ML15261A359

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/98-12,50-270/98-12 & 50-287/98-12 on 980422-0520.No Violations Noted.Major Areas Inspected: Engineering
ML15261A359
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 06/03/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML15261A358 List:
References
50-269-98-12, 50-270-98-12, 50-287-98-12, NUDOCS 9806160200
Download: ML15261A359 (9)


See also: IR 05000269/1998012

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos:

50-269, 50-270, 50-287, 72-04

License Nos:

DPR-38, DPR-47, DPR-55, SNM-2503

Report No:

50-269/98-12, 50-270/98-12, 50-287/98-12

.Licensee:

Duke Energy Corporation

Facility:

Oconee Nuclear Station, Units 1, 2, and 3

Location:

P. 0. Box 1439

Seneca, SC 29679

Dates:

April 22 - May 20, 1998

Inspectors:

M. Scott, Senior Resident Inspector

D. Billings, Resident Inspector

R. Carroll, Project Engineer

Approved by:

C. Ogle, Chief. Projects Branch 1

Division of Reactor Projects

Enclosure

9806160200 980603

PDR

ADOCK 05000269

PDR

EXECUTIVE SUMMARY

Oconee Nuclear Station, Units 1, 2. and 3

NRC Special Inspection Report 50-269/98-12.

50-270/98-12, and 50-287/98-12

The purpose of this special inspection was to review and assess the effects of

deficiencies identified with the Oconee Nuclear Station borated water storage

tank level instrumentation and emergency operating procedures. [Applicable

template codes and the assessment for items inspected are provided.]

Engineering

An apparent violation of Technical Specifications and 10 CFR 50.46 was

identified in all three Oconee units for inoperable borated water

storage tank level instruments due to uncompensation for instrument tap

height differences. This not only had the potential to render emergency

core cooling system pumps inoperable and interrupt long-term core

cooling, but could have precluded meeting the required 46 feet (350,000

gallons) of borated water available in the borated water storage tank

for emergency core cooling. (Section E.8.1; [4A-Poor])

An apparent violation of 10 .CFR 50 Appendix B. Criterion III was

identified in all three Oconee units for failures to appropriately

account for the as-built height configuration of the borated water

storage tank level instrument taps (in

system design drawings and

calibration procedures) and the reactor building emergency sump level

instrument uncertainties (in

emergency operating procedures). This not

only had the potential to render emergency core cooling system pumps

inoperable and interrupt long-term core cooling, but could have

precluded meeting the required 46 feet (350,000 gallons) of borated

water available in the borated water storage tank for emergency core

cooling.

(Section E.8.1; [4A-Poor])

Considered noteworthy, was the questioning attitude on the part of Self

Initiated Technical Audit team which initially identified the borated

water storage tank level instrumentation height discrepancy and the

potential emergency operating procedure sump swapover initiation

conflict brought on by reactor building .emergency sump level instrument

uncertainties.

(Section E.8.1; [5A-Good])

Appropriate root cause analysis and short-term corrective actions were

taken by the licensee upon identification of the borated water storage

tank level instrumentation height discrepancy and the potential

emergency operating procedure sump swapover initiation conflict brought

on by reactor building emergency sump level instrument uncertainties.

(Section E.8.1; [5B-Good])

Report Details

Summary of Plant Status

Unit 1 began and ended the period at 100 percent power.

Unit 2 began the period in a scheduled refueling outage. The unit ended the

period in hot shutdown with startup activities in progress.

Unit 3 began and ended the period at 100 percent power.

Review of Updated Final Safety Analysis Report (UFSAR) Commitments

While performing inspections discussed in this r

eport, the inspectors reviewed

the applicable portions of the UFSAR that related to the areas inspected. The

inspectors verified that the UFSAR wording was consistent with the.observed

plant practices, procedures, and parameters.

III. Engineering

E8

Miscellaneous Engineering Issues (92903)

E8.1

Borated Water Storage Tank Level Set Point Error and Emergency Operating

Procedure Discrepancy

a. Inspection Scope (37551. 92903)

Between November 10, 1997 and December 11, 1997, a licensee Self

Initiated Technical Audit (SITA) of the high pressure injection (HPI)

and low pressure injection (LPI) systems identified items requiring

engineering followup. Followup to the SITA findings by the licensee.

identified two concerns involving the borated water storage tank (BWST)

level instrumentation and an EOP conflict concerning manual emergency

core cooling system (ECCS) swapover from the BWST to the reactor

building emergency sump (RBES).

It was the scope of the special

inspection to review and assess the overall effects of these two

concerns.

b. Observations and Findings

Concern number (1):

BWST Level Instrumentation

On February 12. 1998, engineering conducted evaluation and followup of

the lack of a zero reference on the BWST design drawing. Engineering

identified an error on the drawing that affected all of the level

transmitters on each unit's BWST. The drawing revealed the BWST level

indicator taps to be approximately 1 foot (worst case 1.5 feet) below

the value used in the EOP calculations. Since this was not compensated

for in instrument scaling, this introduced an error between indicated

and actual BWST level.

To prevent air entrainment into the suction of

the ECCS pumps, the EOPs require the swapover from the BWST to the RBES

to be completed (i.e., RBES valves open and BWST valves closed) when

BWST level is

< 6 feet and > 2 feet. The condition of the as-found

2

instrumentation (i..e.. worst case indicating 1.5 feet above actual BWST

level) coupled with the EOP guidance, could have led to vortexing in the

BWST and ECCS pump air entrainment prior to completion of the swapover.

Accordingly, operations declared the BWST level instrumentation

inoperable on all three units, entered Technical Specification (TS) 3.0

for all three units, and initiated a one hour non-emergency notification

to the NRC. Maintenance personnel commenced calibrations of the level

transmitters simultaneously on all three units.

Each unit exited TS 3.0

and entered TS 3.3.4 for instrumentation when the calibration of the

first train of level instrumentation was completed. On February 13,

1998, maintenance completed the calibration of the second train of BWST

level instrumentation for each unit and exited TS 3.3.4 at 2:30 a.m. for

Unit 1, 3:09 a.m. for Unit 2. and 3:05 a.m. for Unit 3.

Licensee investigation identified that the BWST level instruments did

not have a height difference calculation included in the instrument

calibration from initial design. The 1986 safety analysis error

calculations, which became the "Emergency Procedure Guidelines Set

Point" document in 1988 (and revised in July 1989). did not identify the

height differences. The licensee replaced the level transmitters in

1989 to conform to Reg Guide 1.97 criteria, but did not identify the

height difference during that modification either. Another missed

opportunity to discover and correct the problem was during the

licensee's evaluation of Information Notice 91-75, Static Head

Corrections Mistakenly Not Included in Pressure Transmitter Calibration

Procedure.

Concern number (2): .EOP Conflict

During outages from December 1984 - December 1986. the current reactor

building (RB) level instruments were installed. On February 19. 1998,

during a review of the aforementioned SITA findings, engineering

identified that the RB wide range level instruments have large

uncertainties (+8.8 inches/-18.1 inches). These uncertainties could

create a conflict with EOP guidance for mitigation of Loss of Coolant

Accidents (LOCAs).

-The guidance in the EOPs from June 1995 - February 1998 required

initiation of the swapover of the suction for the Building Spray (BS)

and the LPI pumps from the BWST to the RBES when BWST level > 6 feet and

RB level > 4 feet. [Note: Implemented in 1985 to assure adequate RBES

inventory for beyond design basis accidents, the required EOP RB level

was changed from > 2 feet to > 3.5 feet in April 1988;-and then again to

> 4 feet at the end of May 1994. (The required EOP BWST level from 1985

to June 1995 was < 6 feet.)] The licensee determined that actual RB

water level at the time of swapover initiation would be 4.5 feet (worst

case 3.07 feet from April 1986 - November 1997 if trapped water issue

initially identified in Licensee Event Report 50-269/97-10 is

considered); thus, indicated sump levels could range from - 3 feet to

5 feet (worst case - 1.5 to - 3.8 feet). Considering the uncertainties

3

in .the RB level instrumentation, the EOP required BWST and RB level

conditions may not have indicated simultaneously (if

at all).

This

could have caused a delay in swapover initiation, resulting in possible

air binding of the pumps as described in concern number (1)

above.

Following licensee review, operations management provided interim

guidance to the operators to address the procedural deficiency and

completed a revision to the EOPs in late February 1998, which requires

swapover initiation when BWST level > 6 feet and RB level is increasing.

(Also a NOTE was added indicating that wide.range RB water level should

be 3 feet and increasing at the time of swapover.) Additionally,

engineering initiated a Failure Investigation Process (FIP) team to

assess the root cause, corrective actions; and past operability of the

systems. The licensee made a 10 CFR 50.72 notification to the NRC. The

licensee issued a preliminary report in Licensee Event Report (LER) 269/98-04, dated March 14, 1998, which was revised on April 7. 1998.

As indicated above, the licensee installed the current RB level

instruments from December 1984 - December 1986. Revised RB level

instrument uncertainty calculations in February 1988 (+8.8 inches/-21

inches) did not identify an EOP conflict since the RB level for a design

basis LOCA was 5.3 feet at the time. Similarly, an EOP conflict was not

identified in April 1988 when the RB level set point was changed to >

3.5 feet. However, in July 1989 (when the "Emergency Procedure

Guidelines Set Point" document was revised) and in May 1994 (when the RB

level set point was changed to 4 feet) the EOP conflict existed, but was

not recognized. Another opportunity to.identify the EOP conflict was

missed in November 1997 when the trapped water issue (i.e., potentiaT

blocking of installed reactor cavity flange drain and fuel transfer

canal drain strainers traps -

100,000 gallons of water) resulted in an

actual RB water level determination of 3.07 feet (to which the 1996

revised RB level uncertainties of +8.8 inches/-18.1 inches should have

been applied).

Due to previously unaccounted for water allowances

(i.e.. reactor coolant system shrinkage, pressurizer refill, BS piping

refill, and vapor content maintaining RB pressure), actual calculated RB

water level only increased to 4.5 feet after the trapped water issue was

resolved.

Evaluation of Safety Significance

10 CFR 50.46 requires that the ECCS must be designed to be capable of

long-term cooling of the reactor core. In conjunction with this: TS 3.3.4 requires that the BWST have operable two level instrument channels

and contain a minimum level of 46 feet of borated water: TS 3.3.1

requires two independent HPI trains capable of taking suction from the

BWST and LPI system to be operable TS 3.3.2 requires two independent

LPI trains capable of taking suction from the BWST and RBES to be

operable; and TS 3.3.6 requires both BS trains capable of taking suction

from the LPI system to be operable.

The time to exhaust the BWST inventory and manually swapover the ECCS

4

pumps to the RBES varies, depending on the size and location of the

break and the operating times of the pairs of ECCS suction valves from

the BWST and RBES. To prevent air entrainment into the suction of the

ECCS pumps, the EOPs require swapover to be completed (i.e., RBES valves

open and BWST valves closed) when BWST level is < 6 feet and > 2 feet.

Original EOP guidance indicated that swapover to the RBES should occur

upon receipt of a low-low level-alarm that was set at a BWST level of 3

feet (for which actual level would have been 1.5 feet if worst case

instrument tap height of 1.5 feet were applied): there was no

conditional RB level. Subsequently, EOP swapover guidance was changed

to:

BWST level < 6 feet AND RB level > 2 feet (1985); BWST level < 6

feet AND RB level > 3.5 feet (April 1988); BWST level < 6 feet AND > 4

feet (May 1994); and BWST level > 6 feet AND RB level > 4 feet (June

1995 - February 1998).

For all LOCA scenarios where indicated RB level would have been less

than that specified in the EOP at the time for swapover initiation, the

licensee determined that long-term cooling would be achieved. As

discussed in associated LER 50-269/98-04 (revision 1), this conclusion

was predicated on: personnel (operators, Shift Technical Advisor,

Technical Support Center) diligence; LPI and BS pump durability;

availability of the spare C LPI pump: and EOP recovery guidance. The

incremental core damage potential was estimated by the licensee to be

9.2E-7 for this event, compared to the nominal core damage probability

of 8.9E-5 per reactor.

Regardless, a conflict would have existed and the EOP could not have

been performed as written in all LOCA scenarios where RB level

instrument uncertainties would have resulted in indicated RB level being

less than that specified in the EOP at the time for swapover initiation.

Consequently, a resultant delay (coupled with an actual BWST water level

lower than indicated) could have led to vortexing the BWST in a time

limited LOCA scenario thereby, causing possible ECCS (LPI, HPI and BS)

pump inoperability and interruption of long-term core cooling due to air

entrainment prior to completion of the swapover from the BWST to the

RBES.

The inspectors determined that from initial construction until

correction in February 1998, the BWST level instrumentation in all three

Oconee Units did not have a height difference calculation included in

their instrument calibration: thereby making them inoperable due to

indicating as much as 1.5 feet higher than actual BWST level. This not

only had the potential to render ECCS-pumps inoperable and interrupt

long-term core cooling as discussed above, but could have precluded

meeting the required 46 feet (350.000 gallons) of borated water

available in the BWST for emergency core cooling. Accordingly, this is

being identified as apparent violation (EEI) 50-269.270.287/98-12-01:

Failure.to Meet TS and 10 CFR 50.46 for Long-Term Cooling Requirements.

The inspectors also determined that the failures to appropriately

account for the as-built height configuration of the BWST level

5

instrument taps (in

system design drawings and calibration procedures

from initial construction until February 1998) and the RBES level

instrument uncertainties (in

EOPs since instrument installation in

December 1986 until February 1998) did not meet the design control

requirements of 10 CFR 50 Appendix B. Criterion III.

This not only had

the potential to render ECCS pumps inoperable and interrupt long-term

core cooling as discussed above,-but could have precluded meeting the

required 46 feet (350,000 gallons) of borated water available in the

BWST for emergency core cooling. Accordingly, this is being identified

as EEI 50-269,270,287/98-12-02: Failure to .Meet Design Control

Requirements of 10 CFR 50 Appendix B. Criterion III.

Root Cause Analysis and Corrective Actions

The licensee's root cause investigation team concluded that the root

cause of the BWST level instrumentation problem was deficient

documentation (deficient written procedure). The root cause of the RBES

wide range water level EOP Set Point conflict was attributed to design

deficiency (inadequate design analysis). These failures to account for

the as-built height configuration of the BWST level instrument taps and

the RBES level instrument uncertainties could have led to the ECCS being

'seriously degraded or inoperable.

As indicated in LER 50-269/98-04 (revision 1). the licensee's corrective

actions included: revising the BWST drawing and level instrument

calibration procedure to add a zero reference for calibration:

recalibrating BWST level indicators: changing EOPs to resolve the

conflict; reviewing installed instruments used in surveillances and

periodic tests which might require head corrections (none impacted):

surveying Unit 2 reactor coolant system narrow and wide range pressure

instruments and revising calibration procedures to include head

correction (bounding evaluation performed for Units 1 and 3. revealing

no impact): plans to review all EOP.set points for accuracy, minimum,

and maximum values; plans to obtain precise elevations for Units 1 and 3

reactor coolant system narrow and wide range pressure instruments and

revise calibration procedures: plans to ensure directives/procedures

used to perform SITAs assure relevant operating experience is

appropriately addressed; plans to perform risk-informed review of

operating experience: and plans to develop a process to identify,

control and maintain Oconee-specific calculation inputs.

c.

Conclusions

Licensee-identified failures to appropriately account for the as-built

height configuration of the borated water storage tank level instrument

taps (in

system design drawings and calibration procedures) and the

reactor building emergency sump level instrument uncertainties (in

emergency operating procedures)could have potentially rendered emergency

core cooling system pumps inoperable and interrupted long-term core

cooling during a loss of coolant accident in any of the three Oconee

Units. Accordingly, two apparent violations were identified .for failure

6

to meet design control requirements of 10 CFR 50 Appendix B, Criterion

III and failure to meet the requirements of Technical Specifications and

10 CFR 50.46 for long-term core cooling.

Noteworthy was the questioning attitude on the part of Self-Initiated

Technical Audit team which initially identified the borated water

storage tank level instrumentat-ion height discrepancy and the potential

emergency operating procedure sump swapover initiation conflict brought

on by reactor building emergency sump level instrument uncertainties.

The root cause analysis and short-term corrective actions taken by the

licensee upon identification of the issue were considered appropriate.

E8.2 (Closed) Unresolved Item (URI) 50-269,270,287/98-02-10: Inaccurate BWST

and RBES Instrumentation

Following initial inspection of identified deficiencies with the borated

water storage tank level instrumentation and emergency operating

procedures for all three Units of the Oconee Nuclear Station, this URI

was opened pending an in-depth review of associated LER 50-269/98-04

(revision 1).

Based on such a review and the resultant apparent

violations identified in Section E8.1. this URI is considered closed.

V. Management Meetings and Other Areas

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee

management at the conclusion of the inspection on May 21. 1998. The licensee

acknowledged the findings presented. The inspectors asked the licensee

whether any materials examined during the inspection should be considered

proprietary. No proprietary information was identified.

PARTIAL LIST OF PERSONS CONTACTED

E. Burchfield, Regulatory Compliance Manager

T. Curtis, Operations Superintendent

T. Saville, Primary Systems Supervisor

W. Foster, Safety Assurance Manager

C. Little, Electrical Systems/Equipment Engineering Manager

W. McCollum, Vice President, Oconee Site

M. Nazar, Manager of Engineering

J. Forbes, Station Manager

J. Smith, Regulatory Compliance

Other licensee employees contacted included operations, engineering, and

maintenance personnel.

7

INSPECTION PROCEDURES USED

IP 37551:

Onsite Engineering

IP 92903:

Followup - Engineering

ITEMS OPENED, CLOSED, AND DISCUSSED

oened

50-269,270,287/98-12-01

EEI

Failure to Meet TS and 10 CFR 50.46 for

Long-Term Cooling Requirements (Section

E8.1)

50-269,270,287/98-12-02

EEI

Failure to Meet Design Control

Requirements of 10CFR 50 Appendix B,

Criterion III (Section E8.1)

Closed

50-269,270,287/98-02-10

URI

Inaccurate BWST and RBES Instrumentation

(Section E8.2)

Discussed

50-269/98-04 (rev 0 & 1)

LER

ECCS -Outside Design Basis Due To

Instrument Errors/Deficient Procedures

(Section E8.1)

LIST OF-ACRONYMS USED

BS

Building Spray

BWST

Borated Water Storage Tank

CFR

Code of Federal Regulations

EA

Enforcement Action

ECCS

Emergency Core Cooling System

EEI

Apparent Violation

EOP

Emergency Operating Procedures

ES

Engineered Safeguards

HPI

High Pressure Injection

LER

Licensee Event Report

LPI

Low Pressure Injection

LOCA

Loss of Coolant Accident

RB

Reactor Building

RBES

Reactor Building Emergency Sump

SITA

Self-Initiated Technical Audit

STA

Shift Technical Advisor

TS

Technical Specification(s)

TSC

Technical Support Center

UFSAR

Updated Final Safety Analysis Report

.

URI

Unresolved Item

USNRC

United States Nuclear Regulatory Commission