MONTHYEARML24149A3122024-05-0707 May 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Final ML24149A2932024-05-0707 May 2024 Ile Form 2.3-1 Examination Outline Quality Checklist ML24149A3862024-04-19019 April 2024 Ile Form 2.1-1 Examination Preparation Checklist ML24149A3852024-04-19019 April 2024 Ile Form 1.3-1 Exam Security Agreement BW240018, Ile Post-Exam Submittal Letter2024-04-0505 April 2024 Ile Post-Exam Submittal Letter ML24149A3472024-03-14014 March 2024 Ile Proposed Exam Submittal Letter ML24149A3442024-03-14014 March 2024 Ile Form 2.3-2 Operating Test Quality Checklist ML24149A3452024-03-14014 March 2024 Ile Form 2.3-4 Written Exam Quality Checklist ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 ML24149A2562023-10-27027 October 2023 Ile Proposed Outline Submittal Letter ML23234A2462023-08-25025 August 2023 Confirmation of Initial License Examination ML23191A8442023-07-10010 July 2023 05000456; 05000457 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML22199A1842022-04-0505 April 2022 Outline Recommendations-Submittal Comments ML22199A1732022-04-0505 April 2022 Ile ES-201-3 Security Agreement-Final ML22199A1742022-04-0505 April 2022 Ile ES-403-1 Written Exam Grading Quality Checklist ML22199A1812022-04-0505 April 2022 Ile ES-401-9 Written Examination Review Worksheet ML22199A1702022-04-0505 April 2022 Ile ES-201-1 Examination Prep Checklist ML22199A1792022-04-0505 April 2022 Ile ES-401-4 Rejected KAs ML22199A1762022-04-0505 April 2022 Ile ES-301-7 Operating Test Review Worksheet BW220023, Ile Post-Examination Submittal Letter (03/30/2022)2022-03-30030 March 2022 Ile Post-Examination Submittal Letter (03/30/2022) RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22199A1852022-03-18018 March 2022 Ile Administered RO and SRO Admin Topics JPMs-FINAL ML22199A1912022-03-18018 March 2022 Ile Administered RO and SRO List of Reference Handouts-FINAL ML22199A1902022-03-18018 March 2022 Ile Administered Written Examination-FINAL ML22199A1892022-03-18018 March 2022 Ile Administered Simulator Scenarios-FINAL ML22199A1872022-03-18018 March 2022 Ile Administered Sim and Inplant System JPMs-FINAL ML22053A0692022-02-23023 February 2022 Operator Licensing Examination Approval ML22199A2532022-02-22022 February 2022 Ile ES-301-5 Transient and Event Checklists ML22199A2472022-02-22022 February 2022 Ile ES-201-2 NRC-Developed Outline Quality Checklist-Signed ML22199A2632022-02-22022 February 2022 Ile ES-301-1 Admin Topics Outlines ML22199A2702022-02-22022 February 2022 Ile ES-401-2 and ES-401-3 Written Exam Outlines-Final ML22199A2692022-02-22022 February 2022 Ile ES-301-2 Sim and Inplant System JPM Outlines ML22199A2712022-02-22022 February 2022 Ile ES-D-1s Simulator Scenario Outlines ML22199A2302022-02-18018 February 2022 ES-301-6 Competencies Checklists ML22199A2382022-02-18018 February 2022 Ile Proposed Sim and Inplant System JPMs-FINAL ML22199A2402022-02-18018 February 2022 Ile Proposed Written Examination-FINAL ML22199A2362022-02-18018 February 2022 Ile Proposed RO and SRO Admin Topic JPMs-FINAL ML22199A2272022-02-18018 February 2022 ES-301-3 and ES-301-4 Op Test Quality Checklists ML22199A2392022-02-18018 February 2022 Ile Proposed Simulator Scenarios-FINAL ML22199A2342022-02-18018 February 2022 ES-401-6 Written Exam Quality Checklist ML21224A2432021-08-17017 August 2021 Confirmation of Initial License Examination ML21110A4952021-04-19019 April 2021 GFE Results, March 2021 ML22173A2282020-07-17017 July 2020 Bwd 2020 Ile ES-201-1 Rev 11-Final ML22173A2392020-07-17017 July 2020 Bwd 2020 Ile Outline Comments ML22173A2302020-07-17017 July 2020 Bwd 2020 Ile Es 403-1 Signed ML22173A2332020-07-17017 July 2020 Bwd 2020 Ile ES-301-7 Operating Test Review Comments ML22173A2292020-07-17017 July 2020 Bwd 2020 Ile Es 201-3 Final ML22173A2352020-07-17017 July 2020 Bwd 2020 Ile ES-401-4 Record of Rejected KAs Rev 11 ML22173A2372020-07-17017 July 2020 Bwd 2020 Ile ES-401-9 Written Exam Comments-Final 2024-05-07
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24149A3122024-05-0707 May 2024 Ile Form 3.4-1 Events and Evolutions Checklist - Final ML24149A2932024-05-0707 May 2024 Ile Form 2.3-1 Examination Outline Quality Checklist ML24149A3852024-04-19019 April 2024 Ile Form 1.3-1 Exam Security Agreement ML24149A3862024-04-19019 April 2024 Ile Form 2.1-1 Examination Preparation Checklist BW240018, Ile Post-Exam Submittal Letter2024-04-0505 April 2024 Ile Post-Exam Submittal Letter ML24149A3472024-03-14014 March 2024 Ile Proposed Exam Submittal Letter ML24149A3442024-03-14014 March 2024 Ile Form 2.3-2 Operating Test Quality Checklist ML24149A3452024-03-14014 March 2024 Ile Form 2.3-4 Written Exam Quality Checklist ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 ML24149A2562023-10-27027 October 2023 Ile Proposed Outline Submittal Letter ML23234A2462023-08-25025 August 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML22199A1812022-04-0505 April 2022 Ile ES-401-9 Written Examination Review Worksheet ML22199A1742022-04-0505 April 2022 Ile ES-403-1 Written Exam Grading Quality Checklist ML22199A1732022-04-0505 April 2022 Ile ES-201-3 Security Agreement-Final ML22199A1702022-04-0505 April 2022 Ile ES-201-1 Examination Prep Checklist ML22199A1762022-04-0505 April 2022 Ile ES-301-7 Operating Test Review Worksheet ML22199A1792022-04-0505 April 2022 Ile ES-401-4 Rejected KAs ML22199A1842022-04-0505 April 2022 Outline Recommendations-Submittal Comments BW220023, Ile Post-Examination Submittal Letter (03/30/2022)2022-03-30030 March 2022 Ile Post-Examination Submittal Letter (03/30/2022) RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22199A1912022-03-18018 March 2022 Ile Administered RO and SRO List of Reference Handouts-FINAL ML22199A1852022-03-18018 March 2022 Ile Administered RO and SRO Admin Topics JPMs-FINAL ML22199A1872022-03-18018 March 2022 Ile Administered Sim and Inplant System JPMs-FINAL ML22199A1892022-03-18018 March 2022 Ile Administered Simulator Scenarios-FINAL ML22199A1902022-03-18018 March 2022 Ile Administered Written Examination-FINAL ML22053A0692022-02-23023 February 2022 Operator Licensing Examination Approval ML22199A2692022-02-22022 February 2022 Ile ES-301-2 Sim and Inplant System JPM Outlines ML22199A2702022-02-22022 February 2022 Ile ES-401-2 and ES-401-3 Written Exam Outlines-Final ML22199A2532022-02-22022 February 2022 Ile ES-301-5 Transient and Event Checklists ML22199A2632022-02-22022 February 2022 Ile ES-301-1 Admin Topics Outlines ML22199A2472022-02-22022 February 2022 Ile ES-201-2 NRC-Developed Outline Quality Checklist-Signed ML22199A2712022-02-22022 February 2022 Ile ES-D-1s Simulator Scenario Outlines ML22199A2302022-02-18018 February 2022 ES-301-6 Competencies Checklists ML22199A2342022-02-18018 February 2022 ES-401-6 Written Exam Quality Checklist ML22199A2392022-02-18018 February 2022 Ile Proposed Simulator Scenarios-FINAL ML22199A2402022-02-18018 February 2022 Ile Proposed Written Examination-FINAL ML22199A2362022-02-18018 February 2022 Ile Proposed RO and SRO Admin Topic JPMs-FINAL ML22199A2382022-02-18018 February 2022 Ile Proposed Sim and Inplant System JPMs-FINAL ML22199A2272022-02-18018 February 2022 ES-301-3 and ES-301-4 Op Test Quality Checklists ML21224A2432021-08-17017 August 2021 Confirmation of Initial License Examination ML22173A2392020-07-17017 July 2020 Bwd 2020 Ile Outline Comments ML22173A2292020-07-17017 July 2020 Bwd 2020 Ile Es 201-3 Final ML22173A2352020-07-17017 July 2020 Bwd 2020 Ile ES-401-4 Record of Rejected KAs Rev 11 ML22173A2332020-07-17017 July 2020 Bwd 2020 Ile ES-301-7 Operating Test Review Comments ML22173A2302020-07-17017 July 2020 Bwd 2020 Ile Es 403-1 Signed ML22173A2282020-07-17017 July 2020 Bwd 2020 Ile ES-201-1 Rev 11-Final ML22173A2372020-07-17017 July 2020 Bwd 2020 Ile ES-401-9 Written Exam Comments-Final BW200057, Bwd 2020 Ile Post-Exam Package Cover2020-06-27027 June 2020 Bwd 2020 Ile Post-Exam Package Cover ML22173A2432020-06-0909 June 2020 Bwd 2020 Ile Administered RO and SRO Admin JPMs-Final 2024-05-07
[Table view] |
Text
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility:Braidwood Station Date of Examination: 11/10/14 Exam Level: RO SRO-I SRO-U Operating Test Number: 2014 301 Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Type Safety System / JPM Title Code* Function
- a. SIM-102 Perform Movable Control Assembly Quarterly Surveillance D, S, P 1
- b. SIM-205 Raise SI Accumulator level using 1B SI pump A, N, S 2
- c. SIM-302 Transfer to Cold Leg Recirculation A, D, L, S 3
- d. SIM-416S CD/CB Pump Trip N, S 4S
- e. SIM-510 Start 1A CS pump for Surveillance M, S 5
- f. SIM-608A Synchronize 1A DG and respond to Gov Adj and overspeed trip A, D, S 6 failures
- g. SIM-711 Place Channel Service Status from "Out of Service" to "In N, S 7 Service"
- h. SIM-801 Respond to a RCP Thermal Barrier Leak A, D, P, S 8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U) i.IP-104 Local Reactor Trip A, D, E 1
- j. IP-206 Local reset of Phase A D, E 2
- k. IP-409S Locally start the 2B AF pump D, R 4S
@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank <9 / <8 / <4 (E)mergency or abnormal in-plant >1 / >1 / >1 (L)ow-Power / Shutdown >1 / >1 / >1 (N)ew or (M)odified from bank including 1(A) >2 / >2 / >1 (P)revious 2 exams <3/ <3 / < 2 (randomly selected)
(R)CA >1 / >1 / >1 (S)imulator
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Braidwood Station Date of Examination: 11/10/14 Exam Level: RO SRO-I SRO-U Operating Test Number: 2014 301 Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Safety System / JPM Title Type Code*
Function
- a. SIM-102 Perform Movable Control Assembly Quarterly Surveillance D, S, P 1
- b. SIM-205 Raise SI Accumulator level using 1B SI pump A, N, S 2
- c. SIM-302 Transfer to Cold Leg Recirculation A, D, L, S 3
- d. SIM-416S CD/CB Pump Trip N, S 4S e.
- f. SIM-608A Synchronize 1A DG and respond to Gov Adj and overspeed A, D, S 6 trip failures
- g. SIM-711 Place Channel Service Status from "Out of Service" to "In N, S 7 Service"
- h. SIM-801 Respond to a RCP Thermal Barrier Leak A, D, P, S 8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. IP-104 Local Reactor Trip A, D, E 1
- j. IP-206 Local reset of Phase A D, E 2
- k. IP-409S Locally start the 2B AF pump D, R 4S
@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank <9 / <8 / <4 (E)mergency or abnormal in-plant >1 / >1 / >1 (L)ow-Power / Shutdown >1 / >1 / >1 (N)ew or (M)odified from bank including 1(A) >2 / >2 / >1 (P)revious 2 exams <3/ <3 / < 2 (randomly selected)
(R)CA >1 / >1 / >1 (S)imulator