ML13323A399

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-361/80-05 & 50-362/80-03 on 800324-27.No Noncompliance Noted
ML13323A399
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 05/20/1980
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Papay L
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13323A400 List:
References
NUDOCS 8007170530
Download: ML13323A399 (2)


See also: IR 05000361/1980005

Text

fS R

IUNITED

STATES

NUCLEAR REGULATORY COMMISSION

REGION V

1990 N. CALIFORNIA BOULEVARD

SUITE202,WALNUTCREEKPLAZA

WALNUTCREEK,CALIFORNIA94596

MAY 2 0 180

Docket Nos. 50-361,(

E

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California

91770

Attertion:

Dr L, T. Pa'y Vice Ps

Advanced Engineering

Gentlemen:

Subject NRC Inspection at San Onofre Units 2 and 3

This refers to the inspection conducted by Messrs. J. H. Eckhardt and

G. Hernandez of this office on March 24-27, 1980 of activities authorized

by NRC Construction Permit Nos. CPPR-97 and 98, and to the discussions of

.

his findings held with members of your staff on March 27, 1980.

Areas examined during this inspection are described in the enclosed inspection

report. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and

observations by the inspector.

No items of noncompliance with NRC requirements were identified within the

scope of this inspection.

In accordance with Section 2.790 of the NRC's "Rules of Practice", Part 2,

Title 10 Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room. If this

report contains any information that you believe to be proprietary, it is

necessary that you submit a written application to this office, within 30

days of the date of this letter, requesting that such information be withheld

from public disclosure. The application must include a full statement of

the reasons why it is claimed that the information is proprietary. The

application should be prepared so that any proprietary information identified

is contained in an enclosure to the application since the application without

the enclosure will also be placed in the Public Document Room. If we do

not hear from you in this regard within the specified period, the report

will be placed in the Public Document Room.

80 0717-0 0

Southern California Edison Company

-2-

MAY 201980

Should you have any questions concerning this inspection, we will be glad

to discuss them with you.

Sincerely,

G. S. Spencer, Chief

Reactor Construction and Engineering

Support Branch

Enclosure:

IE Inspection Report

Nos. 50-361/80-05

50-362/80-03

cc w/o enclosure:

R. Dietch, Vice President

Nuclear Engineering & Operations, SCE