ML13323B266

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-206/87-05 on 870601-12 & Notice of Violation.Insp Team Determined That Weakness Exists in Performance of Technical Work at Facility,Both Stationwide & in Corporate Ofc
ML13323B266
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 07/17/1987
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Baskin K
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13323B267 List:
References
NUDOCS 8707310121
Download: ML13323B266 (5)


See also: IR 05000206/1987005

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION V

1450 MARIA LANE, SUITE 210

WALNUT CREEK, CALIFORNIA 94596

JUL 17 1987

Docket No. 50-206

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention:

Mr., Kenneth P. Baskin, Vice President

Nuclear Engineering, Safety and Licensing Department

Gentlemen:

SUBJECT:

NRC TEAM INSPECTION OF SAN ONOFRE NUCLEAR GENERATING STATION UNIT 1

This refers to the special team inspection conducted by Mr. R. C. Sorensen and

other NRC personnel on June 1 through June 12, 1987 of activities authorized

by NRC License No. DPR-13, and to the discussion of their findings held with

Mr. H. B. Ray and other members of his staff at the conclusion of the

inspection.

Areas examined during this inspection are described in the enclosed inspection

report. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

Based on the results of this inspection, it appears that certain of your

activities were not conducted in full compliance with NRC requirements as set

forth in the Notice of Violation, enclosed herewith as Appendix A. Your

response to this Notice is to be submitted in accordance with the provisions

of 10 CFR 2.201 as stated in Appendix A, Notice of Violation.

This inspection was conducted during the 42-day mid-cycle maintenance outage

in Unit 1. The objective of the inspection was to determine the effectiveness

of preventive and corrective maintenance practices in preventing, or detecting

and correcting, equipment degradation. This included the witnessing of

in-process maintenance and post maintenance activities, and the observance of

evaluation and correction of unanticipated problems. Samples of design change

packages and maintenance orders were assessed for technical adequacy and

proper implementation. Quality Assurance involvement in various aspects of

maintenance activities was also evaluated. Finally, the radiological controls

associated with the 42-day maintenance outage were observed and assessed.

I am particularly disappointed by the findings which point out weaknesses in

your conduct of technical and engineering work. I did not expect this to be

an area of weakness, and urge you to thoroughly assess your technical and

engineering performance and aggressively implement needed corrective actions

to restore full confidence in these important areas.

A summary of the areas inspected and results is included in Appendix B.

8707310121 870717

PDR

ADOCK 05000206

G

PDR

2

Overall Conclusions

The team determined that weakness exists in the performance of technical work

at San Onofre, both stationwide and at the corporate office, especially in the

area of Class 1E batteries. We cite the following examples as evidence of

this weakness:

a

Proposed Facility Changes (PFCs) improperly dispositioned by Engineering

and Construction (E&C) concerning station Class 1E batteries. PFCs

1-87-3465 and 1-86-3400, both dealing with the addition of Inverter 4A,

both state that the change "has no impact on the existing Technical

Specifications, limiting conditions of operation or surveillance

requirements."

This is clearly in error as the addition of Inverter 4A

does change .the battery no. 1 load profile and, therefore, does affect

its surveillance requirements. The team also noted that these PFCs

passed through several levels of review prior to issuance and that the

error was not detected by these reviews.

o

Failure by E&C to identify which load profile on a particular calculation

was the correct one to use for surveillance testing of battery no. 2.

Page 43 of design calculation 1399, Rev. 1, shows two load profiles, a

solid line labeled "new result" and a dotted line labeled "present

result".

No one that the inspectors spoke with seemed to know what these

terms meant. Consequently, the much greater load profile was used and

battery no. 2 failed the service test in 20 minutes, and could have

sustained damage except for the alertness of the test personnel. Here

too, calculations passed through several levels of review prior to

issuance.

o

Station Technical failed to have the proper load profile values

incorporated into the battery service test procedure. This occurred on

three (3) separate occasions, twice for battery no. 1 and once for

battery no. 2. This resulted in a violation of Technical Specifications.

o

E&C provided the wrong value for the original acceptance test of battery

no. 1. A value of 1240 amps was originally used. However, when a

verification of this value was requested by the team, a new number, 944

amps, was determined as the correct value that should have been used.

Although the old value for the performance test of battery no. 1 was a

conservative one, it still points to a laxness in the performance of a

design calculation.

o

A Construction Work Order (CWO), #87060463000, which was generated by

Startup Engineering and used to test modifications to vital bus no. 4,

lacked adequate detail to enable the modification to be properly tested.

A generic test procedure was referenced in the CWO which provided little

or no specific direction as to how the modification should be tested. A

procedure was generated by the stand-in cognizant engineer and two

technicians, on two sheets of paper, which had not received management

review and approval. Fortunately, the shift superintendent refused to

conduct this "back of the envelope" procedure until it had received

proper management approval.

Furthermore, it was not clear to the team

what the QC hold point, contained in the CWO, required the QC inspector

to verify.

3

it is our position that post modification testing should be spelled out

in specific detail by responsible engineers and receive proper management

review and approval. It should not be left to the discretion of the

operations staff and maintenance technicians to develop "back of the

envelope" procedures.

o

Lack of rigor was observed in the area of documenting the -evaluation of

substitute parts for equivalency. Although no specific deficiencies were

identified, it is the consensus of the team that these evaluations should

be better documented to justify why parts or components which differ from

the original are considered equivalent for safety related applications.

In particular, we are concerned, with regard to battery surveillance testing,

that service tests were performed incorrectly on three different occasions.

The team noted that, through the various review processes involved, numerous

opportunities existed to identify and correct the deficiencies which lead to

these improper service tests.

However, these deficiencies were not

identified, and consequently, the batteries were incorrectly tested.

We understand that extensive corrective action has been undertaken to correct

these problems with station batteries and, in some cases, has already been

implemented. We request that you address the broader aspects of these

problems, determine if other plant systems or components are affected, and

take the necessary corrective action in more generic terms.

In addition to your response to the enclosed Notice of Violation, please

include in your response letter, those actions taken or planned to address the

concerns noted above.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure

will be placed in the NRC Public Document Room.

The responses directed by this letter and the accompanying Notice are not

subject to the clearance procedures of the Office of Management and Budget as

required by the Paperwork Reduction Act of 1980, PL 96-511.

Should you have any questions concerning this inspection, we will be glad to

discuss them with you.

Sinc

ely

J. B. Martin

Regional Administrator

Enclosures:

A.

Appendix A -

Notice of Violation

B..

Appendix B - Areas Inspected and Results

C.

Inspection Report No. 50-206/87-05

A

4

cc W/enc10SUreS.

D. J. Fogarty, SCE

H. B. Ray, SCE (San Clemente)

H. E.. Morgan, SCE (San Clemente)

State of California

5

cc w/enclosures:

D. J. Fogarty SCE

H. B. Ray, SCE (San Clemente)

H. E. Morgan, SCE (San Clemente)

State of California

bcc w/enclosures:

docket file.

G. Cook

B. Faulkenberry

J. Martin

Resident Inspector

Project Inspector

bcc w/enclosures A&B only:

LFMB

M. Smith

REGI

/o

JBu

GFioreli

JMelfi

r-PMcL ulin

RE

T COPY ] REQUEST COPY ] RUEST COPY ] RE UEST COPY I R UEST COPY )

iS /

-]

E9/ NO

]&ES)/

NO

]ZP

/

NO

YE

/

NO

7//5/87

7/'5/87

7T/87

  • ,ADat

BC

1 ns

J

1

RSo

n

RUEST COPY I REQUEST COPY ] RUUEST COPY

COPY ] RE

tQUEST COPY]

E

/NO'

] YS- /

NO

]

EJ /

NO' I

ES

NO

] (YES

/NO

]

//1/87

7-

l8 7

7/1tt/87

7//7

'7/f1 /87

SRichards

RPate

DKi

h

J

in

7/1i/87

7//87

1

RE UEST COPY ] RQUEST COPY] REQUEST

PY ] REQUEST COPY ]

E / NO ] ES/

NO

YES /

]NO

YES / NO 3

SEN TO POR]

ES

/NO