Advises That Second Edition of Integrated Implementation Schedule Submitted in Appropriate for Meeting License Conditions
ML13304A484
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 05/29/1990
From: Kokajko L
Office of Nuclear Reactor Regulation
To: Cotton G, Ray H
San Diego Gas & Electric Co, Southern California Edison Co
References
NUDOCS 9006010253
Download: ML13304A484 (3)


Text

May 29, 1990 Docket Nos. 50-361 and 50-362 Mr. Harold B. Ray Mr. Gary D. Cotton Vice President Senior Vice President Southern California Edison Co.

Engineering and Operations Irvine Operations Center San Diego Gas & Electric Co.

23 Parker Street 101 Ash Street Irvine, California 92718 San Diego, California 92112 Gentlemen:

SUBJECT:

SECOND EDITION OF THE INTEGRATED IMPLEMENTATION SCHEDULE--SAN ONOFRE NUCLEAR GENERATING STATION, UNIT NOS. 2 AND 3 By letter dated May 14, 1990, you submitted the second edition of the Integrated Implementation Schedule for San Onofre Nuclear Generating Station, Unit Nos. 2 and 3. This submittal was in accordance with License Condition 2.C(26) for San Onofre Unit 2 and License Condition 2.C(27) for San Onofre Unit

3.

The staff has reviewed the Integrated Implementation Schedule for San Onofre 2/3. The staff finds that the schedule and the information contained in your letter appear to be appropriate in meeting the License Conditions for San Onofre 2/3.

The staff continues to look forward to working with you on your Integrated Implementation Schedule.

Sincerely,

/s/

Lawrence E. Kokajko, Project Manager Project Directorate V Division of Reactor Projects -

III, IV, V and Special Projects Office of Nuclear Reactor Regulation cc:

See next page DISTRIBUTION Docket File LKokajko NRC & LPDRs OGC PD5 Reading E. Jordan JZwolinski ACRS (10)

DFoster R /5D'1S PD5 (A)DRSP/D:PD5 MfYzer kajko:dr JLarkins

[S02/3 2ND EDITION]

90060102 5:3 900529 FR ADOC 05000361 PDC

l R E G U I 9 0 0

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 May 29, 1990 Docket Nos. 50-361 and 50-362 Mr. Harold B. Ray Mr. Gary D. Cotton Vice President Senior Vice President Southern California Edison Co.

Engineering and Operations Irvine Operations Center San Diego Gas & Electric Co.

23 Parker Street 101 Ash Street Irvine, California 92718 San Diego, California 92112 Gentlemen:

SUBJECT:

SECOND EDITION OF THE INTEGRATED IMPLEMENTATION SCHEDULE--SAN ONOFRE NUCLEAR GENERATING STATION, UNIT NOS. 2 AND 3 By letter dated May 14, 1990, you submitted the second edition of the Integrated Implementation Schedule for San Onofre Nuclear Generating Station, Unit Nos. 2 and 3. This submittal was in accordance with License Condition 2.C(26) for San Onofre Unit 2 and License Condition 2.C(27) for San Onofre Unit

3.

The staff has reviewed the Integrated Implementation Schedule for San Onofre 2/3. The staff finds that the schedule and the information contained in your letter appear to be appropriate in meeting the License Conditions for San Onofre 2/3.

The staff continues to look forward to working with you on your Integrated Implementation Schedule.

Sincerely, Lawrence E. Kokajko, Project Manager Project Directorate V Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation cc:

See next page

Mr. Harold B. Ray San Onofre Nuclear Generating Southern California Edison Company Station, Units 2 and 3 cc:

Charles R. Kocher, Esq.

Mr. Richard J. Kosiba, Project Manager James A. Beoletto, Esq.

Bechtel Power Corporation Southern California Edison Company 12440 E. Imperial Highway Irvine Operations Center Norwalk, California 90060 23 Parker Irvine, California 92718 Mr. Robert G. Lacy Orrick, Herrington & SutcliffeDepartment Orrik, errigto

& StclffeSan Diego Gas & Electric Company ATTN:

David R. Pigott, Esq.

P. 0. Box 1831 600 Montgomery Street San Diego, California 92112 San Francisco, California 94111 Mr. John Hickman Alan R. Watts, Esq.

Senior Health Physicist Rourke & Woodruff Environmental Radioactive Mgmt. Unit 701 S. Parker St. No. 7000 Environmental Management Branch Orange, California 92668-4702 State Department of Health Services 714 P Street, Room 616 Mr. Sherwin Harris Sacramento, California 95814 Resource Project Manager Public Utilities Department Resident Inspector, San Onofre NPS City of Riverside do U.S. Nuclear Regulatory Commission 3900 Main Street Post Office Box 4329 Riverside, California 92522 San Clemente, California 92672 Mr. Charles B. Brinkman Mayor Combustion Engineering, Inc.

City of San Clemente 12300 Twinbrook Parkway, Suite 330 San Clemente, California 92672 Rockville, Maryland 20852 Regional Administrator, Region V Mr. Phil Johnson U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission 1450 Maria Lane/Suite 210 Region V Walnut Creek, California 94596 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Chairman, Board of Supervisors San Diego County Mr. Don Womeldorf 1600 Pacific Highway, Room 335 Chief, Environmental Management Branch San Diego, California 92101 California Department of Health 714 P Street, Room 616 Sacramento, California 95814 (14)