Other: L-PI-13-007, Plants Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), L-PI-13-080, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, L-PI-14-018, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049), L-PI-14-078, Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number., L-PI-15-021, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report, L-PI-16-007, Sixth Six-Month Status Report in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), L-PI-16-063, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, L-PI-16-096, Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, ML12305A287, ML13197A116, ML14030A540, ML14041A204, ML15083A415, ML15224B396, ML15237A403, ML16014A754, ML16014A755
|
MONTHYEARML12305A2872012-10-29029 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other L-PI-13-007, Plants Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-02-26026 February 2013 Plants Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13183A5032013-07-0303 July 2013 Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval ML13197A1162013-07-15015 July 2013 Online Reference Portals for NRC Review of Mitigating Strategies Submittals (Order EA-12-049) Project stage: Other L-PI-13-080, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-26026 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-PI-13-083, Reply to a Notice of Violation2013-08-28028 August 2013 Reply to a Notice of Violation Project stage: Request ML14041A2042014-02-26026 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2, TAC Nos.: MF0834 and MF0835 Project stage: Other L-PI-14-018, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2014-02-26026 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other ML14030A5402014-02-27027 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other L-PI-14-078, Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number.2014-08-25025 August 2014 Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number. Project stage: Other L-PI-15-021, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-26026 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15083A4152015-03-31031 March 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15224B3962015-08-20020 August 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 Project stage: Other ML15237A4032015-08-25025 August 2015 Plants Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other L-PI-15-086, Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-09-29029 September 2015 Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request ML15273A2912015-10-25025 October 2015 Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design-Basis External Events Project stage: Approval ML16014A7542016-01-14014 January 2016 Notification of Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML16014A7552016-01-14014 January 2016 Enclosure 1, Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report2016-01-14014 January 2016 Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report Project stage: Other L-PI-16-007, Sixth Six-Month Status Report in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-24024 February 2016 Sixth Six-Month Status Report in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other L-PI-16-063, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-17017 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-PI-16-096, Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-12-13013 December 2016 Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other 2015-10-25
[Table View] |
Text
Mr. Kevin K. Davison Site Vice President UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 25, 2015 Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 2 - RELAXATION OF THE SCHEDULE REQUIREMENTS FOR ORDER EA-12-049, "ISSUANCE OF ORDER TO MODIFY LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS" (TAC NO. MF0835)
Dear Mr. Davison:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A735), the U.S. Nuclear Regulatory Commission (NRC) ordered Northern States Power Company, Minnesota (the licensee), doing business as Xcel Energy, to take certain actions at the Prairie Island Nuclear Generating Plant (PINGP),
associated with the Fukushima Near-Term Task Force Recommendations. Order EA-12-049 directed that actions be taken by licensees to develop and implement strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities during beyond-design-basis external events (BDBEEs).
Section IV of the order states that licensees proposing to deviate from requirements contained in NRC Order EA-12-049 may request that the Director, Office of Nuclear Reactor Regulation, relax or rescind certain conditions, upon demonstration of good cause. By letter dated September 29, 2015 (ADAMS Accession No. ML15272A505), Xcel Energy submitted a request for an extension of the Order EA-12-049 full compliance date to 60 days following completion of the fall 2015 refueling outage at PINGP, Unit 2, in order to complete construction of an equipment storage structure being built as part of the strategy for compliance with Order EA-12-049. The licensee's request dated September 29, 2015, indicates that construction delays caused by labor issues, weather, and complexities associated with first-time unique building construction necessitate the need for schedule relaxation.
The licensee's letter dated September 29, 2015, indicates that the method chosen to implement the requirements of Order EA-12-049 calls for a single robust storage building to provide reasonable protection from a postulated BDBEE for the equipment, such as portable pumps and generators, incorporated into the mitigating strategy for Order EA-12-049. The building is designed to provide protection from all postulated site external events except for flooding, for which an alternative strategy is planned. The design and construction of the new structure was scheduled to be completed in time to allow placement of the equipment and validation of equipment deployment time prior to start up from the fall 2015 refueling outage at PINGP, Unit
- 2. However, the construction of the building has been delayed, beyond the anticipated schedule, due to three major issues:
1.) Shortage of craft labor in the immediate geographical area, 2.) Weather delays due to rain and electrical storms that have exceeded expectations, 3.) Construction challenges associated with building a structurally complicated one-of-a-kind building.
To allow completion of the building construction, moving equipment and supplies into the building, and performing validation of equipment deployment time, the licensee requests an extension of the PINGP, Unit 2, order implementation date from the completion of the fall 2015 refueling outage to no later than 60 days following completion of the fall 2015 refueling outage.
As detailed in the request dated September, 29, 2015, the licensee notes that the equipment necessary to implement the mitigating strategies will be temporarily stored at the deployment locations, providing a degree of protection from a postulated seismic event. Additionally, the proposed extension timeframe corresponds to a seasonal period that is outside the most probable timeframe for tornados. The licensee will also take steps to protect the mitigating strategies equipment from cold weather, rain, snow, and ice. Since the flooding strategy depends on warning time to pre-position any necessary equipment, the storage building construction delay would not adversely impact the ability to cope with a flood scenario.
Therefore, during the relaxation period, an enhanced plant capability to mitigate a BDBEE will be in place. Further, the licensee notes that the extension period will not impact the PINGP, Unit 1 (full site) compliance date that occurs in the spring of 2016.
In light of the facts presented in the licensee's letter dated September 29, 2015, the NRC staff has determined that the licensee has demonstrated good cause for relaxation of the order implementation date. Construction of the robust building is a complicated construction activity that must be integrated with safe plant operations at the PINGP site. The NRC staff also considered the enhanced plant capability to mitigate a BDBEE that will be in place at PINGP, Unit 2, during the 60-day relaxation period. Further, the NRC staff notes that following the accident at Fukushima Dai-ichi, the NRC concluded that a sequence of events such as the Fukushima Dai-ichi accident is unlikely to occur in the United States based on the current regulatory requirements and existing plant capabilities. Given the plant-specific circumstances at PINGP and that completion by the proposed date is before December 2016, the ultimate implementation date established by the order, the NRC staff approves the requested relaxation.
Accordingly, based upon the authority granted to the Director, Office of Nuclear Reactor Regulation, the requirement of the order for full order implementation for PINGP, Unit 2 is relaxed until 60 days following the completion of the fall 2015 refueling outage at PINGP, Unit 2, to allow the licensee sufficient time complete the building construction, equipment storage, and equipment deployment time validation needed to fully implement the required strategies.
If you have any questions, please contact Peter Bamford, at 301-415-2833.
Docket No. 50-306 cc: Listserv
ML15273A291 OFFICE NRR/JLD/JOMB/PM NRR/JLD /LA NAME PBamford Slent DATE 9/30/2015 9/30/2015 OFFICE OGC, NLO NRR/JLD/D NAME DCylkowski JDavis DATE 10/6/2015 10/15/2015 Sincerely, IRA/
William M. Dean, Director Office of Nuclear Reactor Regulation RidsNrrLASLent Resource RidsOgcMailCenter Resource RidsOeMailCenter Resource RidsNrrMailCenter Resource RidsRgn3MailCenter Resource NRR/JLD/JOMB/BC (A) OE MHalter RFretz 10/1/2015 10/1/2015 NRR/D WDean 10/25/2015