTS, GOLDER ASSOCIATES INC., 2014

/ I I I I I i I I I I I I I I I of Wetland I I I I I I I I

-~ . . . . . '"'-. . I' I

-~-

---,_ I I

-~

"---, I

.............. ~:.......... _, ./

- ~--, ""-.................

I

... '"' .... t-....


~--

I -~-,---------~ /;;Freshwater Discharge Location I I -~ ...

i -~---~-------,_ Jl ~ I; I -....;,;-......_ I I I ---- -, I I I II ---..._,

. . __""""Il I

I I I I l I i I I I I I I I I I I I

~

I

'g

~ I

  • o 20 4o I I

~l!!!!!!!!liiiiiiiiiiiiiil!!!!!!liiiiiiiiiiii I ii~~1~:4ll8~0~--------lF~e~eLt LEGEND ____~-------=~~-=~==~~::~~---=~====================================================:~

TABLE1 - TEMPORARYWETLAND CLIENT z g1 IMPACT ACREAGE FPL @

r;;. Temporary Cooling Canal Wetland ID Habitat Type Acreage ~'

~=; - - Augmentation Pipeline &

HW 510- Canal 0.04

Equipment p 612 - Mangro.e Swamps 0.32

~ L_l Wetland Line PROJECT 510- Canal 0.04 FPL TURKEY POINT i EEEEII

~

[=~J Area ofTemporary Disturbance Limits of Temporary Construction Matting R 641- Freshwater Marshes 6411- Marsh Sawgrass 0.03 0.02 COOLING CANAL FRESHWATER RECHARGE

] TITLE Grand Total 0.45

~

..u, [ZZJ 8

g Area of Temporary Wetland Impact DISHCARGE SYSTEM TEMPORARY WETLAND IMPACTS NOTES

~ PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING CONSULTANT YYYY-MM- DD 2015-01-21 i TRA NSMITTED FOR AGENCY REVIEW

~

PREPARED NRL

"' REF ERENCE DESI GN NRL

~ ( J t Golder

"~ Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 A PPROV ED KAB TEMPORARY WIETLAND IMPACTS, GOLDER ASSOCIATES INC., 2014

~ PROJECT CON TROL Rev. FIG URE

~ 1412354 002 0 7

~ L-----------------------------------------------------------------~

ATTACHMENT C WATER USE PED'.MIT JUPJLICA'Fl!ON

WATER USE PERMIT APPLICATION South Florida Water Management District P.O . Box 24680, West Palm Beach, Florida 33416-4680 (561) 686-8800 www.sfwmd .gov/ePermitting SECTION 1- CONTACT INFORMATION WATER USE PERMIT# (if application is for renewal or modification):

If necessary, attach additional sheets if there are multiple applicants, owners, agents, etc.

1. APPLICANT (Complete legal name in which permit should be issued)

NAME: Florida Power & Light Company If applicant is a business, provide a contact person:_M_a_tt_h_e_w_R_a_ff_e_n_b_e--'rg:;.___ _ _ _ _ __

ADDRESS: 700 Universe Boulevard CITY, STATE , ZIP: Juno Beach, Florida 33408 PHONE: ( 561 ) 691-2808 CELL PHONE: ( 561 ) 573-5888 EMAIL ADDRESS: Matthew.Raffenberg@fpl.com Applicant is: liD Owner 0 Lessee* 0 Other (explain) _ _ _ _ _ _ _ _ _ _ __

  • Attach copy of current lease, or written authorization from property owner
2. OWNER (If different than applicant)

NAME: same as above ADDRESS: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ____

CITY, STATE, Z I P : - - - - - - - - - - - - - - - - - - - - - - - - -

PHONE:(_ ___, _ _ _ _ _ __ CELL PHONE: (_ _ _) - - - - - - - -

EMAIL ADDRESS:

3. AGENT OR CONSULTANT NAME:Karl Bullock COMPANY NAME (if applicable): Golder Associates Inc.

ADDRESS: 6026 NW 1st Place CITY, STATE, ZIP: Gainesville, Florida 32607 PHONE: ( 352 ) 336-5600 CELL PHONE: ( 352 ) -=2=22=--=69:::...:6::....:1~-----

EMAIL ADDRESS: Karl Bullock@golder.com

4. COMPLIANCE CONTACT (Person responsible for sending compliance reports to the District)

NAME:Stacy Foster ADDRESS: 700 Universe Boulevard CITY, STATE, ZIP: Juno Beach, Florida 33408 PHONE: ( 561 ) 691-7065 CELL PHONE: ( 772 ) _2_85_-_56_5_3_ _ __

EMAIL ADDRESS: Stacy.Foster@fpl.com Page 1 of 10 Incorporated by reference in rule 40E-2 .101 (F.A.C.)

Form 1379 (2014-07)

SECTION II- APPLICATION INFORMATION Refer to the Applicant's Handbook for permit application guidance, located online at www.sfwmd .gov. If any fields are not applicable for the proposed use, write N/A in the field.

1. TYPE OF APPLICATION: IZI New 0 Modification 0 Renewal If this application is for a modification, please describe the modification request and the reason the modification is n e c e s s a r y . - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2. REQUESTED PERMIT DURATION: liD 20 years 0 __ years (up to 20 years) 0 I qualify for a duration greater than 20 years, per Florida Statute 373.236 Turkey Point Cooling Canal
3. PROJECT NAME: Augmentation COUNTY: _M_ia_m_i-_D_a_d_e_ _ _ _ __

L31 E Canal North Intake (approximate)- 25°26'53. 78" N, 80°20'59.51" W PHYSICAL ADDRESS: L31E Canal South Intake (approximate) - 25°26'04.84" N, 80°21'09.76" W 4 . RELATED PERMITS (for projects other than Public Supply) 0 ENVIRONMENTAL RESOURCE PERMIT (ERP) PERMIT/APPLICATION No(s):N/A- EO No. 2014-078-DAO-WU/ROW/ERP 0 RIGHT OF WAY (ROW) Permit/Application No(s): N/A- EO No. 2014-078-DAO-WU/ROW/ERP 0 DIVERSION AND IMPOUNDMENT (0&1) Permit/Application No(s): N/A- EO No. 2014-078-DAO-WU/ROW/ERP SECTION Ill - USE CATEGORY Please check all applicable water use categories associated with this permit application and complete the associated supplemental form(s) indicated. Refer to District rules 40E-21.651for water use type definitions.

Supplemental Water Use Category Form 0 Agricultural (e.g., crops, livestock, nursery, aquaculture, pasture) FormA 0 Commercial/Industrial (e.g., service business, food and beverage production , cooling and heating, commercial attraction, manufacturing, chemical processing, power generation, aquifer Form B remediation , mining) 0 Landscape I Recreation (e.g., irrigation of parks, cemeteries, landscaped areas, golf Form C courses, athletic fields, playgrounds) 0 Dewatering (e.g., water use or removal associated with construction or excavation) Form D 0 Public Supply (e.g. , public or privately owned water utility) FormE

~ Diversion and Impoundment (diversion or extraction of water) . Independent Secondary Form F users should use the applicable supplemental form based on type of water use.

Page 2 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C .)

Form 1379 (2014-07)

SECTION IV- SOURCES OF WATER

SUMMARY

OF GROUNDWATER {WELL) FACILITIES Well Name or Number N/A Map Designation Existing or Proposed Date of Proposed Construction Date Installed if Existing Diameter (in)

Total Depth (ft)

Cased Depth (ft)

Screened Interval (ft)

Pumped or Flowing Pump Type (see Instructions)

Pump Intake Depth (ft bls)

Pump or Flow Capacity (GPM)

Working Valve if Artesian (yes, no or not applicable)

Status (see Instructions)

Purpose (see Instructions)

Elevation of the Wellhead (ft NGVD - see Instructions)

Water Use Accounting Method (see Instructions)

Date Last Calibrated (ATTACH calibration report)

Planar Coordinates (if known - see instructions)

Section I Township I Range Page 3 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

Instruction for Completing Groundwater (Wells) Section Well Name or Number: The Applicant's designation of the well. How do you refer to it?

Map Designation: This is how the well is labeled on the map submitted with the application. This may be the same as Well Name or Number, but does not necessarily have to be.

Existing or Proposed: If the well is proposed, enter the date of expected operation. If it is an existing well, enter the date it was installed if you know it.

Diameter: Outside diameter of the well casing.

Total Depth: Total length in feet between the land surface and the bottom of the well.

Cased Depth: The length in feet from the land surface to the bottom of the well casing.

Screened Interval: The distance in feet below land surface to the top and bottom of the well screen, if the well is so equipped.

Pumped or Flowing: Does the well produce water as a result of natural artesian flow, or is it pumped?

Pump Type: This is the type of pump that has been installed for the well (typical choices are as follows):

Centrifugal Diesel turbine Axial flow Windmill Submersible Jet Suction Other (specify)

Electric turbine Hydraulic Portable Pump Intake Depth: Location of the pump depth in feet below land surface. The pump may be on the surface or down inside the well.

Pump or Flow Capacity: The amount of water the pump can produce in gallons per minute (GPM).

Working Valve: If the well is artesian, does it have a working valve to control the flow?

Status: Primary Secondary (i.e. a production well that is rotated)

Standby (i.e. used for freeze protection or emergency)

Monitor Injection (i.e. A/C, pool heat exchange, etc.; sometimes used only periodically)

Recharge (i.e. same as above)

Purpose:

What will the water be used for (typical choices are as follows):

Dairy Irrigation Air Conditioning Swimming Pool Heating Monitor Aquaculture Freeze Protection Irrigation/Lake Recharge Livestock Bottled Water Mining/Dewatering Aquifer Storage and Recovery Industrial Other (specify) Public Water Supply Aquifer Remediation and Recovery Elevation of the Wellhead: This is the elevation of the top of the finished well at the ground surface.

Planar coordinates: The Florida State Plane System (Planar Coordinates) should be submitted if you have a land survey which identifies the location of the well in terms of those measurements. If you do not know what these are, it is not necessary to include them.

Section I Township I Range: The section, township and range in which the pump is located.

Page 4 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SUMMARY

OF SURFACE WATER (PUMP) FACILITIES Pump Name or Number Map Designation L31E Canal N 31E Canal N L31E Canal N L31E CanalS Surface Water Source Local Drainage District Unknown !Unknown Unknown Unknown (if applicable)

Existing or Proposed Existing Existing Existing Existing Date of Proposed N/A J'j/A N/A N/A Installation Date Installed if Existing Model -Godwin Model- Godwin Model - Godwin Model - Rain For Rent Pump type -specifications attached HAF 30AX HAF30AX HAF 30AX FP900 (for list see Instructions) Type- 1\)<iai/Diesel Type- !l)(iaiDiesel Type- !l)(iaiDiesel Type- !l)(iaiDiesel 125,500 GPM 25,500 GPM 25,500 GPM ~8,500 GPM Pump Capacity (GPM)

Pump Horsepower t?38 hp 238 hp 238 hp Unknown po in. 30 in. 30 1n. 36 in.

Pump Diameter (inches)

Pump Intake Elevation 7ft. 7ft. 7ft. 4ft.

{feet NG}JQ} (feet NAVD)

!Primary Primary Primary Primary Status (see Instructions)

Pther- !Other- Other- Pther-Purpose (see Instructions) ft\ugmentation ~ugmentation ~ugmentation fi\ugmentation Two way pump? No No No No (yes I no)

Water Use Accounting Method otalizing rr otalizing rr otalizing Totalizing (see Instructions) Meter Meter Meter Meter Date Last Calibrated (ATTACH calibration report)

Planar Coordinates ilJnknown Unknown ~nknown Unknown (if known -see instructions) 129/57S/40E 29/57S/40E j29/57S/40E 29/57S/40E Section I Township I Range Page 5 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

Instructions for Completing Surface Water (Pumps) Section Pump Name or Number: The Applicant's designation of the pump. How do you would refer to it?

Map Designation: This is how the pump is labeled on the map submitted with the application. This may be the same as Pump Name or Number, but does not necessarily have to be.

Surface Water Source: This is the name of the water body from which the pump withdraws water (e.g.

SFWMD C-51, Lake Worth Drainage District Canal E-3, Un-named canal, onsite lake).

Local Drainage District: If the project is located in a local drainage or "298" district, such as Lake Worth Drainage District, Indian Trails Water Control District, etc., please identify it.

Existing or Proposed: If the pump is proposed enter the date of expected operation. If it is an existing pump, enter the date it was installed if you know it.

Pump Type: Typical choices are:

Centrifugal Diesel Turbine Axial Flow Submersible Suction Electric turbine Hydraulic Other (specify)

Pump Capacity: The amount of water the pump can produce in gallons per minute (GPM).

Pump Horsepower: Horsepower rating of the pump.

Pump Diameter: Size of the intake opening of the pump, in inches.

Pump Intake Elevation: The elevation from which the pump can produce water without cavitating.

Status: Primary Secondary (i.e. a production pump that is rotated)

Standby (i.e. used for freeze protection or emergency)

Purpose:

What will the water be used for (typical choices are as follows):

Dairy Irrigation Air Conditioning Swimming Pool Heating Aquaculture Freeze Protection Irrigation/Lake Recharge Mining/Dewatering Livestock Industrial Aquifer Storage and Recovery Aquifer Remediation and Recovery Other (specify)

Two way pump: Can the pump be used for both intake of irrigation water and discharge of storm water?

Flow Measurement Method: Describe how the amount of water produced by the pump will be measured as per Section 4.1.1. of the Applicant's Handbook.

Date Last Calibrated: When was the flow measurement method last calibrated? ATTACH the calibration report.

Planar coordinates: The Florida State Plane System (Planar Coordinates) should be submitted if you have a land survey which identifies the location of the pump in terms of those measurements. If you do not know what these are, it is not necessary to include them.

Section I Township I Range: The section, township and range in which the pump is located.

Page 6 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SUMMARY

OF SURFACE WATER (CULVERT) FACILITIES N/A Culvert Name or Number Map Designation Surface Water Source Local Drainage District

{if applicable)

Existing or Proposed Date of Proposed Construction Date installed if Existing Culvert type

{for list see Instructions)

Culvert length {Feet)

Culvert Cross-section Culvert Diameter {inches)

Culvert Height {inches)

Culvert Width {inches)

Invert Elevation {Feet NGVD)

Type of Control Device

{for list see Instructions)

Status

{see Instructions)

Purpose {see Instructions)

Two way culvert?

{yes I no)

Water Use Accounting Method

{see Instructions)

Date Last Calibrated {if known)

Planar Coordinates

{if known -see instructions)

Section I Township I Range Page 7 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

Instructions for Completing Surface Water (Culverts) Section Culvert Name or Number: The Applicant's designation of the culvert. How do you refer to it?

Map Designation: This is how the culvert is labeled on the map submitted with the application. This may be the same as Culvert Name or Number, but does not necessarily have to be.

Surface Water Source: This is the name of the water body from which the culvert withdraws water (e.g.

SFWMD C-51, Lake Worth Drainage District Canal E-3, Un-named canal, onsite lake).

Local Drainage District: If the project is located in a local drainage or "298" district, such as Lake Worth Drainage District, Indian Trails Water Control District, etc., please identify it.

Existing or Proposed: If the culvert is proposed enter the date of expected operation. If existing, enter the date it was installed (if known).

Culvert Type: Corrugated; Metal pipe; Reinforced concrete pipe; Steel pipe Culvert Length: Distance between the ends of the culvert in feet.

Culvert Cross-section: Is the culvert round, elliptical, rectangular, or other?

Culvert Diameter: If the culvert is round, the inside diameter of the culvert, in inches.

Culvert Height: If the culvert is not round, the inside height of the culvert, in inches.

Culvert Width: If the culvert is not round, the inside width of the culvert, in inches.

Invert Elevation: The lowest elevation, referenced to NGVD, at which water will flow through the culvert.

Type of Control Device: What controls the flow of water through the culvert (typical choices are):

Control gate; Flap gate; Flashboard riser; Gated riser; Screw gate; Slide gate; Valve; Other (specify)

Status: Primary; Secondary (i.e. a production pump that is rotated); Standby (i.e. used for freeze protection/

emergency)

Purpose:

What will the water be used for (typical choices are as follows):

Dairy Irrigation Aquaculture Freeze Protection Mining/Dewatering Livestock Industrial Irrigation/Lake Recharge Other (specify)

Two way culvert: Can the culvert be used for both intake of irrigation water and discharge of storm water?

Flow Measurement Method: Describe how the amount of water produced by the pump will be measured as per Section 4.1.1. of the Applicant's Handbook.

Date Last Calibrated: When was the flow measurement method last calibrated? ATTACH the calibration report.

Planar coordinates: The Florida State Plane System (Planar Coordinates) should be submitted if you have a land survey which identifies the location of the culvert in terms of those measurements. If you do not know what these are, it is not necessary to include them.

Section I Township I Range: The section, township and range in which the culvert is located.

Page 8 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SECTION V- EVALUATION OF RECLAIMED WATER FEASIBILITY The applicant is required to evaluate the feasibility of utilizing reclaimed water. The feasibility analysis must be completed as outlined in the Applicant's Handbook, subsection 2.2.4.

0 Feasibility analysis attached IZI Not applicable (i.e. no lines in area, crop type restriction, already using reclaimed)

Explanation: No lines in area.

SECTION VI -

SUMMARY

OF REQUESTED WATER USE Total the requested water use from each supplemental form (Agricultural, Irrigation, Commercial I Industrial, Public Water Supply, etc.) in the table below. If the multiple sources add up to more than 100%,

please attach an operating plan with a detailed explanation.

Requested Amounts and Source(s) of Water 1

Source 1 Name Source 2 Name Source 3 Name Source 4 Name Total Requested L-31E Canal Water Use (MGY 2 /MGM ~) (MGY 2/MGM~) (MGY 2/MGM ~) 2 (MGY /MGM 3

)

2 (MGY /MGM )

3 Max. Avail. 1Max. Avail. I I I I Provide the name of the water source. Examples include the Upper Flondan aqu1fer and the Biscayne aqu1fer.

2 MGY =Million gallons per year of water to be withdrawn over a 12-month time period under a 1-in-1 0 year drought condition (i.e. 1,500,000 gallons each day/1 ,000,000 =1.5 x 365 =547.5).

3 MGM =Maximum million gallons per month of water to be withdrawn in any single month under the 1-in-1 0 year drought condition .

SECTION VII - AQUIFER STORAGE AND RECOVERY (complete if applicable)

Source of Recovery Estimated Demand Estimated Injected ASR Facility Name Stored Water 1 Storage Aquifer Water Average/Maximum Average/Maximum Name Destination (MGD) (MGD)

N/A I I I I I I I I Aqu1fer Name, surface water body, water treatment plant name.

Please describe any projected increases or decreases (from historical average) in the amounts stored or recovered.

Page 9 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SECTION VIII-IMPACT EVALUATION When determining whether the permit applicant has provided reasonable assurances that the conditions for issuance are met, the District will consider the projected impact of the proposed withdrawal, along with impacts from any existing legal uses and other pending applications for a water use permit. To provide these assurances, studies and/or impact evaluations may be required. Please refer to the Applicant's Handbook (subsection 3.3) for criteria regarding impact evaluations and attach your analysis, if applicable.

0 Impact evaluation attached lXI Not applicable - Refer to conditions under attached

  • EO No. 2014-078-DAO-WU/ROW/ERP SECTION IX- APPLICANT CERTIFICATION I certify that to the best of my knowledge and belief that all of the information provided on this form and in any attachment to it is correct. I understand that any permit issued shall be subject to review and modification, enforcement action, or revocation, in whole or in part, for any material false statement in an application to continue, initiate, or modify a use, or for any material false statement in any report or statement of fact required of the permittee [Section 373.243(1 ), Florida Statutes]. With advance notice, I agree to provide District staff with proper identification entry to the project site for the purpose of performing analyses of the site for determining whether the conditions for issuance will be met. Further, if a permit is granted, I agree that, with advance notice, District staff with proper identification shall have permission to enter, inspect, observe, col.lect samples, and take measurements of permitted facilities to determine compliance with the permit conditions and permitted plans and specifications.

If applicable) I a u t h o r i z e - - - - - - - - - - - - - - - - - - - - to act as my agent for permit application coordination .

HAifH/d.,J --1' KAPf(,J[J(J<.-1<5 7

~!YJ t/td J:, r J-tf,(_

APPLICANT'S NAME ~PLICANT'S SIGNATURE DATE (print or type)

AUTHORIZED AGENT'S NAME AUTHORIZED AGENT'S SIGNATURE DATE (print or type)

SECTION X- APPLICANT CHECKLIST Please make sure to include the following with the permit application submittal:

lEI Proof of Property Control (i.e. Deed, Lease) as per the Applicant's Handbook, subsection 2.1.1 (may be obtained via the applicable county Property Appraiser's website) -Refer to EO No. 2014-078-DAO-WU/ROW/ERP (i) Application Fee (www.sfwmd .gov)

(i) Location/Site Map (refer to supplemental application forms for specific requirements)- Refer to Project overview Map (i) Supplemental Form(s) and associated supporting information (i.e. maps, calculations)- Refer to Supplemental Form F and Construction Drawings/Details 0 Water Conservation Plan (if applicable) 0 Diversion and Impoundment (D&I) Independent Secondary User- Letter from the D&l that demonstrates legal access, and that the use will not cause the D&l to exceed its permit allocation.

Page 10 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C .)

Form 1379 (2014-07)

High Flow Pump FP900 Floating Pump Overview:

Th e FP900is a self-contained floating pump station capable of producing high flows of water idea l in flood co ntrol and large dewatering projects. The 36inch two-stage high-efficien cy axial flow pump provides for maximum flows up to 48,500 GPM and capable of producing a maximum head of 36 feet.

Features:

Frame is designed to be compatible with the sta ndard intermoda l high cube container (ISO 20), with a three part epoxy coating and polyethylene finish to withstand harsh environments. Flotation is accomplished with a one piece fiberglass tank filled with low density polyethylene foam for security.

Specs: Accesso ries:

  • Suction and Discharge Pipe and Fittings Maximu m Flow 48,500 GPM
  • Fuel Nurse Tank Maximum Head 35 feet Pump Size 36 "

Dry weight Footprint 240" X 102" Fuel Tank 132 Gallon Fuel Consu mption 24 GPH @ 1,900 RPM Liquid Ingenuity.

PUMPS

  • TANKS
  • FILTRATION
  • PIPE
  • SPILLGUARDS 800-742-7246 Rain for Rent is a registered trademark of Western Ollfield s Supply Company. Features and specifications are subject to change without notice. rainforrent.com

~ Rain For Rent CURVE:01-0133-02-82 ALL INFORMATION CONTAINED IN OR DISCLOSED BY THIS DOCUMENT IS CONSIDERED CONFIDENTIAL AND PUMP : FP-900 PROPRIETARY BY RAIN FOR RENT. ALL DISCLOSURES OF DESIGN INFORMATION AND REPRODUCTION OF THIS DOCUMENT AND ALL SAlLES RIGHTS ARE EXCLUSIVELY RPM DISCHARGE NO. OF STAGES IMPELLER BLADES IMPELLER DIA. IMPELLER RESERVED BY AND TO RAIN FOR RENT AND COMMUNICATION OF THIS INFORMATION TO 480 36" 2 6 36" 304SS OTHERS IS PROHIBITED WITHOUT THE PRIOR WRITTEN CONSENT OF RAIN FOR RENT 20- r r-45 90%

18- r-16- f-12- r- 40


....____ 85%

14- f J-35

_.-- ~ -- - -...;

EFFI

!_Ncy 0 12- J-30

.,. ~ - ..... ~

~

'.........._ 80%

L5 8- r- / u I z 25 w u

~

_J

~ 10- r- Li:

~ 75% b 6- -20 8- r-15 70%

6- - 4- -

10 4- -

65%

2- -

2- - 5

- --- IWER2_~ ~

r- - 1--- 1--

- ~- ~- -- 1--

FU L FLOW X 10 1---

~-

r---

~ -

0 0-- 0 60%

US GPM 38,000 40,000 42,000 44,000 46,000 48,000 50,000

(/)

0..

(/)

0:::

w w

w I

I I

I I

I I I I

I I

I I

I I

w I.J....

LITERS/SEC 2400 2500 2600 I

2700 2800 2900 3000 3100

  • FLOW PERFORMANCE IS BASED ON CLEAR WATER TESTING*

D&D IUiachine &Hyd1*aulics, Inc.

1 0845 Metm Par*kway SE For>t Myers, Florida 33866-1202 238-275-7177 o Fax 238-275-5350 E-mail : rnarketing@ddpumps .corn www. dclpumps .com Specifications for D & D Model 30AX 30" Axian Fnow Pumphead x 900D General Description These specifications describe our 30" Hydraulically Da*iven Submersible Axial Flow Pump. The pump is capable of flow capacities up to 25,500 GPM@ 5' TDH and 16,000 GPM@ 25' TDH.

Pumphcad- 30" Axial Flow o Vertical discharge, 3 0" size, with a stainless steel wear ring. Discharge with flange, 150#, AWS e Cast bronze impeller e Hydraulic motor requires 115 GPM @ 2,800 PSI o Hydraulic oil lubricated bearing carrier o Stainless steel pump shaft with radial contact bearings o Viton o-rlng, lip type and mechanical seals o Vane-type hydraulic motor o Pump Specs: 25,500 GPM@ 5' TDH 16,000 GPM @ 25' TDH o Weight: I ,500 Lbs.

l'ngc I of I 912012 HYDRAULIC SUBIVIERSIBLE f, UIVIPS AI\ID P0\1\fER UI\IITS

10/2012 30" AXIAL FLOW PUMP MODEL 30 x 1.0 x 900

~Q)

LL "0

I I I 2(35@0 @ 10' m

I I

10 1--- ... --

cD--,_

Q)

c 1 I

I ctr I --n' I I ,. I ' I 5 ___---1 2j~oo@ 5' 1

  • I I 0 r I I! .. -I*

16000 20000 22000 24000 26000 1 CapaQi!y_(g.p.m.)___~ ___ _

NOTE--pumps can be chosen per specific g.p.m. at any head--need not perform

___!!~ .~ntire curv~ : Please_c:onsuJ.t_f(lctory for special reg_':l~_sts. ___ _

TEST CONDITIONS I

Water-----**------fresh S. G.--------------1.00 I Temp------------70* F Altitud~_----------Sea L~y~L . _j ________ _I

  • Tests were conducted according to Hydraulic Institute ANSI I Hl-1.6

! en I

j I c 0

i i'

({)

I c Ii (])

I I E

I I i I

I:

0

--- ~ -------,---------1~

-m

  • x m

-0 CV)

--- - - . ---~ --" -----**** ----- - ~ --***-*-* -*-

Item Part 30uu A~~Al PUMP No.

Number Description PA~l'§ -1o- 30A1001 ------ - hyclt~~u_lj.Q .JllQ:~qr_

2o

...... __.. ___ 30A1002 *--*- - pot~IJ?l~~~~J?..)_ __

3. 24/30A1003 o' ring_ ______seal ..,. ... -...._... **-

(1*, _-----rralliJ

4. 30A1004 motor ltey

~F1r ______

,...,I

. -~---

5. 30A1005 ... . ...

bearing carrier 19, 6. 24/30A1006 locl\ nut (2)

I I:

, . ,. I.. I. ....... . 7. 24/30A1007 loci\ washer It 8. 24/30A1008 bearing cone (2)

II II _,____ ;17... :_ 18.. 9. 24/30A1009 bearJit_9.~U~J~L .

1/

10. 24/30A1010 pu m...P~ll__c_lf!______

'-15:T1 : .*".*a**.,...

._. .. " \"*'**-""( *--------* -.~ -J/..-. -... ____.,_,_ '-13 110  : 24/30A1 011 mecho seal assem

-- * ** en!~~*£. . rr. JJ * '~ ** * - ~- .!?._. __i. 2..~!90~1 0~ 2 seal holder


.-- . --I.--.:.I',(':"::.-~~r-==

I I _____12.: ...1 ~. :_?.4/~_91\ 1~-1~

0 r ':1;?:;,.-::--=::.,

_ . o'ri11g seal

',1q.*,.* ~*~--- '***

  • I .... ~...':::::::-

r-~ :::::-->-...

___-"~;:.-- :;-=}~... .

=

(

-~~--*1

-... . ...... *- -* ~~*:_ . .

---"'20 , . 14. i 24/30A1014 __ ___Jp se~l .

  • . 15. *-*- -: 30A1015 bro~~....P~~elle!~

C:.:.I*IP  ? * - i~=;r ---~~ ,. .- --/ -\;:_~~~- . - - J.11.1 ~-- - - -

a-.':------ - . ~tLJJ ~----- _. - - . __ _ ---_ . 16. 24/30A1 016 propeller key

--- .... - - - * *~ s~~ ~.~ ~* -***- .:;;~*.:.:.:* _...... 10 .

  • 17.  : 24/30A1017 flat washer,ss i* fa~*----: -2473o~j_Q_18 .. . riytoc~,~~--- -----------

-.'f_:.-:.~:-~ ~Q [= i)*l~x~~r_- - 1 *--:: . ~

  • * - * - * -- * - * * - * *- * ,:r".l , _, ; * ... * * - * * - * , .

. 9. ;- .. * ~- * ~ * *" ~ _ , ..-*** I ~ 21.

5 *- -*- . " ' . ' 4. i 19.  : 3QA19.~@ ... . . diffuser housing

_________..___- .. I 20. 30A1020 wear ring

    • ---**~ I

--- i j * * - - - -- - * - -- * -

  • 1 Bi~--:.::~..1-B \_21. __30A1021 __ .. _ inlet bell housing

,-) rg)(.,-~ r I *.-.*--..  : 22. ' 30A1022 . intake screen I*o l 6. '*

~---1:~ -

__:22o - j 23o --24/SOA1023

  • quicl~ coupler-(R) - 1 1240 *.:i4J?o~:!_o]{_ -f.quiCit ~ouplet~-(r)' . 1 ec11~~ i 25. 2430A1025 ! sea!_hld_ bolt~(6)_

<:.::<:::.<;1=::::.=:::;::-;:-::-- ~~~~'-'-*---- . --- --~--* *-:*-_ --::-:-* !:.:::<"

j________ _2<!_~ __1_021 OPT_Lint~!~~--l_lausing 45~~

. . . 2:

1. 10/2005

4 1 D NOTES

1. DIMENSIONS IN INCHES D
2. DO NOT SCALE DRAWING
3. DRAWING IS NOT FOR CONSTRUCTION
4. CONSULT FACTORY FOR CERTlFIEO DIMENSIONS
5. APPROX. WEIGHT: 7500 LBS
6. FUEL CAPACilY: 175 GALLONS 528" c c

~li~

71i B

1"'"--

1ftT nP I~

I I I I ""¢

" -I gedwin pumps

!i!

~

1M'=~~,:-==-~~ UEA

- HS300 POWER PACK A r-::1

. . . . _ *==

-...=_"=-=a;,.,.---r:::::l

.==;:;;-* ----==-=-----r::l.,..::r.=:l-.dl-1

...=-=.., .--1 D. STETSER . .. . ** . .. .

J 06068 HF485 175 GAL SKID A

I ~ .u~u* oan

  • I

--==*

-=--

!:o f/11 X

X I I X I l 2547 IHIZT 1 OF 1 4 3 2 1

A1'1'ACHMEN:P D WA'Jl'D llTSE St1'tPLEMEN1!AL FORM F

WATER USE PERMIT APPLICATION Diversion and Impoundment Use Supplemental Form F South Florida Water Management District P.O. Box 24680, West Palm Beach, Florida 33416-4680 (561) 686-8800 www.sfwmd .gov/ePermitting Diversion and Impoundment - Projects that divert surface water through a pump or operable water control structure, or divert a combination of surface and groundwater to a conveyance canal network system which the applicant has legal control to operate and maintain for the purposes of providing for the reasonable-beneficial demands of secondary users and consumptive and non-consumptive uses.

SECTION F1 - PARCEL/SITE INFORMATION WATER USE PERMIT # (if application is for renewal or modification): _ _ _ _ _ _ _ _ _ _ __

Section (s), County Parcel Identification Parcel/Site Name Acres Township, Range Number (or attach digital (each non-contiguous parcel or field) Serviced (S_/T_S/R_E) GIS Shape file) 30-7029-001-0012 398.74 29/57S/40E Refer to attached Project Overview Map and GIS shape file Refer to attached Project Overview 30-7029-000-0010 17.96 29/57S/40E Map and GIS shape fil e Refer to attached Project Overview 30-7029-001-0011 136.38 29/57S/40E Map and GIS shape file TOTAL ACRES OWNED/LEASED 553 .08 Submit a map showing (if available, provide items A th rough C in a District-approved electronic format, e.g. ESRI shapefile, Autocad, DXF, KMZ, or compatible GIS file) :

A. The project boundaries of the property owned or controlled by the permittee/applicant; B. A north arrow and map scale; C. Labeled landmarks such as canals, roads and political IDoundaries; and D. The location of all secondary users of the system , including irrigated acreage and land use type .

Page 1 of 2 Incorporated by reference in rule 40E-2 .101 (F.A.C.)

Form 1386 (2014-07)

SECTION F2- WATER USE INFORMATION Please describe the operation by attaching the following information, as applicable (refer to the Applicant's Handbook, Section 2.3.2.C):

IZI The extent (length, cross sections and depth) of the canal network used to deliver the associated water -o~=~~~sgo~~lis 0 Land use classifications within the serviced area IX) Surface water demands directly withdrawn for the system- Refer to EO No. 2014-078-DAO-WU/ROW/ERP 0 Seepage Losses 0 Water necessary to maintain groundwater elevations for the purpose of aquifer recharge and saltwater intrusion prevention 0 Evaporation losses from the canal surfaces 0 Established control elevations during one and 10 year drought events 0 Copies of executed agreements with dependent secondary users IXJ Historic use (permit renewal with no changes)- Refer to EO No. 2014-078-DAO-WU/ROW/ERP

~ Canal locations with established wet and dry season control elevations- Refer to EO No. 2014-078-DAO-WU/ROW/ERP and Project Overview Map SECTION F3- REQUESTED WATER USE Complete the requested water use table below. Provide projected water amount for each use type and the associated water source(s).

2 3 Source of Water (MGY /MGM )

Use Type Source 1 Name1 Source 2 Name Source 3 Name L31 E (N} Canal Secondary Users Total Max. Avail. I Max. Avail. I I Maintenance Demands Total Max. Avail. I Max. Avail.

I I Total Max. Avail. I Max. Avail.

I I 1

Prov1de the name of the water source. Examples Include C 51, LWDD E-1 2

MGY = Million gallons per year of water to be withdrawn over a 12-month time period under a 1-in-1 0 year drought condition (i.e. 1,500,000 gallons each day/1 ,000,000 = 1.5 x 365 = 547.5) 3 MGM = Maximum million gallons per month of water to be withdrawn in any single month under the 1-in-1 0 year drought condition.

SECTION F4- WATER CONSERVATION Please refer to District specific water conservation requirements, in the Applicant's Handbook, Section 2.0.

Page 2 of 2 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1386 (2014-07)

lZZ] Project Boundary I=:J Seclion Township & Range f~ Parcels PROJECT FPL TURKEY POINT COOLING CANAL FRESHWATER RECHARGE TITLE PROJECT OVERVIEW MAP CONSU LTANT YYYY-MM-DD 2014-12-22 PREPARED NRL DESIGN NRL REFERENCE (//JGolder Associates REVIEW KAB PROJECT BOUNDARY, FPL & GOLDER ASSOC IATES INC., 2014 APPROVED KAB PARCELS, MIAMI DADE COUNTY, 2014 SECTION TOWNSHIP & RANGE, FDEP PROJECT CONTROL Rev. FIGURE 1412354 006 0 1

FPL-032R

  • I=PL.

January 23, 2015 Ms. Karin Smith Section Leader South Florida Water Management District 3301 Gun Club Road West Palm Beach, FL 33416-4680 RE: Florida Power & Light Company- Turkey Point Plant Water Use Permit Application Cooling Canal Augmentation P.-oject

Dear Ms. Smith:

Florida Power & Light Company (FPL) is requesting authorization from the South Florida Water Management District (SFWMD) to access the District's right of way, connect to the L-31E canal, and seasonally transfer excess stormwater (above the 254 cubic feet per second required for the Comprehensive Everglades Restoration Project (CERP) Biscayne Bay Coastal Wetlands restoration project) from the L-31E canal to the Turkey Point Plant to aid in reducing temperature and salinity in the Cooling Canal System (CCS).

On August 28, 2014 the SFWMD issued EO No. 201-078-DAO-WU/ROW/ERP (Attachment A) allowing for the temporary installation and removal of piping and pumping systems for transfer of water from the L-31E Canal to the CCS. In accordance with the conditions of the EO, FPL divetied surface water from the L-31E Canal which would have otherwise been discharged to tide. via the S-20F, S-20G, and S-21A coastal structures and was in excess of the flows reserved for protection of fish and wildlife (Rule 40E-10.061, F.A.C.). Withdrawals were tenninated on October 15, 2014.

In lieu of requesting another EO for short-term coverage, FPL is requesting a recurring annual diversion of water from the L-31E under the SFWMD Consumptive Water Use Program. FPL proposes to utilize a similar design (Attachment B) and comply with conditions consistent with those that were approved under EO No. 201-078-DAO-WU/ROW/ERP. Enclosed are the applicable SFWMD Water Use Application Forms and supporting documentation (Attachments C and D) and a check for the Water Use Permitting fee of $6,200.

The proposed work is necessary for the continued safe and reliable operation of the Turkey Point Plant.

FPL appreciates your expedited review of the enclosed drawings and details. Please contact me at 561-691-2808 (Matthew.Raffenberg@fpl.com) or Stacy Foster at 561-691-7065 (stacy.foster@fpl.com) ifyou have any questions.

Sincerely,

~ )11, ~~ /2r HJt(

Matthew J. Raffenberg Director of Environmental Licensing and Permitting

Attachments: Attachment A- SFWMD EO No. 201-078-DAO-WU/ROW/ERP Attachment B - CCS Augmentation Construction Drawings Attachment C- Water Use Permit Application and Supporting Documents Attachment D- Water Use Supplemental Form F and Suppmting Documents

AT'FACl!IMEN1' A s.-.-:mm N~. ZOl~OI18-D~-WU/OOW/ERP

BEFORE THE GOVERNING BOARD OF THE SOUTH FLORIDA WATER MANAGEMENT DISTRICT SFWMD No. 2014-078-DAO-WU/ROW/ERP IN RE:

EMERGENCY FINAL ORDER ISSUED TO FLORIDA POWER AND LIGHT FOR THE PURPOSE OF AUTHORIZING TEMPORARY PUMP INSTALLATION AND WATER WITHDRAWAL ALONG AND FROM THE LN31 E CANAL SYSTEMj MIAMI-DADE COUNTY, FLORIDA

--~------------------------~'

EMERGENCY FINAL ORDER The Executive Director of the South Florida Water Management District (District),

pursuant to Sections 120.569 and 373.119(2), Florida Statutes (Fla. Stat.), after considering the recommendations of District staff and being otherwise fully appraised of the matter, issues the following Emergency Order (Order) containing Findings of Fact, Ultimate Facts and Conclusions of Law:

FINDINGS OF FACT

1. The District is a public corporation of the State .of Florida, existing pursuant to Chapter 25270, Laws of Florida, 1949, and operating pursuant to Chapter 373, Fla. Stat., and Title 40E, Florida Administrative Code (Fla. Admin. Code), as a multi-purpose water management district with its principal office at 3301 Gun Club Road, West Palm Beach, Florida. The District has the power and duty to protect Florida's water resources and to administer and enforce the provisions of Chapter 373, 1

Fla. Stat., and the rules promulgated there under, Title 40E, Fla. Admin. Code. The District has jurisdiction over the matters addressed in this Order.

2. Florida Power and Light (FPL) is a subsidiary of NextEra Energy, Inc. As a regulated utility, FPL is granted an exclusive franchise by the Public Service Commission to provide reliable and cost-effective electric service to customers, including critical infrastructure, within its service territory in Florida. FPL's service territory covers all or parts of 35 Florida counties and serves approximately nine million customers.
3. The customers particularly at issue in this matter are those residing In Miami-Dade and Broward counties. In these counties, FPL provides electrical service to two million customer accounts, including critical infrastructure.
4. FPL owns and operates the electric power generating facility known as the Turkey Point Power Plant (Turkey Point) that is the subject of this emergency authorization request.
5. Turkey Point is located in unincorporated southeast Miami~Dade County, east of Florida City and the City of Homestead. The Turkey Point site covers approximately 11 ,000 acres. Turkey Point is located approximately 25 miles south of Miami and about nine miles east of Florida City. Properties adjacent to Facility are almost exclusively undeveloped land. Turkey Point is bordered to the east by Biscayne Bay and Card Sound. A Turkey Point location map is attached and incorporated as Exhibit A.
6.
  • Turkey Point consists of five steam electric generating unHs: three fossil fuel-fired units (Units 1, 2, and 5) and two nuclear units (Units 3 and 4). Units 1 and 2 2

constructed in the late 1960s each have a continuous generating capacity of approximately 404 megawatts {MW). Operations of units 1 and 2 are on a standby basis and not routinely in service. Unit 5 has a continuous generating capacity of approximately 1150 MW. Units 3 and 4 each have continuous generating capacity of approximately 820 MW.

7. Units 3, 4, and 5 are certified under Florida's Power Plant Siting Act (PPSA). Units 1 and 2 pre-date the PPSA and are not certified.
8. FPL owns and operates a cooling canal system ("CCS"), an approximately 5,900-acre network of unlined canals at Turkey Point, to provide cooling water.

Construction of the CCS was completed in 1973, and the CCS was closed from the surface waters of both Biscayne Bay and Card Sound. The CCS facilities pre-date the PPSA and are not certified. Under routine operations, there are no active surface water inflows utilized to maintain ccs water levels, temperature, or salinity.

9. The L~31 E Canal system is of particular import to FPL's emergency authorization request. The L-31 E Canal system is part of the Central and Southern Florida Flood Control Project (C & SF Project) for which the District is the designated local sponsor pursuant to Section 373.1501, Fla. Stat. As local sponsor, the District operates C&SF Project components, including the L-31E Canal system and the surface water flow to tide from the ass_ociated basins consistent with the guidance provided in the United States Army Corps of Engineers Master Water Control Manual, East Coast Canals, Volume 5.
10. The L~31 E Canal system is a borrow canal and levee system that stretches north - south both intercepting water as it flows eastward to tide in southeast 3

Dade County and providing storm surge protection. A map depicting. the L-31 E Canal system is attached and incorporated as Exhibit B. The L-31 E Canal runs parallel to the South Central Biscayne Bay and across several drainage basins, six of which are named for the associated major east-west canals: Canal 100 (C-100), C-1, C-1 02, C-103, North Canal and Florida City Canal. This canal network and coastal levee system is operated for several C & SF Project purposes, including reducing the potential for flood and storm surge damage as well as limiting saline water intrusion. Water from the L-31 E is discharged to Biscayne Bay at several coastal structures, as depicted on Exhibit B.

11. Operation of the C & SF Project coastal structure gates in this canal network controls the quantity and timing of water discharged into this portion of Biscayne Bay. Overall, these surface water inflows comprise the largest input of fresh water to Biscayne Bay in this area.
12. In the 1990's the U.S. Army Corps of Engineers and the District developed the Comprehensive Everglades Restoration Program (CERP) which was approved by Congress in the Water Resources Development Act of 2000 (WRDA 2000). A component of CERP includes the Biscayne Bay Coastal Wetlands Phase 1 Project.

This project component aims to restore the overland sheetflow in an. area of up to 11,000 acres, and to improve the ecology of Biscayne Bay, including its freshwater and saltwater wetlands, nearshore bay habitat, marine nursery habitat, and the oyster reef community.

13. Implementation of the Biscayne Bay Coastal Wetlands Phase 1 Project will. impound and redistribute freshwater runoff from the existing canal discharges into 4

the coastal wetlands adjoining Biscayne Bay to provide a more natural and historical overland flow pattern through existing coastal wetlands and tidal creeks. This redistribution of freshwater runoff will improve the temporal and spatial distribution of inflows to Biscayne Bay.

14. The WRDA 2000 requires that water be reserved from allocation as an assurance that each CERP project component will meet its goals and objectives. Water is to be reserved consistent with the objectives and information contained within the Central and Southern Florida Project Comprehensive Everglades Restoration Plan Biscayne Bay Coastal Wetlands Project Phase I Final Integrated Project implementation Report and Environmental Impact Statement (PIR) and other sources of information.
15. To this end, the District conducted technical studies identifying water to be reserved for the protection of fish and wildlife within the western near-shore portion of Central Biscayne Bay, engaged in rule development, and adopted the Nearshore Central Biscayne Bay reservation rule and associated implementation rules. (Exhibit C)

The location of the Nearshore Central Biscayne Bay as well as the associated; Project canal system is depicted in Figure 3-1 of the attached and incorporated Exhibit C.

16. The determination of the amo.unt of water needed for protection of fish and wildlife in the Nearshore Central Biscayne Bay reservation rule is based on meeting a year-round salinity target for the nearshore area of central Biscayne Bay of 20 (practical salinity scale) given in the PIR. More detailed analyses were performed to determine the locations and quantities of surface water for the reservation rules. This information is contained in the District's Technical Document to Support a Water Reservation Rule 5

for the Comprehensive Everg1ades Restoration Plan Biscayne Bay Coastal Wetlands Project (July 2013).

17. Rule 40E-1 0.061, Florida Administrative Code, is the water reservation rule for the Nearshore Central Biscayne Bay. Pursuant to this rule, surface water flowing into the Nearshore Central Biscayne Bay, as derived from various and listed contributing canal reaches, is reserved from allocation. Figure 3-4A depicts surface water flow from the C-102 + Military+ C-103 Canal through S-21A + S-20G + S*20F into Biscayne Bay during the Wet Season and is the relevant reservation for this Order; the reserved Target Flow to the Bay is 504 acre-ft I day or 254 cubic feet per second (cfs).
18. On August 27, 2014, FPL requested the District issue an Emergency Order for temporary authorization to utilize the District's right of way and to divert and use water, above that reserved in Rule 40E-10.061, F.A.C., from the L-31E Canal System to help moderate unusually high temperatures and salinity that are occurring in the CCS. A copy of FPL's request and related correspondence between FPL and the Nuclear Regulatory Commission is attached and incorporated as Composite Exhibit D.

In summary, FPL seeks to divert water that is available, above the water reserved by Rule 40E-10.061, F.A.C., which would otherwise be discharged to tide via the S-20F,S-20G and S-21A coastal structures. District staff reviewed and considered FPL's request, the District's right of way, the infrastructure proposal, historic data, District statutory authorizations and rules, and the potential water availability and provided input to the District's Executive Director.

6

19. In support of their emergency authorization request, FPL provided the following information which is contained in Composite Exhibit D and summarized below:
a. United States Nuclear Regulatory Commission (NRC) Operating Licenses for Turkey Point and CCS Temperature Requirements: Turkey Point Power Plant Units 3 & 4 operate under a license from the Nuclear Regulatory Commission. The original operating license included a requirement that the maximum allowed CCS water temperature on the intake or inlet side of Units 3 &

4 cannot exceed 100°F. During July 2014, numerous factors contributed to higher than usual inlet temperatures in the CCS that approached 100°F. Also, during July- August, intake temperatures approached 102°F. After analysis, FPL requested and received temporary approval from the NRC to temporarily deviate from the water temperature requirement as is pursued a permanent change to the plant's operating license. In parallel, FPL submitted and received (August 8, 2014) approval for a License Amendment Request (LAR) that permanently increases the CCS intake water temperature limit from 100°F to 104°F. (Composite Exhibit D) This LAR is conditioned such that if the NRC license timit is exceeded and certain conditions met, both Turkey Point Units 3 and 4 will be required to commence shut down within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> which could impact grid reliability. If Units 3 and 4 were required to shut down, an important piece of FPL's power generation portfolio will not be available to meet the current and anticipated high electricity demand, potentially impacting electrical service to more than 2 million customer accounts in Miami-Dade and Broward Counties, including critical infrastructure.

7

b. CCS Temperatures and Record-Breaking Power Demand: Peak demaRd for electric generation in south Florida is directly related to high temperatures and humidity which generally occur in the summer and early fall.

Beginning in July 2014, Turkey Point's CCS experienced higher than usual temperatures as well as record breaking electricity demand. By the end of July, CCS Plant intake temperatures exceeded 100°F and have continued to exceed 100°F during afternoon peaks, recently reaching a high of 102°F, as depicted in Composite Exhibit D.

c. Factors Contributing to CCS Temperatures:* A number of factors are contributing to higher than usual temperatures in the CCS. These factors include: high summer temperatures; significantly less rainfall in the vicinity of Turkey Point, including rainfall at the CCS; elevated salinity; and an algae bloom.
i. Temperature Data: For the Miami-Dade and Broward areas, the average high in September is 89°F and in October it is 86°F. CCS temperatures exceeded 100°F during July and August, 2014.

ii. Rainfall, Evaporation, Salinity, and Seepage Data: FPL* reports typical annual rainfall at Turkey Point totals range between 50 inches to 75 inches. Normally, summer rainfall is effective in moderating the CCS water temperature and salinity, In 2013, the annual rainfall accumulation at Turkey Point measured at the CCS was less than 20 inches. As of the end of May, 2014, there had been less than 3 inches of rain at the rain station within the CCS.

Although additional rainfall has occurred in June and July, the 8

overall rainfall remains less than 26 inches at the CCS, compared to* 40 inches at the Miami Airport during the same timeframe .

. Moreover, FPL data indicates that the high evaporation, averaging 34 MGD, and losses to groundwater, averaging 12 MGD, have resulted in more water leaving the CCS than is being provided from the aquifer or rainfall and ultimately concentrating salinity in the CCS. FPL reports the CCS salinity has reached levels near 90 ppt, compared to historic levels of approximately 60 ppt.

iii. Algae Bloom: FPL indicates the above described conditions have allowed an algal bloom in the CCS to persist and affect Plant operations. The algae concentration, prior to treatments beginning

. mid-summer, was as high as 1.8 million cells per milliliter, far exceeding the historic average values of 50,000 cells per milliliter.

Recent FPL treatments have reduced the algae concentrations.

However, the turbidity associated with the algae bloom has caused u*nusual amounts of solar energy to be absorbed in the CCS, thereby Increasing CCS temperatures. FPL reports effective treatment of the algae will require the salinity to be reduced to bring the dead algae out of suspension, which is nec~ssary to reduce CCS temperatures and, thereby, restore the heat exchange capacity of the CCS. Detailed information concerning the CCS algae bloom are contained in Composite Exhibit 0, particularly the correspondence between FPL and the NRC.

9

d. FPL's Request for Temporary, Emergency WatE?r Supply: In summary, FPL requests an immediate, temporary emergency authorization kom the District to allow FPL to access the District's right of way, connect to the L-31 E canal, and conditionally withdraw stormwaier from the L-31E Canal, and convey this water to the CCS with above-ground piping. Composite Exhibit 0 contains the design details for FPL's request. FPL's proposed operational plan synchronizes the volumes and rates of its northern and southern pumping operations so as to avert dewatering of wetlands adjacent to the L-31E canal. A portion of the proposed Infrastructure involves temporary installation of pipes across wetlands.
20. Temporary installation of the pipes within wetlands, as shown in Exhibit D, will have only minimal or insignificant individual or cumulative adverse impacts on the water resources of the District. Based on the design proposed in Exhibit 0, FPL's proposed, temporary installation qualifies for an exemption from the requirement to obtain an environmental resource permit pursuant to subsection 373.406(6), Florida Statutes.
21. Water levels in the L-31 E Canal system, the proposed water supply source, are influenced by the operation of coastal canal structures. Operation of the S-20F, S-20G and S-21A are performed consistent with guidance from the United States Army Corps of Engineers regulation schedule and Master Water Control Manual, East Coast Canals, Volume 5. Under normal operating conditions for April 30- October 15 the S-20F, S-20G, and S-21A structures are operated in the "high range" meaning discharges to tide are conditionally made when stages upstream of the structure 10

including stages within the L-31 E Canal are 2.2 ft. NGVD or higher an.d the gates are closed when headwater stages drop to 1.8 ft NGVD.

22. Operational records of the District show combined average daily flow from the C-1 02, Military, C-1 03 canals through Structures S-21A, S-20G, and S-20F, respectively, into this portion of Biscayne Bay are 481 cfs during the month of August (1993 - 2013) and 620 cfs for the month of September (1993 - 2013), with daily combined flows ranging from 0 to more than 3,000 cfs during these months.
23. The combined reserved target flow for structures S-21A, S-20G, and S-20F is 254 cfs suggesting that there is a reasonable expectation that daily flows exceeding the reservation target flows will occur during the months of August and September.
24. Based on FPL's request and the above-described facts, the Executive Director of the District has considered this matter and finds that an emergency exists and the emergency measures proposed herein are necessary to protect the public health, safety or welfare.

ULTIMATE FACTS AND CONCLUSIONS OF LAW

25. Section 373.119(2), Fla. Stat., and Rule 28~106.501, Fla. Admin. Code, authorize the Executive Director of the District, in the event of an emergency requiring immediate action to protect the public health, safety or welfare, with the concurrence of the Governing Board, and without prior notice, to issue an order reciting the existence of such an emergency and requiring that such action be taken as deemed necessary.

Section 120.569, Florida Statutes, also authorizes issuance of emergency authorizations. Moreover, the District is authorized, in summary, to regulate 11.

connections and use of the District's rights of way, use of water, construction of new diversion facilities, initiation- of new water uses, diversion and withdrawal facilities pursuant to a variety of statutes. (e.g.: §§373.083, 373.085, 373.086, 373.1501, 373.171, 373.219, Florida Statutes) The proposed activities are exempt from the requirement to obtain an environmental resource permit pursuant to subsection 373.406(6), Florida Statutes.

26. As to right of way matters, Rules 40E-6.451 and 40E-6.481, Fla. Admin.

Code, further provide an emergency exists when immediate action is necessary to protect lives or property.

27. Pursuant to statutory authorizations, FPL's request and supporting documents, and the facts described herein, the Executive Director finds that an emergency exists requiring immediate action necessary to protect the public health, safety, or welfare. The Executive Director also finds the wetland impacts identified in Exhibit D and authorized by this Order qualify for a Section 373.406(6), Fla. Stat.,

exemption.

28. The action authorized by this_ Emergency Order is appropriate to address this emergency situation:
29. The L-31 E Canal system is part of the C&SF Project for which the District is the designated local sponsor pursuant to Section 373.1501, Fla. Stat. Pursuant to Sections 373.085 and 373.086, Fla. Stat., the District is authorized to operate the C&SF Project, including the S-20 Structure and the L-31 E Can~l system.

12

ORDER Based u~on the Findings of Fact, Ultimate Facts and Conclusions of Law, the Executive Director orders FPL is authorized to undertake the following, *temporary actions in accordance with the conditions stated herein:

30. Temgorary Utilization of District Right of Way:
a. Authorized Facilities and Installation: FPL is authorized to install the infrastructure depicted in Exhibit D on the District's L-31 E Canal right of way.

The design details, including facility description and location, authorized by this Order are contained in the attached and incorporated Exhibit D. To the extent the information contained in Exhibit D conflicts with the terms and conditions of this Emergency Order, this Emergency Order shall control. FPL shall install, operate, and maintain the temporary withdrawal facilities and associated equipment in accordance with this Order. Any deviations from the design schematics identified in Exhibit D shall be presented to the District for approval prior to installation of the modified design. These facilities are temporarily authorized for the purpose of diverting and use water from the L-31 E Canal system to help meet its cooling water needs pursuant to the following conditions.

b.* Right of Way Installation Conditions:

i. Installation
  • Coordination; Prior to commencement of construction or utilization of *the District's right of way and, again, upon completion of the installation of the authorized facilities, FPL is required to contact the District's Field Representative, Mike Worley of the District's Homestead Field Station, (954)410-7383, and schedule a pre-construction 13

meeting and final inspection. The District's Homestead Field Station Superintendent is authorized to make field changes to installations or operations described herein to better achieve the District's objectives; such changes shall be subsequently documented in writing and communicated by the District to FPL.

ii. Site Security: The pumps at both the north and south pumping sites shall be manned continuously throughout the entire time the pumps are deployed pursuant to this Order. The south pumping site shall be manned by a pump operator provided by the pump manufacturer.

iii. Right of Way Conditions: FPL is required to comply with all Right of Way conditions contained in the body of this Order and attached and incorporated Exhibit E.

31. Temporary Water Withdrawal Authorization:

a.. Authorization to Withdraw and Use Water. if available, from the L~

31 E Canal System:

i. Water Availability Restriction: FPL is prohibited from withdrawing and using water from the L~31 E Canal system that is reserved for fish and wildlife by Rule 40E-10.061, F.A.C., for the Nearshore Central Biscayne Bay. The only water available for the purpose of this Order is that water which would otherwise be discharged to tide from either the S-20F, S-20G, and S-21A struCtures and is in excess of the flows reserved for protection of fish and wildlife in Rule 40E-1 0.061, F.A.C. This available surface water may, temporarily, be withdrawn and used within FPL's 14

cooling canal system in accordance with the conditions as set forth herein.

Tl1ere are no assurances provided by this Order that water will be available for FPL's withdrawal and use on any given day.

ii. District's Daily Determination of Water Availability and FPL Pump Operation: On a daily basis, the District will determine the amount and timing that FPL may operate the pumps and facilities authorized herein to withdraw water from the L-31 E Canal system. Only when the combined flows to tide through coastal structures S~20F, S-20G, and Sw21A exceed 254 cfs will the District determine the amount and timing water available for a FPL pump operation. The rate and volume of a potential FPL withdrawal, if any, shall be determined by the District, no later than 10:00 a.m., each day and for the duration of this Order. The District's daily determination of water availability shall cover a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period and last until no later than 9:59a.m. the next day. In the event the District does not provide any written direction to FPL in accordance with t~is paragraph, then FPL shall cease all pumping until further notice.

iii. Communication of Water Availability Determination: The District's Operation Control Center will communicate its daily water availability determination to FPL by e-mail, to the FPL's designated contact(s): Matthew Raffenberg, or his designee, at Matthew.Raffenberg@fpl.com. The District's Operation Control Center may be contacted 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day, 7 days a week at: 561-682~6116 and 15

occ@sfwmd.gov.

  • FPL may not commence any daily withdrawal operations prior to this District communication confirming water availaiJility.

iv. Monitoring and .Reporting: FPL shall monitor and report the amount of water diverted from the L-31 E Canal system to its cooling canal system. When FPL withdraws water, then FPL must generate a daily report including the following detailed information: (1) the water availability determination for each day as provided by the District's Operational Control Center, (2) identification of which pump(s) were used over the course of the day; (3) time on and time off, per pump; (4) RPM setting, per pump, if variable; (5) calculated volume of water pumped, per pump; and (6) cumulative log flows at each pump station. fn addition, the report shall include hourly stage data for the L-31 E Canal measured at TPSW~1 and TPSW~2 for the weekly reporting period, whether or not the pumps operated. Water quality grab samples consisting of conductivity, turbidity, total kjedahl nitrogen, nitrate nitrite as N, phosphorus, ortho phosphorus, ammonia, and TRPH (total recoverable peteroleum hydrocarbons, also known as Florida Petroleum Residual Organic or "FL-PRO") shall be collected prior to initiation of pumping pursuant to this Order and once a week thereafter for the duration of this Order. These samples shall be collected at TPSW-1 and TPSW-2. FPL shall make the sampling logs. and lab reports available upon request. The report shaH*

reference this Order and be submitted by noon, Tuesday of each week for all withdrawals occurring during the preceding week. (The preceding week 16

-reporting period is considered Monday at 1:00 a.m. through Sunday midnight.) The- report shall be e-mailed to both the District's Assistant Executive Director, Len Lindahl at llindahl@sfwmd.gov and Terrie Bates, Division Director - Water Resources, at tbates@sfwmd.gov. Upon Executive review of the weekly report, conference calls may be required.

Additionally, the District may request available monitoring data at any time and FPL shall provide the same within two hours of the District's request.

v. Special Pump Station Criteria:

(a) The District may require FPL to terminate pumping at any time. Upon receipt of any oral or written request from the District to terminate pumping, FPL must cease pumping within two (2) hours.

(b) FPL shall wirelessly coordinate the pumping at both stations to assure that, from a non-flow condition, the north station pumps shall be started first The south station pumps shall be started within 5 minutes of the north station pumps start, with an equivalent flow. Similarly, when pump operation ceases, the south station pumps shall cease first and the north station pumps shall cease within 5 minutes.

vi. Pump Requirements:

(a) Pump On I Off Switches: Each pump authorized pursuant to this Order shall be equipped with an operable, 17

remote .pump operational device prior to initiating pump operations.

(b) Pump discharge curves:- Pump discharge curves used in determining rates of discharge while pumps are operating, as deployed in the field, shall be provided to the District prior to pump operation for the purpose of calculating flow rates and volumes.

(c) Totalizing Hour Meters: FPL shall install totalizing hour meters at each pump authorized by this Order and such meters shall be available for periodic District inspection and verification.

32. Section 373.406(6), F.S., Exemption Conditions:
a. No permanent fill shall be placed in the wetland area described in Exhibit D.
b. All activities which qualify for the subject exemption shall be conducted and operated using appropriate best management practices and in a manner which does not cause a violation of water quality standards, pursuant to Chapter 62-302, Florida Administrative Code.
c. The District's determination that the proposed temporary placement of pipes, pymps, and associated infrastructure qualifies as an exempt activity may be revoked if the installation is substantially modified from that described in Exhibit D, if the basis for the exemption is determined to be materially incorrect, or if the installation results in violation of state water quality standards. Any 18

changE;}s made in the construction plans or location of the project may necessitate a permit from the District. Therefore, FPL is advised to contact the District before beginning any work in wetlands or surface waters which is not specifically described in Exhibit D.

d. Upon termination of this Order, all pipes, mats, other materials and equipment shall immediately be removed from the wetland to allow the wetland vegetation to recover.
33. Immediate Facility Removal and Reinstallation:
a. Prior to a Storm Event: FPL shall remove the temporary withdrawal facilities authorized by this Order located within the District's right of way within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of receipt of notice from the District. The temporary withdrawal facilities should be maintained and secured so as to not impede the District's ability to make flood control releases in advance of a storm event.
b. After a Severe Storm Event: FPL shall notify the District of its intent to reinstall the temporary withdrawal facilities in the District's right-of-way at least three (3) business days before such reinstallation is scheduled to occur.
34. All documents, plans, and reports required by this Order shall be submitted to Len Lindahl via email at llindahl@sfwmd.gov and Terrie Bates via email at tbates@sfwmd.gov.
35. Miscellaneous Conditions:*
a. This Order authorizes FPL to take actions under Chapter 373, Fla.

Stat., as provided herein. This Order does not relieve FPL from the requirements to obtain any other federal, state, or local authorizations.

19

b. This Order does not constitute a-water use or right-of~way permit or grant any legal right to water as set forth in Chapter 373 Fla. Stat., and associated District rules and regulations over the water intercepted and stored under this Order.
c. This Order does not convey any property right to FPL, nor any rights and privileges other than those specified in this Order. This Order shall not be construed as an abandonment or any other such impairment or disposition of the District's property rights.
d. This Order shall not be construed as a substitute for, or waiver of, any right-of-way, surface water management, water use, or other permits required of FPL under the District's rules and regulations.
e. FPL shall insure that harmful impacts to the water resources, off-site land uses, or existing legal uses of water do not occur as a result of this Order. In the event such harmful impacts result from actions authorized by this Order, FPL shall implement all actions, as directed by the District, to cease. such harmful impacts and, if necessary, to mitigate such impacts. Failure to comply with this requirement shall be considered a violation of this Order.
f. Failure to comply with the terms of this Order shall constitute a violation of a District Order under Chapter 373, Fla. Stat., and enforcement proceedings may be brought in any appropriate administrative or judicial forum.
g. The District reserves the right to initiate appropriate legal action, to impose civil penalties, and collect attorney's fees and costs to enforce the terms of this Order.

20

h. This Order may be modified or amended at any time, as appropriate for the protection of the public health, safety, and welfare and the water resources of south Florida by the Governing Board, Executive Director, or Executive Director's designee.
i. The Executive Director or Executive Director's designee may require FPL to remove all or part of the authorized facilities and cease withdrawal and I or use activities under this Order at any time.
j. The District's immunity from liability under Section 373.443, Florida Statutes, for any damages that might result from the activities authorized under this Order, shall not be diminished by the terms of this Order, or any activities taken pursuant to this Order.
k. Failure to comply with 1he conditions contained within this Order shall constitute a violation of a District Order under Chapter 373, Florida Statutes, and enforcement proceedings may be brought in any appropriate administrative or judicial forum.

I. If the District petitions or sues for enforcement of the terms of this Order, the District reserves the right to initiate appropriate legal action, to impose civil penalties and collect attorney's fees and costs.

36. Termination: This Order shall terminate on the earliest of: (1) failure to receive Governing Board concurrence at their next regularly scheduled meeting, (2)

October 15, 2014, or (3) at any time upon written notice from the District's Executive Director or the Executive Director's designee.

21

37. Required Facility Removal: Within 30 days of termination of this Order, FPL shall remove all temporary withdrawal facilities and associated infrastructure authorized by this Order, inoludin.g the pipes buried under 344th Avenue. Moreover, FPL shall properly restore the right-of~way to the District's satisfaction. In the event of failure to so comply within the specified time, the District may remove the temporary withdrawal facilities and associated infrastructure authorized by this Order and associated equipment and FPL shall be responsible for all removal and restoration costs.
38. A Notice of Ri_ghts attached hereto as Exhibit F.
39. This Order shall take effect upon execution by the Executive Director of the District and shall expire as provided herein. This Order is subject to the Governing Board's concurrence at its next regularly scheduled Governing Board meeting.

DONE AND SO ORDERED in West Palm Beach, Florida, on this 28th day of August, 2014.

SOUTH FLORIDA WATER MANAGEMENT DISTRICT By its Executive Director Blake C. Guillory,,£:.~

Executive Director Legal Form Approved:

f:Kl .&~ cr~~

Elizabeth D. Ross, Esq.

22

A'fTACIIM1£NT B fef>NS1'RtTCTION JI)RA,WENGS

Temporary Cooling Canal Wetland ID Habitat Type Acreage Augmentation Pipeline & Equipment HW 510- Canal 0.04 f:Z2J Area of Temporary Wetland Impact p 612 - Mangro\.e Swamps 0.32 PROJECT 510- Canal 0.04 FPL TURKEY POINT R 641 - Frestwtater Marshes 0.03 COOLING CANAL 6411- Marsh Smvgrass 0.02 FRESHWATER RECHARGE Grand Total 0.45 TITLE PROJECT OVERVIEW MAP NOTES PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING CONSULTANT YYYY-MM-DD 2015-01-20 TRANSMITTED FOR AG ENCY REVIEW PREPARED NRL

'SEE ATTAC HED SHEETS FOR DETAIL DESIGN NRL REFERENCE ( j tGolder

Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 AP PROVED KAB TEMPORARY WETLAND IMPACTS, GOLDER ASSOC IATES INC., 2014 PROJECT CONTROL Rev. FIGURE 1412354 001 0 1

I I

I I

I (ii u

c Ill I

I D Intake Pipes w

~

<')

~

I I

o-------- Powerpak (TYP)

I I

I I

I Wetland HW-510 0.04Acres~ I D I I

0 I \

I \

Wetland R-641 /

0.03 Acres /

/

/

/

/

Wetland R-510 I

0.02Acres

(

Discharge I Pipes I I

(ii c I u

Ill I <

~

w

~

<') I  :!

~

~ 0 u I 0

"',0

~

~ I 0

!* 20 40 I m

~

~

  • 0

§ ~~5iiiiiiil

~ ~1~:4llB~O~________JF~e~eLI____________-=~~-=~==~~::~~---=:::=:::::::::::=:==:=:::::::::::::::::::::::::=::::::::j

~ LEGEND TABLE 1- TEMPORARY WETLAND CLIENT -

<o, IMPACT ACREAGE FPL ~,

Temporary Cooling Canal *

~ - - - Augmentation Pipeline & ~

, Equipment

~_.~ L_l Wetland Line PROJECT ~~*

~ FPL TURKEY POINT ~

~ [::::_~] Area of Temporary Disturbance COOLING CANAL ~

~ ffiEII Limits of Temporary Construction FRESHWATER RECHARGE ~

~o:. rz:zJ Area Matting ofTemporary Wetland T INITLTEAKE SYSTEM ~_.~,

!, NOTE;pact TEMPORARY WETLAND IMPACTS ~

~<

PRELIMINARY DRAWI NGS: THESE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING TRANSMITTED FOR AGENCY REVIEW CONSULTANT YYYY*MM-DD 2015-01-21 ~£ t

~

.: REFERENCE

(!~Golder PREPARED DESIGN NRL NRL

' Associates REVIEW KAB

~~ PIPELINE ROUTE , TAYLOR ENGINEERING INC., 2014 TEMPORARY WETLAND IMPACTS, GOLDER ASSOCIATES INC., 2014 APPROVED KAB FIGURE (j PROJECT CON TR OL Rev.

1412354 002 0 2

I I

I I

I I

I I

I I

I I

I Wetland R-510 0.02Acres Gvetland R-6411

!!/

I I

< 0.001 Acres I

I --* \

\

I Modular Work Platform )J I

I \

(Typical Each Side of Pump/'

\

--, \

"' \"

\

\

I I

I I

I I

I I Wetlal/d R-6411 I

o.opAcres I

I I I I 20 40 \

.1 I I I l!!!!!!!!!!!!li~!!!liiiiiiiiil )

I I I I TABLE 1 -TEMPORARY WETLAND CLIENT IMPACT ACREAGE Temporary Cooling Canal FPL Wetland ID Habitat Type Acreage

- - Augmentation Pipeline &

HW 510- Canal 0.04 Equipment p 612- Mangro"' Swamps 0.32 L_l Wetland Line 510- Canal PROJECT 0.04 FPL TURKEY POINT

[=~J Area ofTemporary Disturbance R 641 - Freshwater Marshes 0.03 COOLING CANAL EEEBJ Limits of Temporary Construction 6411 -Marsh Sawgra ss 0.02 FRESHWATER RECHARGE Matting Grand Total 0.45 TITLE r::zzJ Area of Temporary Wetland DISHCARGE SYSTEM Impact TEMPORARY WETLAND IMPACTS NOTES PRELIMINA RY DRAWINGS: THE SE DRAWI NGS ARE NOT FINAL FORM , BUT ARE BEING CONSULTANT YYYY-MM- DD 2015-01 -2 1 TRANSMITTED FOR AGENCY REVIEW PREPARED NRL DESIGN NRL REFERENCE REVIEW KAB PIPELINE ROUTE. TAYLOR ENGINEERING INC., 2014 APPROVE D KAB TEMPO RARY WETLAND IMPACTS, GOLDER ASSOCIATE S INC., 2014 PROJECT CONTROL Rev. FI GURE 1412354 002 0 3

~Edge of Wetland I

i I

I I

I I .----'

i I I _ " \." r Edge of Wetland Wetlald R-6411 "'-/ ~ Wetland P-612 o.f Acres 0.04Acres Wetland P-612 I 0.28Acres i

I I

I I

I I

20 40 TABLE 1. TEMPORARY WETLAND IMPACT ACREAGE Temporary Cooling Canal Wetland ID Habitat Type Acreage

- - Augmentation Pipeline &

HW 510- Canal 0.04 Equipment p 612- Mangro\e Swamps 0.32 L_l Wetland Line PROJECT 510- Canal 0.04 FPL TURKEY POINT

[::::_~] Area ofTemporary Disturbance R 641 -Freshwater Marshes 0.03 COOLING CANAL H.:J:Ill Limits of Temporary Construction 6411 -Marsh Sawgrass 0.02 FRESHWATER RECHARGE Matting Grand Total 0.45 TITLE

[ZZJ Area of Temporary Wetland DISHCARGE SYSTEM Impact TEMPORARY WETLAND IMPACTS NOTES PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM , BUT ARE BEING CONSU LTANT YYYY-MM-DD 2015-01-21 TRANSMITTED FOR AGENCY REVIEW PREPARED NRL DESIGN NRL REFERENCE { f tGolder PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 Associates REVIEW KAB APPROVED KAB TEMPORARY WETLAND IMPACTS, GOLDER ASSOCIATES INC. , 2014 PROJECT CONTROL Rev. FIGURE

~ 1412354 002 0 4

~ L_--------------------------------------------------------------------------~0

Edge of Wetland Wetland P-612 f 0.04Acres Wetland P-612 0.04Acres Edge of Wetland Wetland P-612 0.28Acres Wetland ID Habitat Type Acrea ge HW 510 - Canal 0.04 p 612- Mangro\e Swamps 0.32 PROJECT 510- Canal 0.04 FPL TURKEY POINT

[=~J Area o fTempora ry Disturbance R 641 - Freshwater Marshes 0.03 COOLING CANAL lffiJI Limits of Temp orary Construc tion 6411 - Marsh Sawgrass 0.02 FRESHWATER RECHARGE Matting Grand Total 0.45 TITLE IZZl Area Impact o fTemporary Weiland DISHCARGE SYSTEM TEMPORARY WETLAND IMPACTS NOTES PRELIMINARY DRAWINGS: THE SE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING CONSULTANT YYYY-MM-DD 2015-01-21 TRANSM ITTED FOR AGENCY REVIEW PREPARED NRL DESIGN NRL REFERENCE ( j t Golder Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 APPROVED KAB TEMPORARY WETLAN D IMPACTS, GOLDER ASSOCIATES INC., 2014

I I

I I

Wetland P-612 I

0.04Acres I I

I I

I I

I

--- J Edge of Wetland

--~

--~

--~

'--.._1 I

i I

I I

i Wetland ID Habitat Type Acreage HW 510- Canal 0.04 p 612- Mangrow Swamps 0.32 PROJECT 510- Canal 0.04 FPL TURKEY POINT

[=~J Area ofTemporary Disturbance R 641 - Freshwater Marshes 0.03 COOLING CANAL tEBJI Limits of Temporary Construc tio n 6411 -Marsh Sawgrass 0.02 FRESHWATER RECHARGE Mailing Grand Total 0.45 TITLE

[ZZJ Area of Temporary Weiland DISHCARGE SYSTEM Impact TEMPORARY WETLAND IMPACTS NOTES PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM , BUT ARE BEING CONSULTANT YYYY-MM-DD 2015-01-21 T RANSM ITTED FOR AGENCY REVIEW PREPARED

(!/~Golder NRL DESIGN NRL REFERENCE Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 APPROVED KAB TEMP ORARY WETLAND IMPACTS, GOLDER ASSOCIATES INC., 2014

/ I I I I I i I I I I I I I I I of Wetland I I I I I I I I

-~ . . . . . '"'-. . I' I

-~-

---,_ I I

-~

"---, I

.............. ~:.......... _, ./

- ~--, ""-.................

I

... '"' .... t-....


~--

I -~-,---------~ /;;Freshwater Discharge Location I I -~ ...

i -~---~-------,_ Jl ~ I; I -....;,;-......_ I I I ---- -, I I I II ---..._,

. . __""""Il I

I I I I l I i I I I I I I I I I I I

~

I

'g

~ I

  • o 20 4o I I

~l!!!!!!!!liiiiiiiiiiiiiil!!!!!!liiiiiiiiiiii I ii~~1~:4ll8~0~--------lF~e~eLt LEGEND ____~-------=~~-=~==~~::~~---=~====================================================:~

TABLE1 - TEMPORARYWETLAND CLIENT z g1 IMPACT ACREAGE FPL @

r;;. Temporary Cooling Canal Wetland ID Habitat Type Acreage ~'

~=; - - Augmentation Pipeline &

HW 510- Canal 0.04

Equipment p 612 - Mangro.e Swamps 0.32

~ L_l Wetland Line PROJECT 510- Canal 0.04 FPL TURKEY POINT i EEEEII

~

[=~J Area ofTemporary Disturbance Limits of Temporary Construction Matting R 641- Freshwater Marshes 6411- Marsh Sawgrass 0.03 0.02 COOLING CANAL FRESHWATER RECHARGE

] TITLE Grand Total 0.45

~

..u, [ZZJ 8

g Area of Temporary Wetland Impact DISHCARGE SYSTEM TEMPORARY WETLAND IMPACTS NOTES

~ PRELIMINARY DRAWINGS: THESE DRAWINGS ARE NOT FINAL FORM, BUT ARE BEING CONSULTANT YYYY-MM- DD 2015-01-21 i TRA NSMITTED FOR AGENCY REVIEW

~

PREPARED NRL

"' REF ERENCE DESI GN NRL

~ ( J t Golder

"~ Associates REVIEW KAB PIPELINE ROUTE, TAYLOR ENGINEERING INC., 2014 A PPROV ED KAB TEMPORARY WIETLAND IMPACTS, GOLDER ASSOCIATES INC., 2014

~ PROJECT CON TROL Rev. FIG URE

~ 1412354 002 0 7

~ L-----------------------------------------------------------------~

ATTACHMENT C WATER USE PED'.MIT JUPJLICA'Fl!ON

WATER USE PERMIT APPLICATION South Florida Water Management District P.O . Box 24680, West Palm Beach, Florida 33416-4680 (561) 686-8800 www.sfwmd .gov/ePermitting SECTION 1- CONTACT INFORMATION WATER USE PERMIT# (if application is for renewal or modification):

If necessary, attach additional sheets if there are multiple applicants, owners, agents, etc.

1. APPLICANT (Complete legal name in which permit should be issued)

NAME: Florida Power & Light Company If applicant is a business, provide a contact person:_M_a_tt_h_e_w_R_a_ff_e_n_b_e--'rg:;.___ _ _ _ _ __

ADDRESS: 700 Universe Boulevard CITY, STATE , ZIP: Juno Beach, Florida 33408 PHONE: ( 561 ) 691-2808 CELL PHONE: ( 561 ) 573-5888 EMAIL ADDRESS: Matthew.Raffenberg@fpl.com Applicant is: liD Owner 0 Lessee* 0 Other (explain) _ _ _ _ _ _ _ _ _ _ __

  • Attach copy of current lease, or written authorization from property owner
2. OWNER (If different than applicant)

NAME: same as above ADDRESS: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ____

CITY, STATE, Z I P : - - - - - - - - - - - - - - - - - - - - - - - - -

PHONE:(_ ___, _ _ _ _ _ __ CELL PHONE: (_ _ _) - - - - - - - -

EMAIL ADDRESS:

3. AGENT OR CONSULTANT NAME:Karl Bullock COMPANY NAME (if applicable): Golder Associates Inc.

ADDRESS: 6026 NW 1st Place CITY, STATE, ZIP: Gainesville, Florida 32607 PHONE: ( 352 ) 336-5600 CELL PHONE: ( 352 ) -=2=22=--=69:::...:6::....:1~-----

EMAIL ADDRESS: Karl Bullock@golder.com

4. COMPLIANCE CONTACT (Person responsible for sending compliance reports to the District)

NAME:Stacy Foster ADDRESS: 700 Universe Boulevard CITY, STATE, ZIP: Juno Beach, Florida 33408 PHONE: ( 561 ) 691-7065 CELL PHONE: ( 772 ) _2_85_-_56_5_3_ _ __

EMAIL ADDRESS: Stacy.Foster@fpl.com Page 1 of 10 Incorporated by reference in rule 40E-2 .101 (F.A.C.)

Form 1379 (2014-07)

SECTION II- APPLICATION INFORMATION Refer to the Applicant's Handbook for permit application guidance, located online at www.sfwmd .gov. If any fields are not applicable for the proposed use, write N/A in the field.

1. TYPE OF APPLICATION: IZI New 0 Modification 0 Renewal If this application is for a modification, please describe the modification request and the reason the modification is n e c e s s a r y . - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2. REQUESTED PERMIT DURATION: liD 20 years 0 __ years (up to 20 years) 0 I qualify for a duration greater than 20 years, per Florida Statute 373.236 Turkey Point Cooling Canal
3. PROJECT NAME: Augmentation COUNTY: _M_ia_m_i-_D_a_d_e_ _ _ _ __

L31 E Canal North Intake (approximate)- 25°26'53. 78" N, 80°20'59.51" W PHYSICAL ADDRESS: L31E Canal South Intake (approximate) - 25°26'04.84" N, 80°21'09.76" W 4 . RELATED PERMITS (for projects other than Public Supply) 0 ENVIRONMENTAL RESOURCE PERMIT (ERP) PERMIT/APPLICATION No(s):N/A- EO No. 2014-078-DAO-WU/ROW/ERP 0 RIGHT OF WAY (ROW) Permit/Application No(s): N/A- EO No. 2014-078-DAO-WU/ROW/ERP 0 DIVERSION AND IMPOUNDMENT (0&1) Permit/Application No(s): N/A- EO No. 2014-078-DAO-WU/ROW/ERP SECTION Ill - USE CATEGORY Please check all applicable water use categories associated with this permit application and complete the associated supplemental form(s) indicated. Refer to District rules 40E-21.651for water use type definitions.

Supplemental Water Use Category Form 0 Agricultural (e.g., crops, livestock, nursery, aquaculture, pasture) FormA 0 Commercial/Industrial (e.g., service business, food and beverage production , cooling and heating, commercial attraction, manufacturing, chemical processing, power generation, aquifer Form B remediation , mining) 0 Landscape I Recreation (e.g., irrigation of parks, cemeteries, landscaped areas, golf Form C courses, athletic fields, playgrounds) 0 Dewatering (e.g., water use or removal associated with construction or excavation) Form D 0 Public Supply (e.g. , public or privately owned water utility) FormE

~ Diversion and Impoundment (diversion or extraction of water) . Independent Secondary Form F users should use the applicable supplemental form based on type of water use.

Page 2 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C .)

Form 1379 (2014-07)

SECTION IV- SOURCES OF WATER

SUMMARY

OF GROUNDWATER {WELL) FACILITIES Well Name or Number N/A Map Designation Existing or Proposed Date of Proposed Construction Date Installed if Existing Diameter (in)

Total Depth (ft)

Cased Depth (ft)

Screened Interval (ft)

Pumped or Flowing Pump Type (see Instructions)

Pump Intake Depth (ft bls)

Pump or Flow Capacity (GPM)

Working Valve if Artesian (yes, no or not applicable)

Status (see Instructions)

Purpose (see Instructions)

Elevation of the Wellhead (ft NGVD - see Instructions)

Water Use Accounting Method (see Instructions)

Date Last Calibrated (ATTACH calibration report)

Planar Coordinates (if known - see instructions)

Section I Township I Range Page 3 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

Instruction for Completing Groundwater (Wells) Section Well Name or Number: The Applicant's designation of the well. How do you refer to it?

Map Designation: This is how the well is labeled on the map submitted with the application. This may be the same as Well Name or Number, but does not necessarily have to be.

Existing or Proposed: If the well is proposed, enter the date of expected operation. If it is an existing well, enter the date it was installed if you know it.

Diameter: Outside diameter of the well casing.

Total Depth: Total length in feet between the land surface and the bottom of the well.

Cased Depth: The length in feet from the land surface to the bottom of the well casing.

Screened Interval: The distance in feet below land surface to the top and bottom of the well screen, if the well is so equipped.

Pumped or Flowing: Does the well produce water as a result of natural artesian flow, or is it pumped?

Pump Type: This is the type of pump that has been installed for the well (typical choices are as follows):

Centrifugal Diesel turbine Axial flow Windmill Submersible Jet Suction Other (specify)

Electric turbine Hydraulic Portable Pump Intake Depth: Location of the pump depth in feet below land surface. The pump may be on the surface or down inside the well.

Pump or Flow Capacity: The amount of water the pump can produce in gallons per minute (GPM).

Working Valve: If the well is artesian, does it have a working valve to control the flow?

Status: Primary Secondary (i.e. a production well that is rotated)

Standby (i.e. used for freeze protection or emergency)

Monitor Injection (i.e. A/C, pool heat exchange, etc.; sometimes used only periodically)

Recharge (i.e. same as above)

Purpose:

What will the water be used for (typical choices are as follows):

Dairy Irrigation Air Conditioning Swimming Pool Heating Monitor Aquaculture Freeze Protection Irrigation/Lake Recharge Livestock Bottled Water Mining/Dewatering Aquifer Storage and Recovery Industrial Other (specify) Public Water Supply Aquifer Remediation and Recovery Elevation of the Wellhead: This is the elevation of the top of the finished well at the ground surface.

Planar coordinates: The Florida State Plane System (Planar Coordinates) should be submitted if you have a land survey which identifies the location of the well in terms of those measurements. If you do not know what these are, it is not necessary to include them.

Section I Township I Range: The section, township and range in which the pump is located.

Page 4 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SUMMARY

OF SURFACE WATER (PUMP) FACILITIES Pump Name or Number Map Designation L31E Canal N 31E Canal N L31E Canal N L31E CanalS Surface Water Source Local Drainage District Unknown !Unknown Unknown Unknown (if applicable)

Existing or Proposed Existing Existing Existing Existing Date of Proposed N/A J'j/A N/A N/A Installation Date Installed if Existing Model -Godwin Model- Godwin Model - Godwin Model - Rain For Rent Pump type -specifications attached HAF 30AX HAF30AX HAF 30AX FP900 (for list see Instructions) Type- 1\)<iai/Diesel Type- !l)(iaiDiesel Type- !l)(iaiDiesel Type- !l)(iaiDiesel 125,500 GPM 25,500 GPM 25,500 GPM ~8,500 GPM Pump Capacity (GPM)

Pump Horsepower t?38 hp 238 hp 238 hp Unknown po in. 30 in. 30 1n. 36 in.

Pump Diameter (inches)

Pump Intake Elevation 7ft. 7ft. 7ft. 4ft.

{feet NG}JQ} (feet NAVD)

!Primary Primary Primary Primary Status (see Instructions)

Pther- !Other- Other- Pther-Purpose (see Instructions) ft\ugmentation ~ugmentation ~ugmentation fi\ugmentation Two way pump? No No No No (yes I no)

Water Use Accounting Method otalizing rr otalizing rr otalizing Totalizing (see Instructions) Meter Meter Meter Meter Date Last Calibrated (ATTACH calibration report)

Planar Coordinates ilJnknown Unknown ~nknown Unknown (if known -see instructions) 129/57S/40E 29/57S/40E j29/57S/40E 29/57S/40E Section I Township I Range Page 5 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

Instructions for Completing Surface Water (Pumps) Section Pump Name or Number: The Applicant's designation of the pump. How do you would refer to it?

Map Designation: This is how the pump is labeled on the map submitted with the application. This may be the same as Pump Name or Number, but does not necessarily have to be.

Surface Water Source: This is the name of the water body from which the pump withdraws water (e.g.

SFWMD C-51, Lake Worth Drainage District Canal E-3, Un-named canal, onsite lake).

Local Drainage District: If the project is located in a local drainage or "298" district, such as Lake Worth Drainage District, Indian Trails Water Control District, etc., please identify it.

Existing or Proposed: If the pump is proposed enter the date of expected operation. If it is an existing pump, enter the date it was installed if you know it.

Pump Type: Typical choices are:

Centrifugal Diesel Turbine Axial Flow Submersible Suction Electric turbine Hydraulic Other (specify)

Pump Capacity: The amount of water the pump can produce in gallons per minute (GPM).

Pump Horsepower: Horsepower rating of the pump.

Pump Diameter: Size of the intake opening of the pump, in inches.

Pump Intake Elevation: The elevation from which the pump can produce water without cavitating.

Status: Primary Secondary (i.e. a production pump that is rotated)

Standby (i.e. used for freeze protection or emergency)

Purpose:

What will the water be used for (typical choices are as follows):

Dairy Irrigation Air Conditioning Swimming Pool Heating Aquaculture Freeze Protection Irrigation/Lake Recharge Mining/Dewatering Livestock Industrial Aquifer Storage and Recovery Aquifer Remediation and Recovery Other (specify)

Two way pump: Can the pump be used for both intake of irrigation water and discharge of storm water?

Flow Measurement Method: Describe how the amount of water produced by the pump will be measured as per Section 4.1.1. of the Applicant's Handbook.

Date Last Calibrated: When was the flow measurement method last calibrated? ATTACH the calibration report.

Planar coordinates: The Florida State Plane System (Planar Coordinates) should be submitted if you have a land survey which identifies the location of the pump in terms of those measurements. If you do not know what these are, it is not necessary to include them.

Section I Township I Range: The section, township and range in which the pump is located.

Page 6 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SUMMARY

OF SURFACE WATER (CULVERT) FACILITIES N/A Culvert Name or Number Map Designation Surface Water Source Local Drainage District

{if applicable)

Existing or Proposed Date of Proposed Construction Date installed if Existing Culvert type

{for list see Instructions)

Culvert length {Feet)

Culvert Cross-section Culvert Diameter {inches)

Culvert Height {inches)

Culvert Width {inches)

Invert Elevation {Feet NGVD)

Type of Control Device

{for list see Instructions)

Status

{see Instructions)

Purpose {see Instructions)

Two way culvert?

{yes I no)

Water Use Accounting Method

{see Instructions)

Date Last Calibrated {if known)

Planar Coordinates

{if known -see instructions)

Section I Township I Range Page 7 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

Instructions for Completing Surface Water (Culverts) Section Culvert Name or Number: The Applicant's designation of the culvert. How do you refer to it?

Map Designation: This is how the culvert is labeled on the map submitted with the application. This may be the same as Culvert Name or Number, but does not necessarily have to be.

Surface Water Source: This is the name of the water body from which the culvert withdraws water (e.g.

SFWMD C-51, Lake Worth Drainage District Canal E-3, Un-named canal, onsite lake).

Local Drainage District: If the project is located in a local drainage or "298" district, such as Lake Worth Drainage District, Indian Trails Water Control District, etc., please identify it.

Existing or Proposed: If the culvert is proposed enter the date of expected operation. If existing, enter the date it was installed (if known).

Culvert Type: Corrugated; Metal pipe; Reinforced concrete pipe; Steel pipe Culvert Length: Distance between the ends of the culvert in feet.

Culvert Cross-section: Is the culvert round, elliptical, rectangular, or other?

Culvert Diameter: If the culvert is round, the inside diameter of the culvert, in inches.

Culvert Height: If the culvert is not round, the inside height of the culvert, in inches.

Culvert Width: If the culvert is not round, the inside width of the culvert, in inches.

Invert Elevation: The lowest elevation, referenced to NGVD, at which water will flow through the culvert.

Type of Control Device: What controls the flow of water through the culvert (typical choices are):

Control gate; Flap gate; Flashboard riser; Gated riser; Screw gate; Slide gate; Valve; Other (specify)

Status: Primary; Secondary (i.e. a production pump that is rotated); Standby (i.e. used for freeze protection/

emergency)

Purpose:

What will the water be used for (typical choices are as follows):

Dairy Irrigation Aquaculture Freeze Protection Mining/Dewatering Livestock Industrial Irrigation/Lake Recharge Other (specify)

Two way culvert: Can the culvert be used for both intake of irrigation water and discharge of storm water?

Flow Measurement Method: Describe how the amount of water produced by the pump will be measured as per Section 4.1.1. of the Applicant's Handbook.

Date Last Calibrated: When was the flow measurement method last calibrated? ATTACH the calibration report.

Planar coordinates: The Florida State Plane System (Planar Coordinates) should be submitted if you have a land survey which identifies the location of the culvert in terms of those measurements. If you do not know what these are, it is not necessary to include them.

Section I Township I Range: The section, township and range in which the culvert is located.

Page 8 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SECTION V- EVALUATION OF RECLAIMED WATER FEASIBILITY The applicant is required to evaluate the feasibility of utilizing reclaimed water. The feasibility analysis must be completed as outlined in the Applicant's Handbook, subsection 2.2.4.

0 Feasibility analysis attached IZI Not applicable (i.e. no lines in area, crop type restriction, already using reclaimed)

Explanation: No lines in area.

SECTION VI -

SUMMARY

OF REQUESTED WATER USE Total the requested water use from each supplemental form (Agricultural, Irrigation, Commercial I Industrial, Public Water Supply, etc.) in the table below. If the multiple sources add up to more than 100%,

please attach an operating plan with a detailed explanation.

Requested Amounts and Source(s) of Water 1

Source 1 Name Source 2 Name Source 3 Name Source 4 Name Total Requested L-31E Canal Water Use (MGY 2 /MGM ~) (MGY 2/MGM~) (MGY 2/MGM ~) 2 (MGY /MGM 3

)

2 (MGY /MGM )

3 Max. Avail. 1Max. Avail. I I I I Provide the name of the water source. Examples include the Upper Flondan aqu1fer and the Biscayne aqu1fer.

2 MGY =Million gallons per year of water to be withdrawn over a 12-month time period under a 1-in-1 0 year drought condition (i.e. 1,500,000 gallons each day/1 ,000,000 =1.5 x 365 =547.5).

3 MGM =Maximum million gallons per month of water to be withdrawn in any single month under the 1-in-1 0 year drought condition .

SECTION VII - AQUIFER STORAGE AND RECOVERY (complete if applicable)

Source of Recovery Estimated Demand Estimated Injected ASR Facility Name Stored Water 1 Storage Aquifer Water Average/Maximum Average/Maximum Name Destination (MGD) (MGD)

N/A I I I I I I I I Aqu1fer Name, surface water body, water treatment plant name.

Please describe any projected increases or decreases (from historical average) in the amounts stored or recovered.

Page 9 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1379 (2014-07)

SECTION VIII-IMPACT EVALUATION When determining whether the permit applicant has provided reasonable assurances that the conditions for issuance are met, the District will consider the projected impact of the proposed withdrawal, along with impacts from any existing legal uses and other pending applications for a water use permit. To provide these assurances, studies and/or impact evaluations may be required. Please refer to the Applicant's Handbook (subsection 3.3) for criteria regarding impact evaluations and attach your analysis, if applicable.

0 Impact evaluation attached lXI Not applicable - Refer to conditions under attached

  • EO No. 2014-078-DAO-WU/ROW/ERP SECTION IX- APPLICANT CERTIFICATION I certify that to the best of my knowledge and belief that all of the information provided on this form and in any attachment to it is correct. I understand that any permit issued shall be subject to review and modification, enforcement action, or revocation, in whole or in part, for any material false statement in an application to continue, initiate, or modify a use, or for any material false statement in any report or statement of fact required of the permittee [Section 373.243(1 ), Florida Statutes]. With advance notice, I agree to provide District staff with proper identification entry to the project site for the purpose of performing analyses of the site for determining whether the conditions for issuance will be met. Further, if a permit is granted, I agree that, with advance notice, District staff with proper identification shall have permission to enter, inspect, observe, col.lect samples, and take measurements of permitted facilities to determine compliance with the permit conditions and permitted plans and specifications.

If applicable) I a u t h o r i z e - - - - - - - - - - - - - - - - - - - - to act as my agent for permit application coordination .

HAifH/d.,J --1' KAPf(,J[J(J<.-1<5 7

~!YJ t/td J:, r J-tf,(_

APPLICANT'S NAME ~PLICANT'S SIGNATURE DATE (print or type)

AUTHORIZED AGENT'S NAME AUTHORIZED AGENT'S SIGNATURE DATE (print or type)

SECTION X- APPLICANT CHECKLIST Please make sure to include the following with the permit application submittal:

lEI Proof of Property Control (i.e. Deed, Lease) as per the Applicant's Handbook, subsection 2.1.1 (may be obtained via the applicable county Property Appraiser's website) -Refer to EO No. 2014-078-DAO-WU/ROW/ERP (i) Application Fee (www.sfwmd .gov)

(i) Location/Site Map (refer to supplemental application forms for specific requirements)- Refer to Project overview Map (i) Supplemental Form(s) and associated supporting information (i.e. maps, calculations)- Refer to Supplemental Form F and Construction Drawings/Details 0 Water Conservation Plan (if applicable) 0 Diversion and Impoundment (D&I) Independent Secondary User- Letter from the D&l that demonstrates legal access, and that the use will not cause the D&l to exceed its permit allocation.

Page 10 of 10 Incorporated by reference in rule 40E-2.101 (F.A.C .)

Form 1379 (2014-07)

High Flow Pump FP900 Floating Pump Overview:

Th e FP900is a self-contained floating pump station capable of producing high flows of water idea l in flood co ntrol and large dewatering projects. The 36inch two-stage high-efficien cy axial flow pump provides for maximum flows up to 48,500 GPM and capable of producing a maximum head of 36 feet.

Features:

Frame is designed to be compatible with the sta ndard intermoda l high cube container (ISO 20), with a three part epoxy coating and polyethylene finish to withstand harsh environments. Flotation is accomplished with a one piece fiberglass tank filled with low density polyethylene foam for security.

Specs: Accesso ries:

  • Suction and Discharge Pipe and Fittings Maximu m Flow 48,500 GPM
  • Fuel Nurse Tank Maximum Head 35 feet Pump Size 36 "

Dry weight Footprint 240" X 102" Fuel Tank 132 Gallon Fuel Consu mption 24 GPH @ 1,900 RPM Liquid Ingenuity.

PUMPS

  • TANKS
  • FILTRATION
  • PIPE
  • SPILLGUARDS 800-742-7246 Rain for Rent is a registered trademark of Western Ollfield s Supply Company. Features and specifications are subject to change without notice. rainforrent.com

~ Rain For Rent CURVE:01-0133-02-82 ALL INFORMATION CONTAINED IN OR DISCLOSED BY THIS DOCUMENT IS CONSIDERED CONFIDENTIAL AND PUMP : FP-900 PROPRIETARY BY RAIN FOR RENT. ALL DISCLOSURES OF DESIGN INFORMATION AND REPRODUCTION OF THIS DOCUMENT AND ALL SAlLES RIGHTS ARE EXCLUSIVELY RPM DISCHARGE NO. OF STAGES IMPELLER BLADES IMPELLER DIA. IMPELLER RESERVED BY AND TO RAIN FOR RENT AND COMMUNICATION OF THIS INFORMATION TO 480 36" 2 6 36" 304SS OTHERS IS PROHIBITED WITHOUT THE PRIOR WRITTEN CONSENT OF RAIN FOR RENT 20- r r-45 90%

18- r-16- f-12- r- 40


....____ 85%

14- f J-35

_.-- ~ -- - -...;

EFFI

!_Ncy 0 12- J-30

.,. ~ - ..... ~

~

'.........._ 80%

L5 8- r- / u I z 25 w u

~

_J

~ 10- r- Li:

~ 75% b 6- -20 8- r-15 70%

6- - 4- -

10 4- -

65%

2- -

2- - 5

- --- IWER2_~ ~

r- - 1--- 1--

- ~- ~- -- 1--

FU L FLOW X 10 1---

~-

r---

~ -

0 0-- 0 60%

US GPM 38,000 40,000 42,000 44,000 46,000 48,000 50,000

(/)

0..

(/)

0:::

w w

w I

I I

I I

I I I I

I I

I I

I I

w I.J....

LITERS/SEC 2400 2500 2600 I

2700 2800 2900 3000 3100

  • FLOW PERFORMANCE IS BASED ON CLEAR WATER TESTING*

D&D IUiachine &Hyd1*aulics, Inc.

1 0845 Metm Par*kway SE For>t Myers, Florida 33866-1202 238-275-7177 o Fax 238-275-5350 E-mail : rnarketing@ddpumps .corn www. dclpumps .com Specifications for D & D Model 30AX 30" Axian Fnow Pumphead x 900D General Description These specifications describe our 30" Hydraulically Da*iven Submersible Axial Flow Pump. The pump is capable of flow capacities up to 25,500 GPM@ 5' TDH and 16,000 GPM@ 25' TDH.

Pumphcad- 30" Axial Flow o Vertical discharge, 3 0" size, with a stainless steel wear ring. Discharge with flange, 150#, AWS e Cast bronze impeller e Hydraulic motor requires 115 GPM @ 2,800 PSI o Hydraulic oil lubricated bearing carrier o Stainless steel pump shaft with radial contact bearings o Viton o-rlng, lip type and mechanical seals o Vane-type hydraulic motor o Pump Specs: 25,500 GPM@ 5' TDH 16,000 GPM @ 25' TDH o Weight: I ,500 Lbs.

l'ngc I of I 912012 HYDRAULIC SUBIVIERSIBLE f, UIVIPS AI\ID P0\1\fER UI\IITS

10/2012 30" AXIAL FLOW PUMP MODEL 30 x 1.0 x 900

~Q)

LL "0

I I I 2(35@0 @ 10' m

I I

10 1--- ... --

cD--,_

Q)

c 1 I

I ctr I --n' I I ,. I ' I 5 ___---1 2j~oo@ 5' 1

  • I I 0 r I I! .. -I*

16000 20000 22000 24000 26000 1 CapaQi!y_(g.p.m.)___~ ___ _

NOTE--pumps can be chosen per specific g.p.m. at any head--need not perform

___!!~ .~ntire curv~ : Please_c:onsuJ.t_f(lctory for special reg_':l~_sts. ___ _

TEST CONDITIONS I

Water-----**------fresh S. G.--------------1.00 I Temp------------70* F Altitud~_----------Sea L~y~L . _j ________ _I

  • Tests were conducted according to Hydraulic Institute ANSI I Hl-1.6

! en I

j I c 0

i i'

({)

I c Ii (])

I I E

I I i I

I:

0

--- ~ -------,---------1~

-m

  • x m

-0 CV)

--- - - . ---~ --" -----**** ----- - ~ --***-*-* -*-

Item Part 30uu A~~Al PUMP No.

Number Description PA~l'§ -1o- 30A1001 ------ - hyclt~~u_lj.Q .JllQ:~qr_

2o

...... __.. ___ 30A1002 *--*- - pot~IJ?l~~~~J?..)_ __

3. 24/30A1003 o' ring_ ______seal ..,. ... -...._... **-

(1*, _-----rralliJ

4. 30A1004 motor ltey

~F1r ______

,...,I

. -~---

5. 30A1005 ... . ...

bearing carrier 19, 6. 24/30A1006 locl\ nut (2)

I I:

, . ,. I.. I. ....... . 7. 24/30A1007 loci\ washer It 8. 24/30A1008 bearing cone (2)

II II _,____ ;17... :_ 18.. 9. 24/30A1009 bearJit_9.~U~J~L .

1/

10. 24/30A1010 pu m...P~ll__c_lf!______

'-15:T1 : .*".*a**.,...

._. .. " \"*'**-""( *--------* -.~ -J/..-. -... ____.,_,_ '-13 110  : 24/30A1 011 mecho seal assem

-- * ** en!~~*£. . rr. JJ * '~ ** * - ~- .!?._. __i. 2..~!90~1 0~ 2 seal holder


.-- . --I.--.:.I',(':"::.-~~r-==

I I _____12.: ...1 ~. :_?.4/~_91\ 1~-1~

0 r ':1;?:;,.-::--=::.,

_ . o'ri11g seal

',1q.*,.* ~*~--- '***

  • I .... ~...':::::::-

r-~ :::::-->-...

___-"~;:.-- :;-=}~... .

=

(

-~~--*1

-... . ...... *- -* ~~*:_ . .

---"'20 , . 14. i 24/30A1014 __ ___Jp se~l .

  • . 15. *-*- -: 30A1015 bro~~....P~~elle!~

C:.:.I*IP  ? * - i~=;r ---~~ ,. .- --/ -\;:_~~~- . - - J.11.1 ~-- - - -

a-.':------ - . ~tLJJ ~----- _. - - . __ _ ---_ . 16. 24/30A1 016 propeller key

--- .... - - - * *~ s~~ ~.~ ~* -***- .:;;~*.:.:.:* _...... 10 .

  • 17.  : 24/30A1017 flat washer,ss i* fa~*----: -2473o~j_Q_18 .. . riytoc~,~~--- -----------

-.'f_:.-:.~:-~ ~Q [= i)*l~x~~r_- - 1 *--:: . ~

  • * - * - * -- * - * * - * *- * ,:r".l , _, ; * ... * * - * * - * , .

. 9. ;- .. * ~- * ~ * *" ~ _ , ..-*** I ~ 21.

5 *- -*- . " ' . ' 4. i 19.  : 3QA19.~@ ... . . diffuser housing

_________..___- .. I 20. 30A1020 wear ring

    • ---**~ I

--- i j * * - - - -- - * - -- * -

  • 1 Bi~--:.::~..1-B \_21. __30A1021 __ .. _ inlet bell housing

,-) rg)(.,-~ r I *.-.*--..  : 22. ' 30A1022 . intake screen I*o l 6. '*

~---1:~ -

__:22o - j 23o --24/SOA1023

  • quicl~ coupler-(R) - 1 1240 *.:i4J?o~:!_o]{_ -f.quiCit ~ouplet~-(r)' . 1 ec11~~ i 25. 2430A1025 ! sea!_hld_ bolt~(6)_

<:.::<:::.<;1=::::.=:::;::-;:-::-- ~~~~'-'-*---- . --- --~--* *-:*-_ --::-:-* !:.:::<"

j________ _2<!_~ __1_021 OPT_Lint~!~~--l_lausing 45~~

. . . 2:

1. 10/2005

4 1 D NOTES

1. DIMENSIONS IN INCHES D
2. DO NOT SCALE DRAWING
3. DRAWING IS NOT FOR CONSTRUCTION
4. CONSULT FACTORY FOR CERTlFIEO DIMENSIONS
5. APPROX. WEIGHT: 7500 LBS
6. FUEL CAPACilY: 175 GALLONS 528" c c

~li~

71i B

1"'"--

1ftT nP I~

I I I I ""¢

" -I gedwin pumps

!i!

~

1M'=~~,:-==-~~ UEA

- HS300 POWER PACK A r-::1

. . . . _ *==

-...=_"=-=a;,.,.---r:::::l

.==;:;;-* ----==-=-----r::l.,..::r.=:l-.dl-1

...=-=.., .--1 D. STETSER . .. . ** . .. .

J 06068 HF485 175 GAL SKID A

I ~ .u~u* oan

  • I

--==*

-=--

!:o f/11 X

X I I X I l 2547 IHIZT 1 OF 1 4 3 2 1

A1'1'ACHMEN:P D WA'Jl'D llTSE St1'tPLEMEN1!AL FORM F

WATER USE PERMIT APPLICATION Diversion and Impoundment Use Supplemental Form F South Florida Water Management District P.O. Box 24680, West Palm Beach, Florida 33416-4680 (561) 686-8800 www.sfwmd .gov/ePermitting Diversion and Impoundment - Projects that divert surface water through a pump or operable water control structure, or divert a combination of surface and groundwater to a conveyance canal network system which the applicant has legal control to operate and maintain for the purposes of providing for the reasonable-beneficial demands of secondary users and consumptive and non-consumptive uses.

SECTION F1 - PARCEL/SITE INFORMATION WATER USE PERMIT # (if application is for renewal or modification): _ _ _ _ _ _ _ _ _ _ __

Section (s), County Parcel Identification Parcel/Site Name Acres Township, Range Number (or attach digital (each non-contiguous parcel or field) Serviced (S_/T_S/R_E) GIS Shape file) 30-7029-001-0012 398.74 29/57S/40E Refer to attached Project Overview Map and GIS shape file Refer to attached Project Overview 30-7029-000-0010 17.96 29/57S/40E Map and GIS shape fil e Refer to attached Project Overview 30-7029-001-0011 136.38 29/57S/40E Map and GIS shape file TOTAL ACRES OWNED/LEASED 553 .08 Submit a map showing (if available, provide items A th rough C in a District-approved electronic format, e.g. ESRI shapefile, Autocad, DXF, KMZ, or compatible GIS file) :

A. The project boundaries of the property owned or controlled by the permittee/applicant; B. A north arrow and map scale; C. Labeled landmarks such as canals, roads and political IDoundaries; and D. The location of all secondary users of the system , including irrigated acreage and land use type .

Page 1 of 2 Incorporated by reference in rule 40E-2 .101 (F.A.C.)

Form 1386 (2014-07)

SECTION F2- WATER USE INFORMATION Please describe the operation by attaching the following information, as applicable (refer to the Applicant's Handbook, Section 2.3.2.C):

IZI The extent (length, cross sections and depth) of the canal network used to deliver the associated water -o~=~~~sgo~~lis 0 Land use classifications within the serviced area IX) Surface water demands directly withdrawn for the system- Refer to EO No. 2014-078-DAO-WU/ROW/ERP 0 Seepage Losses 0 Water necessary to maintain groundwater elevations for the purpose of aquifer recharge and saltwater intrusion prevention 0 Evaporation losses from the canal surfaces 0 Established control elevations during one and 10 year drought events 0 Copies of executed agreements with dependent secondary users IXJ Historic use (permit renewal with no changes)- Refer to EO No. 2014-078-DAO-WU/ROW/ERP

~ Canal locations with established wet and dry season control elevations- Refer to EO No. 2014-078-DAO-WU/ROW/ERP and Project Overview Map SECTION F3- REQUESTED WATER USE Complete the requested water use table below. Provide projected water amount for each use type and the associated water source(s).

2 3 Source of Water (MGY /MGM )

Use Type Source 1 Name1 Source 2 Name Source 3 Name L31 E (N} Canal Secondary Users Total Max. Avail. I Max. Avail. I I Maintenance Demands Total Max. Avail. I Max. Avail.

I I Total Max. Avail. I Max. Avail.

I I 1

Prov1de the name of the water source. Examples Include C 51, LWDD E-1 2

MGY = Million gallons per year of water to be withdrawn over a 12-month time period under a 1-in-1 0 year drought condition (i.e. 1,500,000 gallons each day/1 ,000,000 = 1.5 x 365 = 547.5) 3 MGM = Maximum million gallons per month of water to be withdrawn in any single month under the 1-in-1 0 year drought condition.

SECTION F4- WATER CONSERVATION Please refer to District specific water conservation requirements, in the Applicant's Handbook, Section 2.0.

Page 2 of 2 Incorporated by reference in rule 40E-2.101 (F.A.C.)

Form 1386 (2014-07)

lZZ] Project Boundary I=:J Seclion Township & Range f~ Parcels PROJECT FPL TURKEY POINT COOLING CANAL FRESHWATER RECHARGE TITLE PROJECT OVERVIEW MAP CONSU LTANT YYYY-MM-DD 2014-12-22 PREPARED NRL DESIGN NRL REFERENCE (//JGolder Associates REVIEW KAB PROJECT BOUNDARY, FPL & GOLDER ASSOC IATES INC., 2014 APPROVED KAB PARCELS, MIAMI DADE COUNTY, 2014 SECTION TOWNSHIP & RANGE, FDEP PROJECT CONTROL Rev. FIGURE 1412354 006 0 1