ML15215A137

From kanterella
Jump to navigation Jump to search

NRR E-mail Capture - Vogtle Electric Generating PLANT- Technical Review Checklist Related to Interim ESEP Supporting Implementation of NTTF R2.1, Seismic (TAC NO.MF5271 and MF5272)
ML15215A137
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/31/2015
From: Diane Jackson
Office of New Reactors
To: Mohamed Shams
Japan Lessons-Learned Division
References
TAC MF5271, TAC MF5272
Download: ML15215A137 (12)


Text

NRR-PMDAPEm Resource From: Jackson, Diane Sent: Friday, July 31, 2015 1:21 PM To: Shams, Mohamed Cc: DiFrancesco, Nicholas; Wyman, Stephen; Spence, Jane; Devlin-Gill, Stephanie; Roche, Kevin; Yee, On; Stirewalt, Gerry; Lyons, Sara; Jain, Bhagwat; Basavaraju, Chakrapani; Graizer, Vladimir; 50.54f_Seismic Resource; RidsNroDsea Resource

Subject:

VOGTLE ELECTRIC GENERATING PLANT- TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO.MF5271 AND MF5272)

Attachments: Vogtle R2.1 seismic ESEP staff review.docx July 31, 2015 MEMORANDUM TO: Mohamed K. Shams, Chief Hazards Management Branch (JHMB)

Japan Lessons-Learned Division Office of Nuclear Reactor Regulation FROM: Diane T. Jackson, Chief Geosciences and Geotechnical Engineering Branch 2 (RGS2)

Division of Site Safety and Environmental Analysis Office of New Reactors

SUBJECT:

VOGTLE ELECTRIC GENERATING PLANT- TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM EXPEDITED SEISMIC EVALUATION PROCESS SUPPORTING IMPLEMENTATION OF NTTF RECOMMENDATION 2.1, SEISMIC, RELATED TO THE FUKUSHIMA DAI-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NO.

MF5271 AND MF5272)

The NRC technical staff working through the Geosciences and Geotechnical Engineering Branches 1 and 2 (RGS1 and RGS2) completed the Technical Review Checklist of the VOGTLE ELECTRIC GENERATING PLANT response to Enclosure 1, Item (6) of the March 12, 2012, request for information letter issued per Title 10 of the Code of Federal Regulations, Subpart 50.54(f), to power reactor licensees and holders of construction permits requesting addressees to provide further information to support the NRC staffs evaluation of regulatory actions to be taken in response to Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic which implements lessons learned from Japans March 11, 2011, Great Thoku Earthquake and subsequent tsunami. This addresses the staff review of the interim Expedited Seismic Evaluation Process (ESEP) report in response to Requested Item (6) of Enclosure 1, Recommendation 2.1: Seismic, of the 50.54(f) letter. Attached is a file containing the technical review checklist to prepare a response letter to the licensee.

The NRC staff reviewed the information provided and, as documented in the enclosed staff checklist, determined that sufficient information was provided to be responsive to this portion of the Enclosure 1 of the 50.54(f) letter. The application of this staff review is limited to the interim ESEP as part of NTTF R2.1: Seismic activities.

This electronic memo constitutes the DSEA concurrence provided that only editorial changes are made to the staff assessment that would not affect the technical conclusions or technical context of the assessment.

This concludes the NRCs efforts associated with TAC NO. MF5271 and MF5272 for the review of the interim ESEP report for the VOGTLE ELECTRIC GENERATING PLANT.

1

Docket No: 50-424 and 50-425 CONTACT: Stephanie Devlin-Gill Office of New Reactors 301-415-5301 Copy: Nicholas DiFrancesco, Steve Wyman, Jane Spence, Stephanie Devlin-Gill, Kevin Roche, On Yee, Gerry Stirewalt, Sara Lyons, BP Jain, Basavaraju Chakrapani, Vladimir Graizer, 50.54f Seismic Resource, RidsNroDseaResource 2

Hearing Identifier: NRR_PMDA Email Number: 2268 Mail Envelope Properties (031774c5d3294445b36243de5fb56eb7)

Subject:

VOGTLE ELECTRIC GENERATING PLANT- TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO.MF5271 AND MF5272)

Sent Date: 7/31/2015 1:21:10 PM Received Date: 7/31/2015 1:21:11 PM From: Jackson, Diane Created By: Diane.Jackson@nrc.gov Recipients:

"DiFrancesco, Nicholas" <Nicholas.DiFrancesco@nrc.gov>

Tracking Status: None "Wyman, Stephen" <Stephen.Wyman@nrc.gov>

Tracking Status: None "Spence, Jane" <Jane.Spence@nrc.gov>

Tracking Status: None "Devlin-Gill, Stephanie" <Stephanie.Devlin-Gill@nrc.gov>

Tracking Status: None "Roche, Kevin" <Kevin.Roche@nrc.gov>

Tracking Status: None "Yee, On" <On.Yee@nrc.gov>

Tracking Status: None "Stirewalt, Gerry" <Gerry.Stirewalt@nrc.gov>

Tracking Status: None "Lyons, Sara" <Sara.Lyons@nrc.gov>

Tracking Status: None "Jain, Bhagwat" <Bhagwat.Jain@nrc.gov>

Tracking Status: None "Basavaraju, Chakrapani" <Chakrapani.Basavaraju@nrc.gov>

Tracking Status: None "Graizer, Vladimir" <Vladimir.Graizer@nrc.gov>

Tracking Status: None "50.54f_Seismic Resource" <50.54f_Seismic.Resource@nrc.gov>

Tracking Status: None "RidsNroDsea Resource" <RidsNroDsea.Resource@nrc.gov>

Tracking Status: None "Shams, Mohamed" <Mohamed.Shams@nrc.gov>

Tracking Status: None Post Office: HQPWMSMRS07.nrc.gov Files Size Date & Time MESSAGE 3064 7/31/2015 1:21:11 PM Vogtle R2.1 seismic ESEP staff review.docx 50866 Options Priority: Standard Return Notification: No Reply Requested: No

Sensitivity: Normal Expiration Date:

Recipients Received:

TECHNICAL REVIEW CHECKLIST BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO EXPEDITED SEISMIC EVALUATION PROCESS INTERIM EVALUATION IMPLEMENTING NTTF RECOMMENDATION 2.1 SEISMIC VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 DOCKET NOS. 50-424 AND 50-425 By letter dated March 12, 2012 (USNRC, 2012a), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f) Conditions of License (hereafter referred to as the 50.54(f) letter). Enclosure 1 of the 50.54(f) letter requests addressees to reevaluate the seismic hazard at their site using present-day methods and guidance for licensing new nuclear power plants, and identify actions to address or modify, as necessary, plant components affected with the reevaluated seismic hazards. Requested Information Item (6) in Enclosure 1 to the 50.54(f) letter requests addressees to provide an interim evaluation and actions taken or planned to address a higher seismic hazard relative to the design basis, as appropriate, prior to completion and submission of the seismic risk evaluation.

Additionally, by letter dated April 12, 20131, the Electric Power Research Institute (EPRI) staff submitted EPRI TR 3002000704 Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic (hereafter referred to as the guidance). The Augmented Approach proposed that licensees would use an Expedited Seismic Evaluation Process (ESEP) to address the interim actions as requested by Information Item (6) in the 50.54(f) letter. The ESEP is a simplified seismic capacity evaluation with a focused scope of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all AC power and loss of access to the ultimate heat sink to withstand the Review Level Ground Motion, which is up to two times the safe shutdown earthquake (SSE).

Due to the expedited and interim nature of the ESEP, the assessment does not include many considerations that are part of a normal risk evaluation. These deferred items, include but are not limited to, structures, piping, non-seismic failures, and operator actions, as well scenarios such as addressing loss of coolant accidents. By letter dated May 7, 20132, the NRC staff endorsed the guidance. Central and eastern United States licensees with a reevaluated seismic hazard exceeding the SSE submitted an ESEP interim evaluation in December 2014.

Consistent with the interim nature of this activity, the staff performed the review of the licensees submittal to assess whether the intent of the guidance was implemented. A multi-disciplined team checked whether the identified methods were consistent with the guidance. A senior expert panel reviewed the teams questions, if any, and checklist for consistency and scope.

New or updated parameters (e.g., In-Structure Response Spectra, High Confidence of Low Probability of Failure calculations) presented by the licensees were assessed only based on licensee statements for acceptability for the Item (6) response. The application of this staff review is limited to the ESEP interim evaluation as part of NTTF R2.1: Seismic activities.

1 ADAMS Accession No. ML13102A142 2 ADAMS Accession No. ML13106A331

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Vogtle Electric Generating Plant, Units 1 & 2 By letter dated December 30, 2014,3 Southern Nuclear Operating Co., Inc. (the licensee) provided an Expedited Seismic Evaluation Process (ESEP) report in a response to Enclosure 1, Requested Information Item (6) of the 50.54(f) letter, for the Vogtle Electric Generating Plant, Units 1 & 2 (Vogtle).

I. Review Level Ground Motion The licensee:

  • described the determination of the review level ground motion Yes (RLGM) using one of the means acceptable by the guidance
  • identified location of the control point and is consistent with March Yes submittal
  • compared the site ground motion response spectra used to select Yes the ESEP RLGM to the SSE Vogtle used 2 x SSE.

Notes from reviewer: None Deviation(s) or Deficiency(ies)s and Resolution:

No deviations or deficiencies were identified The NRC staff concludes:

  • the licensees RLGM meets the intent of the guidance Yes
  • the RLGM is reasonable for use in the interim evaluation Yes II. Selection of the Success Path The licensee:
  • described the success path Yes
  • described normal and desired state of the equipment for the Yes success path
  • ensured that the success path is consistent with the plants overall Yes mitigating strategies approach or provided a justification for an alternate path
  • stated that the selection process was in accordance with the Yes guidance or meets the intent of the guidance
  • used installed FLEX Phase 1 equipment as part of the success Yes path
  • included FLEX Phase 2 and/or 3 connections Yes
  • considered installed FLEX Phase 2 and/or 3 equipment Yes Notes from reviewer:None Deviation(s) or Deficiency(ies)s and Resolution:

No deviations or deficiencies were identified The NRC staff concludes that:

  • the selected success path is reasonable for use in the interim Yes evaluation
  • the licensee considered installed Phase 2 and 3 connections or Yes equipment in the interim evaluation 3 ADAMS Accession No. ML15049A517 2

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Vogtle Electric Generating Plant, Units 1 & 2 III. Selection of the Equipment List The licensee:

  • developed and provided the ESEL by applying the ESEP Yes
  • identified equipment considering the following functions:

o Core cooling (with focus on Mode 1) function Yes o Available, sustainable water source Yes o Containment function and integrity Yes Notes from reviewer:

1. The staff requested clarification regarding interlock failures for inaccessible valves that were excluded from consideration. The licensees response (ML15114A446) stated that remote operation of inaccessible valves is no longer part of the Phase 3 mitigation strategy. The licensee provided an explaination of how core cooling would be maintained. The staff finds that the response adequately addressed the question and met the intent of the guidance for this interim evaluation.

Deviation(s) or Deficiency(ies) and Resolution:

  • No deviations or deficiencies were identified PWR Plants ONLY The licensee included indicators / instrumentation for the following functions:

level, pressure, temperature, that would be indicative of (but not explicitly Yes identified to specific instruments): water level of the steam generator (SG),

pressure of SG, containment, and reactor coolant system (RCS); and temperature of the RCS.

BWR Plants ONLY The licenseeconsidered indicators for the following functions: level, pressure, temperature that would be indicative of, but not explicitly identified N/A with, specific instruments: Temperature of suppression pool, RCS, containment; pressure of suppression pool, RCS, and drywell; water level of the suppression pool.

Notes from reviewer:

1. The staff reviewed the rationale for the diesel fuel oil storage tank and fuel oil day tank components to be included only in the Unit 2 ESEL and not in the Unit 1 ESEL, because the licensees FLEX strategy relies on diesel-powered equipment beginning in Phase 2, including portable diesel generators and portable pumps. The staff reviewed the Mitigiating Strategies interim staff evaluation and audit report dated January 16, 2014 (ML13339A781). The staff noted that the licensee can cope with an extended loss of all power and loss of ultimate heat sink event potentially affecting both Units 1 and 2 by relying on one Unit 2 tank for a duration sufficient to obtain off-site resources and off-site fuel oil delivery. The staff determined that this information adequately addressed this issue, and meets the intent of the guidance, therefore, no clarification question was necessary.

Deviation(s) or Deficiency(ies) and Resolution:

  • No deviations or deficiencies were identified 3

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Vogtle Electric Generating Plant, Units 1 & 2 Through a sampling of the ESEP key components, the NRC staff concludes that:

  • the licensees process to develop the ESEL meets the intent of the Yes guidance for the interim evaluation
  • the desired equipment state for the success path were identified Yes
  • the licensee considered the support equipment for the ESEL Yes
  • both front-line and support systems appeared to be included in the ESEL as evidenced by inclusion of SSCs on the success path and of Yes support systems (e.g., batteries, motor control centers, inverters)

IV. Walkdown Approach The licensee:

  • described the walkdown screening approach, including walkbys Yes and walkdowns performed exclusively for the ESEP, in accordance with the guidance
  • credited previous walkdown results, including a description of Yes current action(s) to verify the present equipment condition and/or configuration (e.g., walk-bys), in accordance with the guidance
  • stated that the walkdown was performed by seismically trained Yes personnel Notes from reviewer: None Deviation(s) or Deficiency(ies)s and Resolution:
  • No deviations or deficiencies were identified The licensee:
  • described adverse material condition of the equipment (e.g., Yes material degradation)
  • credited previous walkdown results, included a description of Yes current action(s) to verify the present equipment condition (e.g.,

walk-bys), meeting the intent of the guidance The licensee:

  • described the conditions of structural items considered for the interim evaluation, including:

o spatial interactions (i.e., interaction between block walls and N/A (Note 1) other items/components) o anchorage Yes o piping connected to tanks (i.e., differential movement Yes between pipes and tanks at connections) 4

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Vogtle Electric Generating Plant, Units 1 & 2 Notes from reviewer:

1. The licensee stated that there are no block walls in the vicinity of the ESEL items.
2. The staff requested clarficiation regarding whether anchorage for ESEL items that screened out based on their functional capacity were evaluated. The licensees response (ML15114A446) stated that anchorage for each item on the ESEL was evaluated regardless of whether the ESEL item screened out of further review for functional and structural capacities and provided additional information regarding the seismic review team assessment.The staff finds that the response adequately addressed the question and meets the intent of the guidance for this interim evaluation.

Deviation(s) or Deficiency(ies) and Resolution:

  • No deviations or deficiencies were identified The licensee reported no deviations for Vogtle Units 1 and 2 If deviations were identified, there is a discussion of how the deficiencies were or will be addressed in the ESEP submittal report. N/A The NRC staff concludes that:
  • the licensee described the performed walkdown approach, Yes including any credited previous efforts (e.g., Individual Plant Examination of External Events(IPEEE) consistent with the guidance
  • the licensee addressed identified deviations consistent with the N/A guidance, if any V. Capacity Screening Approach and HCLPF Calculation Results The licensee:
  • described the capacity screening process for the ESEL items, Yes consistent with the guidance (e.g., use of EPRI NP-6041 screening table).
  • presented the results of the screened-out ESEL items in the ESEP Yes report.
  • described the development of in-structure response spectra (ISRS) Yes based on scaling
  • described the development of ISRS based on new analysis N/A consistent with the guidance
  • described the method for estimating HCLPF capacity of screened-in Yes ESEL items, including both structural and functional failure modes consistent with the guidance:

o use of Conservative Deterministic Failure Margin (CDFM) Yes o use of fragility analysis (FA) N/A o use of experience data or generic information N/A

  • credited IPEEE spectral shape for HCLPF capacity estimates is similar to or envelopes the RLGM, and anchored at the same control N/A point
  • presented the results of HCLPF capacities including associated 5

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Vogtle Electric Generating Plant, Units 1 & 2 failure modes for screened-in ESEL items Yes

  • reviewed the ESEL items with the lowest HCLPF values to ensure that their capacities are equal or greater than the RLGM Yes Notes from reviewer:
1. The staff requested clarification on the screening of ESEL items located at an elevation greater than 40 ft. above grade. The licensees response (ML15114A446) explained that there is no equipment on the VEGP ESEL located more than 40' above grade. The staff finds this response acceptable and meets the guidance for this interim evaluation.

Deviation(s) or Deficiency(ies) and Resolution:

  • No deviations or deficiencies were identified The NRC staff concludes that:
  • the licensee described the implementation of the capacity screening Yes process consistent with the intent of the guidance
  • the licensee presented capacity screening and calculation results, as Yes appropriate, in the ESEP report
  • the method used to develop the ISRS is consistent with guidance for Yes use in the ESEP
  • for HCLPF calculations, the licensee used HCLPF calculation Yes methods as endorsed in the guidance
  • no anomalies were noted in the reported HCLPF Yes VI. Inaccessible Items The licensee:
  • provided a list of inaccessible items Yes
  • provided a schedule of the planned walkdown and evaluation for all Yes inaccessible items
  • provided Regulatory Commitment to complete walkdowns Yes Vogtle will complete walkdowns and evaluations,and provide results no later than March 31, 2017.

Notes from reviewer:

1. The licensee stated that several local instruments and junction boxes were inaccessible and described the walkdown alternatives utilized in accordance with the guidance. All installed ESEP items were walked down or an alterative was utilized.

ESEP items which were not installed at the time of the walkdown were identified with commitments for follow-up actions.

2. The licensee stated that ESEL items (eight per unit) not installed at the time of the walkdowns will be evaluated after installation per the SMA methology by December 2016 (i.e., two years after submission of the ESEP report). The licensee committed to submit a letter summarizing the resultswithin 90 days following completion of ESEP activities but no later than March 31, 2017.

Deviation(s) or Deficiency(ies) and Resolution:

  • No deviations or deficiencies were identified 6

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Vogtle Electric Generating Plant, Units 1 & 2 The NRC staff concludes that the licensee:

  • listed inaccessible items Yes
  • committed to provide the results (e.g. walkdowns, walkbys, etc) of Yes the remaining inaccessible items consistent with the guidance
  • substitutions, if needed, were appropriately justified Yes VII. Modifications to Plant Equipment The licensee:
  • identified modifications for ESEL items necessary to achieve HCLPF No values that bound the RLGM (excluding mitigative strategies equipment (FLEX)), as specified in the guidance
  • provided a schedule to implement such modifications (if any), Yes consistent with the intent of the guidance
  • provided Regulatory Commitment to complete modifications Yes
  • provided Regulatory Commitment to report completion of Yes modifications Vogtle will:
  • complete modifications by: December 2016
  • report completion of modifications no later than March 31, 2017 Notes from reviewer:
1. The licensee indicated that no modifications were identified for installed ESEL items.

However, the licensee stated that ESEL items (eight per unit) not installed at the time of the walkdowns will be evaluated after installation per the SMA methology and will implement any necessary modificationsby December 2016 (i.e., two years after submission of the ESEP report). The licensee committed to submit a letter summarizing the results within 90 days following completion of ESEP activities but no later than March 31, 2017.

Deviation(s) or Deficiency(ies) and Resolution:

  • No deviations or deficiencies were identified The NRC staff concludes that the licensee:
  • identified plant modifications necessary to achieve the target seismic Yes capacity
  • provided a schedule to implement the modifications (if any) Yes consistent with the guidance VIII.

Conclusions:

The NRC staff assessed the licensees implementation of the ESEP guidance. Due to the interim applicability of the ESEP evaluations, use of the information for another application would require a separate NRC review and approval. Based on its review, the NRC staff concludes that the licensees implementation of the interim evaluation meets the intent of the guidance. The staff concludes that, through the implementation of the ESEP guidance, the licensee identified and evaluated the seismic capacity of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all AC power and loss of access to the ultimate heat sink to withstand a seismic event up to the Review Level Ground Motion (RLGM). In the case of Vogtle, the RLGM was set at the maximum ratio of two times the SSE in accordance with the guidance. The staff did not identify deviations or exceptions taken from the guidance. The 7

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Vogtle Electric Generating Plant, Units 1 & 2 application of this staff review is limited to the ESEP interim evaluation as part of NTTF R2.1:

Seismic activities. The licensee did not identify modifications for the installed ESEL items.

ESEL items not installed at the time of the walkdowns will be evaluated after installation and any necessary modifications will be completed by December 2016 (i.e., two years after submission of the ESEP report). The licensee committed to submit a letter summarizing the results within 90 days following completion of ESEP activities but no later than March 31, 2017.

In summary, the licensee, by implementing the ESEP interim evaluation, has demonstrated additional assurance which supports continued plant safety while the longer-term seismic evaluation is completed to support regulatory decision making. The NRC staff concludes that the licensee responded appropriately to Enclosure 1, Item (6) of the 50.54(f) letter, dated March 12, 2012, for Vogtle Electric Generating Plant, Units 1 and 2.

Principal Contributors: Vladimir Graizer, Kevin Roche, Sara Lyons, Jinsuo Nie, B.P. Jain, Basavaraju Chakrapani, Gerry Stirewalt, Carl Constatino (NRC Consultant) 8