MONTHYEARML14139A2702014-05-20020 May 2014 One. Unit 1 - Acceptance of Licensing Action, Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Acceptance Review ML14139A2752014-05-30030 May 2014 One. Unit 1 - Online Reference Portal for License Amendment Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Other ML15086A0492015-03-27027 March 2015 Regulatory Audit Plan for 4/20-23/15 Audit in Support of Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Other ML15091A4312015-05-0505 May 2015 Request for Additional Information, Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML15128A1782015-05-0808 May 2015 NRR E-mail Capture - Corrections to ANO-1 NFPA 805 Requests for Additional Information - TAC No MF3419 Project stage: RAI 1CAN061501, 60-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-06-16016 June 2015 60-Day Response to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Response to RAI ML15225A2542015-08-14014 August 2015 Summary of 4/20-23/2015 Audit in Support of Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Other ML15251A2202015-09-0808 September 2015 NRR E-mail Capture - 2nd Round Requests for Additional Information - ANO-1 NFPA 805 LAR - TAC No. MF3419 Project stage: RAI ML15280A1142015-10-0606 October 2015 NRR E-mail Capture - Second Round Follow-up Requests for Additional Information - ANO-1 NFPA 805 LAR - TAC No. MF3419 (Formal Transmittal) Project stage: RAI 1CAN111501, Second Set of Round 2 Responses to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-11-0404 November 2015 Second Set of Round 2 Responses to Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Response to RAI 1CAN111502, Clarification of Response to Round 2 Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-8052015-11-17017 November 2015 Clarification of Response to Round 2 Request for Additional Information Adoption of National Fire Protection Association Standard NFPA-805 Project stage: Request ML16012A0492016-01-12012 January 2016 NRR E-mail Capture - 3rd Round Request for Additional Information - ANO-1 NFPA 805 LAR - TAC No. MF3419 Project stage: RAI ML16070A1312016-03-10010 March 2016 NRR E-mail Capture - 4th Round Request for Additional Information - ANO-1 NFPA 805 LAR - TAC No. MF3419 Project stage: RAI 2015-05-05
[Table View] |
|
---|
Category:Letter
MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation ML23209A6022023-08-0909 August 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 ML23208A2132023-08-0303 August 2023 Regulatory Audit Summary Concerning Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23188A1732023-07-12012 July 2023 Request for Withholding Information from Public Disclosure ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements IR 05000313/20234032023-06-28028 June 2023 Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23180A1082023-06-20020 June 2023 ANO Unit 1 SAR Amendment 31, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report IR 05000313/20234012023-06-13013 June 2023 Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23121A3012023-05-10010 May 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk - Informed Completion Times ML23114A3572023-05-10010 May 2023 Regulatory Audit Summary Concerning Review of Request for Alternative ANO-CISI-002 Regarding Containment Inservice Inspection Frequency ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23108A1362023-04-24024 April 2023 Approval of Request for Half-Nozzle Repair of Reactor Vessel Closure Head Penetration No. 46 ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G 2024-01-24
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 30, 2014 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 1 -NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 LICENSE AMENDMENT APPLICATION ONLINE REFERENCE PORTAL (TAC NO. MF3419)
Dear Sir or Madam:
By letter dated January 29, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14029A438), Entergy Operations, Inc. (Entergy, the licensee),
submitted a license amendment request (LAR) to adopt National Fire Protection Association (NFPA) 805, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition," at Arkansas Nuclear One, Unit 1 (AN0-1).
To improve the efficiency of the U.S. Nuclear Regulatory Commission (NRC) reviews, the licensee's representatives and the NRC staff have discussed the use of an online reference portal that would allow the NRC staff, and its contractors, limited read-only access to the basis documents and other reference materials cited in the application. By letter dated December 20, 2011 (ADAMS Accession No. ML113340218), the NRC staff described the requested portal process. By letter dated April 26, 2012 (ADAMS Accession No. ML121020516), a similar process was requested for AN0-2. The online reference portal would allow the NRC staff to audit basis documents to determine whether the information included in the documents support the application. Documents identified as necessary for analysis of the application will be identified by the NRC staff. The licensee will be formally requested to submit those documents on the NRC docket. Use of the online reference portal is acceptable as long as the following conditions are met:
- The online reference portal will be password-protected and passwords will be assigned to those directly involved in the review on a need-to-know basis;
- The online reference portal will be sufficiently secure to prevent staff from printing, saving, or downloading any documents; and
- Conditions of use of the online reference portal will be displayed on the log-in screen and will require concurrence by each user.
The NRC staff requests that the portal for AN0-1 be populated with the documents listed in the enclosure to this letter. This will help with the preparation for the site audits and increase effectiveness of the review prior to the audit. By letter dated May 20, 2014 (ADAMS Accession No. ML14139A270), the NRC staff accepted the AN0-1 NFPA 805 application for review.
Therefore, the NRC also requests that Entergy provide access to the AN0-1 portal for NRC staff use and send the necessary information to access the portal, such as username and password, to the contact listed below, as soon as possible.
The conditions associated with the online reference portal must be maintained throughout the duration of the review process. Please provide written confirmation that Entergy agrees to the terms and conditions set forth in this letter.
If you have any questions, please contact me at (301) 415-2833 or via e-mail at peter. bamford@nrc.gov.
Sincerely, Peter J. Bamford, Proj ct Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-313
Enclosure:
Generic List of Requested Documents cc w/encl: Distribution via Listserv
GENERIC LIST OF SHAREPOINT PORTAL REQUESTED DOCUMENTS FOR NFPA 805
- 1. National Fire Protection Association (NFPA) Code Deviations and Justifications
- 2. All applicable Probabilistic Risk Assessment (PRA) Peer Review Reports
- 3. All site calculations reference in the License Amendment Request (LAR)
- 4. Credited Fire Protection (FP) System and Feature Drawings
- a. Layout Drawings: fire barriers, installed fire detection and suppression systems, fire areas, fire zones, stairwells, fire doors, fire dampers, etc.
- b. Piping and Instrumentation Diagrams (P&IDs): FP Water System
- c. System Descriptions for Fire Suppression, Water Supply, and Detection (including incipient or very early warning fire detection (VEWFD))
- d. Hydraulic Calculations for Fire Service and Fire Suppression System Water Demand (if used to support non-fire water use in Title 10 of the Code of Federal Regulations, paragraph 50.48(c)(2)(vii))
- 5. Drawings related to systems credited in the Nuclear Safety Capability Assessment (NSCA) as well as those required to fully understand plant response:
- a. P&IDs: Reactor Coolant System, Main Steam, Main Feedwater, Circulating Water, Service Water, etc.
- b. Safe Shutdown/NSCA Logic Diagrams (if used)
- c. Electrical Distribution System One-Lines (alternating current (AC) and direct current (DC))
- 6. Those documents that fulfill the NFPA 805 requirement for "Design Basis Document (DBD)"
- a. Fire Area Calculations (e.g. Fire Safety Analyses, Fire Risk Analyses, Plant Change Evaluations, Fire Risk Evaluations, etc.)
- b. NSCA Calculation (Safe Shutdown/Circuit Analysis)
- c. Multiple Spurious Operation (MSO) Expert Panel Report
- d. Thermo-hydraulic Analysis serving as the basis for Variance from Deterministic Requirements (VFDR) and recovery action (RA) timing
- e. Evaluation of Recovery Actions for feasibility Enclosure
- f. Fire Hazards Analysis (FHA) (if separate from the fire area calculations)
- g. Non-Power Operation (NPO) Calculation(s)
- h. Radioactive Release Calculation(s)
- i. Pre-fire Plans
- 7. Fire PRA Calculations
- a. Plant Boundary/Partitioning Methods and Results (TASK 1)
- b. Component Selection Calculation (TASK 2)
- c. Cable Selection and Circuit Analysis (TASKS 3, 9, and 10)
- d. Ignition Frequency Calculation (TASK 6)
- e. Fire PRA Quantification Calculations (TASK 5) including:
- i. Seismic Fire Interactions (TASK 13) Methodologies and results (including assumptions) ii. Screening Methodologies and Results (TASKS 4 and 7) (including assumptions) iii. Fire Risk Quantifications (TASK 14) Methodologies and Results (including assumptions) iv. Multi-compartment Screening and Analysis
- v. Post-fire Human Reliability Analysis (HRA) Methodologies and Results (including assumptions) (TASK 12) vi. Detailed proposed modification descriptions (Engineering Change Requests/Records) sufficient to comprehend potential impact/improvement to Fire PRA
- f. NFPA 805 Application Calculation (provides all the delta risk calculations for VFDRs)
- g. Control Room Risk Calculation
- h. Uncertainty and Sensitivity Calculations (TASK 15)
- i. Fire Modeling Calculations used to support the Fire PRA (zone of influence (ZOI), hot gas layer, bounding, detailed fire modeling, etc.)
ii Plant Specific Verification and Validation (V&V) Analysis iii. Non-public V&V References (e.g.; Electric Power Research Institute (EPRI) Fire Modeling, Generic Treatment) iv. Fire Modeling Assumptions and Calculations performed to support target selection (e.g.; ZOI, secondary fires, transient combustible/ignition sources) including those that deviate from NUREG/CR-6850 (TASKS 8 and 11)
- 8. Fire Modeling used in the Fire Modeling Performance-based Approach
- a. Plant Specific V&V Analysis performed
- b. Non-public V&V References (e.g.; EPRI Fire Modeling, Generic Treatments ... )
- c. Fire Modeling Assumptions and Calculations performed to support Performance-Based Evaluations (e.g.; ZOI, secondary fires, transient combustible/ignition sources ... ) considered outside NUREG/CR 6850 Assumptions and Parameters (TASKS 8 and 11)
- d. Hot Gas Layer (HGL) Determination Calculations (including Assumptions)
- 9. Fire Protection Program Manual
- 10. Fire Protection Quality Assurance (QA) Program (including FP Structure System Components (SSCs) and FP Features)
- 11. NFPA 805 Monitoring Program Calculations and Procedures
- 12. Technical Requirements Manual (TRM)
- 13. Updated Final Safety Analysis Report (UFSAR) Changes (including current UFSAR 9.5.1 Fire Protection and Section 7.4 Alternate Shutdown/Instrumentation)
ML14139A275 *via email OFFICE NRR/DORL/LPL4-1/PM NRR/DORLILPL4-1/LA NRR/DORLILPL4-1/BC NRR/DORL/LPL4-1/PM NAME PBamford JBurkhardt MMarkley PBamford DATE 5/19/14 5/29/14 5/30/14 5/30/14