Forwards Supplemental Safety Evaluation Accepting Util Response to Generic Ltr 83-28,Item 4.2 (Parts 1 & 2)
ML13330B383
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/16/1988
From: Trammell C
Office of Nuclear Reactor Regulation
To: Baskin K
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13330B384 List:
References
GL-83-28, TAC-53148, NUDOCS 8809270033
Download: ML13330B383 (3)


Text

September 16, 1988 Docket No.:

50-206 DISTRIBUTION Docket File ACRS (10)

NRC & LPDRs JBradfute CTrammell (2)

Mr. Kenneth P. Baskin MVirgilio Vice President JLee Southern California Edison Company OGC-White Flint 2244 Walnut Grove Avenue PD5 Plant File Post Office Box 800 EJordan Rosemead, California 91770 JPartlow

Dear Mr. Baskin:

SUBJECT:

GENERIC LETTER 83-28, ITEM 4.2 (PARTS 1 AND 2) (Tac No. 53148)

Re:

San Onofre Nuclear Generating Station, Unit No. 1 We have completed our review of Item 4.2 (Parts 1 and 2) to Generic Letter 83-28. As discussed in more detail in the enclosed Safety Evaluation, we find your response to this item acceptable. This item is therefore resolved for San Onofre Unit No. 1.

Sincerely, original signed by Charles M. Trammell, Senior Project Manager Project Directorate V Division of Reactor Projects -

III, IV, V and Special Projects

Enclosure:

Safety Evaluation cc w/enclosure:

See next page D5 DR D5 Trammell:dr GK ton 9/V 88 9/J /88 OFFICIAL RECORD COPY 88O9270033 880916 PDR ADOCK 05000206 P

PDC

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 September 16, 1988 Docket No.: 50-206 Mr. Kenneth P. Baskin Vice President Southern California Edison Company 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

Dear Mr. Baskin:

SUBJECT:

GENERIC LETTER 83-28, ITEM 4.2 (PARTS 1 AND 2) (Tac No. 53148)

Re:

San Onofre Nuclear Generating Station, Unit No. 1 We have completed our review of Item 4.2 (Parts 1 and 2) to Generic Letter 83-28. As discussed in more detail in the enclosed Safety Evaluation, we find your response to this item acceptable. This item is therefore resolved for San Onofre Unit No. 1.

Sincerely, Charles M. Trammell, Senior Project Manager Project Directorate V Division of Reactor Projects -

III, IV, V and Special Projects

Enclosure:

Safety Evaluation cc w/enclosure:

See next page

Mr. Kenneth P. Baskin San Onofre Nuclear Generating Southern California Edison Company Station, Unit No. 1 cc Charles R. Kocher, Assistant Mr. Jack McGurk, Acting Chief General Counsel Radiological Health Branch James Beoletto, Esquire State Department of Health Southern California Edison Company Services Post Office Box 800 714 P Street, Office Bldg. 8 Rosemead, California 91770 Sacramento, California 95814 David R. Pigott Mr. Hans Kaspar, Executive Director Orrick, Herrington & Sutcliffe Marine Review Committee, Inc.

600 Montgomery Street 531 Encinitas Boulevard, Suite 105 San Francisco, California 94111 Encinitas, California 92024 Mr. Robert G. Lacy Manager, Nuclear San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Resident Inspector/San Onofre NPS U.S. NRC P. 0. Box 4329 San Clemente, California 92672 Mayor City of San Clemente San Clemente, California 92672 Chairman Board of Supervisors County of San Diego 1600 Pacific Highway Room 335 San Diego, California 92101 Director Energy Facilities Siting Division Energy Resources Conservation &

Development Commission 1516 - 9th Street Sacramento, California 95814 Regional Administrator, Region V U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596