ML15173A213

From kanterella
Jump to navigation Jump to search

NRR E-mail Capture - Dresden Units 2 and 3 - Technical Review Checklist Related to Interim ESEP Supporting Implementation of NTTF R2.1, Seismic (TAC No. MF5239 and MF5240)
ML15173A213
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 06/19/2015
From: Diane Jackson
Office of New Reactors
To: Mohamed Shams
Japan Lessons-Learned Division
References
TAC MF5239, TAC MF5240
Download: ML15173A213 (11)


Text

NRR-PMDAPEm Resource From: Jackson, Diane Sent: Friday, June 19, 2015 1:00 PM To: Shams, Mohamed Cc: DiFrancesco, Nicholas; Wyman, Stephen; Spence, Jane; Devlin-Gill, Stephanie; Roche, Kevin; Nakanishi, Tony; Lehman, Bryce; Tsirigotis, Alexander; Jardaneh, Mahmoud; Candelario, Luissette; 50.54f_Seismic Resource; RidsNroDsea Resource; Yee, On

Subject:

DRESDEN UNITS 2 AND 3 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5239 AND MF5240)

Attachments: Dresden R2.1 seismic ESEP NRC review.docx June 19, 2015 MEMORANDUM TO: Mohamed K. Shams, Chief Hazards Management Branch (JHMB)

Japan Lessons-Learned Division Office of Nuclear Reactor Regulation FROM: Diane T. Jackson, Chief Geosciences and Geotechnical Engineering Branch 2 (RGS2)

Division of Site Safety and Environmental Analysis Office of New Reactors

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM EXPEDITED SEISMIC EVALUATION PROCESS SUPPORTING IMPLEMENTATION OF NTTF RECOMMENDATION 2.1, SEISMIC, RELATED TO THE FUKUSHIMA DAI-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NO. MF5239 AND MF5240)

The NRC technical staff working through the Geosciences and Geotechnical Engineering Branches 1 and 2 (RGS1 and RGS2) completed the Technical Review Checklist of the DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 response to Enclosure 1, Item (6) of the March 12, 2012, request for information letter issued per Title 10 of the Code of Federal Regulations, Subpart 50.54(f), to power reactor licensees and holders of construction permits requesting addressees to provide further information to support the NRC staffs evaluation of regulatory actions to be taken in response to Fukushima Near-Term Task Force (NTTF)

Recommendation 2.1: Seismic which implements lessons learned from Japans March 11, 2011, Great Thoku Earthquake and subsequent tsunami. This addresses the staff review of the interim Expedited Seismic Evaluation Process (ESEP) report in response to Requested Item (6) of Enclosure 1, Recommendation 2.1:

Seismic, of the 50.54(f) letter. Attached is a file containing the technical review checklist to prepare a response letter to the licensee.

The NRC staff reviewed the information provided and, as documented in the enclosed staff checklist, determined that sufficient information was provided to be responsive to this portion of the Enclosure 1 of the 50.54(f) letter. The application of this staff review is limited to the interim ESEP as part of NTTF R2.1: Seismic activities.

This electronic memo constitutes the DSEA concurrence provided that only editorial changes are made to the staff assessment that would not affect the technical conclusions or technical context of the assessment.

This concludes the NRCs efforts associated with TAC NO. MF5239 and MF5240 for the review of the interim ESEP report for the DRESDEN NUCLEAR POWER STATION.

Docket No: 50-237 and 50-249 CONTACT: Stephanie Devlin-Gill Office of New Reactors 301-415-5301 Copy: Nicholas DiFrancesco, Stephen Wyman, Jane Spence, Stephanie Devlin-Gill, Kevin Roche, On Yee, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, Mahmoud Jardaneh, Luissette Candelario, 50.54(f)

Seismic Resource; RidsNroDsea Resource 1

Hearing Identifier: NRR_PMDA Email Number: 2166 Mail Envelope Properties (933495689F8EB5409FE4267845E41B8816D43EEF28)

Subject:

DRESDEN UNITS 2 AND 3 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5239 AND MF5240)

Sent Date: 6/19/2015 1:00:28 PM Received Date: 6/19/2015 1:00:30 PM From: Jackson, Diane Created By: Diane.Jackson@nrc.gov Recipients:

"DiFrancesco, Nicholas" <Nicholas.DiFrancesco@nrc.gov>

Tracking Status: None "Wyman, Stephen" <Stephen.Wyman@nrc.gov>

Tracking Status: None "Spence, Jane" <Jane.Spence@nrc.gov>

Tracking Status: None "Devlin-Gill, Stephanie" <Stephanie.Devlin-Gill@nrc.gov>

Tracking Status: None "Roche, Kevin" <Kevin.Roche@nrc.gov>

Tracking Status: None "Nakanishi, Tony" <Tony.Nakanishi@nrc.gov>

Tracking Status: None "Lehman, Bryce" <Bryce.Lehman@nrc.gov>

Tracking Status: None "Tsirigotis, Alexander" <Alexander.Tsirigotis@nrc.gov>

Tracking Status: None "Jardaneh, Mahmoud" <Mahmoud.Jardaneh@nrc.gov>

Tracking Status: None "Candelario, Luissette" <Luissette.Candelario@nrc.gov>

Tracking Status: None "50.54f_Seismic Resource" <50.54f_Seismic.Resource@nrc.gov>

Tracking Status: None "RidsNroDsea Resource" <RidsNroDsea.Resource@nrc.gov>

Tracking Status: None "Yee, On" <On.Yee@nrc.gov>

Tracking Status: None "Shams, Mohamed" <Mohamed.Shams@nrc.gov>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 3106 6/19/2015 1:00:30 PM Dresden R2.1 seismic ESEP NRC review.docx 49409 Options Priority: Standard Return Notification: No Reply Requested: No

Sensitivity: Normal Expiration Date:

Recipients Received:

TECHNICAL REVIEW CHECKLIST BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO INTERIM EXPEDITED SEISMIC EVALUATION PROCESS IMPLEMENTING NTTF RECOMMENDATION 2.1 SEISMIC DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 DOCKET NOS. 50-237 AND 50-249 By letter dated March 12, 2012 (USNRC, 2012a), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f) Conditions of License (hereafter referred to as the 50.54(f) letter). Enclosure 1 of the 50.54(f) letter requests addressees to reevaluate the seismic hazard at their site using present-day methods and guidance for licensing new nuclear power plants, and identify actions to address or modify, as necessary, plant components affected with the reevaluated seismic hazards. Requested Information Item (6) in Enclosure 1 to the 50.54(f) letter requests addressees to provide an interim evaluation and actions taken or planned to address a higher seismic hazard relative to the design basis, as appropriate, prior to completion and submission of the seismic risk evaluation.

Additionally, by letter dated April 12, 20131, the Electric Power Research Institute (EPRI) staff submitted EPRI TR 3002000704 Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic (hereafter referred to as the guidance). The Augmented Approach proposed that licensees would use an Expedited Seismic Evaluation Process (ESEP) to address the interim actions as requested by Information Item (6) in the 50.54(f) letter. The ESEP is a simplified seismic capacity evaluation with a focused scope of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all AC power and loss of access to the ultimate heat sink to withstand the Review Level Ground Motion, which is up to two times the safe shutdown earthquake (SSE).

Due to the expedited and interim nature of the ESEP, the assessment does not include many considerations that are part of a normal risk evaluation. These deferred items, include but are not limited to, structures, piping, non-seismic failures, and operator actions, as well scenarios such as addressing loss of coolant accidents. By letter dated May 7, 20132, the NRC staff endorsed the guidance. Central and eastern United States licensees with a reevaluated seismic hazard exceeding the SSE submitted an ESEP interim evaluation in December 2014.

Consistent with the interim nature of this activity, the staff performed the review of the licensees submittal to assess whether the intent of the guidance was implemented. A multi-disciplined team checked whether the identified methods were consistent with the guidance. A senior expert panel reviewed the teams questions, if any, and checklist for consistency and scope.

New or updated parameters (e.g., In-Structure Response Spectra, High Confidence of Low Probability of Failure calculations) presented by the licensees were assessed only based on licensee statements for acceptability for the Item (6) response. The application of this staff review is limited to the ESEP interim evaluation as part of NTTF R2.1: Seismic activities.

1 ADAMS Accession No. ML13102A142 2 ADAMS Accession No. ML13106A331

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Dresden Nuclear Power Station, Units 2 and 3 By letter dated December 26, 20143, Exelon Generating Co., LLC (the licensee), provided an Expedited Seismic Evaluation Process (ESEP) report in a response to Enclosure 1, Requested Information Item (6) of the 50.54(f) letter, for the Dresden Nuclear Power Station, Units 2 and 3 (Dresden).

I. Review Level Ground Motion The licensee:

  • described the determination of the review level ground motion Yes (RLNGM) using one of the means acceptable by the guidance
  • identified location of the control point and is consistent with March Yes submittal
  • compared the site ground motion response spectra used to select Yes the ESEP RLGM to the SSE.

Dresdenused a scaled SSE at a ratio of 1.78 Notes from the Reviewer:None Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section The NRC staff concludes:
  • the licensees RLGM meets the intent of the guidance Yes
  • the RLGM is reasonable for use in the interim evaluation Yes II. Selection of the Success Path The licensee:
  • described the success path Yes
  • described normal and desired state of the equipment for the success Yes path
  • ensured that the success path is consistent with the plants overall Yes mitigating strategies approach or provided a justification for an alternate path
  • stated that the selection process was in accordance with the Yes guidance or meets the intent of the guidance
  • used installed FLEX Phase 1 equipment as part of the success path Yes
  • included FLEX Phase 2 and/or 3connections Yes
  • considered installed FLEX Phase 2 and/or 3equipment Yes Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:
  • No deviation or deficiencies were found in the review of this particular section.

3 ADAMS Accession No. ML14360A123 Page 2

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Dresden Nuclear Power Station, Units 2 and 3 The NRC staff concludes that:

  • the selected success path is reasonable for use in the interim Yes evaluation
  • the licensee considered installed Phase 2 and 3 connections or Yes equipment in the interim evaluation.

III. Selection of the Equipment List The licensee:

  • developed and provided the ESEL by applying the ESEP Yes
  • identified equipment considering the following functions:

o Core cooling (with focus on Mode 1) function Yes o Available, sustainable water source(1) Yes o Containment function and integrity Yes Notes from the Reviewer:

1. The licensee did not list the low-pressure coolant injection discharge to the isolation condenser makeup connection point that is to be installed in the ESEL. However, the licensee stated in page 24 of the ESEP report:These items are being installed to meet the RLGM input. The staff finds this is to be an acceptable approach for the interim evaluation.

Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section.

For PWR Plants only The licensee included indicators / instrumentation for the following functions:

level, pressure, temperature, that would be indicative of (but not explicitly N/A identified to specific instruments): water level of the steam generator (SG),

pressure of SG, containment, and reactor coolant system (RCS); and temperature of the RCS.

For BWR Plants only The licensee considered indicators for the following functions:

level, pressure, temperature that would be indicative of (but not explicitly Yes identified to specific instruments): Temperature of suppression pool, RCS, containment); Pressure of suppression pool, RCS, and drywell; water level of the suppression pool,reactor pressure vessel (RPV) water level.

Notes from the Reviewer:

1. The staff asked a question to the licensee regarding the components necessary to indicate the wide range ofRPV water level. The staff finds that the licensee response (ML15089A005) adequately addressed the concern and met the intent of the guidance.

Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section.

Through a sampling of the ESEP key components, the NRC staff concludes Page 3

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Dresden Nuclear Power Station, Units 2 and 3 that:

  • the licensees process to develop the ESEL meets the intent of the Yes guidance for the interim evaluation.
  • the desired equipment state for the success path were identified Yes
  • the licensee considered the support equipment for the ESEL Yes
  • both front-line and support systems appeared to be included in the ESEL as evidenced by inclusion of SSCs on the success path and of Yes support systems (e.g., batteries, motor control center (MCC),

inverters).

IV. Walkdown Approach The licensee:

  • described the walkdown screening approach, including walkbys and Yes walkdowns performed exclusively for the ESEP, in accordance with the guidance Yes
  • credited previous walkdown results, including a description of current action(s) to verify the present equipment condition and/or configuration (e.g., walk-bys), in accordance with the guidance Yes
  • stated that the walkdown was performed by seismically trained personnel Notes from the Reviewer:None Deviation(s) or Deficiency(ies), and Resolution:
  • No deviation or deficiencies were found in the review of this particular section The licensee:
  • described adverse material condition of the equipment (e.g. material Yes degradation)
  • credited previous walkdown results, included a description of current action(s) to verify the present equipment condition (e.g., walk-bys), Yes meeting the intent of the guidance.

The licensee:

  • described the conditions of structural items considered for the interim evaluation, including:

o spatial interactions (i.e. interaction between block walls and Yes other items/components) o anchorage Yes o piping connected to tanks (i.e. differential movement between pipes and tanks at connections) Yes Page 4

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Dresden Nuclear Power Station, Units 2 and 3 Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section.

The licensee reported deviations for Dresden. No If deviations were identified, there is a discussion of how the deficiencies were or will be addressed in the ESEP submittal report. N/A The NRC staff concludes that:

  • the licensee described the performed walkdown approach, including Yes any credited previous efforts (e.g.,Individual Plant Evaluation for External Events (IPEEE)) consistent with the guidance
  • the licensee addressed identified deviations consistent with the N/A guidance, if any V. Capacity Screening Approach and HCLPF Calculation Results The licensee:
  • described the capacity screening process for the ESEL items, Yes consistent with the guidance (e.g., use of EPRI NP-6041 screening table).(1)
  • presented the results of the screened-out ESEL items in the ESEP Yes report
  • described the development of ISRS based on scaling Yes
  • described the development of ISRS based on new analysis N/A consistent with the guidance
  • described the method for estimating HCLPF capacity of screened-in Yes ESEL items, including both structural and functional failure modes consistent with the guidance:

o use of Conservative Deterministic Failure Margin (CDFM) Yes o use of fragility analysis (FA) N/A o use of experience data or generic information Yes

  • credited IPEEE spectral shape for HCLPF capacity estimates is similar to or envelopes the RLGM, and anchored at the same control N/A point (3)
  • presented the results of HCLPF capacities including associated failure modes for screened-in ESEL items Yes
  • reviewed the ESEL items with the lowest HCLPF values to ensure Yes that their capacities are equal or greater than the RLGM Page 5

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Dresden Nuclear Power Station, Units 2 and 3 Notes from the Reviewer:

1. The staff asked a question to the licensee requesting the licensee to clarify whether screening was performed beyond 40 ft above grade. The staff finds that the licensee response (ML15089A005) provided a detailed answer summarizing the assessment of each ESEL item located beyond 40 ft above grade, consistent with the guidance.

Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section.

The NRC staff concludes that:

  • the licensee described the implementation of the capacity screening Yes process consistent with the intent of the guidance
  • the licensee presented capacity screening and calculation results, as Yes appropriate, in the ESEP report
  • the method used to develop the ISRS is consistent with guidance for Yes use in the ESEP
  • for HCLPF calculations, the licensee used HCLPF calculation Yes methods as endorsed in the guidance
  • no anomalies were noted in the reported HCLPF Yes VI. Inaccessible Items The licensee:
  • provided a list of inaccessible items(1) (2) Yes
  • provided a schedule of the planned walkdown and evaluation for all N/A inaccessible items
  • provided Regulatory Commitment to complete walkdowns. N/A Dresden will provide results or complete walkdown by: N/A N/A Notes from the Reviewer:
1. The licensee identified five inaccessible valves inside containment shield wall due to the online status of the plant.The licensee screened these valves by comparison to identical valves, in accordance with guidance.
2. The Diesel Storage Fuel Tank is buried and thus inaccessible. The licensee stated that the anchorage configurations of buried tanks are inherently seismically rugged and of no concern as judged by the licensees seismic review team (SRT)based on available documentation. The conclusion of the review as judged by the SRT was that there was adequateflexibility of the attached lines. The staff concluded this issue as acceptable for this interim evaluation.

Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section.

Page 6

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Dresden Nuclear Power Station, Units 2 and 3 The NRC staff concludes that the licensee:

  • listed inaccessible items Yes
  • committed to provide the results (e.g. walkdowns, walkbys, etc.) of Yes the remaining inaccessible items consistent with the guidance
  • substitutions, if needed, were appropriately justified Yes VII. Modifications to Plant Equipment The licensee:
  • identified modifications for ESEL items necessary to achieve HCLPF N/A values that bound the RLGM (excluding mitigating strategies equipment (FLEX)), as specified in the guidance.
  • provided a schedule to implement such modifications (if any), N/A consistent with the intent of the guidance.
  • provided Regulatory Commitment to complete modifications. N/A
  • provided Regulatory Commitment to report completion of N/A modifications.

Dresden will:

  • complete modifications by__N/A_
  • report completion of modifications by ______N/A___

Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section.

The NRC staff concludes that the licensee:

  • identified plant modifications necessary to achieve the target seismic N/A capacity
  • provided a schedule to implement the modifications (if any) N/A consistent with the guidance VIII.

Conclusions:

The NRC staff assessed the licensees implementation of the ESEP guidance. Due to the interim applicability of the ESEP evaluations, use of the information for another application would require a separate NRC review and approval. Based on its review, the NRC staff concludes that the licensees implementation of the interim evaluation meets the intent of the guidance. The staff concludes that, through the implementation of the ESEP guidance, the licensee identified and evaluated the seismic capacity of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all AC power and loss of access to the ultimate heat sink to withstand a seismic event up to the Review Level Ground Motion (RLGM). In the case of Dresden, the RLGM was scaled to the ratio of 1.78 times the SSE, in accordance with the guidance. The staff did not identify deviations or exceptions taken from the guidance. The licensee did not identify any modifications based on the ESEP.The application of this staff review is limited to the interim ESEP as part of NTTF R2.1: Seismic activities.

Page 7

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Dresden Nuclear Power Station, Units 2 and 3 In summary, the licensee, by implementing the interim ESEP, has demonstrated additional assurance which supports continued plant safety while the longer-term seismic evaluation is completed to support regulatory decision making. The NRC staff concludes that the licensee responded appropriately to Enclosure 1, Item (6) of the 50.54(f) letter, dated March 12, 2012, for Dresden Nuclear Power Station, Units 2 and 3.

Technical Reviewers: Stephanie Devlin-Gill, On Yee, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, Mahmoud Jardaneh, Luissette Candelario, and Richard Morante (NRC Consultant)

Page 8