Forwards IE Insp Repts 50-361/79-25 & 50-362/79-24 on 790904-07 & 24-28.No Noncompliance Noted
ML13309A787
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 10/31/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Arenal A
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13309A788 List:
References
791030, NUDOCS 7912060018
Download: ML13309A787 (2)


See also: IR 05000361/1979025

Text

tp

REGO

0

UNITED STATES

0

NUCLEAR REGULATORY COMMISSION

o

REGION V

1990 N. CALIFORNIA BOULEVARD

SUITE 202, WALNUT CREEK PLAZA

.

WALNUT CREEK, CALIFORNIA 94596

OCT 31 1979

Docket Nos.

50-36

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead-, California 91770

Attention: Mr. A. Arenal

Vice President

Gentlemen:

Subject: NRC Inspection at San Onofre Units 2 and 3

This refers to the inspections conducted by Mr. R. J. Pate of this

office during the period September 4-7 and 24-28, 1979, of activities

authorized by NRC Construction Permit Nos. CPPR-97 and 98, and to the

discussions of his findings held with Mr. P. A. Croy and other members

of your staff on September 28, 1979.

Areas examined during this inspection are described in the enclosed

inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records,

interviews with personnel, and observations by the inspector.

No items of noncompliance with NRC requirements were identified within

the scope of this inspection.

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10 Code of Federal Regulations, a copy of this letter

and the enclosed inspection report will be placed in the NRC's Public

Document Room. If this report contains any information that you believe

to be proprietary, it is necessary that you submit a written application

79128060

Southern California Edison Company

- 2 -

OUT 31 1979

to this office, within 20 days of the date of this letter, requesting

that such information be withheld from public disclosure. The application

must include a full statement of the reasons why it is claimed that

the information is proprietary. The application should be prepared

so that any proprietary information identified is contained in an

enclosure to the application since the application without the enclosure

will also be placed in the Public Document Room. If we do not hear

from you in this regard within the specified period, the report will

be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be

glad to discuss them with you.

Sincerely,

G. S. Spencer, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report

Nos. 50-361/79-25

50-362/79-24

cc w/o enclosure:

J. H. Drake, Vice President

Engineering & Construction, SCE