Forwards IE Insp Repts 50-361/79-23 & 50-362/79-22 on 790820-24 & Notice of Violation
ML13309A821
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 10/26/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Arenal A
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13309A819 List:
References
NUDOCS 8001020151
Download: ML13309A821 (2)


See also: IR 05000361/1979023

Text

_.t0SREG~j

lC1

42*

  • UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGIONV

1990 N. CALIFORNIA BOULEVARD

SUITE 202, WALN

CREEK PLAZA

VVALNUTCREEKCALIFORNIA94596

OCT 23 WS~

Docket Nos. 50-361

50-362

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention: Mr. A. Arenal, Vice President

Advanced Engineering

Gentlemen:

This refers to the inspection conducted by Messrs. J. H. Eckhardt

and J. 0. Elin of this office on August 20-24, 1979, of activities

authorized by NRC Construction Permit Nos. CPPR-97 and CPPR-98, and

to the discussion of our findings held with Mr. D. E. Nunn and other

members of your staff at the conclusion of the inspection.

Based on the results of this inspection, it appears that one of your

activities was not conducted in full compliance with NRC requirements,

as set forth in the Notice of Violation, enclosed herewith as Appendix A.

This item of noncompliance has been categorized into a level as

described in our correspondence to all NRC licensees dated December 31,

1974.

This notice is sent to you pursuant to-the provisions of Section 2.201,

of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.20.1 requires you to submit to this office,

within thirty days of your receipt of this notice, a written statement

or explanation in reply including (1) corrective steps which have

been taken by you and the results achieved; (2) corrective steps which

will be taken to avoid further violations; and (3) the date when full

compliance will be achieved.

sooS o2.0

Southern California Edison Company

- 2

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room. If this report contains any information that you believe

to be proprietary, it is necessary that you submit a written application

to this office, within 30 days of the date of this letter, requesting

that such information be withheld from public disclosure. The application

must include a full statement of the reasons why it is claimed that the

information is proprietary. The application should be prepared so that

any proprietary information identified is contained in an enclosure to

the application, since the application without the enclosure will also

be placed in the Public Document Room. If we do not hear from you in

this regard within the specified period, the report will be placed in

the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

G. S. Sp ncer, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

1.IE Inspection Report

Nos. 50-361/79-23

50-362/79-22

2.Appendix A - Notice of Violation

cc w/o enclosure:

J. H. Drake, Vice President

Engineering and Construction, SCE