MONTHYEARET 14-0034, Application to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process2014-11-20020 November 2014 Application to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process Project stage: Request ML15037A4002015-02-0606 February 2015 NRR E-mail Capture - Acceptance Review Project stage: Acceptance Review ML15040A2692015-02-0909 February 2015 NRR E-mail Capture - Draft RAI for TAC No. MF5280 Project stage: Draft RAI ML15040A6252015-02-10010 February 2015 Request for Additional Information, License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process Project stage: RAI ET 15-0008, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation.2015-03-18018 March 2015 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation. Project stage: Response to RAI ML15082A0052015-03-27027 March 2015 Request for Additional Information, Round 2, Request to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process Project stage: RAI ET 15-0010, Response to Second Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation.2015-05-0404 May 2015 Response to Second Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation. Project stage: Request ML15169A2132015-07-28028 July 2015 Issuance of Amendment No. 212, Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation Project stage: Approval 2015-02-09
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24296A0632024-10-22022 October 2024 NRR E-mail Capture - Acceptance Review Wolf Creek License Amendment and Exemption Requests for a risk-informed Resolution to GSI-191 ML24263A0832024-09-19019 September 2024 NRR E-mail Capture - Acceptance Review Wolf Creek Revision to Technical Specification to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions ML24250A0252024-09-0606 September 2024 NRR E-mail Capture - Acceptance Review Wolf Creek Revision to Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology) ML23360A1562023-12-26026 December 2023 NRR E-mail Capture - Acceptance Review Wolf Creek Request to Revise the Ventilation Filter Testing Program in Technical Specifications ML23166A0622023-06-15015 June 2023 NRR E-mail Capture - Acceptance Review - Wolf Creek Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded post-tensioning System Components ML23090A1042023-03-31031 March 2023 NRR E-mail Capture - Acceptance Review Wolf Creek Request for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML23090A0072023-03-31031 March 2023 NRR E-mail Capture - Acceptance Review Wolf Creek Request for Relief for Follow-Up Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Peened Surface ML23080A0652023-03-21021 March 2023 NRR E-mail Capture - Wolf Creek Generating Station Evacuation Time Estimate Analysis Review ML23026A0222023-01-25025 January 2023 NRR E-mail Capture - Acceptance Review Wolf Creek Request to Revise Technical Specifications to Adopt Technical Specification Task Force (TSTF)-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements ML23009A4082023-01-0909 January 2023 NRR E-mail Capture - Acceptance Review Wolf Creek Request to Revise TS to Adopt Technical Specification Task Force (TSTF)-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22361A0052022-12-27027 December 2022 NRR E-mail Capture - Request for Additional Information Wolf Creek Request for Deviation from Fire Protection Program Requirements ML22321A2662022-11-16016 November 2022 January 2023 Emergency Preparedness Program Inspection - Request for Information ML22307A1372022-11-0202 November 2022 August 2022 Emergency Preparedness Exercise Inspection Unresolved Item - Request for Information ML22251A1312022-09-0808 September 2022 NRR E-mail Capture - Acceptance Review - Wolf Creek Request for Deviation from Fire Protection Program Requirements to Allow Use of Portable Lighting ML22215A2742022-08-0202 August 2022 Inservice Inspection Request for Information ML22208A1322022-07-27027 July 2022 NRR E-mail Capture - Wolf Creek Table of Contents LAR ML22166A3222022-06-14014 June 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22131A0522022-05-11011 May 2022 NRR E-mail Capture - Draft Supplemental Information Needed for Acceptance - Wolf Creek Inservice Inspection Relief Request for Reactor Pressure Vessel Head Penetration Nozzles with Peened Surface ML22055A1142022-02-23023 February 2022 NRR E-mail Capture - Request for Additional Information - Wolf Creek Request to Revise Diesel Generator Completion Time ML22045A4512022-02-14014 February 2022 NRR E-mail Capture - Request for Additional Information - Wolf Creek Steam Generator Inspection Report 24th Refueling ML22026A4392022-01-26026 January 2022 NRR E-mail Capture - Wolf Creek Acceptance Review Results - Removal of TS Table of Contents (L-2022-LLA-0008) ML22025A3612022-01-21021 January 2022 PI&R RFI Final ML21327A2602021-11-23023 November 2021 NRR E-mail Capture - Request for Additional Information - Wolf Creek Revision of Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ML21309A0332021-11-0505 November 2021 NRR E-mail Capture - Acceptance Review - Wolf Creek Revision of Technical Specification 3.8.1, AC Sources - Operating ML21307A4202021-11-0303 November 2021 NRR E-mail Capture - Acceptance Review - Wolf Creek Revision of Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ML21271A1952021-09-28028 September 2021 E-mail 9-28-21 RFI for Wc EP Inspection Nov 2021 ML21259A0652021-09-16016 September 2021 NRR E-mail Capture - Draft Supplemental Information Needed for Acceptance - Wolf Creek License Amendment and Exemption Requests Regarding GSI-191 (EPIDs L-2021-LLA-0152 and L-2021-LLE-0039) ML21221A1282021-08-0505 August 2021 NRR E-mail Capture - Urgent: Draft Request for Additional Information - Wolf Creek one-time Request for Exemption from the Biennial Emergency Preparedness Exercise ML21189A0252021-07-0101 July 2021 NRR E-mail Capture - Acceptance Review - Wolf Creek Request Revision to the Emergency Plan Related to on-shift Staffing ML21230A3922021-05-19019 May 2021 May 19, 2021 Dricks Response to Gurdziel Letter Dated May 13, 2021 - August 17, 2021 ML21102A3342021-04-12012 April 2021 Email 4-12-21 RFI for In-Office Rvw of Recent RERP and a Related EPIP Change ML21064A0342021-03-0404 March 2021 NRR E-mail Capture - Wolf Creek Generating Station Upcoming Steam Generator Tube Inservice Inspection ML20353A2712020-12-18018 December 2020 NRR E-mail Capture - Acceptance Review - Wolf Creek Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange ML20349A3092020-12-14014 December 2020 NRR E-mail Capture - Acceptance Review - Wolf Creek License Amendment Request for Change to Owner Licensee Names ML20297A3022020-10-22022 October 2020 NRR E-mail Capture - Acceptance Review - Wolf Creek Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ML20262A7512020-09-17017 September 2020 NRR E-mail Capture - Requests for Additional Information: Wolf Creek Amendment Request to Modify Technical Specification Surveillance Frequency Consistent with TSTF-425 ML20191A0222020-07-0606 July 2020 NRR E-mail Capture - Acceptance Review - Wolf Creek Request in Support of Replacement Engineered Safety Features Transformers with Load Tap Changers ML20162A1642020-06-0909 June 2020 Email June 9, 2020 - RFI in Preparation for Wolf Creek EP Program Inspection ML20149K4272020-05-22022 May 2020 NRR E-mail Capture - Acceptance Review - Wolf Creek License Amendment Request Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) ML20133J8972020-05-12012 May 2020 12 May 2020 E-mail - RFI for NRC In-Office Inspection of Recent Wcngs Eplan_Eal Changes ML20132A3442020-05-11011 May 2020 NRR E-mail Capture - Acceptance Review - Wolf Creek Generating Station License Amendment Request to Revise Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML20009E4802020-01-0909 January 2020 Relief Request to Utilize Code Case N-666-1 for Wolf Creek Generating Station - Request for Additional Information ML19273A0232019-09-30030 September 2019 NRR E-mail Capture - Acceptance Review - License Amendment Request to Revise Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System, ML19268B7172019-09-25025 September 2019 NRR E-mail Capture - Acceptance Review - Inservice Inspection (ISI) Program Relief Request to Use Code Case N-666-1 ML19261A2272019-09-18018 September 2019 NRR E-mail Capture - Regulatory Audit Plan - Wolf Creek Generating Station License Amendment Request to Revise Technical Specification 3.3.5 ML19255H3032019-09-12012 September 2019 NRR E-mail Capture - Acceptance Review - Relief Request I4R-07 to Utilize Code Case N-513-4 ML19224A5242019-08-12012 August 2019 NRR E-mail Capture - Request for Additional Information - License Amendment Request to Revise Wolf Creek Generating Station Technical Specification 3.3.5 ML19274D2752019-07-31031 July 2019 Request for Information-IR 05000482 2019-004, Dated 7/31/2019 ML19203A2362019-07-19019 July 2019 LTR-19-0291 Tom Gurdziel, E-mail July 18, 2019, Confirmatory Order on Wolf Creek ML19112A1772019-04-22022 April 2019 NRR E-mail Capture - Acceptance Review - License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation 2024-09-06
[Table view] |
Text
NRR-PMDAPEm Resource From: Lyon, Fred Sent: Monday, February 09, 2015 10:23 AM To: Wideman Steve G (stwidem@WCNOC.com)
Cc: Muilenburg William T (wimuile@WCNOC.com)
Subject:
Draft RAI for TAC No. MF5280 Heres an RAI that Im preparing to send you; 45 day response from date of letter. Please share it with your folks and let me know if you need a clarifying phoncon. Thanks, Fred P.S. these are due to the deviations from the TSTF you requested.
By letter dated November 20, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14330A247), Wolf Creek Nuclear Operating Corporation (the licensee) submitted to the U.S. Nuclear Regulatory Commission (NRC) a license amendment request to revise the Wolf Creek Generating Station (WCGS) Technical Specifications (TS) requirements to address NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, as described in Technical Specification Task Force (TSTF) Traveler TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation.
The NRC staff requests the following additional information in order to complete its review of the request.
Reactor Systems Branch (SRXB) Questions:
- 1. What were the historic void volumes found that are applicable to performance of TS surveillance requirements (SRs) 3.5.2.3 and 3.6.6.9, and how did these compare to the acceptance criteria? How do those void volumes compare to follow-up calculations that were performed if the original criteria were not met?
- 2. Is the WCGS design basis no gas? If not, please provide the documentation that established the design basis.
- 3. Please provide a description of the process used to restore the plant to the design basis condition at the earliest practical time following discovery of a gas volume that exceeds the design basis.
- 4. Please describe the methodology used to determine gas volumes that do not jeopardize operability that are applicable to SRs 3.5.2.3 and 3.6.6.9.
- 5. How is potential leakage from the reactor coolant system addressed?
1
Hearing Identifier: NRR_PMDA Email Number: 1865 Mail Envelope Properties (Fred.Lyon@nrc.gov20150209102300)
Subject:
Draft RAI for TAC No. MF5280 Sent Date: 2/9/2015 10:23:25 AM Received Date: 2/9/2015 10:23:00 AM From: Lyon, Fred Created By: Fred.Lyon@nrc.gov Recipients:
"Muilenburg William T (wimuile@WCNOC.com)" <wimuile@WCNOC.com>
Tracking Status: None "Wideman Steve G (stwidem@WCNOC.com)" <stwidem@WCNOC.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 1992 2/9/2015 10:23:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: