MONTHYEARLR-N13-0205, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Base Case Velocity.2013-09-10010 September 2013 Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Base Case Velocity. Project stage: Response to RAI 0CAN091301, Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi2013-09-12012 September 2013 Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Project stage: Response to RAI ML14079A4232014-03-12012 March 2014 Enclosure 1, Byron Nuclear Generating Station, Flood Hazard Reevaluation Report, Revision 0 Project stage: Request LR-N14-0042, SL-012270, Revision 0, Salem Generating Station Flood Hazard Reevaluation, Page 2-35 Through Page 2-552014-03-12012 March 2014 SL-012270, Revision 0, Salem Generating Station Flood Hazard Reevaluation, Page 2-35 Through Page 2-55 Project stage: Request 05000285/LER-2014-002, Regarding Reactor Manual Trip Due to Control Rod Misalignment2014-03-12012 March 2014 Regarding Reactor Manual Trip Due to Control Rod Misalignment Project stage: Request LR-N14-0051, PSEG Nuclear LLCs Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima2014-03-28028 March 2014 PSEG Nuclear LLCs Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Project stage: Response to RAI 0CAN031404, ANO, Units 1 & 2 - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (Nttf)Review of Insights from the Fukushima2014-03-28028 March 2014 ANO, Units 1 & 2 - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (Nttf)Review of Insights from the Fukushima Da Project stage: Response to RAI ML14092A4172014-03-31031 March 2014 Response to March 12, 2012 Information Request Seismic Hazard and Screening Report (CEUS Sites) for Recommendation 2.1 Project stage: Request RS-14-065, Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the2014-03-31031 March 2014 Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Project stage: Response to RAI LIC-14-0047, Omaha Public Power District - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushi2014-03-31031 March 2014 Omaha Public Power District - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Project stage: Request 05000336/LER-2014-001, Regarding Completion of Plant Shutdown Required by Technical Specifications2014-03-31031 March 2014 Regarding Completion of Plant Shutdown Required by Technical Specifications Project stage: Request 05000336/LER-2014-005, Regarding Train a Containment Spray Inoperable Due to Gas Voids2014-07-16016 July 2014 Regarding Train a Containment Spray Inoperable Due to Gas Voids Project stage: Request ML14204A6202014-07-21021 July 2014 Response to Request for Additional Information Regarding Seismic Hazard and Screening Report for Seismic Recommendation 2.1 Project stage: Response to RAI NL-14-099, Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights.2014-08-18018 August 2014 Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights. Project stage: Request 0CAN081401, Response to Request for Additional Information (RAI) Associated with Near-Term Task Force (NTTF) Recommendation 2.1, Seismic Hazard and Screening Report2014-08-21021 August 2014 Response to Request for Additional Information (RAI) Associated with Near-Term Task Force (NTTF) Recommendation 2.1, Seismic Hazard and Screening Report Project stage: Response to RAI PLA-7224, Response to March 12, 2012 Information Request - Supplemental Information Related to the Seismic Hazard and Screening Report for Recommendation 2.1 - PLA-72242014-08-28028 August 2014 Response to March 12, 2012 Information Request - Supplemental Information Related to the Seismic Hazard and Screening Report for Recommendation 2.1 - PLA-7224 Project stage: Request RS-14-206, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other RS-14-230, Supplemental Information Related to the Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2, 1 of the Near-Term Task Force Review Of.2014-08-29029 August 2014 Supplemental Information Related to the Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2, 1 of the Near-Term Task Force Review Of. Project stage: Supplement ML14224A5262014-09-22022 September 2014 Screening and Prioritization Results of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Project stage: Other LIC-14-0124, Supplemental Information Related to Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The.2014-10-22022 October 2014 Supplemental Information Related to Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The. Project stage: Supplement 0CAN111401, Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-11-0404 November 2014 Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Other NL-14-139, Additional Information Regarding the Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-11-0505 November 2014 Additional Information Regarding the Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Request ML14310A0222014-11-13013 November 2014 Report Regarding Individual Plant Examination of External Events Supporting Information for Seismic Screening Project stage: Other ML14246A4282014-11-21021 November 2014 Screening and Prioritization Results Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident Based on Individual Plant Examination of External Events Project stage: Approval ML14310A0332014-12-15015 December 2014 NRC Response to Licensees Notification of Revised Regulatory Commitments Associated with Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Revie Project stage: RAI ML15329A1812015-12-0808 December 2015 Staff Assessment of Information Provided Pursuant of Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f)Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights Project stage: Approval ML15328A2682015-12-15015 December 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review Project stage: Other ML15344A1092015-12-15015 December 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Project stage: Other ML17123A3782016-04-27027 April 2016 Reevaluated Seismic Hazard Mitigating Strategies Assessment Report Project stage: Other LIC-16-0039, Ft. Calhoun, Unit 1 - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Accident2016-05-25025 May 2016 Ft. Calhoun, Unit 1 - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Accident Project stage: Response to RAI ML16365A0322016-12-21021 December 2016 Response to March 12, 2012 Information Request, Spent Fuel Pool Seismic Evaluation for Recommendation 2.1 Project stage: Other 0CAN121602, Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information Per Nuclear Energy Institute (NEI) 12-06, Appendix H, Revision 2, H.4.3 Path 32016-12-30030 December 2016 Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information Per Nuclear Energy Institute (NEI) 12-06, Appendix H, Revision 2, H.4.3 Path 3 Project stage: Other 2014-07-16
[Table View] |
Text
0CAN111401 November 4, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
Dear Sir or Madam:
On March 12, 2012, the NRC issued Reference 1 to all power reactor licensees. By Reference 5, Entergy Operations, Inc. (Entergy) provided the Seismic Hazard and Screening Reports for Arkansas Nuclear One, Units 1 and 2 (ANO-1 and ANO-2) requested by Reference 1. The reports provided the basis for both units to screen out of expending further resources associated with the Expedited Seismic Evaluation Process (ESEP) (Reference 2).
The screening was based on demonstrating that the plant capacity spectra for the ANO units from the Individual Plant Examination for External Events (IPEEE) exceed the new ground motion response spectrum (GMRS) in the one to ten Hertz range. In Reference 6, the NRC determined that ANO-1 and ANO-2 had been conditionally screened-in because additional information was needed to support a final screening and prioritization decision. Entergy responded to the NRC request for additional information in Reference 7, and in a conference call held on October 21, 2014. Entergy expects the NRC final screening and prioritization to conclude that further evaluation associated with the ESEP is not required for ANO-1 and 2.
In Reference 6, the NRC stated the following:
Plants identified as conditional screen-in should submit the Expedited Approach by December 31, 2014 and, until a final determination is made, conduct a seismic risk evaluation as prioritized in Enclosure 2.
In Reference 1, the NRC requested interim evaluations and actions "...to address the higher seismic hazard....prior to completion of risk evaluation." Section 1 of the Augmented Approach guidance (Reference 4) states that "...this report addresses interim evaluations...
to be implemented prior to performing complete plant seismic risk evaluations. The NRC endorsement of the Augmented Approach guidance (Reference 5), states that the ESEP can provide seismic margin "...prior to performing the complete plant seismic risk evaluations.
Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Site Vice President Arkansas Nuclear One
0CAN111401 Page 2 of 3 From a seismic safety perspective, the IPEEE, which used the Electric Power Research Institute (EPRI) seismic margin assessment approach, has already demonstrated that the plant can safely shut down with plant seismic capacity above the GMRS. The ESEP review per the Reference 3 guidance would only consider a minimal increase above the safe shutdown earthquake in seismic demand and would be bounded by the IPEEE evaluations already conducted. The review of a limited set of components to these demand levels, in accordance with the ESEP guidance, would not provide a significant difference in safety insight or indication of seismic margin for the units beyond what was already provided by the IPEEE.
Since the ANO units have demonstrated seismic capacities above the GMRS, Entergy concludes the nuclear safety benefit from the performance of an ESEP is not commensurate with resource expenditures and is furthermore bounded by the already conducted IPEEE evaluations. Therefore, unless the NRC subsequently determines that the ESEP is applicable to the ANO units, Entergy does not intend to perform the ESEP. The plan to perform a high frequency and spent fuel pool evaluation, as indicated in the Seismic Hazard and Screening Reports (Reference 5), remains unchanged.
This letter contains no new regulatory commitments. Should you have any questions regarding this submittal, please contact Stephenie Pyle at 479.858.4704.
I declare under penalty of perjury that the foregoing is true and correct; executed on November 4, 2014.
Sincerely, ORIGINAL SIGNED BY JEREMY G. BROWNING JGB/nbm
REFERENCES:
- 1. NRC Letter, Request for Information (RFI) Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident, dated March 12, 2012, (0CNA031208)
(ML12053A340)
- 2. Nuclear Energy Institute Letter to NRC, Proposed Path Forward for NTTF Recommendation 2.1: Seismic Reevaluations, dated April 9, 2013 (ML13101A379)
- 3. Entergy letter to NRC, Entergys Response to NRC RFI Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the NTTF Review of Insights from the Fukushima Dai-ichi Accident, dated April 29, 2013 (0CAN041306) (ML12305A372)
- 4. Electric Power Research Institute (EPRI) Technical Report 3002000704, Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima NTTF Recommendation 2.1 - Seismic, dated May 2013
0CAN111401 Page 3 of 3
- 5. Entergy letter to NRC, Seismic Hazard and Screening Report (Central Eastern United States (CEUS) Sites), Response to NRC Request For Information(RFI) Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Accident, dated March 28, 2014 (0CAN031404) (ML14092A021)
- 6. NRC letter, Screening and Prioritization Results Regarding Information Pursuant to Title 10 Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Re-Evaluations for Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-Ichi Accident, dated May 9, 2014 (0CNA051401) (ML14111A147)
- 7. Entergy letter to NRC, Response to Request for Additional Information (RAI) Associated with Near-Term Task Force (NTTF)
Recommendation 2.1, Seismic Hazard and Screening Report, dated August 21, 2014 (0CAN081401) cc:
Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Ms. Andrea E. George MS O-8B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852 U. S. Nuclear Regulatory Commission Attn: Mr. John Hughey MS 13-C5 One White Flint North 11555 Rockville Pike Rockville, MD 20852