MONTHYEARIR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) ML24135A1562024-05-13013 May 2024 July 2024 Emergency Preparedness Exercise Inspection - Request for Information ML24114A2032024-04-22022 April 2024 Request for Information for EP Program and Performance Indicator Verification Inspection (Wolf Creek Nuclear Generating Station) Inspection Report 05000482/2024003 ML24065A3662024-03-0404 March 2024 Notification of Site Inspection for License Renewal and Request for Information Inspection (05000323/2024011) IR 05000275/20230062024-02-28028 February 2024 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2023006 and 05000323/2023006) ML23249A2782023-09-0606 September 2023 Inservice Inspection Request for Information IR 05000275/20230052023-08-22022 August 2023 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2023005 and 05000323/2023005) - Mid Cycle Letter IR 05000275/20220062023-03-0101 March 2023 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2022006 and 05000323/2022006) ML23005A1732023-01-0909 January 2023 Notification of Commercial Grade Dedication Inspection IR 05000275/20220052022-08-23023 August 2022 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2022005 and 05000323/2022005) ML22194A8872022-07-11011 July 2022 September 2022 Emergency Preparedness Exercise Inspection - Request for Information Email ML22068A2312022-03-17017 March 2022 Notification of NRC Design Bases Assurance Inspection (Team) 05000275/2022011 and 05000323/2022011 and Initial Request for Information IR 05000275/20210062022-03-0202 March 2022 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2021006 and 05000323/2021006) ML22019A0412021-12-29029 December 2021 RFI ML21230A3902021-09-0101 September 2021 DC Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21229A2242021-08-17017 August 2021 Notification of NRC Triennial Heat Exchanger/Heat Sink Performance Inspection (05000275/2021004 and 05000323/2021004) and Request for Information ML21130A3642021-06-21021 June 2021 DC 2021401 Information Request ML21069A2102021-03-12012 March 2021 Notification of Inspection (NRC Inspection Report 05000275/2021002, 05000323/2021002) and Request for Information IR 05000275/20200062021-03-0303 March 2021 DC 2020 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 & 2 (Report 05000275/2020006 & 05000323/2020006) ML21061A3302021-02-25025 February 2021 Request for Information: Diablo Canyon Power Plant, Dated January 6, 2021; IR 05000275/323/2021-001 Occupational Radiation Safety Inspection - 2, 4 ML20301A2212020-10-27027 October 2020 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000275/2021010 and 05000323/2021010) and Request for Information IR 05000275/20200052020-09-0101 September 2020 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2020005 and 05000323/2020005) ML20280A5432020-06-0303 June 2020 DC 2020 PIR Request for Information ML20055E1082020-03-0303 March 2020 DC 2019006 Annual Assessment Letter IR 05000275/20190052019-08-30030 August 2019 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2, Report 05000275/2019005 and 05000323/2019005 IR 05000275/20180062019-03-0404 March 2019 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2018006 and 05000323/2018006) ML19043A9452019-02-20020 February 2019 Notification of Inspection (NRC Inspection Report 05000275/2019002, 05000323/2019002 and Request for Information IR 05000275/20180052018-08-31031 August 2018 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2018005 and 05000323/2018005) IR 05000275/20170062018-03-0101 March 2018 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2017006 and 05000323/2017006) ML17243A3022017-08-28028 August 2017 Updated Non-Public Security Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 IR 05000275/20170052017-08-28028 August 2017 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2017005 and 05000323/2017005) IR 05000275/20160062017-03-0101 March 2017 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2016006 and 05000323/2016006) ML17037D1232017-02-0606 February 2017 Notification of Inspection (NRC Inspection Report 05000275/2017002; 05000323/2017002) and Request for Information IR 05000275/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (NRC Physical Security Inspection Report Number 05000275/2016401 and 05000323/201640) IR 05000275/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2016005 and 05000323/2016005) ML16239A2532016-08-31031 August 2016 Mid-Cycle Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2016005 and 05000323/2016005) IR 05000275/20150062016-03-0202 March 2016 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2015006 and 05000323/2015006) IR 05000275/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (NRC Physical Security Inspection Report Number 05000275/2015401 and 05000323/2015401) IR 05000275/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2015005 and 05000323/2015005) IR 05000275/20140012015-03-0404 March 2015 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2, (Report 05000275/2014001 and 05000323/2014001) IR 05000275/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (NRC Physical Security Inspection Report Number 05000275/2014402 and 05000323/2014402) IR 05000275/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2014006 and 05000323/2014006) IR 05000275/20130012014-03-0404 March 2014 IR 05000275-13-001 & 05000323-13-001, 02/12/2014, Diablo Canyon, Unit 1 & 2, Annual Assessment Inspection Plan ML13246A2882013-09-0303 September 2013 Midcycle Assessment Letter 2013 ML13206A1892013-07-25025 July 2013 IR 05000275-13-004, and 05000323-13-004, Diablo Canyon Power - Notification of NRC Triennial Heat Sink Performance Inspection IR 05000275/20128012013-03-0404 March 2013 Annual Assessment Letter for Diablo Canyon Power Plant Units 1 & 2 (IR 05000275-12-801 and 05000323-12-801) ML13032A3142013-02-0101 February 2013 IR 05000275-13-007, 05000323-13-007, on 05/20/2013, Diablo Canyon - Notification of NRC Component Design Bases Inspection and Initial RAI IR 05000275/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - Diablo Canyon Power Plant (05000275/2012006, 05000323/2012006) IR 05000275/20120012012-03-0505 March 2012 Annual Assessment Letter for Diablo Canyon Power Plant - Units 1 and 2 (Report 05000275/2012001 and 05000323/2012001) ML1124401692011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Diablo Canyon Power Plant - Units 1 and 2 2024-08-22
[Table view] Category:Letter
MONTHYEARML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A1922024-11-0101 November 2024 Ltr to G. Frausto Coastal Band of Chumash Indians Re DCPP Dseis ML24302A1952024-11-0101 November 2024 Ltr to M. Olivas Tucker Ytt Re DCPP Dseis ML24302A1912024-11-0101 November 2024 Ltr to C. Mcdarment Tule River Tribe Re DCPP Dseis ML24302A1942024-11-0101 November 2024 Ltr to K. Kahn Santa Ynez Band of Chumash Indians Re DCPP Dseis ML24302A1962024-11-0101 November 2024 Ltr to SLO County Chumash Indians Re DCPP Dseis ML24302A1932024-11-0101 November 2024 Letter to G. Pierce Salinan Tribe of Monterey, SLO Re DCPP Dseis ML24302A1972024-11-0101 November 2024 Letter to V. Sage Walker Northern Chumash Tribal Council Re DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 IR 05000275/20240032024-10-30030 October 2024 Integrated Inspection Report 05000275/2024003 and 05000323/2024003 and Independent Spent Fuel Storage Installation Report 07200026/2024001 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24284A3122024-10-28028 October 2024 Ltr to P Ting, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants ML24284A3112024-10-28028 October 2024 Ltr to a Peck, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants IR 05000275/20240132024-10-28028 October 2024 – License Renewal Report 05000275/2024013 and 05000323/2024013 DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application 2024-09-09
[Table view] |
Text
rch 4, 2015
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR DIABLO CANYON POWER PLANT, UNITS 1 AND 2 (REPORT 05000275/2014001 AND 05000323/2014001)
Dear Mr. Halpin:
On February 17, 2015, the Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Diablo Canyon Power Plant, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014, through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined the performance at Diablo Canyon Power Plant, Units 1 and 2, during the most recent quarter was within the Regulatory Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because of one White finding in the Emergency Preparedness Cornerstone, for Units 1 and 2. In a letter to you, dated September 2, 2014, the NRC provided its mid-cycle 2014 assessment indicating that the performance at Diablo Canyon Power Plant, Units 1 and 2, was within in the Licensee Response Column of the NRCs ROP Action Matrix, though the NRC was still reviewing unresolved item URI 05000275/2013005-01; 05000323/2013005-01, Procedures for Recommending Protective Actions for Members of the Public on the Pacific Ocean.
In a letter to you, dated February 11, 2015, the NRC provided its final significance determination associated with an inspection finding in the Emergency Preparedness cornerstone for Units 1 and 2 (relative to the aforementioned unresolved item). The finding, which we concluded was of low to moderate safety significance (White), involved the failure to obtain prior approval for an emergency plan change that reduced the effectiveness of the emergency plan. Specifically, on November 4, 2005, without approval from the NRC, Diablo Canyon Power Plant staff removed instructions in emergency plan implementing procedures for making protective action recommendations for members of the public on the ocean within the 10-mile Emergency Planning Zone, reducing the plans effectiveness. Given the significance of the finding referenced above, the NRC determined the performance at Diablo Canyon Power Plant, Units 1 and 2, to be in the Regulatory Response Column of the ROP Action Matrix beginning the fourth quarter of 2014. The NRC plans to conduct a supplemental inspection to review the actions taken to address the performance issues associated with the White finding in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area. The NRC will plan this inspection activity when you provide written notification of your readiness for the inspection.
This supplemental inspection will provide assurance that the root causes and contributing causes of the risk-significant performance issues are understood, that the extent of condition and extent of cause of risk-significant performance issues are identified, and that your corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence.
The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation is ongoing. This audit includes an onsite component in order for the NRC to evaluate mitigating strategies as described in licensee submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to the first unit at each site achieving compliance with the Orders, and will aid staff in development of a Safety Evaluation for the site. The onsite component at your site has been scheduled for the week of August 17, 2015. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact Wayne Walker at (817) 200-1148 with any questions you have regarding this letter.
Sincerely,
/RA/
Troy W. Pruett, Director Division of Reactor Projects Docket: 05000275; 05000323 License: DPR-80, DPR-82 Enclosure:
Inspection Plan
Page 1 of 2 Diablo Canyon 02/26/2015 19:46:17 Inspection / Activity Plan Report 22 03/01/2015 - 06/30/2016 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site INSP - OPERATOR REQUAL INSPECTION 3 1, 2 05/18/2015 05/22/2015 IP 7111111B Licensed Operator Requalification Program ISFSI - ROUTINE INSPECITON 1 1, 2 06/08/2015 06/12/2015 IP 60855 Operation Of An ISFSI EP-1 - BIENNIAL EP PROGRAM INSPECTION 1 1, 2 07/20/2015 07/24/2015 IP 7111402 Alert and Notification System Testing 1, 2 07/20/2015 07/24/2015 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 07/20/2015 07/24/2015 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 07/20/2015 07/24/2015 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies EP-2 - EP PERFORMANCE INDICATORS 1 1, 2 07/20/2015 07/24/2015 IP 71151-EP01 Drill/Exercise Performance 1, 2 07/20/2015 07/24/2015 IP 71151-EP02 ERO Readiness 1, 2 07/20/2015 07/24/2015 IP 71151-EP03 Alert & Notification System Reliability RS 24 - RADIATION SAFETY 2 1, 2 08/03/2015 08/07/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 08/03/2015 08/07/2015 IP 71124.04 Occupational Dose Assessment RS 13 PI - RADIATION SAFETY 2 1, 2 10/12/2015 10/16/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/12/2015 10/16/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/12/2015 10/16/2015 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 10/12/2015 10/16/2015 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION 1R19 1 1 10/12/2015 10/23/2015 IP 7111108P Inservice Inspection Activities - PWR EB1-21T - DC COMPONENT DESIGN BASIS INSPECTION 6 1, 2 02/08/2016 03/11/2016 IP 7111121 Component Design Bases Inspection EXAMS - INITIAL OPERATOR EXAM 4 1 03/21/2016 03/25/2016 X02569 INITIAL EXAM DIABLO CANYON UNIT 1 (04/2016)
2 03/21/2016 03/25/2016 X02570 INITIAL EXAM DIABLO CANYON UNIT 2 (04/2016)
1 04/18/2016 04/26/2016 X02569 INITIAL EXAM DIABLO CANYON UNIT 1 (04/2016)
2 04/18/2016 04/26/2016 X02570 INITIAL EXAM DIABLO CANYON UNIT 2 (04/2016)
RS 12 PI - RADIATION SAFETY 2 1, 2 05/09/2016 05/13/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 05/09/2016 05/13/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 05/09/2016 05/13/2016 IP 71151-OR01 Occupational Exposure Control Effectiveness This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Diablo Canyon 02/26/2015 19:46:17 Inspection / Activity Plan Report 22 03/01/2015 - 06/30/2016 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RS 12 PI - RADIATION SAFETY 2 1, 2 05/09/2016 05/13/2016 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION 2R19 1 2 05/09/2016 05/20/2016 IP 7111108P Inservice Inspection Activities - PWR TSB 52B - BIENNIAL PI&R INSPECTION 4 1, 2 06/27/2016 07/01/2016 IP 71152B Problem Identification and Resolution This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. Please contact Wayne Walker at (817) 200-1148 with any questions you have regarding this letter.
Sincerely,
/RA/
Troy W. Pruett, Director Division of Reactor Projects Docket: 05000275; 05000323 License: DPR-80, DPR-82 Enclosure:
Inspection Plan DISTRIBUTION See next page DC 2014 Annual Assessment Ltr. ML15063A590 SUNSI Review ADAMS: Sensitive Non-Publicly Available Keyword By: RA Yes No Non-Sensitive Publicly Available RGN-002 OFFICE SPE:DRP/A BC:DRS/PSB1 BC:DRP/A D:DRS DD:DRP NAME RAlexander:tk MHaire WWalker AVegel TPruett SIGNATURE /RA/ /RA/
DATE 2/20/15 2/25/15 OFFICIAL RECORD
Letter to Edward Halpin from Troy Pruett, dated March 4, 2015 SUBJECT: ANNUAL ASSESSMENT LETTER FOR DIABLO CANYON POWER PLANT, UNITS 1 AND 2 (REPORT 05000275/2014001 AND 05000323/2014001)
DISTRIBUTION:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
Acting DRP Deputy Director (Thomas.Farnholtz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Thomas.Hipschman@nrc.gov)
Resident Inspector (John.Reynoso@nrc.gov)
Site Administrative Assistant (Madeleine.Arel-Davis@nrc.gov)
Branch Chief, DRP/A (Wayne.Walker@nrc.gov)
Senior Project Engineer, DRP/A (Ryan.Alexander@nrc.gov)
Project Engineer, DRP/A (Thomas.Sullivan@nrc.gov)
Project Engineer, DRP/A (Margaret.Tobin@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Siva.Lingam@nrc.gov)
RIV State Liaison Officer (Bill.Maier@nrc.gov)
DRP Branch Chiefs (R4DRP-BC1@nrc.gov)
DRS Branch Chiefs (R4DRS-BC1@nrc.gov)
Director, DIRS, NRR (Scott.Morris@nrc.gov)
Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)
Director, DORL, NRR (Michele.Evans@nrc.gov)
Deputy Director, DORL, NRR (George.Wilson@nrc.gov)
Acting Chief, PLB IV, DORL, NRR (Eric.Oesterle@nrc.gov)
Director, NSIR/DPR (Robert.Lewis@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Michael.Waters@nrc.gov))
ROPassessment.Resource@nrc.gov ROPreports.Resource@nrc.gov OEMAIL.Resource@nrc.gov