UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
230 PEACHTREE STREET, NN.
SUITE 1217
ATLANTA, GEORGIA 30303
SEP 8
1978
In Reply Refer To:
RII:TJM
50-261/78-17
Carolina Power and Light Company
ATTN:
Mr. J. A. Jones
Executive Vice President
Engineering, Construction
and Operation
336 Fayetteville Street
Raleigh, North Carolina 27602
Gentlemen:
This refers to the inspection conducted by Mr. T. J. McHenry of this
.office
on August 1-4, 1978, of activities authorized by NRC Operating
License No. DPR-23 for the H. B. Robinson 2 facility, and to the dis
cussions of our findings held with Mr. R. B. Starkey 9t the conclusion
of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection
consisted of selective examinations of procedures and representative
records, interviews with personnel, and observations by the inspector.
During the inspection, it was found that certain activities under your
license appear to be in noncompliance with NRC requirements. This item
and references to pertinent requirements are listed in the Notice of
Violation enclosed herewith as Appendix A. This notice is sent to you
pursuant to the provisions of Section 2.201 of the NRC's "Rules of
Practice," Part 2, Title 10, Code of Federal Regulations. Section 2.201
requires you to submit to this office, within 20 days of your receipt of
this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results
achieved; (2) corrective steps which will be taken to avoid further
noncompliance; and (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's "Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter
and the enclosed inspection report will be placed in the NRC's Public
Document Room. If this report contains any information that you (or
Carolina.Power & Light Company
-2-
SEP 8
1978
your contractor) believe to be proprietary, it is necessary that you
make a written application within 20 days to this office to withhold
such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is
claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained
in a separate part of the document. If we do not hear from you in this
regard within the specified period, the report will be placed in the
Public Document Room.
Should you have any questions concerning this letter, we will be glad
to discuss them with you.
Sincerely,
F. J. Long, Chief
Reactor Operations and
Nuclear Support Branch
Enclosures:
.
Appendix A, Notice of Violation
Inspection Report No. 50-261/78-17
cc: Mr. R. B. Starkey, Plant Manager
P. 0. Box 790
Hartsville, South Carolina 29550