Letter Sequence Request |
---|
|
Results
Other: CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, CNL-14-133, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos.., CNL-15-037, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-15-175, Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-16-026, Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 2012, ML12307A104, ML13063A183, ML13247A286, ML14041A192, ML15033A430
|
MONTHYEARML12307A1042012-10-29029 October 2012 Tennessee Valley Authority - Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13063A1832013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13247A2862013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML14041A1922014-02-16016 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Sequoyah Nuclear Plant, Units 1 and 2, TAC Nos.: MF0864 and MF0865 Project stage: Other ML14002A1132014-02-19019 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Acceptance Review CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-03-0505 March 2014 Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other CNL-14-133, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos..2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos.. Project stage: Other ML14302A1972014-11-0606 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Acceptance Review L-2014-362, Request for Schedule Relaxation from NRC Order EA-12-049 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-12-19019 December 2014 Request for Schedule Relaxation from NRC Order EA-12-049 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request CNL-15-037, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15033A4302015-03-0303 March 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-15-065, Request for Schedule Relaxation from NRC Order EA-12-049, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design External Event2015-04-0202 April 2015 Request for Schedule Relaxation from NRC Order EA-12-049, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design External Event Project stage: Request ML15104A7032015-04-29029 April 2015 Relaxation of the Schedule Requirements of Order EA-12-049, Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. Project stage: Approval CNL-15-175, Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-16-026, Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 20122016-02-11011 February 2016 Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 2012 Project stage: Other 2014-03-05
[Table View] |
|
---|
Category:Letter type:L
MONTHYEARL-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-157, Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles2024-10-0303 October 2024 Response to Requests for Additional Information Regarding License Amendment Request (278) to Facilitate a Transition to 24-Month Fuel Cycles L-2024-147, Submission of Periodic Reports2024-10-0101 October 2024 Submission of Periodic Reports L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-112, Condition Prohibited by Technical Specifications2024-07-10010 July 2024 Condition Prohibited by Technical Specifications L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report L-2024-072, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report L-2024-073, Cycle 34 Core Operating Limits Report2024-05-0101 May 2024 Cycle 34 Core Operating Limits Report L-2024-048, Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision2024-04-30030 April 2024 Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision L-2024-069, Radiological Emergency Plan Revision 762024-04-22022 April 2024 Radiological Emergency Plan Revision 76 L-2024-066, Sixth 10-Year Inservice Testing Interval Relief Request No. PR-022024-04-17017 April 2024 Sixth 10-Year Inservice Testing Interval Relief Request No. PR-02 L-2024-057, 0 for Turkey Point, Unit 3 - Condition Prohibited by Technical Specifications2024-04-11011 April 2024 0 for Turkey Point, Unit 3 - Condition Prohibited by Technical Specifications L-2024-013, Submittal of Periodic Reports2024-03-28028 March 2024 Submittal of Periodic Reports L-2024-040, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-03-28028 March 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-047, Proposed Use of a Subsequent ASME Code Edition and Addenda2024-03-28028 March 2024 Proposed Use of a Subsequent ASME Code Edition and Addenda L-2024-044, Revised Steam Generator Tube Inspection Reports2024-03-19019 March 2024 Revised Steam Generator Tube Inspection Reports L-2024-011, and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-014, 2023 Annual Radioactive Effluent Release Report2024-02-29029 February 2024 2023 Annual Radioactive Effluent Release Report L-2024-025, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-02-22022 February 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation L-2024-008, Supplement to License Amendment Request 278. Incorporate Advanced Fuel Products. Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles2024-02-0909 February 2024 Supplement to License Amendment Request 278. Incorporate Advanced Fuel Products. Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2024-007, Inservice Inspection Program Owners Activity Report (OAR-1)2024-01-18018 January 2024 Inservice Inspection Program Owners Activity Report (OAR-1) L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-172, Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons. Firearms Background Checks. and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-146, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-078, License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles2023-11-15015 November 2023 License Amendment Request 278, Incorporate Advanced Fuel Products, Extend Surveillance Intervals and 10 CFR 50.46 Exemption Request to Facilitate Transition to 24-Month Fuel Cycles L-2023-077, License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis2023-10-11011 October 2023 License Amendment Request 277 Updated Spent Fuel Pool Criticality Analysis L-2023-110, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-08-25025 August 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-115, Inservice Inspection Program Owner'S Activity Report (OAR-1)2023-08-21021 August 2023 Inservice Inspection Program Owner'S Activity Report (OAR-1) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 L-2023-094, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-07-27027 July 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) L-2023-086, Request Temporary Suspension of Turkey Point License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation.2023-06-28028 June 2023 Request Temporary Suspension of Turkey Point License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation. L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-069, Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project2023-05-31031 May 2023 Response to Requests for Additional Information Regarding License Amendment Request No. 276, Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2023-072, Preparation and Scheduling of Operator Licensing Examinations2023-05-22022 May 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal L-2023-061, 2022 Annual Radiological Environmental Operating Report2023-05-12012 May 2023 2022 Annual Radiological Environmental Operating Report 2024-09-25
[Table view] |
Text
0December FPL.
19, 2014 L-2014- 362 U. S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, D.C. 20555-0001 Re: Turkey Point Unit 3 Docket Nos. 50-250 Florida Power and Light Company's, Turkey Point Unit 3, Request for Schedule Relaxation from NRC Order EA-12-049 "Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
References:
- 1. US. Nuclear Regulatory Commission, Order Number EA-12-049, Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012 (ML12056A045)
This letter transmits a request for relaxation of schedule requirements contained in the Nuclear Regulatory Commission (NRC) Order EA- 12-049.
By letter dated March 12, 2012, (Reference 1) the NRC ordered Florida Power & Light Company (FPL) to take certain actions at Turkey Point Units 3 and 4, associated with the Fukushima Near-Term Task Force Recommendations. Order EA-12-049 directed that actions be taken by licensees to develop and implement strategies to maintain or restore core cooling, containment and spent fuel pool (SFP) cooling capabilities during beyond-design-basis external events.
Section IV of the order states, "As applicable, the Director, Office of Nuclear Reactor Regulation or the Director, Office of New Reactors may, in writing, relax or rescind any of the above conditions upon demonstration by the Licensee or [construction permit] holder of good cause."
In accordance with Section IV of NRC Order EA-12-049, FPL, is requesting that the Director, Office of Nuclear Reactor Regulation, relax the requirement for completion of full implementation for Turkey Point Unit 3, as prescribed in Section IV A.2 of NRC Order EA 049 for reasons detailed in the attachment to this letter. That requirement states in part, "All holders of operating licenses issued under Part 50... shall complete full implementation no later than two (2) refueling cycles after submittal of the overall integrated plan, as required in Condition C. L.a, or December 31, 2016, whichever comes first."
Florida Power & Light Company 9760 S.W. 344 HStreet Homestead, FL 33035
Turkey Point Unit 3 L-2014-362 Docket No. 50-250 Page 2 of 2 The proposed schedule relaxation aligns the Turkey Point Unit 3 to Turkey Point Unit 4 schedule for full compliance with the NRC Order EA-12-049 requirements.
FPL considers that, upon approval by the NRC, the alternative full implementation date regarding NRC Order EA- 12-049 proposed in the attachment will constitute a condition of the NRC Order EA-12-049 for Turkey Point Unit 3.
There are no new regulatory commitments contained in this letter.
Should you have any questions regarding this submittal, please contact Mr. Robert J. Tomonto, Turkey Point Licensing Manager, at 305-246-7327.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on December /, 2014 Sincerely, 4<6 Michael Kiley Site Vice President Turkey Point Nuclear Plant Enclosure cc: USNRC Regional Administrator, Region II USNRC Project Manager, Turkey Point Nuclear Plant USNRC Senior Resident Inspector, Turkey Point Nuclear Plant
ATTACHMENT to L-2014-362 REQUEST FOR SCHEDULE RELAXATION OF NRC ORDER EA-12-049 REQUIREMENT IV.A.2 FOR TURKEY POINT NUCLEAR PLANT UNIT 3 Relaxation Request:
Pursuant to Section IV of the Nuclear Regulatory Commission (NRC) Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (Reference 1), Florida Power & Light Company's (FPL),
Turkey Point Unit 3, herby submits a request for schedule relaxation from the Order requirements for completion of full implementation no later than two (2) refueling cycles after submittal of the overall integrated plan as required in Condition C. L.a of the Order, or December 31, 2016, whichever occurs first.
Order Requirement from Which Relaxation is Requested:
NRC Order EA-12-049,Section IV.A.2 requires completion of full implementation of the Order requirements no later than two (2) refueling cycles after submittal of the overall integrated plan, as required in Condition C. 1.a of the Order, or December 31, 2016, whichever comes first.
In accordance with the requirements of the Order, FPL submitted the Turkey Point Units 3 and 4 Mitigation Strategies Overall Integrated Plan (Reference 2) on February 26, 2013. The first six-month status report (Reference 3) revised the milestones to show a change in the target completion date for full implementation due to the longer duration of the extended power uprate refueling outages. Accordingly, the second refueling outage is currently scheduled to commence in October 2015 for Unit 3 and in March 2016 for Unit 4. Therefore, consistent with the schedule requirements of order EA- 12-049, full implementation of the mitigating strategies for Unit 3 must be completed prior to startup from the October 2015 refueling outage, and for Unit 4, prior to the startup from the March 2016 refueling outage.
Justification for Relaxation Request:
NRC Order EA- 12-049 requires the development, implementation, and maintenance of guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event.Section II of this order dictates the need to have guidance and strategies available to prevent fuel damage in the reactor and spent fuel pit should the loss of power, motive force and normal access to the ultimate heat sink affect all units at a site simultaneously.
Turkey Point Nuclear Plant is a two unit site with significant physical and procedural interdependencies. The two units share certain common structures, systems and components (such as auxiliary feedwater cross connections, and DC buses), common control room, and common Operational Staff resources.
Page 1 of 3
ATTACHMENT to L-2014-362 Compliance to NRC Order EA-12-049 schedule requirements for full implementation for Turkey Point Unit 3 would result in an interim period (for approximately six months) that the two units would not be consistently configured for responding to the beyond design basis event at the site. For example, the low leakage reactor coolant pump seals would not have been replaced on Unit 4 yet. This inconsistency in plant design configuration would complicate the cooldown requirements and it would result in conflicting demands on how to use the limited supply of the emergency feedwater make-up water during the event mitigation philosophy for both Turkey Point units.
The physical modifications for Unit 3 will be completed prior to restart from the second refueling outage, currently scheduled for November 2015. While most of the physical modifications are unit specific, due to the interdependency of needed systems and structures, the interim period would require special procedures and training that would create operational challenges on both units with respect to external event mitigation philosophy. As such, compliance to the Unit 3 schedule requirements of the NRC Order EA-12-049 would create a considerable hardship without a compensating increase in the level of safety.
FPL is requesting herein that the Director, Office of Nuclear Reactor Regulation, relax the requirement for full implementation for the Turkey Point Unit 3 as prescribed in Section IV.A.2 of NRC Order EA-12-049 schedule requirements. Specifically, FPL proposes to defer the full implementation of the Order requirement for Turkey Point Unit 3 to align with the implementation of Turkey Point Unit 4 to meet the NRC Order EA- 12-049 requirements.
Accordingly, FPL requests that the NRC Order EA-12-049,Section IV.A.2 requirements for full implementation date for the Turkey Point Unit 3 be relaxed to the following milestone:
Turkey Point Unit 3 - Restart from the scheduled Unit 4 Cycle 29 refueling outage (Forecasted for May 2016)
The requested schedule relaxation to the alternative full implementation date for Unit 3 would allow both Turkey Point Units 3 and 4 to be in compliance with the NRC Order EA-12-049 requirements at the same time.
The justification for this relaxation is based on a reduced risk to safety through the implementation of a more consistent and overall site response to a beyond design basis event through the use of a consistent and unified approach to procedural development and training.
From a natural hazard risk perspective, the Turkey Point seismic reanalysis has determined that the maximum potential seismic activity that could affect the site is significantly less than the current licensing basis. The reevaluated flood hazards events that are not bounded by the current licensing basis are: the hurricane storm surge and the local intense precipitation. In the case of the hurricane storm surge event, the proposed schedule relaxation of approximately six months spans the calendar during the lowest probable hurricane activity (Hurricane season is June 1st through November 30th in the Eastern US). For the local intense precipitation, the Page 2 of 3
ATTACHMENT to L-2014-362 potential flooding levels do not adversely affect the equipment important to safety.
Accordingly, the risk of these natural hazard events during the six months relaxation period is considered negligible.
FPL considers that upon approval by the NRC, the alternative full implementation date, proposed above, will constitute a condition of the NRC Order EA-12-049 for Turkey Point Unit 3.
==
Conclusion:==
As described above, compliance with the Unit 3 NRC Order EA-12-049 schedule requirements for full implementation of the mitigation strategies would result in hardship or unusual difficulty without a compensating increase in the level of safety. Therefore, in accordance with the provisions of Section IV of the Order, we request relaxation of the requirement described in Section IV.A.2 of the NRC Order Ea- 12-049.
References:
I. US. Nuclear Regulatory Commission, Order Number EA-12-049, Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012 (ML12056A045)
- 2. L-2013-061, Florida Power and Light Company's Overall Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 26, 2013 ( ML13072A038)
- 3. L2013-249, Florida Power and Light Company's First Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 21, 2013 (ML13248A311)