Other: L-PI-13-007, Plants Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), L-PI-13-080, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, L-PI-14-018, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049), L-PI-14-078, Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number., L-PI-15-021, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report, L-PI-16-007, Sixth Six-Month Status Report in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), L-PI-16-063, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, L-PI-16-096, Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, ML12305A287, ML13197A116, ML14030A540, ML14041A204, ML15083A415, ML15224B396, ML15237A403, ML16014A754, ML16014A755
|
MONTHYEARML12305A2872012-10-29029 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other L-PI-13-007, Plants Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-02-26026 February 2013 Plants Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other L-MT-13-015, Plants Overall Integrated Plan in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents (Order Number EA-12-050)2013-02-28028 February 2013 Plants Overall Integrated Plan in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Hardened Containment Vents (Order Number EA-12-050) Project stage: Other L-MT-13-017, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13182A0512013-07-0202 July 2013 Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval ML13183A5032013-07-0303 July 2013 Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval ML13197A1162013-07-15015 July 2013 Online Reference Portals for NRC Review of Mitigating Strategies Submittals (Order EA-12-049) Project stage: Other L-PI-13-080, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-26026 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-PI-13-083, Reply to a Notice of Violation2013-08-28028 August 2013 Reply to a Notice of Violation Project stage: Request L-MT-13-079, Monticellos First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 Monticellos First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13220A1392013-11-25025 November 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies Project stage: Other L-PI-14-018, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2014-02-26026 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other ML14041A2042014-02-26026 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2, TAC Nos.: MF0834 and MF0835 Project stage: Other ML14030A5402014-02-27027 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other L-MT-14-014, Plants Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2014-02-28028 February 2014 Plants Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other L-PI-14-078, Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number.2014-08-25025 August 2014 Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number. Project stage: Other L-MT-14-073, Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Plants Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML14290A3672014-10-22022 October 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 Project stage: Other ML14294A0612014-11-21021 November 2014 Relaxation of Certain Schedules Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events Project stage: Approval L-MT-15-004, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2015-02-24024 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) Project stage: Other L-PI-15-021, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-26026 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15072A0982015-03-17017 March 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15083A4152015-03-31031 March 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other L-MT-15-059, Fifth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-20020 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15224B3962015-08-20020 August 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 Project stage: Other ML15237A4032015-08-25025 August 2015 Plants Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other L-PI-15-086, Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-09-29029 September 2015 Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request L-MT-15-047, Update of Information Related to NRC Order Update of Information Related to NRC Order EA-12-049, Mitigation Strategies for Beyond-Design-Basis External Events2015-10-12012 October 2015 Update of Information Related to NRC Order Update of Information Related to NRC Order EA-12-049, Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML15273A2912015-10-25025 October 2015 Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design-Basis External Events Project stage: Approval ML16014A7552016-01-14014 January 2016 Enclosure 1, Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML16014A7542016-01-14014 January 2016 Notification of Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report2016-01-14014 January 2016 Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report Project stage: Other L-MT-16-009, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-22022 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other L-PI-16-007, Sixth Six-Month Status Report in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-24024 February 2016 Sixth Six-Month Status Report in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other L-PI-16-063, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-17017 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-MT-16-038, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2016-08-19019 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other L-PI-16-096, Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-12-13013 December 2016 Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other L-MT-17-066, Supplemental Information for the Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events2017-09-28028 September 2017 Supplemental Information for the Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Supplement 2014-08-28
[Table View] |
Text
Xce/ Energy@
July 15, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant, Units 1 and 2 Docket Nos. 50-282 and 50-306 Renewed License Nos. DPR-42 and DPR-60 414 Nicollet Mall - MP4 Minneapolis, MN 55401 L-XE-13-009 10 CFR 50.4 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed License No. DPR-22 Online Reference Portals for NRC Review of Mitigating Strategies Submittals (Order EA-12-049) for Prairie Island Nuclear Generating Plant and Monticello Nuclear Generating Plant
References:
- 1. NRC letter to NSPM, "Monticello Nuclear Generating Plant-Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 (TAC NO. MF0923)," dated July 2, 2013.
- 2. NRC letter to NSPM, "Prairie Island Nuclear Generating Plant, Units 1 and 2 - Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 (TAC NOS. MF0834 and MF0835),"
dated July 3, 2013.
To improve the efficiency of the NRC reviews, the industry and the NRC staff discussed the use of an online reference portal that would allow the NRC staff and contractors limited read-only access to the basis documents and other materials cited in the responses to NRC Order EA-12-049. The online reference portal would allow the NRC staff to audit basis documents that support the information in the submittal. Documents necessary to support the NRC Safety Evaluation of the submittal will be identified by the staff and the licensees will be formally requested to submit those documents on the NRC docket.
The NRC issued letters (References 1 and 2) to Northern States Power Company, a Minnesota corporation, d/b/a Xcel Energy (hereafter "NSPM"), requesting the online
Document Control Desk Page 2 reference portals be set up and populated to support review of the responses for the Prairie Island Nuclear Generating Plant (PINGP) and the Monticello Nuclear Generating Plant (MNGP). The NRC staff requested written confirmation that NSPM agrees with the terms and condition set forth in the Reference 1 and 2 letters.
The purpose of this letter is to confirm that NSPM agrees to the terms and conditions in the NRC letter. Specifically, NSPM agrees to provide an online reference portal with the following conditions placed on the portal:
The online reference portal will be password-protected and passwords will be assigned to those directly involved in the review on a need-to-know basis; The online reference portal will be sufficiently secure to prevent staff from printing, saving, or downloading any documents; and Conditions of use of the online reference portal will be displayed on the log-in screen and will require concurrence by each user.
The above conditions will be maintained through the duration of the PINGP and the MNGP NRC Order EA-12-049 response reviews.
Please contact Lynne Gunderson, Licensing Engineer, at 612-396-0173, if additional information or clarification is required.
Summary of Commitments This letter makes no new commitments and no revisions to existing commitments.
Martin C. Murphy Director, Nuclear Licensing Regulatory Affairs Northern States Power Company - Minnesota cc: