ML13316B896

From kanterella
Jump to navigation Jump to search
Insp Rept 50-206/88-10 on 880222-0330.Major Areas Inspected: Environ Qualification Deficiencies
ML13316B896
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 04/27/1988
From: Huey F, Johnson P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML13316B895 List:
References
50-206-88-10, NUDOCS 8805170325
Download: ML13316B896 (8)


See also: IR 05000206/1988010

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION V

Report No.

50-206/88-10

Docket No.

50-206

License No.

DPR-13

EA 88-99

Licensee:

Southern California Edison Company

P. 0. Box 800, 2244 Walnut Grove Avenue

Rosemead, California 92770

Facility:

San Onofre Unit 1

Location:

San Onofre, San Clemente, California

Dates of

Inspection:

February 22 through March 30, 1988

Inspector:

,

_

_

_

_

_

__

_

torF R. H!Pey, Senior Resident

Date Signed

Inspectbr, Units 1, 2 and 3

Approved By:

_2

P. H. OTbhnson, Chief

Date Signed

Reactor Projects Section 3

Inspection Summary

Inspection on February 22 through March 30, 1988 (Report No. 50-206/88-10)

Areas Inspected:

This was a special inspection of Unit 1 conducted following the identification

of environmental qualification deficiencies.

Results:

General Conclusions and Significant Safety Matters:

Several examples of lack of proper environmental qualification of Unit 1

safety equipment were identified during this inspection. A review

conducted by the licensee in response to the inspector's findings

identified numerous additional examples. The nature and large number of

deficiencies identified indicates a programmatic breakdown of licensee

implementation of environmental qualification controls, as required by

8805170325 880427

PEIR

ADOCK 05000206

g

DCD

-2

NRC regulations. The licensee was requested to address the root cause of this

program breakdown and identify warranted corrective actions prior to restart of

Unit 1 from the current mid-cycle outage.

Summary of Violations:

Enforcement action resulting from this inspection will be the subject of

separate correspondence.

DETAILS

1.

Persons Contacted

Southern California Edison Company

  • C. McCarthy, Vice President, Site Manager
  • K. Baskin, Vice President, Nuclear Engineering, Safety and

Licensing

W. Moody, Deputy Site Manager

H. Morgan, Station Manager

  • M. Medford, Manager, Nuclear Engineering and Licensing

D. Schone, Quality Assurance Manager

D. Stonecipher, Quality Control Manager

R. Krieger, Operations Manager

  • J. Reilly, Technical Manager
  • D. Pilmer, Manager, Nuclear Engineering

J. Reeder, Operations Superintendent, Unit 1

M. Wharton, Assistant Technical Manager

San Diego Gas and Electric Company

  • R. Lacey, Manager of Nuclear Department
  • Denotes those attending management meeting on March 24, 1988.

The inspector also contacted other licensee employees during the course of

the inspection, including engineering, licensing, and construction

personnel and QA and QC engineers.

2.

Background

On February 5, the inspector completed the initial portion of a systematic

review of licensee implementation of environmental qualification (EQ)

requirements for Unit I safety injection equipment located in harsh

environment areas outside of containment. The inspection emphasized the

physical inspection of specific components located in harsh environment

areas rather than a review of existing qualification packages.

In performing this review, the inspector noted what appeared to be

deficiencies in the licensee's implementation of the environmental

qualification program at Unit 1. Accordingly, the inspector expanded the

original scope of the inspection to cover other safety related systems

located in harsh environment areas outside of containment.

The requirements for environmental qualification of electrical equipment

important to plant safety are identified in 10 CFR 50.49. The

requirements applicable to this inspection include the following:

2

10 CFR 50.49(a) requires each holder of a license for operation of a

nuclear power plant to establish a program for environmentally

qualifying the electric equipment defined in paragraph (b).

10 CFR 50.49(b) defines equipment important to safety and covered by

10 CFR 50.49 to be:

(1) Safety-related electric equipment (i.e., that equipment relied

upon to remain functional during and following design basis

events),

(2) Non-safety-related electric equipment whose failure could affect

the satisfactory fulfillment of a safety function, and

(3) Certain post-accident monitoring equipment.

10 CFR 50.49(d) requires the licensee to prepare a list of equipment

covered under 10 CFR 50.49(a).

10 CFR 50.49(f) states that each item of electrical equipment shall

be qualified by test and/or analysis to show that the equipment to be

qualified is acceptable.

10 CFR 50.49(g) established a deadline of November 30, 1985, for

completion of final environmental qualification of all electrical

equipment covered by this section.

10 CFR 50.49(j) states that a record of the qualification of

electrical equipment shall be maintained in a qualification file in

an auditable form to permit verification that the equipment is

qualified and meets the specified performance requirements under

postulated environmental conditions.

3.

Specific Findings (37701)

As of the close of this inspection, the findings indicated significant

deficiencies in the licensee environmental qualification program as

implemented for Unit 1.

Specific examples of identified environmental qualification deficiencies

are described below. A preliminary review of these examples indicated two

major categories of environmental qualification program deficiency. The

first category involved failure of the design control process to properly

address EQ concerns, as required by 50.49(b)(1), for plant modifications

performed after compilation of the Master EQ List but prior to

implementation of the EQ program. The second category involved failure to

consider possible electrical interaction between associated electrical

circuits, as required by 50.49(b)(2).

It appears that the deficiencies identified during this inspection existed

prior to the November 30, 1985 qualification deadline described in 10 CFR

50.49(g). Specific examples of observed environmental qualification

deficiencies are as follows:

3

a.

On January 7, 1988, a licensee quality assurance inspection

identified EQ deficiencies related to six solenoid valves (SV 17, SV

17A, SV 18, SV 18A, SV 875A, and SV875B) associated with four safety

injection and feedwater miniflow recirculation valves (CV 875A/B and

CV 36/37). In particular, the six valves were not included on the

environmental qualification master list (EQML), as required by 10 CFR

50.49(d). In addition, only SV 18 and SV 18A had been qualified by

test or analysis, as required by 10 CFR 50.49(f). The plant safety

analysis relies on these valves to prevent main feedwater pump damage

during a small break loss-of-coolant accident (LOCA).

b. On January 25, the NRC inspector found that the main. feedwater pump

motor air filters did not conform to the description of those filters

in the pump motor EQ package. In particular, the metal filters

described in the pump motor environmental qualification package had

been replaced with cardboard air filters. The metal air filters are

specified to ensure that the pump will remain operable during harsh

steam environment conditions.

c.

On February 1, the NRC inspector determined that two safety injection

bonnet vent valves (SV2900 and SV3900) were not included on the EQML

as required by 10 CFR 50.49(d). The plant safety analysis relies on

these valves to ensure proper operation of the safety injection

discharge valves.

d. On February 5, the NRC inspector determined that two auxiliary

feedwater pump discharge valves (MOV 1202 and MOV 1204) were not

included on the EQML as required by 10 CFR 50.49(d), and that the

valves were not qualified by test or analysis, as required by 10 CFR

50.49(f). The position taken by the licensee was that these valves,

were found in an "essentially qualified" condition (requiring only

minor corrective action, such as change of lubricant). The safety

analysis requires that these valves open and close (respectively) to

allow automatic initiation of auxiliary feedwater.

e. On February 10, the NRC inspector identified EQ deficiencies

associated with the three main feedwater block valves (MOV 20, 21 and

22).

In particular, the valves were not included on the EQML as

required by 10 CFR 50.49(d), and the valves were not qualified by

test or analysis, as required by 10 CFR 50.49(f). The plant safety

analysis relies on these valves to back up the HV852 valves for

isolation of feedwater to the steam generators.

When the inspector identified this concern, the licensee stated that

this deficiency had been recognized (in September 1987) in the course

of completing the Unit 1 single failure analysis. The single failure

analysis also confirmed that the feedwater system bypass valve

solenoids (SV 149, SV 150 and SV 151) and the feedwater system

regulating valve solenoids (SV 456, SV 457 and SV 458) were not

properly qualified. These components were included within the scope

of the Justification for Continued Operation provided for the single

failure issue (which assumed these components to be inoperable).

However, a comprehensive evaluation of the EQ deficiencies as related

to root cause and possible program problems was not pursued at that

4

time, in contrast to prompt actions initiated by the licensee

following the identification of single failure deficiencies.

f. In response to concerns raised by the NRC inspector on February 5,

the licensee's nuclear engineering department committed to perform a

detailed review of safety systems and safety system interfaces which

are located in harsh environment areas. Although still in progress

at the end of this inspection, this review had identified numerous

additional examples of improperly or inadequately qualified

components affecting safety-related systems. In particular:

The licensee concluded that the following additional components were

not included on the EQML as required by 10 CFR 50.49(d):

(1) Seven charging system flow controllers (FY 1112, FY 1115A,

FY 1115B, FY 1115C, FY 11150, FY 1115E,

FY 1115F).

(2) Three charging system recirculation flow indicators (FT 2114B,

FT 2114C, FT 3114A).

The licensee determined that the following additional components were

not included on the EQML as required by 10 CFR5 0.49(d), .and also

were not shown to be qualified by test or analysis as required by 10

CFR 50.49(f):

(1) Four charging system auxiliary spray valve position switches

(ZSO 1304, ZSO 1305, ZSC 1304, ZSC 1305).

(2) Four safety injection miniflow valve position switches

(ZSO 1875A, ZSO 18758, ZSC 1875A, ZSC 18758).

(3) One auxiliary feedwater pump bearing cooling water valve

(SV 135).

(4) Twelve safety injection switchover valve air solenoids (SV 520,

SV 521, SV 522, SV 523, SV 524, SV 525, SV 526, SV 527, SV 528,

SV 529, SV 530, SV 531)

(5) Seven charging system flow control valves (SV 1112, SV 1115DA,

SV 1115DB, SV 1115EA, SV 1115EB, SV 1115FA, SV 1115FB).

(6) Two charging system recirculation pump bearing water valves

(SV 2077 and SV 3078).

(7) Two charging system auxiliary spray valve converters (HY 1304

and HY 1305).

Items (4) and (6) above involve non-safety-related components which

by electrical interactions (10 CFR 50.49(b)(2)) could cause failure

of safety-related components. The remainder are safety-related

components which are required to function during or following an

accident, as.discussed in 10 CFR 50.49(b)(1).

5

4.

Additional Discussion

W

The above findings associated with the EQ issue were among items discussed

with licensee representatives during a mid-level management meeting in the

Region V office on February 25, 1988. A copy of the memorandum

summarizing this meeting is enclosed as Attachment 1 to this inspection

report.

During discussions with licensee management on February 26, 1988, the

inspector emphasized the importance of prompt licensee assessment of the

impact of the above environmental qualification program deficiencies on

the ability of the licensee to restart Unit 1 following the current

mid-cycle outage (scheduled for completion in April). The inspector

requested that the licensee provide the NRC with a submittal to

specifically define the licensee's plan of action on this matter.

An SCE letter, dated March 11, 1988, provided the licensee's response to

the above NRC request. The licensee's letter described the circumstances

contributing to the identified EQ problems and addressed the actions

planned to correct deficiencies in the licensee EQ program. In

particular:

a. The licensee confirmed that the cause of the Unit 1 EQ deficiencies

was a combination of (a) inadequate design controls over equipment

installed in the plant after development of the initial EQ Master

List in 1981 but before the implementation of enhanced design

controls in 1984, and (b) an inadequate review of electrical

interactions as required by 10 CFR 50.49(b)(2).

Licensee Event

SReport 50-206/88-01, dated March 30, 1988, provided additional detail

in this regard.

Although final review and corrective actions have

not yet been completed, the licensee has stated that, based on the

more rigorous controls implemented from the onset of Units 2/3

construction, similar deficiencies are not expected to be encountered

on these units.

b. The licensee committed to define and properly qualify all Unit 1

safety-related electrical equipment, as required by 10 CFR

50.49(b)(1), prior to the end of the current mid-cycle outage.

c.

The licensee stated that the planned review of electrical

interactions, as required by 10 CFR 50.49(b)(2), was an extensive

effort and would not be completed until August 31, 1988, after the

unit returned to service following the mid-cycle outage.

On March 24, 1988, licensee, Region V, and NRR management met in the

Region V Office to discuss the licensee's proposed corrective actions and

plans for unit restart. The results of this meeting are documented in

meeting report 50-206/88-11, dated March 29, 1988. During the meeting,

licensee management representatives stated that a reassessment had been

completed of Unit 1 safety related equipment required to be qualified

pursuant to 10 CFR 50.49(b)(1).

They stated that this reassessment had

identified 48 components to be added to the EQ Master List. The licensee

stated that all of these components would be properly qualified prior to

completion of the ongoing mid-cycle outage.

6

The licensee also reviewed the scope of effort to complete the evaluation

of EQ electrical interactions, as required by 10 CFR 50.49(b)(2). The NRC

representatives expressed concern regarding SCE's plans to restart the

unit before completion of the review of 10 CFR 50.49(b)(2) electrical

interactions. The licensee was requested to submit for NRC review the

rationale for proceeding with restart in the absence of a clear knowledge

as to the state of compliance with 10 CFR 50.49(b)(2).

Following the March 24 meeting, further licensee review identified several

additional components requiring environmental qualification in accordance

with the requirements of 10 CFR 50.49(b)(1). On March 29, 1988, in a

discussion with the NRC staff, the licensee committed to provide, prior to

unit restart, the requested (b)(2) rationale and the basis for SCE's

conclusion that all components covered by (b)(1) had been identified.

This was provided by SCE in a letter dated April 1, 1988; however, the

licensee subsequently informed Region V that Unit 1 would remain shut down

until the 50.49(b)(2) review was completed and all EQ issues had been

resolved.

The failure of the licensee to properly qualify Unit 1 electrical

equipment in accordance with the environmental qualification requirements

of 10 CFR 50.49 is an apparent violation. Enforcement action, in this

regard, will be the subject of separate correspondence.

5.

Exit Meeting (30703)

As documented in meeting report 50-206/88-11, dated March 29, 1988, a

management meeting was conducted with the licensee representatives

identified in Paragraph 1 on March 24, 1988. During this meeting, the

inspector summarized the inspection scope and findings, as described in

the Results section of this report.

The licensee acknowledged the inspection findings and noted that

appropriate corrective actions would be implemented where warranted. The

licensee did not identify as proprietary any of the information provided

to or reviewed by the inspectors during this inspection.