ML14178A143

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/91-17 on 910713-0809.Violations Noted.Major Areas Inspected:Operational Safety Verification,Maint Observation,Onsite Review Committee Activities & Followup
ML14178A143
Person / Time
Site: Robinson 
Issue date: 08/22/1991
From: Christensen H, Garner L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14178A140 List:
References
50-261-91-17, NUDOCS 9109100072
Download: ML14178A143 (10)


See also: IR 05000261/1991017

Text

pVjF REG&,

UNITED STATES

0

'NUCLEAR

REGULATORY COMMISSION

REGION 1I

C 0101

MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

Report No.:

50-261/91-17

Licensee:

Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.: DPR-23

'Facility Name: H. B. Robinson

Inspection Conducted:

July 13 -

August 9, 1991

Lead Inspector:

B4

o

.

, e4

. or

LI. W. Gar~er, nior R;W~den ,Anspector

D~te Si~ned

Other Inspectors: K. R. Jury, Resident Inspector

. E. Carroll, Project Engineer

Approved b

e.

d9/=

. 0.ChClstensen, Section Chief

Dat

Si

ed

Division of Reactor Projects

SUMMARY

Scope:

This routine, announced inspection was conducted in the areas of operational

safety verification,

maintenance observation,

onsite review committee

activities, and followup.

Results:

A violation with two examples was identified for failing to adequately

establish procedures (paragraph 2).

A violation was identified for failing to utilize a maintenance work request to

perform maintenance activities (paragraph 3).

A non-cited violation was identified for failing to complete a procedure usage

cover sheet prior to initiating work (paragraph 3).

0

9109100072 910823

PDR

ADOCK 05000261

PDR

REPORT DETAILS

1. Persons Contacted

R. Barnett, Manager, Outages and Modifications

  • C. Baucom, Senior Specialist, Regulatory Compliance

D. Bauer, Regulatory Compliance Coordinator, Regulatory Compliance

  • S. Billings, Technical Aide, Regulatory Compliance
  • R. Chambers, Manager, Operations

T. Cleary, Manager -

Balance of Plant Systems and Reactor Engineering,

Technical Support

D. Crook, Senior Specialist, Regulatory Compliance

C. Dietz, Manager, Robinson Nuclear Project

  • W. Dorman, Acting Manager, Nuclear Assessment Department Site Unit

J. Eaddy, Manager, Environmental and Radiation Support

S. Farmer, Manager - Engineering Programs, Technical Support

R. Femal, Shift Supervisor, Operations

  • W. Gainey, Manager, Plant Support Unit
  • P. Jenney, Project Specialist, Regulatory Compliance

J. Kloosterman, Manager, Regulatory Compliance

D. Knight, Shift Supervisor, Operations

  • A. McCauley, Manager - Electrical Systems, Technical Support

R. Moore, Shift Supervisor, Operations

  • A. Padgett, Manager, Environmental and Radiation Control

M. Page, Manager, Technical Support

D. Seagle, Shift Supervisor, Operations

  • J. Sheppard, Plant General Manager, H. B. Robinson
  • R. Smith, Manager, Maintenance
  • D. Stadler, Onsite Licensing Engineer, Nuclear Licensing

W. Stover, Shift Supervisor, Operations

D. Winters, Shift Supervisor, Operations

  • H. Young, Manager, Quality Control

Other licensee employees contacted included technicians,

operators,

mechanics, security force members, and office personnel.

  • Attended exit interview on August 13, 1991.

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2. Operational Safety Verification (71707)

The inspectors evaluated licensee activities to confirm that the facility

was being operated safely and in conformance with regulatory requirements.

These activities were confirmed by direct observation, facility tours,

interviews and discussions with licensee personnel and management,

verification of safety system status, and review of facility records.

2

To verify equipment operability and compliance with TS,

the inspectors

reviewed shift logs, Operations' records, data sheets, instrument traces,

and records of equipment malfunctions.

Through work observations and

discussions with Operations staff members,

the inspectors verified the

staff was knowledgeable of plant conditions, responded properly to alarms,

adhered to procedures and applicable administrative controls, cognizant of

in-progress surveillance and maintenance activities,

and aware of

inoperable equipment status.

The inspectors performed channel

verifications and reviewed component status and safety-related parameters

to verify conformance with TS.

Shift changes were observed, verifying

that system status continuity was maintained and that proper control.room

staffing existed.

Access to the control

room was controlled and

operations personnel carried out their assigned duties in an effective

manner. Control room demeanor and communications were appropriate.

Plant tours were conducted to verify equipment operability, assess the

general condition of plant equipment,

and to verify that radiological

controls, fire protection controls,

physical protection controls,

and

equipment tagging procedures were properly implemented.

Inadequate EPP-10 Procedure

On July 22,

1991,

the inspectors observed that the alternate hot leg

recirculation flow path specified in EPP-10,

Transfer To Hot Leg

Recirculation, revision 4, did not open all the valves required for the

flow path.

The alternate flow path is from the RHR pump discharge header

via the CVCS system to the B RCS hot leg.

The pathway utilizes the normal

charging line which enters containment at penetration 24.

On March 1,

1991,

EPP-9,

Transfer To Cold Leg Recirculation, was revised to close

manual valves CVC-202A,

282,

and 309A, and to seal this penetration with

IVSW.

A combination of valves 282 and either 202A or 309A, are required

to be open for alternate hot leg recirculation to be established via

penetration 24.

Prior to the EPP-9 revision which closes these valves, it

was not necessary to verify that these valves were open during EPP-10

performance as a flow path through this penetration exists during normal

operation.

However,

performance of the revised EPP-9 not only closes

these valves within the first hour of a design basis LOCA, but would most

likely result in radiation fields which would preclude subsequent

reopening of these valves. . Thus,

when EPP-10 would be performed under

accident conditions, i.e. approximately 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> after initiation of a

LOCA,

the alternate hot leg recirculation flow pathway could not be

established. The safety significance of the flow path's unavailability is

minor, in that, multiple failures must occur for the normal hot leg

recirculation flowpath to be unavailable. However, if the plant design is

such that an alternate hot leg recirculation flow path can be established,

the inclusion of this flow path into EOPs is expected.

The licensee is

presently reviewing the availability of an alternate hot leg recirculation

flow path via the RHR shutdown cooling suction line or re-establishment of

the previously specified RHR/CVCS flowpath.

Incorporation of a viable

alternate hot leg recirculation flowpath into EPP-10 is anticipated to be

completed by the end of August 1991.

3

The failure to identify that EPP-10 was adversely impacted by a revision

to EPP-9 is of special concern, since the V & V process for EOPs was

identified as a weakness in IR 89-16. In response to that weakness, a new

V & V process was developed in 1990 to be utilized during and subsequent

to, the EOP upgrade project which is scheduled for completion at the end

of 1991.

EOPs which had not been upgraded were not being verified and

validated by this new V & V process. The individual responsible for the

EOP upgrade project indicated that all future EOP revisions would now use

the new V & V process.

Because of the similarities between the past EOP

review process and that used for other types of operating procedures, the

weakness which allowed the EPP-9/EPP-10 problem to occur could exist for

other procedure revision processes.

The failure to adequately establish

EPP-10 constitutes one example of a violation: ' Failure To Adequately

Establish Procedures, 91-17-01.

Inadequate Review Of SP-1023

As documented in IR 91-15, SP-1023, IVSW Leak Test of Penetration 6, was

performed on July 11,

1991,

to return the RCDT pump discharge outboard

containment isolation valve,

WD-1722,

to service.

The inspectors

completed their test review and determined that the SP was adequately

performed on the established configuration, and as such,

successfully

demonstrated valve integrity.

Prior to performing the test, the licensee identified that the SP provided

a precaution and limitation which incorrectly referenced the applicable

TS.

The SP stated that the performance of the test would place the plant

in a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> LCO to hot shutdown per TS 3.3.6.1 and 3.3.6.2.

However, TS 3.0 was applicable, which is an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to hot shutdown LCO. Subsequent to

the issuance of the SP, and preparation for its performance, the operating

shift reviewed the procedure and detected the LCO discrepancy.

A

temporary procedure change was implemented to correct this error prior to

test initiation.

Evidently during the preparation of SP-1023,

the procedure preparer had

identified TS 3.0 as being applicable during the test; however, during the

review process,

discussions among

operations and technical support

personnel resulted in the incorrect determination that TS 3.3.6.1 and TS 3.3.6.2 were applicable, not TS 3.0. The failure to properly identify the

applicable TS in SP-1023 constitutes a second example of violation:

91-17-01, Failure To Adequately Establish Procedures.

One violation with two examples was identified.

3. Monthly Maintenance Observation (62703)

The inspectors observed safety-related maintenance activities on systems

and components to ascertain that these activities were conducted in

accordance with TS,

approved procedures, and appropriate industry codes

and standards.

The inspectors determined that these activities did not.

4

violate LCOs and that required redundant components were operable.

The

inspectors verified that required administrative, material,

testing,

radiological,

and fire prevention controls were adhered to.

In

particular, the inspectors observed/reviewed the following maintenance

activities:

WR/JO 91-AJJA1

Perform Current Traces on SI-876A, SI-867B,

and SI-869 Using VOTES

WR/JO 90-AEUY1

Replace PT-121, CVCS Charging Pump

Discharge Pressure Transmitter

Valve SI-867A Breaker Tripping

On July 29,

1991,

while taking current traces and voltage readings on

valve SI-867A,

BIT inlet bypass valve,

the valve's power supply

breaker tripped instantaneously to the valve's switch manipulation on the

RTGB.

Concurrent with this action was a loss of indication on a voltmeter

(multimeter) being used for voltage readings. The valve was declared out

of service and TS 3.3.1.2.e (24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to hot shutdown LCO) was entered at

10:45 a.m.

as one flow path was determined to be inoperable.

The

redundant flow path (valve SI-867B) was demonstrated to be operable by

performing a stroke test per OST-152, SI system.

The voltage readings and current traces were being taken in support of AC

MOV motor torque calculation RNP-E-7013, to better estimate rated locked

rotor current, as neither actual field nor vendor data was available for

the calculation. The 600 VAC rated power supply breaker evidently tripped

when a 300 VAC multimeter (connected across B & C motor phases) shorted

out. The multimeter is designed to measure a maximum of 300 VAC; however,

it

was being utilized on a 480 VAC system.

Apparently, the impressed

voltage (which is above the meter range) shorted the spark gap circuitry

in the voltmeter, thus shorting the spike suppressor and tripping the

breaker. Subsequent to the breaker tripping, the breaker was reset and WR

91-AKND1 was initiated to perform a current trace and stroke time test for

the valve. Applicable portions of OST-152 were performed to verify proper

operation of remote position indicators, measure stroke time,

and to

verify that the valve assumed proper position on loss of operating power.

The current traces and OST-152 were both successfully performed and the

valve (and flow path) was declared back-in-service at 2:00 p.m..

Upon

reviewing

the circumstances surrounding this situation,

the

inspectors concluded there were several work control breakdowns which

occurred.

The first involved the communications between NED,

Technical

Support,

Maintenance,

and Operations.

There appeared to be a non

formalized communication process being utilized in accomplishing the

valve's voltage readings.

The apparent sequence occurred as follows:

(1) NED requested the current and voltage readings be taken per a

memorandum;

(2) Technical Support subsequently requested a WR

be

generated,

however,

the generated WR (91-AJJA1)

only required current

traces be taken, not voltage readings; and (3) the maintenance technicians

5

were verbally requested to also take voltage readings, however, Operations

was not informed nor aware voltage reading were going to be taken. While

this non-formalized "communication"

may not have been the root cause of

the event, it appeared to be a contributor. The second breakdown involved

the technicians performing the test being unaware that the multimeters

being utilized were unacceptably rated to measure the power supply's

voltage.

However, labels were on the meters indicating they were only to

be utilized up to a maximum of 300 VAC.

These labels were placed on the

meters due to a similar misapplication in early 1989 which resulted in a

reactor trip.

Maintenance

Manual

Procedure

MMM-001,

Maintenance

Administration Program, revision 12,

requires a proper work request be

utilized in performing all maintenance activities and labor by craft

personnel.

If

the voltage readings were specified to be taken and

correctly ranged multimeters were identified to be used on the WR, this

situation may have been precluded.

Failure to adequately perform

maintenance activities is a violation:

Maintenance Activities Were

Performed Without Utilizing A Work Request, 91-17-02.

CVCS Charging Pump Pressure Transmitter, PT-121, Replacement

During the replacement of PT-121 per WR 90-AEUY1,

the inspectors noted

that after the technicians began implementing Process Instrumentation

Calibration Procedure PIC-006,

Pressure Transmitter, revision 1, the

Procedure Usage Cover Sheet had not been filled out.

Maintenance

Management Manual Procedure MMM-001,

Maintenance Administration Program,

Revision 12,

Section 5.1.8,

requires that procedures

issued for

performance of maintenance shall be provided with a Procedure Usage Cover

Sheet. The inspectors discussed this concern with a technician performing

the test and a NAD representative. The technician subsequently left the

work site and had the cover sheet completed as required.

Apparently, the

fact that the maintenance supervisor failed to complete the cover sheet

was overlooked by the technicians performing the work.

Upon cover sheet

completion, it

was determined that PIC-006 was to be used as "reference",

and that each segment is required to be verified after completion. As the

technicians were just in the process of setting up their testing apparatus

and the procedure was to be used as a reference, the failure to have this

cover sheet completed was not considered to be of significant concern and

appears to be an isolated event. Not completing the Procedure Usage Cover

prior to work initiation is considered a violation; however,

this

violation meets the criteria specified in Section V.A.

of the NRC

Enforcement Policy for not issuing a Notice of Violation and is not cited.

This violation is identified as a NC'V:

Failure to Complete Procedure

Usage Cover Sheet as Required, 91-17-03.

Two violations (one being non-cited) were identified.

4. Onsite Review Committee (40500)

The inspectors evaluated certain activities of the PNSC to determine

whether the onsite review functions were conducted in accordance with TS

and other regulatory requirements. In particular, the inspectors attended

6

the July 19,

1991

special

PNSC which reviewed the MFRVs'

fuse

installation procedure, SP-1026,

and proposed

FW line leak repair.

All

potential concerns with the SP were thoroughly discussed and resolved. It

was ascertained that provisions of the TS dealing with membership, review

process, frequency, and qualifications were satisfied.

No violations or deviations were identified.

5.

Followup (92700, 92701, 92702)

(Closed)

Part 21 89-12 and 89-18, Potential Failures Of Limitorque SMB-00

And SMB-000 Torque Switches.

On November 3, 1988, Limitorque issued a 10

CFR 21 Notification (89-18)

regarding post mold shrinkage on Melamine

torque switches used in their old style SMB-00 and SMB-000 actuators. On

September 29, 1989, Limitorque issued a second 10 CFR Notification (89-12)

regarding the loosening of stationary contact screws on the side of SMB-00

and SMB-000 cam-type torque switches with fiber spacers under their

contact bridge.

In response to these notifications, the licensee

identified 83 potentially affected valves (63 of which were safety

related).

Through a discussion with the licensee's MOV Technical Support

Coordinator and a review of associated work documents,

the inspector

confirmed

that

the

recommended verifications/replacements were

appropriately accomplished. This item is closed.

(Closed)

IFI 89-07-02,

Review Permanent Solution To RTD Thermowell

Cracking Phenomena.

During RO 12,

the RCS bypass temperature manifolds

were removed and fast response RTD thermowells were installed in their

place.

Unlike loops B and C, physical interferences prevented

installation of the A loop hot leg thermowells inside the existing RTD

bypass piping scoops.

Instead, the three A loop hot leg thermowells were

modified to facilitate installation in an elbow of thicker wall pipe

further downstream.

As discussed in IR 89-07,

the A loop hot leg

thermowells were subsequently redesigned when vibration induced fatigue

failure resulted in through-wall leakage.

Since conservative analysis

demonstrated that the redesigned thermowells would last at least 0.8

years, the licensee authorized unit operation for up to 9 months while

working on a final resolution.

Based on subsequent analysis, the

redesigned thermowells are now expected to last for the life of the plant.

The inspector reviewed associated engineering evaluations 89-52 (which

utilized a forcing function that reflects the redesigned thermowell

insertion length of 3.5 inches versus the earlier 4.5 inches) and 90-101

(which is based on vibration data taken at the start of RO 13), and had no

further concerns regarding this matter.

Closed IFI 89-23-02, Review Planned PM Schedule For AFW Components.

This

item addressed the concern that AFW pump cavitation damage and motor rotor

bar cracking identified in 1989, could have been detected earlier through

a more comprehensive PM program. As discussed in IR 91-15 the motor rotor

bar cracking concern has evidently been resolved and monitoring of rotor

bar condition is routinely being performed. The licensee also developed a

comprehensive PM schedule for the

AFW

pumps, motors,

and system

7

components.

Included in the pump PM schedule are: overhaul/teardown,

vibration analysis, flow checks, bearing inspections, and SDAFWP overspeed

trip mechanism inspection.

The AFW pump motors are scheduled for a

rotating overhaul/teardown sequence which consists of the motor scheduled

for refurbishment being replaced with the motor most recently refurbished.

In addition, motor diagnostic analysis and vibration analysis will be

regularly performed.

Also scheduled for PMs are FCVs 1424,

1425,

and

6416,

and air operated valves.

System Check valves and MOVs will be

maintained in accordance with the MVMP.

Additionally, system flow

orifices will be replaced on a refueling intervals and SDAFWP steam traps

and strainers will be inspected on the same interval.

The inspectors

verified that WRs have been generated for selected PM activities that are

to be accomplished during the next RO. Based on the established schedule,

this item is closed.

(Closed)

VIO 89-23-04,

Failure To Adequately Establish Measures

For

Suitability of Processes Essential To Safety-Related Functions As Required

By 10 CFR 50 Appendix B Criterion III.

This violation addressed two

unrelated examples. The first example involved an incorrect application

of Bernoulli's Equation in an AFW modification acceptance test procedure.

The other example concerned a SW modification which did not adequately

take into account the affects of the welding process utilized on the coal

tar lined pipe.

In the first example, the AFW acceptance test procedure

was revised to account for elevation and velocity head losses, and the

modified piping was retested with satisfactory results.

With respect to

the second example,

subsequent coal tar fouling was detected in the SW

tubes of containment fan coolers HVH 1-4.

Immediate corrective actions,

which are discussed in detail in IR 89-23,

included such things as

cleaning the HVH units and flushing the loose coal tar pieces from all

affected piping (i.e., from the suction of the SW booster pumps to the

outlet piping of the HVH units).

The affected SW piping was subsequently

replaced in RO 13.

The inspector reviewed associated design deficiency

reports (89-45 and 90-06) which were generated as a result of these two

issues and considered the indicated post event reviews conducted with

design personnel to be appropriate. This item is closed.

No violations or deviations were identified.

6.

Exit Interview (30703)

The inspection scope and findings were summarized on August 13, 1991, with

those persons indicated in paragraph 1.

The inspectors described the

areas inspected and discussed in detail the inspection findings listed

below and in the summary.

Dissenting comments were not received from the

licensee.

The licensee did not identify as proprietary any of the

materials provided to,

or reviewed

by the inspectors during this

inspection.

8

Item Number

Description/Reference Paragraph

91-17-01

VIO - Failure to Adequately Establish

Procedures as Required (paragraph 2).

91-07-02

VIO - Failure to Utilize a Work

Request

to

Perform

Maintenance

Activities (paragraph 3).

91-17-03

NCV -

Failure to Complete Procedure

Usage Cover Sheet (paragraph 3).

7. List of Acronyms and Initialisms

a.m.

Ante Meridiem

AC

Alternating Current

AFW

Auxiliary Feedwater

BIT

Boron Injection Tank

CFR

Code of Federal Regulations

CVCS

Chemical Volume Control System

CVS

Chemical Volume System

EOF

Emergency Operations Facility

EOP

Emergency Operation Procedures

EPP

End Path Procedures

FCV

Flow Control Valves

FW

Feedwater

HVE

Heating Ventilation Exhaust

HVH

Heating Ventilation Handling

IFI

Inspector Followup Item

i.e.

That is

IR

Inspection Report

IVSW

Isolation Valve Seal Water

LCO

Limiting Condition for Operation

LOCA

Loss of Coolant Accident

MFRV

Main Feedwater Regulating Valve

MMM

Maintenance Management Manual

MOD

Modification and Design Control Procedure

MOV

Motor Operated Valve

MVMP

Managed Valve Maintenance Program

NAD

Nuclear Assessment Department

NCV

Non-cited Violation

NED

Nuclear Engineering Department

NOV

Notice of Violation

NRC

Nuclear Regulatory Commission

OST

Operations Surveillance Test

PIC

Process Instrument Calibration

p.m.

Post Meridiem

PM

Preventive Maintenance

PNSC

Plant Nuclear Safety Committee

RCDT

Reactor Coolant Drain Tank

9

RCS

Reactor Coolant System

RHR

Residual Heat Removal

RNP

Robinson Nuclear Project

RO

Refueling Outage

RTB

Reactor Trip Breaker

RTGB

Reactor Turbine

SDAFWP

System Driven Auxiliary FeedwaterPump

SI

Safety Injection

SO

Senior Operator

SP

Special Procedure

SW

Service Water

TS

Technical Specification

V & V

Verification.& Validation

VAC

Volts Alternating Current

VIO

Violation

VOTES

Valve Operation Test And Evaluation System

W/R

Work Request

WR/JO

Work Request/Job Order