MONTHYEARLR-N13-0205, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Base Case Velocity.2013-09-10010 September 2013 Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Base Case Velocity. Project stage: Response to RAI 0CAN091301, Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi2013-09-12012 September 2013 Response to NRC Request for Information (RFI) Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Project stage: Response to RAI LR-N14-0042, SL-012270, Revision 0, Salem Generating Station Flood Hazard Reevaluation, Page 2-35 Through Page 2-552014-03-12012 March 2014 SL-012270, Revision 0, Salem Generating Station Flood Hazard Reevaluation, Page 2-35 Through Page 2-55 Project stage: Request 05000285/LER-2014-002, Regarding Reactor Manual Trip Due to Control Rod Misalignment2014-03-12012 March 2014 Regarding Reactor Manual Trip Due to Control Rod Misalignment Project stage: Request ML14079A4232014-03-12012 March 2014 Enclosure 1, Byron Nuclear Generating Station, Flood Hazard Reevaluation Report, Revision 0 Project stage: Request LR-N14-0051, PSEG Nuclear LLCs Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima2014-03-28028 March 2014 PSEG Nuclear LLCs Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Project stage: Response to RAI 0CAN031404, ANO, Units 1 & 2 - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (Nttf)Review of Insights from the Fukushima2014-03-28028 March 2014 ANO, Units 1 & 2 - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (Nttf)Review of Insights from the Fukushima Da Project stage: Response to RAI ML14092A4172014-03-31031 March 2014 Response to March 12, 2012 Information Request Seismic Hazard and Screening Report (CEUS Sites) for Recommendation 2.1 Project stage: Request 05000336/LER-2014-001, Regarding Completion of Plant Shutdown Required by Technical Specifications2014-03-31031 March 2014 Regarding Completion of Plant Shutdown Required by Technical Specifications Project stage: Request RS-14-065, Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the2014-03-31031 March 2014 Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Project stage: Response to RAI LIC-14-0047, Omaha Public Power District - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushi2014-03-31031 March 2014 Omaha Public Power District - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Project stage: Request 05000336/LER-2014-005, Regarding Train a Containment Spray Inoperable Due to Gas Voids2014-07-16016 July 2014 Regarding Train a Containment Spray Inoperable Due to Gas Voids Project stage: Request ML14204A6202014-07-21021 July 2014 Response to Request for Additional Information Regarding Seismic Hazard and Screening Report for Seismic Recommendation 2.1 Project stage: Response to RAI NL-14-099, Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights.2014-08-18018 August 2014 Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights. Project stage: Request 0CAN081401, Response to Request for Additional Information (RAI) Associated with Near-Term Task Force (NTTF) Recommendation 2.1, Seismic Hazard and Screening Report2014-08-21021 August 2014 Response to Request for Additional Information (RAI) Associated with Near-Term Task Force (NTTF) Recommendation 2.1, Seismic Hazard and Screening Report Project stage: Response to RAI PLA-7224, Response to March 12, 2012 Information Request - Supplemental Information Related to the Seismic Hazard and Screening Report for Recommendation 2.1 - PLA-72242014-08-28028 August 2014 Response to March 12, 2012 Information Request - Supplemental Information Related to the Seismic Hazard and Screening Report for Recommendation 2.1 - PLA-7224 Project stage: Request RS-14-206, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other RS-14-230, Supplemental Information Related to the Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2, 1 of the Near-Term Task Force Review Of.2014-08-29029 August 2014 Supplemental Information Related to the Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2, 1 of the Near-Term Task Force Review Of. Project stage: Supplement LIC-14-0124, Supplemental Information Related to Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The.2014-10-22022 October 2014 Supplemental Information Related to Seismic Hazard and Screening Report in Response to NRC Request for Information Pursuant to 10CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The. Project stage: Supplement 0CAN111401, Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-11-0404 November 2014 Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Other NL-14-139, Additional Information Regarding the Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-11-0505 November 2014 Additional Information Regarding the Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Request ML14310A0222014-11-13013 November 2014 Report Regarding Individual Plant Examination of External Events Supporting Information for Seismic Screening Project stage: Other ML14246A4282014-11-21021 November 2014 Screening and Prioritization Results Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident Based on Individual Plant Examination of External Events Project stage: Approval ML14310A0332014-12-15015 December 2014 NRC Response to Licensees Notification of Revised Regulatory Commitments Associated with Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Revie Project stage: RAI ML15096A3402015-05-0707 May 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations for Recommendation 2.1, Seismic, of the NTTF Review of Insights from the Fukushima Dai-Ichi Accident Project stage: Approval ML15328A2682015-12-15015 December 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review Project stage: Other ML15344A1092015-12-15015 December 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Project stage: Other ML17123A3782016-04-27027 April 2016 Reevaluated Seismic Hazard Mitigating Strategies Assessment Report Project stage: Other ML16365A0322016-12-21021 December 2016 Response to March 12, 2012 Information Request, Spent Fuel Pool Seismic Evaluation for Recommendation 2.1 Project stage: Other 0CAN121602, Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information Per Nuclear Energy Institute (NEI) 12-06, Appendix H, Revision 2, H.4.3 Path 32016-12-30030 December 2016 Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information Per Nuclear Energy Institute (NEI) 12-06, Appendix H, Revision 2, H.4.3 Path 3 Project stage: Other 2014-03-31
[Table View] |
Text
Entergy Nuclear Northeast Indian Point Energy Center Entergy 450 Broadway, GSB P. 0. Box 249 Buchanan, NY 10511-0249 Tel 914 254 6700 John A Ventosa Site Vice President NL-14-099 August 18, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Request for Review of Entergy Seismic Hazard and Screening Report (CEUS Sites),
Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Indian Point Unit No. 3 Docket No. 50-286 License No. DPR-64
REFERENCES:
1 NRC Letter, Screening and Prioritization Results Regarding Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)
Regarding Seismic Hazard Re-evaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated May 9, 2014 (ML14111A147) 2 New York Power Authority letter to NRC, Individual Plant Examination of External Events (IPEEE), dated September 26, 1997 (ML11227A102) 3 Entergy letter to NRC, Indian Point Nuclear Power Plant Units 2 and 3, Reassessment of the Seismic Core Damage Frequency, dated June 26, 2013 (ML13183A279 & ML13183A280) 4 NRC Letter to Entergy, Request for Information Pursuantto Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ML12073A348) 5 Entergy letter to NRC, Entergy Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 31, 2014 (ML14099A111)
NL-14-099 Docket No. 50-286 Page 2 of 3 6 EPRI Report 1025287, Seismic Evaluation Guidance: Screening, Prioritization and Implementation Details (SPID) for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Seismic (ML12333A170) 7 NRC Letter, Endorsement of Electric Power Research Institute Final Draft Report 1025287, "Seismic Evaluation Guidance", dated February 15, 2013
Dear Sir or Madam:
In Reference 1, NRC categorized IP3 as Screened In, Prioritization Group 1, Seismic Risk Evaluation required. Group 1 plants were requested to conduct a seismic risk evaluation and submit it by June 30, 2017. Entergy requests that the prioritization group for the additional IP3 Seismic Risk Evaluation be changed to "Priority Group 3." The requested evaluation requires specialized resources which have limited availability and Entergy has three plants categorized in Group 1 and one in Group 2. The re-catorization will allow the more appropriate focus of the limited resources available to perform a seismic risk evaluation on other Entergy plants which do not have IPEEE results which bound the reevaluated seismic hazard. Additionally, the Group 1 seismic risk evaluation for IP2 should provide insights concerning the seismic robustness of IP3.
In support of this request, Entergy notes the Indian Point Individual Plant Examination of External Events (IPEEE) was submitted to the NRC, reflected a conservative understanding of the Indian Point seismic risk (Reference 2). On June 26, 2013, Entergy submitted a Reassessment of the Seismic Core Damage Frequency (SCDF) for Indian Point Nuclear Power Plant Units 2 (IP2) and 3 (IP3) (Reference 3). The purpose of the reassessment was, in part, to determine a more realistic and accurate understanding of the Indian Point SCDF. The reassessment demonstrated that the SCDF for IP3 is significantly better than previous estimates in Reference 2. The reassessment additionally provided an updated tool for evaluating the safety implications of the reevaluated seismic hazards being developed in response to Reference 4.
As explained in Reference 5, Entergy determined that the reevaluated seismic hazard for IP3 is higher than the safe shutdown earthquake previously evaluated as part of the licensing of the plant.
However, using the reassessed IPEEE of Reference 3, rather than IPEEE of Reference 2, and the guidance in Reference 6, Entergy further determined that the plant capacity is higher than the new reevaluated hazard. The IPEEE and its reassessment were reviewed for adequacy utilizing the guidance provided in Section 3.3 of Reference 6.
In Reference 1, NRC categorized IP3 as Screened In, Prioritization Group 1, Seismic Risk Evaluation required. Group 1 plants were requested to conduct a seismic risk evaluation and submit it by June 30, 2017. As discussed in Reference 5, based on the results of Entergy's IPEEE screening reevaluation, IP3 screens-out of performing another risk evaluation using the criteria of Reference 6. The screening reevaluation was performed using the updated IPEEE HCLPF Spectrum (IHS) (Reference 3) submitted to the NRC in June, 2013. As noted in Reference 5, Entergy believes that a comparison to the updated IHS (Reference 3) is more appropriate than a comparison to the original IPEEE analysis (Reference 2) for the screening. This letter requests the NRC review the analyses submitted in Reference 3 and 5, and revisit its prioritization determination
NL-14-099 Docket No. 50-286 Page 3 of 3 contained in Reference 1. Since the seismic risk evaluation has already been submitted, such a review should provide confidence in the IP3 seismic robustness earlier than otherwise would be obtained in following the 2017 schedule for performance and submittal of another risk evaluation.
This request does not affect the December 2014 Expedited Seismic Evaluation Process submittal planned for IP3. Additionally, the Group 1 seismic risk evaluation for IP2 should provide insights concerning the seismic robustness of IP3.
If you have any questions or require additional information, please contact Robert Walpole, Regulatory Assurance Manager, at (914) 254-6710.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August 2014.
Sincerely, JAV/sp cc: Mr. Douglas V. Pickett, Senior Project Manager, NRC NRR DORL Mr. William M. Dean, Regional Administrator, NRC Region I NRC Resident Inspectors Office Mr. John B. Rhodes, President and CEO, NYSERDA Ms. Bridget Frymire, New York State Dept. of Public Service