ML14176A688

From kanterella
Jump to navigation Jump to search
Revised Pages 4 & 7 to IE Insp Rept 50-261/81-25
ML14176A688
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 10/30/1981
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14176A689 List:
References
50-261-81-25, NUDOCS 8111170478
Download: ML14176A688 (7)


See also: IR 05000261/1981025

Text

4

numbers for Part 21 evaluations, for writing a procedure for

Regulatory Compliance to use in evaluation and for changing

QAP 104 to delineate responsibility between Regulatory Compliance

and QA/QC.

Until these changes can be reviewed for adequacy, they

will be carried collectively as an open item (261/81-15-251).

d. Inadequate Reading List for QA/QC Personnel

The licensee uses required reading lists for qualificatic~n of"QA/QC

personnel.

The reading list currently being ised is lacking many of

the accepted regulations, guides, and standards with which personnel

should be familiar in order to be trained.

A prime example is the

reading of 10 CFR 50.59, in that QA/QC personnel are required to make

surveillance reports on changes conducted under 10 CFR 50.59.

The

licensee is in the process of completely updating all training being

given to QA/QC personnel and provided a target date of January 1, 1982

for having the revised reading list in use. Until the revised training

can

be

reviewed,

this item will

be carried as an open item

(261/81-15-25).

6. Design, Design Changes and Modifications (37700)

This functional are'a was reviewed by the Performance Appraisal Section team

inspection and is documented in IE Inspection Report, Management Appraisal

30-261/81-05

(PAS)

dated August 13,

1981..

The inspector reviewed the

results of this report and determined that this functional area is similar

to that normally inspected by

Region II,

consequently

no additional

inspection is required at this time.

Discussions with the NRC resident

inspector also identified that his inspection effort routinely includes

monitoring of selected design modifications in progress as documented in

monthly inspection reports.

7. Implementation, Audit Program (40704)

This functional area was reviewed by the Performan-a Appraisal Section team

inspection and is documentated in IE Inspection Report, Management Appraisal

50-261/81-05

(PAS)

dated August 13,

1981.

The inspector reviewed the

results of this report and determined that this functional area is similar

to that normally inspected by Region II

and no additional inspection is

required at this time.

8. Training (41700)

This functional area was reviewed by the Performance Appraisal Section team

inspection and is documentated in IE Inspection Report, Management Appraisal

50-261/81-05

(PAS)

dated August 13,

1981.

The inspector reviewed the

results of this report and determined that this functional area is similar

to that normally inspected by Region II

and no additional inspection is

required at this time.

PDR ADOC 0 8 0 0

PDR

5

9. Requalification Training (41701)

This functional area was reviewed by the Performance Appraisal Section team

inspection and is documentated in IE Inspection Report, Management Appraisal

50-261/81-05

(PAS)

dated August 13,

1981.

The inspector reviewed the

results of this report and determined that this functional area is similar

to that normally inspected by Region II

and only limited additional

inspection was performed.

The licensee's requalification program was reviewed for meeting the revised

grading criteria for annual requalification examinations.

Based on this

review one unresolved item was identified. As stated in NUREG 0737, the

NRC requires individuals to make greater than 70% in each section and

greater than 80% overall on their license examinations or retake the entire

examination. The licensee is not requiring an entirely new examination for

individuals making less than 80% overall. This problem will be carried as

an unresolved item (261/81-25-05) pending NRC management review.

10.

Procedures (42700)

References:

(a) Regulatory Guide

1.33, Quality Assurance Program

Requirements

(b) 10 CFR 50.59, Changes, Tests and Experiments

(c) GP3B, Reactor Trip Recovery, Revision 5, dated 6/81

(d) GP4, Power Operation, Revision 6, dated 8/81

(e) OP25,

Reactor Coolant System Operation, Revision 3.2,

dated 7/78

(f) OP40, Component Cooling System, Revision 2.4, dated 7/78

(g) OP14, Auxiliary Feedwater System, Revision 15 dated 8/81

(h) OP28,

Charging and Volume Control,

Revision 10,

dated

2/81

(i) OP42,

Safety

Injection

and

Containment

Spray,

Revision 17, dated 10/80

(j)

OP23,

Reactor Control and Protection Systems,

Revision

5.3, dated 7/78

(k) Al-20, Component Cooling Heat Exchanger A/B Outlet High,

Revision 7, 6/81

(1) A2-4, Accumulator Tank A Hi/Low Level, Revision 3, dated

4/81

(m) A3-8, Pressurizer Protection Hi Pressure, Revision 3,

dated 4/81

(n) B1-35, Reactor Coolant Pump's Hi Vibration, Revision 7,

dated 3/81

(o) C1-39, Condensate Storage Tank Level Hi/Lo, Revision 4,

dated 8/81

(p) A3-35, Volume Control Tank Hi/Lo Level

(q) E1-1,

Incident Involving Reactor Cooling Systems

Depressurization, Revision 28, dated 6/81

6

(r)

E1-7, Station Blackout, Revision 9, dated 6/81

(s) AP 1, Malfunction of Reactor Control System, Revision 3

dated 6/81

(t) AP 1.9, Malfunction of Reactor Coolant System Pressure

Control, Revision 1, dated 5/79

(u) MI 10-6, Repair Process for Disassembly, Inspection and

Reassembly of Reactor Coolant Pump,

Revision 26, dated

8/81

(v) MI 10-14,

Component Cooling

Heat

Exchanger

Tube

Plugging, Revision 19, dated 3/73

(w) MI 11-1,1, Reactor Coolant Temperature OPAT Protection,

Revision 1.10, dated 2/78

(x) MI 11-13, VCT Level, Revision 1.16, dated 2/78

(Y) MI 11-33,

Boron Injection Tank Level,

Revision 1.16,

dated 2/78

(z) MI 10-21,

Disassembly, Repair, and Reassembly of Steam

Driven Auxiliary Feed Pump, Revision 4, dated 5/79

(aa) Administrative Procedure 8.0,

Plant Records,

Revision

106, dated 7/81

(bb) Administrative Procedure 10.0,

Personnel Training and

Retraining, Revision 98, dated 3/81

(cc)

Technical Specifications Section 6

(dd) Administrative Instructions in their entirety

For References (c)-(bb),

the inspector verified that review and approval

were in accordance with Technical Specifications,

license changes were

reflected in the procedures,

temporary changes were properly approved and

did not conflict with Technical Specifications, changes were in conformance

with

10 CFR. 50.59 requirements,

technical

content. was adequate,

and

controlled copies were current as to revision.

Based on the above review and actual observation of procedure use, two open

items and one inspector followup item were identified.

a. Procedure for Control of Temporary Procedures and Changes

AI.5.3, Deviations From Established. Procedures Revision 98 dated 3/81

does not present any formal mechanism for keeping track of temporary

changes once they have been instituted and sent to the PNSC for review.

When a temporary change is made,

the operators :make a pen and ink

change directly on the working copy in order to maintain awareness of.

the change. This is an acceptable method but should be documented.:

The licensee provided a target date of October 31, 1981 for changing

their procedure to requ ire this documentation.

This change will be

reviewed in a subsequent inspection and will be carried as an open item

(261/81-25-06).

0s

7

b. Quorum for PNSC Review

Technical Specification 6.5.1.6 requires that for a quorum the

Chairman/Vice Chairman plus three additional members must be present.

AI 3.4, Quorum,

Revision ;86,

dated 12/80 states that for special

meetings (as opposed to monthly meetings) a member may be considered

present if he is in telephone communication. The NRC position is that

telephone communication may be us'ed only when there is an emergency

condition or no reasonable way of convening all needed persons for a

special condition. Th.e inspector reviewed the special meetings for a

two-year period and determined that the licensee was following the NRC

position, but the procedure was not requiring that adherence.

Until

the licensee changes the procedure to require adherence to

NRC

position, this item will be carried as an open item (261/81-25-07).

c. Conflict in Technical Specification 6.2

Technical Specification Figure 6.2-2 requires the Senior Control

Operator to hold an SRO license. The words in Technical Specification 6.2 only requires the Shift Foreman to hold an SRO and the Senior

Control

Operator to hold an

RO license.

This conflict will be

clarified, as part of a change to the operating organization submitted

in a Technical Specification change to NRR for approval.

Until this

change is approved, this item will be carried as an inspector followup

item (261/81-25-08).

11.

Personnel Qualification Program (30701)

References:

(a) Technical Specification Section 6

(b) ANSI 18.1,

1971, Selaction and Training of Nuclear Power

Plant Personnel

The inspector reviewed the administrative controls for every position at the

site against the licensee'; cowmitments in references (a) and (b).

Also

using references (a) and (b),

the inspector reviewed the background and

qualifications for every manager, supervisor, foreman, director and operator

on site as well as a sample of five workers from each technician, QA/QC,

specialist, and craftsmen area.

Based on this review one inspector folloVup item was identified.

The

inspector noted that the site QA/QC Director and two QA/QC specialists had

transferred into operations QA from construction QA with no formal training

in the regulatory guides, standards, or audit/surveillance techniques they

would encounter.

The licensee identified a similar item in audit QAA

125-10. Until the NRC can evaluate the response to the corporate QA

findings, this item will

be tracked as

an inspector followup item

(261/81-15-25).

8

12.

Offsite Support Staff (40703)

References:

(a) Technical Specifications-Section 6

(b) ANSI 18.1-1976, Selection and Training of Nuclear Power

Plant Personnel

(c) 10 CFR 50,

Appendix B, Quality Assurance Criteria for

Nuclear Power plants

(d) Licensee Letter OQA-81-026, dated 3/18/81

(e) ANSI

18.7-1976,

Administrative Controls

and Quality

Assurance for the Operational Phase of Nuclear Power

Plants

The inspector reviewed the following position descriptions to verify that

they describe the responsibilities, authority and lines of communication

which meet the requirements of References (a)-(e)

and the Corporate QA

Program Manual: Manager-Corporate Quality Assurance; Principle Specialist,

Performance Evaluation; Manager-Operations QA/QC; Senior Specialist, QA/QC;

Director,

QA/QC Operating Plants; Manager,

Engineering Support Nuclear

Plants; Principle Engineer,

Mechanical; Principle Engineer, Electrical;

Project Engineer. The inspector interviewed six of the individuals listed

above and reviewed the background and qualifications of all individuals

holding the above positions.

The inspector reviewed the results of audits performed by the corporate

group and observed an audit being performed at the site. The inspector and

audit team found many deficiencies in the area of corrective action systems.

These items were identified by the PAS inspection in IE Report 50-261/81-05

(PAS) dated August 13, 1981.

Based on this review and the interviews conducted

, one open item was

identified.

As part of the qualification for Lead Auditors in the

Performance Evaluation Section, individuals are required to complete a

reading file which contains the regulatory requirements and commitments of

the licensee. An individual must complete this reading file prior to being

considered for Lead Auditor but is never directly questioned as to content.

The Auditors interviewed by the inspector appeared knowledgeable as to the

contents of regulatory and licensee requirements, but no direct method has

been established to insure transfer of knowledge. In addition, the required

reading file is not part of an approved procedure.

Until the licensee

establishes a formal method for determination of knowledge transfer and the

reading file becomes part of an approved procedure, this item will remain

open (261/81-25-10).

13.

Maintenance (62700)

This functional area was reviewed by the Performance Appraisal Section team

inspection and is documentated in IE Inspection Report, Management Appraisal

50-261/81-05

(PAS)

dated August 13,

1981.

The inspector reviewed the

results of this report and determined that this functional area is similar

  • .

9

9

to that normally inspected by Region II

and no additional inspection is

required at this time.

Discussions with the NRC resident also identified

that their inspection effort routinely includes monitoring of maintenance in

progress as documented in monthly inspection reports.

14.

Maintenance Program (62702)

This functional area was reviewed by the Performance Appraisal Section team

inspection and is documentated in IE Inspection Report, Management Appraisal

50-261/81-05

(PAS)

dated August 13,

1981.

The inspector reviewed the

results of this report and determined that this functional area is similar

to that normally inspected by Region II and no additional inspection is

required at this time.

15.

Nonroutine Reporting Program (90714)

Reference:

TI 303,

Dissemination of Information/Feedback of Operating

Experience, Revision 3, dated 2/81

The inspector reviewed the licensee's program to ascertain whether responsi

bilities had been assigned for review and evaluation of off-normal operating

events, planned and unplanned maintenance activities, surveillance testing

and outage activities to assure conformance with regulatory requirements.

The inspector also reviewed the program to ascertain whether vendor

bulletins and circulars are reviewed for applicability. At this time there

are no formal procedures for review and evaluation of vendor items, but the

licensee follows an informal procedure whereby items are distributed through

responsible managers

and supervisors to an engineer who is a.ssigned

responsibility. In addition, all items are reviewed by PNSC for safety

significance.

The licensee is presently evaluating the need for formal

procedures.

Based on this review,

one open item was identified.

The licensee has

recently undergone a site and corporate reorganization.

There are now three

organizations on site (there used to be only one)

who are responsible for

review and evaluation of off-normal events for safety significance.

The

Regulatory Compliance group and the Onsite Nuclear Safety group are still in

the process of developing procedures to implement their chartered functions.

The third group, the Site QA/QC Organization, has changed its reportability

to Corporate Headquarters and has given some of its functions to the other

two groups.

At the present time, there is no formal method for the licensee

to transfer between sites internal findings, such as CQA audits and NCRs,

which may be generic.

Two of these organizations, Onsite Nuclear Safety and

QA/QC,

report directly to Corporate Headquarters.

Once the new organiza

tions are completely in place with operating procedures, transfer of generic

findings through a corporate focal point will probably take place. Until

the organizations can function as chartered and the NRC can review the new

operation for transfer of internal findings, this item will remain open

(261/81-25-11).

10

16.

Licensee Action on Previously Identified Inspector Items (92701)

a. (Open) Open Item (261/79-19-09):

Calibration Program for Safety

Related Instruments. The inspector reviewed the program the licensee

is developing for calibration of nontechnical specification safety

related instrumentation. This item was originally identified by the

licensee's Corporate QA Department in Surveillance Report OQAI 79-25

.with a scheduled completion date of January 1, 1980.

The item was

reviewed in three subsequent inspections (261/80-06, 22, 25) but had

not been completed. The program has progressed close to completion and

the licensee stated they will attempt to finish by January 1, 1982.

The licensee will be requested to specifically reply to this item in

the inspection report transmittal letter.

b.

(Open) Inspector Followup Item (261/79-19-19): Warehousing. This item

was reviewed in two previous inspections (261/80-06,

25) and most of

the areas were completed. In this inspection the final two areas of

concern were reviewed. SR-3, Storing Plant Material and Equipment,

Revision 2, dated 4/81, Section 4.2 addresses protection of parts and

materials

and

meets the ANSI N45.2.2 requirement for Section 3.

MP-1-5A, Overhead and Gantry Crane, Revision 0, dated 7/81 and TI 106,

Crane and Forklift Qualification, Revision 2, dated 9/81 meet the

procedure requirements of ANSI N45.2.2, Section 7. The only require

ment remaining is to perform the training.

The licensee is considering

a vendor group to perform this training by December 31, 1981. Due to

the extended time for completion, this item will be addressed in the

inspection report cover letter requesting a commitment for completion.