Letter Sequence Approval |
|---|
|
|
MONTHYEARML13220A1032013-08-0101 August 2013 Application to Modify Technical Specifications Regarding AC Sources - Operating (TS-WBN-13-02) Project stage: Request ML13206A4272013-08-0101 August 2013 Online Reference Portal for Nuclear Regulatory Commission Review of Fukushima Near Term Task Force Related Documents Project stage: Request ML13260A2022013-09-17017 September 2013 Accepted for Review of Application to Modify Watts Bar Nuclear Plant Unit 1 Tech Spec Regarding AC Sources Project stage: Approval ML14056A5252014-02-26026 February 2014 E-mail, Request for Additional Information Regarding Application to Modify Technical Specifications Related to AC Sources-Operating Project stage: RAI CNL-14-015, Response to NRC Request for Additional Information Related to Application to Modify Technical Specifications Regarding AC Sources - Operating (TS-WBN-13-02)2014-04-21021 April 2014 Response to NRC Request for Additional Information Related to Application to Modify Technical Specifications Regarding AC Sources - Operating (TS-WBN-13-02) Project stage: Response to RAI ML14132A2432014-06-16016 June 2014 Summary of 4/24/214, Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 2, Request for Additional Information Related to License Amendment to Modify AC Power Source Technical Specifications Project stage: RAI CNL-14-107, Response to NRC Request for Additional Information Related to Application to Modify Technical Specifications Regarding AC Sources - Operating (TS-WBN-13-02)2015-01-29029 January 2015 Response to NRC Request for Additional Information Related to Application to Modify Technical Specifications Regarding AC Sources - Operating (TS-WBN-13-02) Project stage: Response to RAI ML15090A6112015-03-31031 March 2015 NRR E-mail Capture - Watts Bar Unit 1 Draft RAIs for CSST License Amendment Request, TAC MF2549 Project stage: Draft RAI ML15105A5252015-04-15015 April 2015 NRR E-mail Capture - Final RAIs MF2549 WBN, U1 CSST License Amendment Request Project stage: RAI CNL-15-078, Response to NRC Request for Additional Information Related to Application to Modify Technical Specifications Regarding AC Sources - Operating (TS-WBN-13-02)2015-06-12012 June 2015 Response to NRC Request for Additional Information Related to Application to Modify Technical Specifications Regarding AC Sources - Operating (TS-WBN-13-02) Project stage: Response to RAI ML15232A1162015-08-24024 August 2015 FRN Re. Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing Project stage: Other ML15232A1132015-08-24024 August 2015 LTR Re. Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing (TAC No. 2549) Project stage: Other ML15225A0942015-09-29029 September 2015 Issuance of Amendment Regarding Alternating Current Sources Project stage: Approval CNL-19-110, Application to Revise Technical Specifications 3.8.1, AC Sources - Operating (WBN-TS-18-10)2019-12-17017 December 2019 Application to Revise Technical Specifications 3.8.1, AC Sources - Operating (WBN-TS-18-10) Project stage: Request 2015-01-29
[Table View] |
Text
Chen. Qiao-Lynn From:
Hon, Andrew Sent:
Tuesday, September 17, 2013 10:58 AM To:
Shea, Joseph W (jwshea@tva.gov)
Cc:
Mathew, Roy; Matharu, Gurcharan; Broaddus, Doug; Poole, Justin; Schrull, Edward Dustin (edschrull@tva.gov); Chen, Qiao-Lynn
Subject:
Accepted for Review of Application to Modify Watts Bar Nuclear Plant Unit 1 Tech Spec Regarding AC Sources - TAC MF-2549, ML13260A202
Dear Mr. Shea,
By letter dated August 1, 2013 (ADAMS NO. ML13220A103), TVA submitted the subject license amendment request for Watts Bar Unit-1. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
If you have any questions, please contact me.
ADAMS Accession No. ML13260A202 Andy Hon, PE Project Manager (Watts Bar Nuclear Unit-1)
Plant Licensing Branch 1/-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 301-415-8480 OWFN08E5 Mail Stop 08G-9a andrew.hon@nrc.gov 1