Other: CNL-14-030, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), CNL-14-131, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant, CNL-14-191, Compliance Status Letter and Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049, CNL-14-192, Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant, CNL-14-232, Closure of Open Item Discussed in Tennessee Valley Authoritys Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051), ML12307A105, ML13063A440, ML13247A288, ML13254A297, ML13261A038, ML14128A129
|
MONTHYEARML12307A1052012-10-29029 October 2012 Tennessee Valley Authority - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13072A5482013-02-27027 February 2013 OL - Documents Needed for Fes Project stage: Request ML13063A4402013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13067A0302013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13182A3962013-07-0505 July 2013 And Watts Bar Nuclear Plant - Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval ML13204A2312013-08-0202 August 2013 RAI Related Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI ML13161A2862013-08-0202 August 2013 Acknowledgement Letter for 60 Day Response to Issuance of Seismic Guidance Related to the NTTF Recommendation 2.1, Seismic Reevaluations Project stage: Request ML13254A2972013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13247A2882013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Watts Bar Nuclea Project stage: Other ML13261A0382013-08-28028 August 2013 Tennessee Valley Authority, Watts Bar, First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13248A4572013-08-29029 August 2013 Confirmatory Order (NRC Office of Investigation Report No. 2-2011-003) - EA-12-021- Confirmation Action Status Update Project stage: Other ML13254A0652013-09-0606 September 2013 Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI ML13275A3732013-10-24024 October 2013 Interim Staff Evaluation and Request for RAI Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI CNL-13-125, Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-11-22022 November 2013 Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Response to RAI ML13338A6832013-11-26026 November 2013 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Watts Bar Nuclear Plant, Units 1 and 2, TAC MF0950 and MF1177 Project stage: Other ML13343A0362013-12-20020 December 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other CNL-14-007, Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number2014-01-10010 January 2014 Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA Project stage: Response to RAI CNL-14-014, Revised Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2014-02-0707 February 2014 Revised Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other CNL-14-030, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-28028 February 2014 Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML14058A1052014-03-0606 March 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies Relating to Order EA-12-049 (Mitigating Strategies) Project stage: Other ML14128A1292014-05-15015 May 2014 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-14-072, Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-02014-06-25025 June 2014 Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051 Project stage: Response to RAI ML14211A3462014-08-18018 August 2014 Report for the Westinghouse Audit in Support of Reliable Spent Fuel Instrumentation Related to Order EA-12-051 Project stage: Acceptance Review CNL-14-131, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant Project stage: Other CNL-14-134, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order Number EA-12-049) for Watts Bar Nucle2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order Number EA-12-049) for Watts Bar Nuclear Project stage: Other CNL-14-192, Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant2014-10-29029 October 2014 Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant Project stage: Other CNL-14-191, Compliance Status Letter and Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-0492014-10-30030 October 2014 Compliance Status Letter and Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-14-232, Closure of Open Item Discussed in Tennessee Valley Authoritys Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)2014-12-19019 December 2014 Closure of Open Item Discussed in Tennessee Valley Authoritys Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: Other CNL-14-233, Compliance Letter & Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No EA-12-0492015-03-12012 March 2015 Compliance Letter & Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No EA-12-049 Project stage: Other ML15078A1932015-03-27027 March 2015 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Approval L-11-011, Transmittal of Response to NRC Bulletin 2011-01, Mitigating Strategies2015-06-29029 June 2015 Transmittal of Response to NRC Bulletin 2011-01, Mitigating Strategies Project stage: Request 2014-01-10
[Table View] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 August 28, 2013 10 CFR 2.202 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391
Subject:
Tennessee Valley Authority Watts Bar Nuclear Plant's First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
References:
- 1. NRC Order Number EA-12-051, "Issuance of Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ML12054A679)
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ML12221A339)
- 3. NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-1 2-051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"' Revision 1, dated August 2012 (ML12240A307)
- 4. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," dated October 29, 2012 (ML12307A105)
- 5. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response-to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-1 2-051) for Watts Bar Nuclear Plant," dated February 28, 2013 (ML13063A440)
Printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 August 28, 2013 On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Tennessee Valley Authority (TVA). Reference 1 was immediately effective and directs TVA to install reliable spent fuel pool level instrumentation (SFPLI). Specific requirements are outlined in of Reference 1.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document Nuclear Energy Institute (NEI) 12-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2.
Reference 4 provided the TVA initial status report regarding SFPLI strategies. Reference 5 provided the TVA Watts Bar Nuclear Plant, Units 1 and 2 overall integrated plan.
Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports.
The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since submittal of the overall integrated plan, including any changes to the compliance method or schedule.
The enclosure describes the plans that TVA will use to meet the regulatory requirements outlined in Attachment 2 of Reference 1, but does not identify any additional actions to be taken by TVA.
Therefore, this letter contains no regulatory commitments.
If you have any question regarding this submittal, please contact Kevin Casey at (423) 751-8523).
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2013.
Respe~4 Ily, 1W. Shea Vice President, Nuclear Licensing
Enclosure:
Tennessee Valley Authority Watts Bar Nuclear Plant's First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) cc: See Page 3
U.S. Nuclear Regulatory Commission Page 3 August 28, 2013 cc (Enclosure):
NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Watts Bar Nuclear Plant, Unit 1 NRC Project Manager - Watts Bar Nuclear Plant, Unit 2 NRC Senior Resident Inspector - Watts Bar Nuclear Plant
ENCLOSURE TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT'S FIRST SIX-MONTH STATUS REPORT IN RESPONE TO THE MARCH 12, 2012, COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051)
ENCLOSURE 1
Introduction Watts Bar Nuclear Plant (WBN) developed an Overall Integrated Plan (Reference 1 in Section 8 of this Enclosure), documenting the requirements to install reliable spent fuel pool level instrumentation (SFP LI), in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal of the Overall Integrated Plan, including any changes to the compliance method or schedule.
2 Milestone Accomplishments The following milestone(s) have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of July 30, 2013.
10% Design Review is complete.
Contract for Level channels with battery backup, excluding remote display, has been awarded.
3 Milestone Schedule Status The following updates the milestone schedule to support the Overall Integrated Plan. This section provides the activity status of each item, and the expected completion date noting any change. The dates are planning dates subject to change as design and implementation details are developed.
The milestone target completion dates do not impact the order implementation date.
Page 1 of 4
Target ARevised Milestone Completion Activity Target Date Status Completion Date Submit 60 Day Status Report 10/29/2012 Complete Submit Overall Integrated Plan 02/28/2013 Complete Submit 6 Month Updates:
Update 1 08/28/2013 Complete Update 2 02/28/2014 Not Started Update 3 08/28/2014 Not Started Update 4 02/28/2015 Not Started Update 5 08/28/2015 Not Started Update 6 02/282016 Not Started Update 7 08/28/2016 Not Started RAI Response 09/03/2013 Started Modifications:
Unit 1 Design Engineering 10/18/2013 10%
09/27/2013 Unit 1 Installation 08/31/20141 Not Started 04/08/2014 Unit 2 Design Engineering 10/18/2013 10%
09/27/2013 Unit 2 Installation 08/31/2014 Not Started 04/08/2014 Procedures:
Create Procedures 2 06/30/2014 Not Started Training:
Develop Training Plan 2 06/30/2014 Not Started Training Complete' 08/31/2014 Not Started Full Site SFP LI Implementation 11/05/2015 Not Started 08/31/2014 Submit Completion Report 10/12/2014 Not Started Notes: 1. The original target completion date for implementation for Unit 1 corresponded to the completion of the second refueling outage following submittal of the February 28, 2013, integrated plan. For Unit 2, the original target completion date was prior to November 5, 2015, or Unit 2 initial startup, whichever occurred first. Implementation of the SFPLI is currently scheduled to be performed on-line for Unit 1 and prior to Unit 2 initial startup as indicated by the revised target completion dates.
- 2. These milestones were not included in the February 28, 2013, Overall Integrated Plan.
4 Changes to Compliance Method The primary and backup instrument channel battery life was anticipated to exceed 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> in the February 2013 Integrated Plan. A preliminary battery life calculation has been completed.
TVA is updating the anticipated battery life to 84 hours9.722222e-4 days <br />0.0233 hours <br />1.388889e-4 weeks <br />3.1962e-5 months <br /> to provide margin for issues that may arise during the design process.
There are no other changes to the compliance method as documented in the Overall Integrated Plan (Reference 1).
Page 2 of 4
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Watts Bar Nuclear Plant (WBN) expects to comply with the order implementation date and no relief/relaxation is required at this time.
6 Open Items from Overall Integrated Plan and NRC Evaluation The following tables provide a summary of the open items Plan or the NRC Evaluation and the status of each item.
documented in the Overall Integrated Overall Integrated Plan Open Item Status 01-1)
TVA will complete an instrument channel Engineering and vendor uncertainty calculation and document instrument documentation are in progress.
channel accuracy and calibration requirements.
This will complete on the Design Engineering milestone shown above.
01-2)
TVA plans to utilize Guided Wave Radar Engineering and vendor technology. Confirm final technology selection after documentation are in progress.
contracts are complete.
This will complete on the Design Engineering milestone shown above.
01-3)
Confirm that the sensor cable and light weight at Engineering and vendor the bottom of sensor cable will not damage the SFP liner documentation are in progress.
from impact during seismic event.
This will complete on the Design Engineering milestone shown.
above.
01-4)
After detailed engineering design is complete, Engineering and vendor confirm that SFP level channel components and cable documentation are in progress.
routing will be contained within seismic structures such This will complete on the Design that the installation will comply with the reasonable Engineering milestone shown protection guidance of NEI 12-06.
above.
NRC Evaluation Open Item Status None N/A 7
Potential NRC Evaluation Impacts There are no potential impacts to the NRC Evaluation identified atthis time.
Page 3 of 4
8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.
- 1. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant," dated February 28, 2013.
- 2. NRC Order Number EA-1 2-051, "Issuance of Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012.