Forwards IE Insp Repts 50-361/79-22 & 362/79-21 on 790813-31 & Notice of Violation
ML13309A796
Person / Time
Site: San Onofre  
Issue date: 10/02/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Arenal A
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13309A793 List:
References
NUDOCS 7912130707
Download: ML13309A796 (2)


See also: IR 05000361/1979022

Text

0ONITED STATES

NUCLEAR REGULATORY COMMISSION

REGION V

1990 N. CALIFORNIA BOULEVARD

SUITE 202, WALNUT CREEK PLAZA

WALNUT CREEK, CALIFORNIA 94596

October 2, 1979

Docket Nos. 50-361

t

50-362

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention: Mr. ,A.

Arenal

Vice President

Gentl emen:

Subject: NRC Inspection at San Onofre Units 2 and 3

This refers to the inspections conducted by Mr. R. J. Pate of this

office during the period August 13-31, 1979 of activities authorized by

NRC Construction Permit Nos. CPPR-97 and 98, and to the discussions of

his findings held with Mr. D. E. Nunn and other members of your staff on

August 17, 24, and 31, 1979.

Areas examined during this inspection are described in the enclosed

inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, in

terviews with personnel, and observations by the inspector.

Based on the results of this inspection, it appears that one of your

activities was not conducted in full compliance with NRC requirements,

as set forth in the Notice of Violation, enclosed herewith as Appendix A.

This item of noncompliance has been categorized into a level as de

scribed in our correspondence to all NRC licensees dated December 31,

1974.

This notice is sent to you pursuant to the provisions of Section 2.201,

of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.201 requires you to submit to this office,

within thirty (30) days of your receipt of this notice, a written state

ment or explanation in reply including (1) corrective steps which have

been taken by you and the results achieved; (2)

corrective steps which

will be taken to avoid further violations; and (3) the date when full

compliance will be achieved.

79121380

Soutbern California Edison Company

-2-

October 2, 1979

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room. If this report contains any information that you believe

to be proprietary, it is necessary that you submit a written application

to this office, within 30 days of the date of this letter, requesting

that such information be withheld from public disclosure. The application

must include a full statement of the reasons why it is claimed that the

information is proprietary. The application should be prepared so that

any proprietary information identified is contained in an enclosure to

the application, since the application without the enclosure will also

be placed in the Public Document Room. If we do not hear from you in

this regard within the specified period, the report will be placed in

the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

G. S. Spencer, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

A. Notice of Violation

B. IE Inspection Report

Nos. 50-361/79-22

50-362/79-21

cc w/o enclosure B:

J. H. Drake, Vice President

Engineering and Construction