UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 August 19, 1992 Docket No. 50-206 Mr. Harold B. Ray Senior Vice President Southern California Edison Company Irvine Operations Center 23 Parker Street Irvine, California 92718
Dear Mr. Ray:
SUBJECT:
DISPOSITION OF LICENSING ACTIONS ASSOCIATED WITH CLOSURE OF SAN ONOFRE NUCLEAR GENERATING STATION UNIT 1 (TAC NO. M84196)
Your letter dated July 8, 1992, restated your intention to permanently cease power operations at San Onofre Unit 1 at the end of the current fuel cycle.
The letter included a list of open regulatory actions that are currently applicable to San Onofre Unit 1 and proposed a disposition for these actions based on the impending shutdown of the reactor. We reviewed your list and conducted an independent evaluation of the open actions to determine the safety significance of the individual actions in terms of (1) power operations during the remaining months of core life, (2) reactor shutdown procedures, (3) reactor defueling, and (4) defueled plant operations. Our evaluation concluded that the existing open actions can be grouped into the four categories listed in Enclosures 1 through 4.
Enclosures (1) and (2) list open actions that would not enhance safety for the curtailed Unit 1 operating plan that is currently proposed. Typically these actions are long term actions, focused on power operations. It is not likely that these actions can be resolved and implemented in time to be beneficial during the remaining three to four months of core life at Unit 1.
Accordingly, we will not commit any additional resources to complete these actions and we do not require any additional effort from you. These actions that are being closed-out are subdivided into actions initiated by you (Enclosure 1) and actions initiated by the NRC (Enclosure 2).
For the sake of thoroughness, actions are included in these enclosures that appear to be complete in all respects except their implementation is not documented in the NRC data base. Actions in this category are annotated with an asterisk.
Enclosure (3) is a list of six actions that are relevant to safety during the near term power operations or during plant operations in the defueled condition. Resolution of these actions will be required in accordance with existing requirements and schedules.
b Enclosure (4) is included primarily for record purposes. This is a list of actions that were closed by previous correspondence based on the anticipated permanent closure of the Unit 1 reactor.
9208200072 920819 PDR ADOCK 05000206
Mr. Harold August 19, 1992 Please.note that we have assigned a tracking number (TAC number) to this letter. This tracking number will remain active until a Possession-Only License is issued to Unit 1. In the event that your plans to permanently cease power operations at the end of the current Unit 1' fuel cycle are changed, the open actions closed by this letter and those listed in Enclosure (4) will need to be readdressed before restart can begin. Additionally, the Confirmatory Order issued by the NRC on January 2, 1990, includes prerequisites that apply to the next fuel cycle. Please notify us immediately if you disagree with our method for disposition of the remaining Unit 1 regulatory actions or if your Unit 1 closure plans change.
Sincerely, diinal signed by Theodore R. Quay, Director Project Directorate V Ofic ofton Nucleare Reato Reglaio
- 2. Actions Initiated by NRC
- 3. Actions to be Completed
- 4. Actions to be Reopened if San Onofre 1 is Restarted After Cycle 11 cc w/enclosures:
See next page DISTRIBUTION:
Docket Filel NRC & Local PDRs PDV r/f JPartlow BBoger MVirgilio TQuay GKalman JBradfute DFoster OGC (15B18)
ACRS (10)
PDV p/f KPerkins, RV SWeiss(11B20)
EHylton (11B20)
SShankman, EDO CRossi JLieberman EJordan OC/LFMB WRussell, 12G18 TMurley, 12G18 ADTN DAR WR sell T rley
/ /92
/ 92 OFC
- PDV/LA PD PDV/P lPDV/D AD45/DRPW D/DRPW ADP/NR NAME IDFoste rad e GK ITQuay MVirgQl o BBogerMA/
JPart DATE I
/92 92
/ /92 g/12'/92 1/
/92 1 /%'(/
92
/92 OFFICIAL RECORD COPY DOCUMENT NAME:
S084196.LTR
Mr. Harold B. Ray
- 2 Please note that we have assigned a tracking number (TAC number) to this letter. This tracking number will remain active until a Possession-Only License is issued to Unit 1. In the event that your plans to permanently cease power operations at the end of the current Unit 1 fuel cycle are changed, the open actions closed by this letter and those listed in Enclosure (4) will need to be readdressed before restart can begin. Additionally, the Confirmatory Order issued by the NRC on January 2, 1990, includes prerequisites that apply to the next fuel cycle. Please notify us immediately if you disagree with our method for disposition of the remaining Unit 1 regulatory actions or if your Unit I closure plans change.
Sincerely,
Enclosures:
- 1. Actions Initiated by SCE
- 2. Actions Initiated by NRC
- 3. Actions to be Completed
- 4. Actions to be Reopened if San Onofre 1 is Restarted After Cycle 11 cc w/enclosures:
See next page
Mr. Harold B. Ray San Onofre Nuclear Generating Southern California Edison Company Station, Unit No. 1 cc:
Mr. Howard J. Wong Mr. Richard J. Kosiba, Project Manager U.S. Nuclear Regulatory Commission Bechtel Power Corporation Region V 12440 E. Imperial Highway 1450 Maria Lane, Suite 210 Norwalk, California 90650 Walnut Creek, California 94596 Mr. Robert G. Lacy Manager, Nuclear Department San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Resident Inspector/San Onofre NPS c/o U.S. Nuclear Regulatory Commission P. 0. Box 4329 San Clemente, California 92674 Mayor City of San Clemente 100 Avenida Presidio San Clemente, California 92672 Chairman, Board of Supervisors County of San Diego 1600 Pacific Highway, Room 335 San Diego, California 92101 Regional Administrator, Region V U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Mr. Hank Kocol Radiologic Health Branch State Department of Health Services Post Office Box 942732 Sacramento, California 94234 Mr. Don J. Womeldorf Chief, Environmental Management Branch California Department of Health Services 714 P Street, Room 616 Sacramento, California 95814
Enclosure I ACTIONS INITIATED BY SCE TAC MPA Start NRC Implementation Num Num Title Date Review Documented M61092 SAN ONOFRE I - HVAC TECHNICAL 03/28/86 Incomplete No SPECIFICATIONS M71806 SAN ONOFRE 1 - INCREASE SURVEILLANCE 12/29/88 Incomplete No INTERVALS FOR RPS ANALOG CHANNEL TESTS (AA-161)
M71807 SAN ONOFRE I - CONTAINMENT SPRAY 12/29/88 Incomplete No ACTUATION LCO'S AND SURVEILLANCES (AA-162)
M73621 SAN ONOFRE I - CONTAINMENT VENT. AND 06/07/89 Incomplete No AIR LOCK LEAK TEST CRITERIA (AA-170)
M75295 SAN ONOFRE 1 - RVLIS EXTENSION REQUEST 11/01/89 01/02/90 No I (AA-174)
M76374 SAN ONOFRE 1-OPERATOR TRAINING (AA-176) 03/06/90 Incomplete No M7641B SAN ONDFRE 1 - PLANT REFERENCE SIMULATOR 03/23/90 03/22/91 No SCHEDULAR EXEMPTION REQUEST (10CFR55.45)
M77705 SAN ONOFRE I - ECCS ACTUATION LOGIC AND 09/28/90 02/28/91 No t VITAL BUS TRANSFER (AA-189)
M77834 SAN ONOFRE I - T.S. 3.1.4 - RX. COOLANT 10/16/90 Incomplete No LEAKAGE (AA-184)
M80050 SAN ONOFRE I - RESPOND TO SCE LETTER 03/29/91 04/12/91 No I DATED 3/29/91, UNDER - ESTIMATION OF REFILL VOLUME IN LOCA ANALYSIS MB0427 SAN ONOFRE 1 - REFILL VOLUME DIFFERENCES 05/17/91 09/15/91 No t M80465 SAN ONOFRE 1 - INTEGRATED LEAK RATE TEST 05/22/91 Incomplete No APPENDIX J EXEMPTION M80467 SAN ONOFRE I - TEST PRESSURE FOR 05/22/91 Incomplete No CONTAINMENT INTER6RITY TESTING MB0645 SAN ONOFRE I - CONTROL ROD INSERTION 06/18/91 Incomplete No LIMITS RESULTING FROM VOLUME ERROR (AA-196)
ACTIONS INITIATED BY SCE (continued)
TAC MPA Start NRC Implementation Num Num Title Date Review Documented M81716 SAN ONOFRE I - CANTAINMENT TSP AND BORON 09/17/91 Incomplete No INVENTORY LIMITS (AA-198)
MBIB04 SAN ONOFRE I - CORE REACTIVITY 07/27/91 Incomplete No MONITORING REQUIREMENTS (AA-197)
M81805 SAN ONDFRE I - CORE AXIAL OFFSET LIMITS 06/IB/91 Incomplete No (AA-196)
M81806 SAN ONOFRE 1 - LICENSE EXTENSION 10/01/91 Incomplete.
No (AA-200)
ACTIONS INITIATED BY NRC TAC MPA Start NRC Implementation Num Num Title Date Review Documented M06320 A002 SAN ONOFRE 1 - GENERIC-WCAP 8802
(--/--/--)
08/08/79 No I AUGMENTED INSER. INSPEC. OF PIPE WELDS AT RV NOZZLES - ALTERNATE M10051 8023 SAN ONOFRE I - POTENTIAL EQUIPMENT 08/12/76 01/02/90 No I FAILURES ASSOCIATED WITH GRID VOLTAGE M10189 B024 SAN ONOFRE I - CONTAINMENT PURGE
(--/--/--)
03/15/61 No I M13178 0004 SAN ONOFRE I - REACTOR VESSEL CAVITY 02/02/78 02/01/84 No t SEAL RING M41435 SAN ONOFRE I - lIl.5.A-EFFECTS OF PIPE
(--/--/--)
04/26/84 No BREAKS ON STRUCTURES, SYSTEMS AND COMPONENTS INSIDE CONTAINMENT M41473 SAN ONOFRE 1 - 111.5.B-PIPE BREAKS
(--/--I--)
04/23/64 No OUTSIDE CONTAINMENT M41672 SAN ONOFRE 1 - VI.4-CONTAINMENT
(--/--/--)
10/27/83 No ISOLATION SYSTEM M42615 B024 SAN ONOFRE I - LONG TERM REVIEW 1li29/78 02/17/84 No $
CONTAINMENT PURGE AND VENT M42777 B062 SAN ONOFRE I - ESF RESET CONTROL DESIGN 03/13/80 10/05/82 No I DEFICIENCY - I&E BULLETIN 80-06 M43664 C014 SAN ONOFRE I - SEISMIC QUALIFICATION OF 02/10/81 07/01/86 No $
THE AUXILIARY FEEDWATER SYSTEM M46482 SAN ONOFRE 1 - NUREG-0737 Ill.D.3.4,
(--1--/--)
02/03/84 No CONTROL ROOM HABITABILITY M47074 SAN ONOFRE - REVIEW OF THE DESIGN &
(--/--/--)
04/01/85 No I OPERATION OF VENTILATION SYSTEMS M48388 8048 SAN ONOFRE 1 - ADEQUACY OF STATION 05/01/80 07/29/83 No I ELECTRIC DISTRIBUTION VOLTAGES M51130 A017 SAN ONOFRE1 - INSTRUMENTATION TO FOLLOW 12/16/85 02/22/91 No THE COURSE OF AN ACCIDENT (RG 1.97)
M51280 F009 SAN ONOFRE I - 1.D.2.3-SAFETY 03/17/87 07/17/89 No PARAMETER DISPLAY CONSOLE - FULLY IMPLEMENTED
ACTIONS INITIATED BY NRC (continued)
TAC MPA Start NRC Implementation Num Num Title Date Review Documented M53630 B085 SAN ONOFRE I - ITEM 1.2 - POST TRIP 11/28/83 12/05/90 No REVIEW-DATA AND INFORMATION CAPABILITY M56162 F071 SAN ONOFRE I - I.D.1.2-DETAILED CONTROL 12/16/85 01/02/90 No ROOM DESIGN REVIEW
SUMMARY
REPORT F-71 M56408 F070 SAN ONOFRE 1 - III.D.3.4.3-CONTROL 11/14/84 Incomplete No ROOM HABITABILITY - IMPLEMENT MODIFICATIONS M64952 SAN ONOFRE 1 - STATION DISTRIBUTION 06/19/86 Incomplete No VOLTAGE MONITORING AND ADMINISTRATIVE CONTROLS M68598 A022 SAN ONOFRE 1 - IMPLEMENTATION OF THE 04/17/89 Incomplete No STATION BLACKOUT RULE, 10CFR50.63 M71713 8107 SAN ONOFRE 1 - INSTRUMENT AIR (GENERIC 08/30/90 11/05/90 No LETTER 88-14)
M72163 X811 SAN ONOFRE I - BULLETIN BB-11 06/01/89 02/12/92 No PRESSURIZER SURGE LINE THERMAL STRATIFICATION M73198 1901 SAN ONOFRE 1 - FAILURE OF WESTINGHOUSE 06/19/89 08/30/89 No STEAM GENERATOR TUBE MECHANICAL PLUGS (BULLETIN 89-01)
M73703 F072 SAN ONOFRE 1 - SAFETY PARAMETER DISPLAY 07/12/89 01/02/90 No SYSTEM - RESPONSE TO GL 89-06" M73736 SAN ONOFRE 1 - DUALITY GROUP 05/31/89 Incomplete No CLASSIFICATION (SEP TO PIC 111-1)
M74463 8111 SAN ONOFRE I - INDIVIDUAL PLANT
(--/--/--)
Incomplete No EVALUATIONS (GL 88-20)
M74628 F075 SAN ONOFRE 1 - 1.D.2.2, SAFETY 07/12/89 01/02/90 No PARAMETER DISPLAY CONSOLE - INSTALLED M74993 8113 SAN ONOFRE 1 - USI A SAFETY 04/17/90 Incomplete No IMPLICATIONS OF CONTROL SYSTEMS (GL 89-19)
ACTIONS INITIATED BY NRC (continued)
TAC MPA Start NRC Implementation Num Num Title Date Review Documented M75107 SAN ONOFRE 1 - THERMAL SHIELD REPAIR 10/06/89 Incomplete No PLANS M76356 B105 SAN ONOFRE 1-GL-87-02 SEISMIC 10/07/88 Incomplete No QUALIFICATION OF EQUIPMENT IN OPERATING PLANTS M76486 SAN ONOFRE 1 -
HIGH ENERGY LINE BREAK 04/03/90 Incomplete No SCOPING ANALYSIS M77376 8114 SAN ONOFRE I - GENERIC LETTER 90-06 12/27/90 Incomplete No (61-70) PORV AND BLOCK VALVE RELIABILITY M77449 8115 SAN ONOFRE I - GENERIC LETTER 90-06 12/27/90 Incomplete No (61-94) - LOW TEMPERATURE OVERPRESSURE PROTECTION M79020 SAN ONOFRE 1 - SINGLE FAILURE ANALYSIS 07/31/90 Incomplete No REVIEW M79689 SAN ONOFRE I - OVERPRESSURE MITIGATION 02/01/91 Incomplete No SYSTEM (LTOP)
M61655 B117 SAN ONOFRE 1 - BULLETIN 89-01, 08/30/91 Incomplete No SUPPLEMENT 2: FAILURE OF WESTINGHOUSE S6 TUBE MECHANICAL PLUGS ACTIONS TO BE COMPLETED TAC MPA Start NRC Implementation Num Num Title Date Review Documented M76808 SAN ONOFRE I - REVISES SEP COOLING 05/16/90 07/16/90 No REQUIREMENTS M82259 SAN ONOFRE 1 - ODCM REVISION 6 05/31/91 03/11/92 No M63123 SAN ONOFRE 1 -
APPLICATION FOR POSESSION 04/02/92 Incomplete No ONLY LICENSE (AA-203)
M63124 SAN ONDFRE 1 - FOUR MONTH EXTENSION 04/06/92 Incomplete No OF STEAM GENERATOR INSPECTION INTERVAL (AA-206)
M83164 SAN ONOFRE 1 - RWST DEGRADATION 04/26/92 Incomplete No M83927 X201 SAN ONOFRE I - THERMO-LAG (BULLETIN 07/30/92 Incomplete No 92-01)
ACTIONS TO BE REOPENED IF SAN ONOFRE 1 IS RESTARTED AFTER CYCLE 11 TAC MPA Start NRC Action Num Num Title Date Review Closed M45171 F026 SAN ONOFRE 1 - II.F.2.4-INSTRUMENTATION 06/20/86 04/23/92 04/23/92 FOR ICC - INSTALL ADDITIONAL INSTRUMENTATION M65867 SAN ONOFRE 1 - IPSAR SECTION 4.12.2 -
03/30/84 06/04/92 09/26/91 CONTAINMENT BUCKLING M74629 FOB3 "SAN ONDFRE I - II.F.2.3-INSTRUMENTATION 06/20/86 04/23/92 12/12/91 FOR DETECTION OF ICC - DES. OTHER MB3509 8120 SAN ONOFRE I - GENERIC LETTER 92 05/15/92 06/03/92 05/15/92 REACTOR VESSEL STRUCTURAL INTEGRITY