Forwards IE Insp Repts 50-361/79-18 & 50-362/79-18 on 790626-29.No Noncompliance Noted
ML13309A740
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 07/27/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Johari Moore
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML13309A741 List:
References
NUDOCS 7909200047
Download: ML13309A740 (2)


See also: IR 05000361/1979018

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION V

1990 N. CALIFORNIA BOULEVARD

V

~SUITE

202, WALNUT CREEK PLAZA

WALNUT CREEK, CALIFORNIA 94596

JUL 2 7 179

Docket Nos. 50-361

50-362

Southern California Edison Company

P. 0. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention: Mr. J. B. Moore

Vice President

Gentlemen:

Subject:

NRC Inspection at San Onofre Units 2 and 3

This refers to the inspection conducted by Mr. J. H. Eckhardt of this office

on June 26-29, 1979, of activities authorized by NRC Construction Permit Nos.

CPPR-97 and CPPR-98, and to the .disccusion of our findings held with Mr.

D. E. Nunn and other members of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the enclosed inspection.

report. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and obser

vations by the inspector.

No items of noncompliance with NRC requirements were identified within the

scope of this inspection.

In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the-NRC's Public.Document Rclom. If this

report contains any information that you believe to be proprietary, it is necessary

that you submit a written application to this office, within 20 days of the date

of this letter, requesting that such information be withheld from public disclos

ure. The application must include a full statement of the reasons why it is

claimed that the information is proprietary. The application should be prepared

Southern California Edison Company

-2

JU

27 7

so that any proprietary information identified is contained in an enclosure to

the application, since the application without the enclosure will also be placed

in the Public Document Room. If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be glad to

discuss them with you.

Sincerely,

G. S. Sp ncer, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection Report

Nos. 50-361/79-18

50-362/79-18

cc w/o enclosure:

J. H. Drake, Vice President

Engineering & Construction, SCE