Text
AUG 2 6 1981
Carolina Power and Light Company
ATTN:
Mr. J. A. Jones, Senior Executive
Vice President and Chief
Operating Officer
411 Fayetteville Street
Raleigh, NC 27602
Gentlemen:
Subject:
Report No. 50-261/81-22
This refers to the routine inspection conducted by Mr. S. Weise of this office on
July 11, 1981 through August 10, 1981, of activities authorized by NRC License
No. DPR-23 for the H. B. Robinson Unit 2 facility. Our preliminary findings
were discussed with Mr. R. B. Starkey, Plant Manager, at the conclusion of
the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
During the inspection, it was found that certain activities under your license
appear to violate NRC requirements. This item and references to pertinent
requirements are listed in the Notice of Violation enclosed herewith as
Appendix A. Elements to be included in your response are delineated in
Appendix A.
We have examined actions you have taken with regard to previously identified
enforcement matters. These are discussed in the enclosed inspection report.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this
letter and the enclosed report will be placed in the NRC's Public Document Room.
If the report contains any information that you believe to be exempt from dis
closure under 10 CFR 9.5(a)(4), it is necessary that you: (a) notify this office
by telephone within ten days from the date of this letter of your intention to
file a request for withholding; and (b) submit within twenty-five days from the
date of this letter a written application to this office to withhold such informa
tion. If your receipt of this letter has been delayed such that less than seven
days are available for your review, please notify this office promptly so that a
new due date may be established. Consistent with section 2.790(b)(1), such
application must be accompanied by an affidavit executed by the owner of the
information which identifies the document or part thereof sought to be withheld,
and a full statement of the reasons on the basis of which it is claimed that the
information should be withheld from public disclosure. This section further
requires the statement to address with specificity the considerations listed in
10 CFR 2.790(b)(4). The information sought to be withheld shall be incorporated
as far as possible into a separate part of the affidavit. If we do not hear from
(IR A03O
0 0 02 6 '
P DR
Carolina Power and Light Company
2
you in this regard within the specified periods noted above, the report will be
placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
R. C. Lewis, Director
Division of Resident and Reactor
Project Inspection
Enclosures:
1. Appendix A, Notice of Violation
2. Inspection Report No. 50-261/81-22
cc w/encl:
R. B. Starkey, Jr., Plant Manager
bcc w/encl:
NRC Resident Inspector
Document Management Branch
State of South Carolina
Sr rCJu1lan
RButcher
RCL *s(/