Other: CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, CNL-14-133, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos, CNL-15-037, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-15-175, Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-16-026, Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 2012, ML12307A104, ML13063A183, ML13247A286, ML14002A113, ML14041A192, ML14302A197, ML15033A430
|
MONTHYEARML12307A1042012-10-29029 October 2012 Tennessee Valley Authority - Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13063A1832013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13182A3962013-07-0505 July 2013 And Watts Bar Nuclear Plant - Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval ML13247A2862013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML13252A0082013-08-29029 August 2013 Submittal of the Details of the Planned Drill to the Revised Flood Mode Operation Abnormal Operating Procedure (AOP) N.03, External Flooding Project stage: Request ML14041A1922014-02-16016 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Sequoyah Nuclear Plant, Units 1 and 2, TAC Nos.: MF0864 and MF0865 Project stage: Other ML14002A1132014-02-19019 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-03-0505 March 2014 Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other 05000327/LER-2014-001, Regarding Never Performed Technical Specification Surveillance for Common Spare Component Cooling System Pump2014-03-26026 March 2014 Regarding Never Performed Technical Specification Surveillance for Common Spare Component Cooling System Pump Project stage: Request CNL-14-133, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos Project stage: Other ML14302A1972014-11-0606 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other L-2014-362, Request for Schedule Relaxation from NRC Order EA-12-049 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-12-19019 December 2014 Request for Schedule Relaxation from NRC Order EA-12-049 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request CNL-15-037, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15033A4302015-03-0303 March 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-15-065, Request for Schedule Relaxation from NRC Order EA-12-049, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design External Event2015-04-0202 April 2015 Request for Schedule Relaxation from NRC Order EA-12-049, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design External Event Project stage: Request ML15104A7032015-04-29029 April 2015 Relaxation of the Schedule Requirements of Order EA-12-049, Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Approval CNL-15-175, Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-16-026, Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 20122016-02-11011 February 2016 Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 2012 Project stage: Other 2014-02-19
[Table View] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 August 29, 2013 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating Licensing No. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328
Subject:
Submittal of the Details of the Planned Drill to the Revised Sequoyah Nuclear Plant Flood Mode Operation Abnormal Operating Procedure (AOP)
N.03, "External Flooding"
Reference:
- 1.
Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Extension Request Regarding the Flooding Hazard Reevaluation Report Required by NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1, Flooding, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident,"
dated March 12, 2013 (ML13080A073)
- 2.
Letter from TVA to NRC, "Application to Revise Watts Bar Nuclear Plant Unit I Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01)," dated July 19, 2012 (ML12236A164)
On March 12, 2013, the Tennessee Valley Authority (TVA) submitted an extension request regarding the flooding hazard reevaluation report required by the March 12, 2012, NRC Request for Information for Recommendation 2.1, Flooding (Reference 1). Included in the Reference 1 is a status of flood hazard interim actions and a list of additional actions planned. One of the additional actions planned described in the referenced letter was revision of the Sequoyah Nuclear Plant (SQN) flood mode operation Abnormal Operating Procedure (AOP) N.03, "External Flooding." Revisions to the AOP have been made to facilitate more efficient transition to flood mode operation at SQN. To ensure the AOP can be appropriately implemented, TVA committed to perform a drill to the revised AOP by December 31, 2013. TVA also committed to provide details of the planned drills by August 29, 2013.
Printed on recycled paper VIA oz
U.S. Nuclear Regulatory Commission Page 2 August 29, 2013 The purpose of this letter is to provide the details of the proposed drill. The drill will involve participation by TVA emergency organizations to include a Control Room Operations cell, Technical Support Center (TSC), Operations Support Center (OSC), and a Central Emergency Control Center (CECC) cell. OSC teams will be simulated to be dispatched to the field after being briefed. No actual plant equipment will be operated or modified during the drill.
The scenario is based on the most limiting preparation time event for Watts Bar Nuclear Plant (WBN) as described in section 2.4.14.10 of the proposed WBN, Unit 1, Updated Final Safety Analysis Report (UFSAR) License Amendment Request (LAR) dated July 19, 2012 (Reference 2). This scenario is the 1/2 Probable Maximum Flood (PMF) rain event with subsequent seismically induced failure of both Norris and Tellico dams.
This Drill will not be utilized to formally address elements contained within Nuclear Energy Institute (NEI) 99-02, "Regulatory Assessment Performance Indicator Guideline", for performance indicators regarding Drill/Exercise Performance (DEP).
The Drill Goals are to:
- 1. Demonstrate that the emergency response organization can effectively utilize the revised flood mode operating instructions and procedures to simulate implementation of actions required during an extreme flooding event.
- 2. Demonstrate that emergency response procedures are adequate and identify any need for improvement or revision.
- 3. Allow personnel to demonstrate and test the capabilities of the emergency response organization to protect the health and safety of plant personnel and the general public in accordance with the Nuclear Power - Radiological Emergency Plan (NP-REP), Site Emergency Plan Implementing Procedures (EPIPs), and the CECC EPIPs.
- 4. Provide an interactive scenario to ensure proficiency of onsite and offsite emergency response capabilities.
- 5. Provide training for emergency response personnel.
- 6. Visibly demonstrate safe operations during the execution of the drill.
This letter contains no new regulatory commitments. If you have questions regarding this matter, please contact Kevin Casey at (423) 751-8523.
Respectfully, W. Shea ice President, Nuclear Licensing cc: See page 3