Text
Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 K. P. BASKIN TELEPHONE
- MANAGER, GENERATION ENGINEERING September 11, 1979 213-572-1401 Director, Office of Nuclear Reactor Regulation Attention:
Mr. D. L. Ziemann, Chief Operating Reactors Branch #2 Division of Operating Reactors U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Gentlemen:
Subject:
Docket No. 50-206 Provisional Operating License No. DPR-13 Inservice Inspection and Testing Program San Onofre Nuclear Generating Station Unit 1
References:
(1) Letter from K. P. Baskin to K. R. Goller dated September 28, 1977, Docket 50-206 (2) Letter from K. P. Baskin to K. R. Goller dated May 26, 1978, Docket 50-206 (3) Letter from A. Schwencer to J. H. Drake dated December 22, 1977, Docket 50-206 (4) Letter from K. P. Baskin to D. L.. Ziemann dated September 4, 1979, Docket 50-206 As required by 10CFR 50.55a(g), we submitted Inservice Inspection and Testing Programs for San Onofre Unit 1 as enclosures with Reference (1).
Supplemental information regarding these programs was submitted with Reference (2).
These programs were authorized for implementation on January 1, 1978, and requests for relief were granted on an interim basis per Reference (3).
On June 26 and 27, 1978, we met with the NRC staff in a working session to resolve concerns associated with the programs.
Reference (4) provided proposed procedure revisions and associated relief requests for the Inservice Inspection and Pump Testing Programs as a result of the above meeting. This submittal provides proposed revisions to the Inservice Valve Testing procedure and associated relief requests as a result of the above meeting.
1790920 7'
D. L. Ziemann, Chief September 11, 1979 One copy of each of the Inservice Inspection and Pump Testing Program relief requests and associated proposed procedure revisions was included with Reference (4).
Enclosed are forty copies of each of the proposed procedure revisions and relief requests for all Inservice Inspection and Testing Programs.
These revised programs and implementing procedures will be incorporated following your approval for all testing and inspections performed thereafter.
Should you have any questions or require additional information, do not hesitate to contact me.
Sincerely, Enclosures cc: