JUL 2 3 1981
Duke Power Company
ATTN:
Mr. W. 0. Parker, Jr.
Vice President, Steam Production
P. 0. Box 2178
78
Charlotte, NC 28242
Gentlemen:
Subject:
Report Nos. (Q
69/81-1
50-270/81-14 and 50-287/81-14
This refers to the routine safety inspection conducted by Mr. F. Jape of this
office on June 10 to July 10, 1981, of activities authorized by NRC License Nos.
DPR-38, DPR-47 and DPR-55 for the Oconee Nuclear facility and to the discussion
of our findings held with Mr. J. E. Smith, Station Manager, at the conclusion of
the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspectors.
Within the scope of this inspection, no violations or deviations were disclosed.
We have examined actions you have taken with regard to previously identified
enforcement matters and unresolved items.
The status of these items is discussed
in the enclosed report.
One new unresolved item resulted from this inspection and is discussed in the
enclosed report. This item will be examined during subsequent inspections.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this
letter and the enclosed report will be placed in the NRC's Public Document Room.
If the report contains any information that you believe to be exempt from
disclosure under 10 CFR 9.5(a)(4), it is necessary that you:
(a) notify this
office by telephone within ten days from the date of this letter of your
intention to file a request for withholding; and (b) submit within twenty-five
days from the date of this letter a written application to this office to
withhold such information. If your receipt of this letter has been delayed such
that less than seven days are available for your review, please notify this
office promptly so that a new due date may be established.
Consistent with
section 2.790(b)(1), such application must be accompanied by an affidavit
executed by the owner of the information which identifies the document or part
thereof sought to be withheld, and a full statement of the reasons on the basis
of which it is claimed that the information should be withheld from public
disclosure.
This section further requires the statement to address with
specificity the considerations listed in 10 CFR 2.790(b)(4). The information
8108180432 810723
PDR ADOCK 050002691
f
G
PDR1
JUL 2 3 1981
Duke Power Company
2
sought to be withheld shall be incorporated as far as possible into a separate
part of the affidavit. If we do not hear from you in this regard within the
specified periods noted above, the report will be placed in the Public Document
Room.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
Paul J. Kellogg, Acting Chief
Reactor Projects Branch 2, Division
of Resident and Reactor Project Inspection
Enclosures:
Inspection Report Nos. 50-269/81-14,
50-270/81-14 and 50-287/81-14
cc w/encl:
J. E. Smith, Station Manager
bcc w/encl:
NRC Resident Inspector
Central Files
Local Public Document Room
Washington Public Document Room
Nuclear Safety Information Center
Technical Information Center
Document Management Branch
State of South Carolina
RIRRPI
RI :RRPI
RII:RR
8 Mas
nt
PJKeogg
- 7/
//81
/A/81
7) 1/81